Project Management for Engineers Textbook Exam Questions - 1226 Verified Questions

Page 1


Project Management for Engineers

Textbook Exam Questions

Course Introduction

Project Management for Engineers introduces engineering students to the fundamental principles, tools, and techniques of effective project management in technical environments. The course covers project life cycles, scope definition, scheduling, budgeting, resource allocation, risk management, quality control, and leadership in engineering projects. Students learn industry-standard methodologies such as Agile and Waterfall, as well as the use of project management software. Emphasis is placed on teamwork, communication, and problem-solving skills necessary to successfully plan, execute, and deliver complex engineering projects on time and within budget. Case studies and real-world examples provide practical context for applying project management strategies in various engineering disciplines.

Recommended Textbook

Successful Project Management with Microsoft Project 2010 5th Edition by Jack Gido

Available Study Resources on Quizplus

14 Chapters

1226 Verified Questions

1226 Flashcards

Source URL: https://quizplus.com/study-set/455

Page 2

Chapter 1: Project Management Concepts

Available Study Resources on Quizplus for this Chatper

74 Verified Questions

74 Flashcards

Source URL: https://quizplus.com/quiz/8069

Sample Questions

Q1) How could currency fluctuations and exchange rates impact the accomplishment of the project objective and customer satisfaction?

Answer: Responses will vary.Responses should include suggestions that the prices of resources may change and cause the budget to be exceeded and the customer may not be satisfied.

Currency fluctuations and exchange rates impact the prices of resources.These changes may cause the budget to be exceeded.

Q2) A group volunteered to keep a section of highway clean. This is an example of a project.

A)True

B)False

Answer: False

Q3) While performing the work, all the activities in the baseline plan must be performed in accordance to

A) what the person responsible for the activity wants.

B) lesson learned from prior projects.

C) how the sponsor has completed all their projects in the past.

D) the project schedule and technical specifications.

Answer: D

To view all questions and flashcards with answers, click on the resource link above.

Page 3

Chapter 2: Identifying and Selecting Projects

Available Study Resources on Quizplus for this Chatper

70 Verified Questions

70 Flashcards

Source URL: https://quizplus.com/quiz/8070

Sample Questions

Q1) The project title should

A) summarize the need and justification for the project.

B) state what is expected to be accomplished.

C) state the major end products or items expected to be produced.

D) be concise and create a vision for the end result of the project.

Answer: D

Q2) The building constructed will have at least R-38 insulation rating for the ceiling and R-28 for the walls. This is an example of the ________________ in a project charter.

A) acceptance criteria

B) project objective

C) project description

D) success criteria and expected benefits

Answer: A

Q3) A milestone schedule lists target dates for phases of a project.

A)True

B)False

Answer: True

To view all questions and flashcards with answers, click on the resource link above. Page 4

Chapter 3: Developing Project Proposals

Available Study Resources on Quizplus for this Chatper

111 Verified Questions

111 Flashcards

Source URL: https://quizplus.com/quiz/8071

Sample Questions

Q1) Quantitative and qualitative benefits to the customer should be stated to help convince the customer of the value of the proposed result.

A)True

B)False

Answer: True

Q2) A ballpark estimate is acceptable for the proposal. There will be time to figure out the budget after the contract is won.

A)True

B)False

Answer: False

Q3) The customer will pay the contractor a bonus if the project is completed ahead of schedule or exceeds other customer performance requirements.

A)True

B)False

Answer: False

To view all questions and flashcards with answers, click on the resource link above.

Page 5

Chapter 4: Defining Scope, Quality, Responsibility, and Activity Sequence

Available Study Resources on Quizplus for this Chatper

129 Verified Questions

129 Flashcards

Source URL: https://quizplus.com/quiz/8072

Sample Questions

Q1) The customer may hire an independent third party or laboratory to be its representative or perform tests when checking the quality of a project deliverables.

A)True

B)False

Q2) It is important to plan for __________ in performing the project to assure that the work is done according to specifications and applicable standards and that deliverables meet acceptance criteria.

A) quality

B) resources

C) time

D) scope creep

Q3) It is easier to define the details for __________, but as the project progresses or moves from phase to phase, the project team or contractor can progressively elaborate the details as more information is known or becomes clear.

A) tasks that require a small effort

B) only tasks that take a day to complete

C) tasks near the end of the project

D) the near-term efforts

To view all questions and flashcards with answers, click on the resource link above. Page 6

Chapter 5: Developing the Schedule

Available Study Resources on Quizplus for this Chatper

79 Verified Questions

79 Flashcards

Source URL: https://quizplus.com/quiz/8073

Sample Questions

Q1) The project control process must occur regularly throughout the project and include all of the following except

A) Record information on changes to the project scope, schedule, and budget.

B) Gather data on actual performance.

C) Having a single inspection of the project's deliverables at the end of the project.

D) Establish regular reporting meetings to compare actual to planned progress.

Q2) In many cases, especially for smaller projects, most activities involve people resources-that is,

A) all the people who are employed by the project sponsor.

B) all the people who are employed by the project contractor.

C) the members of the project team who may be utilized full time or part time during the project.

D) the stakeholders for the project.

Q3) The project team can progressively elaborate the estimated durations as more information is known or becomes clear to allow for more accurate estimated durations.

A)True

B)False

Q4) Schedule control involves four steps. List the four steps in order.

To view all questions and flashcards with answers, click on the resource link above.

Page 7

Chapter 6: Resource Utilization

Available Study Resources on Quizplus for this Chatper

21 Verified Questions

21 Flashcards

Source URL: https://quizplus.com/quiz/8074

Sample Questions

Q1) A resource requirements plan illustrates

A) who is responsible for which activities.

B) the amount of labor expenses for the project.

C) the expected utilization of resources by time period during the time span of the project.

D) the budget for material and cost resources.

Q2) Why are activities drawn in a serial relationship in a network diagram?

A) The activities use different resources.

B) The activities are independent of each other.

C) From a technical standpoint, the activities must be performed in that sequence.

D) The order of completion doesn't matter.

Q3) Activities can be delayed only to the point where all their positive slack is used up, as any further delays would cause the project to

A) increase costs of all the activities in the project.

B) extend beyond the project completion time.

C) be completed ahead of schedule.

D) increase its requirements for additional resources for all activities.

To view all questions and flashcards with answers, click on the resource link above.

8

Chapter 7: Determining Costs, Budget, and Earned Value

Available Study Resources on Quizplus for this Chatper

69 Verified Questions

69 Flashcards

Source URL: https://quizplus.com/quiz/8075

Sample Questions

Q1) When the CPI goes below 1.0 or gradually gets smaller, corrective action should not be taken, the project is performing well.

A)True

B)False

Q2) Committed costs are also known as discharged or postponed costs.

A)True

B)False

Q3) Allocating total project costs for the various elements to the appropriate work packages will establish

A) the committed costs for the work package.

B) the anticipated expense for the work package.

C) how to apply resources to the work package.

D) a total budgeted cost (TBC) for each work package.

Q4) When the budgets for all the work packages are summed,

A) they should exceed the amount of funds available.

B) they cannot exceed the total project budgeted cost.

C) if the total is too high then the amounts should be force-fitted into the customer's budget.

D) if the total is too low then extra non-project expenses should be added.

To view all questions and flashcards with answers, click on the resource link above. Page 9

Chapter 8: Managing Risk

Available Study Resources on Quizplus for this Chatper

45 Verified Questions

45 Flashcards

Source URL: https://quizplus.com/quiz/8076

Sample Questions

Q1) Managing risk includes taking action to foster the likelihood of occurrence or the impact of such unfavorable events.

A)True

B)False

Q2) Risk management involves identifying, assessing, and responding to project risks in order to minimize the likelihood of occurrence and/or potential impact of adverse events on the accomplishment of the project objective.

A)True

B)False

Q3) ________ is a rating of low, medium, or high based on the expected level of change in completing the project's objective if the risk were to occur during the project.

A) The action trigger

B) The priority order

C) The mitigation plan

D) The degree of impact

Q4) Establishing risk categories may help to identify and evaluate risks. List some categories to help identify risks.

To view all questions and flashcards with answers, click on the resource link above.

Chapter 9: Closing the Project

Available Study Resources on Quizplus for this Chatper

42 Verified Questions

42 Flashcards

Source URL: https://quizplus.com/quiz/8077

Sample Questions

Q1) Projects also can be terminated by the sponsor or customer for financial situations.

A)True

B)False

Q2) The purpose of identifying and documenting lessons learned is to capitalize on the knowledge and experience gained on the project in order to

A) improve performance on future projects.

B) create a large database of information.

C) establish a procedure of identification and documentation.

D) keep project team members busy.

Q3) The purposes of __________ should be to determine whether the project provided the customer with the expected benefits, assess the level of customer satisfaction, and obtain any feedback that would be helpful in future business relationships with this customer or with other customers.

A) a post-project evaluation meeting with the customer or sponsor

B) a project progress meeting with project stakeholders

C) an analysis session with the project team

D) a pre-RFP meeting with the customer

To view all questions and flashcards with answers, click on the resource link above.

11

Chapter 10: The Project Manager

Available Study Resources on Quizplus for this Chatper

129 Verified Questions

129 Flashcards

Source URL: https://quizplus.com/quiz/8078

Sample Questions

Q1) ________ may be: initiated by the customer, initiated by the project team, caused by unanticipated occurrences during the performance of the project, or required by the users of the project results.

A) Reports

B) Changes

C) Project planning

D) Project scope documentation

Q2) Good project managers spend more time talking than listening.

A)True

B)False

Q3) Leadership is getting things done through others; the project manager achieves results by not trusting the project team.

A)True

B)False

Q4) The project manager can improve her or his ability to handle stress by keeping physically fit through regular exercise and good nutrition.

A)True

B)False

To view all questions and flashcards with answers, click on the resource link above.

Page 12

Chapter 11: The Project Team

Available Study Resources on Quizplus for this Chatper

225 Verified Questions

225 Flashcards

Source URL: https://quizplus.com/quiz/8079

Sample Questions

Q1) A potential conflict on projects is Organizational Issues where organizational issues can cause conflict. There may be disagreement over all the following except

A) the need for certain procedures established by the project manager.

B) ambiguous project communication.

C) from failure to make timely decisions.

D) payment schedules from the customer.

Q2) Team members need to be careful to jump to the first solution suggested or the most obvious solution.

A)True

B)False

Q3) Brainstorming hinders excitement, creativity, better solutions, and greater commitment.

A)True

B)False

Q4) Having a common goal such as the project objective can A) break the team apart.

B) increase the cost of the project.

C) enhance the differences of the team.

D) bring a diverse group together.

To view all questions and flashcards with answers, click on the resource link above. Page 13

Chapter 12: Project Communication and Documentation

Available Study Resources on Quizplus for this Chatper

121 Verified Questions

121 Flashcards

Source URL: https://quizplus.com/quiz/8080

Sample Questions

Q1) Allow time for interaction with the audience, if appropriate.

A)True

B)False

Q2) Verbal communication should be straightforward and unambiguous.

A)True

B)False

Q3) The project manager should summarize the meeting results at the end of the meeting.

A)True

B)False

Q4) Making sure the visual aids are readable from the most front seat in the room where the presentation will be given because the most important people will sit in the front.

A)True

B)False

Q5) Know the first two or three sentences of your presentation.

A)True

B)False

Q6) List some common barriers to effective listening:

Q7) List the most common types of project meetings.

Page 14

To view all questions and flashcards with answers, click on the resource link above.

Chapter 13: Project Management Organizational Structures

Available Study Resources on Quizplus for this Chatper

65 Verified Questions

65 Flashcards

Source URL: https://quizplus.com/quiz/8081

Sample Questions

Q1) A disadvantage of an autonomous project organizational structure is that project team members do not have a functional "home."

A)True

B)False

Q2) In _______,in most cases if an individual serves part-time on a project task force, the individual continues to perform her regular functional jobs.

A) an autonomous project organizational structure

B) a functional organizational structure

C) a matrix organizational structure

D) a project management office

Q3) A disadvantage of an autonomous project organizational structure is that there is a high level of knowledge transfer among projects.

A)True

B)False

Q4) A disadvantage of an autonomous project organizational structure is that individuals are dedicated to working on one project.

A)True

B)False

To view all questions and flashcards with answers, click on the resource link above. Page 15

Chapter 14: Project Management Information Systems

Available Study Resources on Quizplus for this Chatper

46 Verified Questions

46 Flashcards

Source URL: https://quizplus.com/quiz/8068

Sample Questions

Q1) Although all modern project management information systems allow project information to be posted and shared directly through the internet, there is no variance in the web-based tools they contain.

A)True

B)False

Q2) _________features of most systems often provide a suite of tools such as automatic e-mail notifications, collaboration management, customer collaboration, discussion forums, email integration, file attachments, international characters, message center, mobile access, multiple languages, and online meetings.

A) The communication

B) The budgeting and cost management

C) The sales and business development

D) The documentation management

Q3) Some systems allow very basic integration with a few popular information systems, whereas others provide sophisticated integration with distributed databases and even object-oriented databases.

A)True

B)False

To view all questions and flashcards with answers, click on the resource link above. Page 16

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
Project Management for Engineers Textbook Exam Questions - 1226 Verified Questions by Quizplus - Issuu