Operations Management is a comprehensive course that explores the principles, strategies, and techniques used to design, operate, and improve business processes within manufacturing and service organizations. Students will learn about key topics such as process analysis, capacity planning, inventory management, quality control, supply chain management, and lean operations. The course emphasizes both quantitative and qualitative decision-making skills, equipping learners to optimize resource use, enhance productivity, and achieve sustainable competitive advantage in dynamic marketplaces. Case studies and real-world examples are integrated to illustrate the practical application of operations management concepts.

Recommended Textbook

Successful Project Management 6th Edition by Jack Gido

Available Study Resources on Quizplus

13 Chapters

1197 Verified Questions

1197 Flashcards

Source URL: https://quizplus.com/study-set/3621

Page 2

Chapter 1: Project Management Concepts

Available Study Resources on Quizplus for this Chatper

79 Verified Questions

79 Flashcards

Source URL: https://quizplus.com/quiz/71896

Sample Questions

Q1) A project objective is the tangible end product that the project team must produce or deliver.

A)True

B)False

Answer: True

Q2) Determining the market for a product for a gain of 5% market share within 18 months and $20,000 budget.This is an example of a project objective.

A)True

B)False

Answer: True

Q3) The project scope document should include a list of deliverables and associated acceptance criteria.

A)True

B)False

Answer: True

Q4) Projects are constrained only by the scope, schedule, and budget.

A)True

B)False

Answer: False

To view all questions and flashcards with answers, click on the resource link above. Page 3

Chapter 2: Identifying and Selecting Projects

Available Study Resources on Quizplus for this Chatper

70 Verified Questions

70 Flashcards

Source URL: https://quizplus.com/quiz/71897

Sample Questions

Q1) The acceptance criteria describe the criteria necessary for the sponsor to approve the deliverables.

A)True

B)False

Answer: True

Q2) Disadvantages for doing a project may have a positive impact on an organization.

A)True

B)False Answer: True

Q3) Part of preparing a request for proposal is soliciting the request to potential bidders on the project.

A)True

B)False Answer: True

Q4) The RFP must include the customer requirements and the name of the sponsor's designee

A)True

B)False Answer: False

To view all questions and flashcards with answers, click on the resource link above. Page 4

Chapter 3: Developing Project Proposals

Available Study Resources on Quizplus for this Chatper

112 Verified Questions

112 Flashcards

Source URL: https://quizplus.com/quiz/71898

Sample Questions

Q1) Always put the client first.

A)True

B)False

Answer: True

Q2) Describe the differences between a complex proposal and a simplified proposal.

Answer: Responses will vary.They should contain a description of a complex project proposal and a simplified project proposal.All the minimum parts of a simplified project proposal are included in a complex project proposal, but not all complex project proposal sections are included in a simplified project proposal. A complex project proposal may contain hundreds of pages with charts, graphs, and tables to display the technical, management, and cost sections.The complex proposal may be in sections or volumes for organization.A simplified project proposal will include at a minimum a statement of the customer's need, assumptions, project scope, deliverables, schedule, price, risks, and expected benefits.

Q3) A specific proposed solution should be suggested for the customer's need.

A)True

B)False

Answer: False

To view all questions and flashcards with answers, click on the resource link above.

Chapter 4: Defining Scope, Quality, Responsibility, and Activity Sequence

Available Study Resources on Quizplus for this Chatper

129 Verified Questions

129 Flashcards

Source URL: https://quizplus.com/quiz/71899

Sample Questions

Q1) The WBS should be decomposed to a level that identifies individual work packages for

A)each person that planned the project.

B)each resource assigned to the project.

C)the level of detail specified by the customer.

D)each specific deliverable listed in the project scope document.

Q2) Describe the quality standards that must be included or referenced in the quality plan.

Q3) The project objective is usually defined in terms of the

A)all the constraints for the project.

B)end product or deliverable, schedule, and budget.

C)initiating, planning, executing, and controlling.

D)project scope.

Q4) The contractor or project team needs to gain agreement from on the project scope document.

A)the sponsor or customer

B)all the stakeholders

C)only the contractor's chief financial officer

D)only the subcontractors

6

To view all questions and flashcards with answers, click on the resource link above.

Chapter 5: Developing the Schedule

Available Study Resources on Quizplus for this Chatper

86 Verified Questions

86 Flashcards

Source URL: https://quizplus.com/quiz/71900

Sample Questions

Q1) Having the person who will be responsible for performing a specific activity estimate the duration for that activity from that person and that may be introduced by having one person estimate the durations for all of the activities.

A)takes more effort, creates a problem

B)gives the status of the project, sets best practices

C)generates a commitment , avoids any bias

D)elevates the placement perception, creates errors

Q2) As a part of the Scrum technique in agile project management, a sprint is usually one to four

A)days.

B)minutes.

C)weeks.

D)months.

Q3) Calculate the earliest finish for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.

A)day 5

B)day 3

C)day 1

D)Cannot be calculated based upon information given.

To view all questions and flashcards with answers, click on the resource link above.

Page 7

Chapter 6: Resource Utilization

Available Study Resources on Quizplus for this Chatper

22 Verified Questions

22 Flashcards

Source URL: https://quizplus.com/quiz/71901

Sample Questions

Q1) Resource-limited scheduling is a method for

A)developing a schedule that attempts to minimize the fluctuations in requirements for resources.

B)making sure all the resources do the same amount of work.

C)making sure every task has the same number of resources.

D)developing the shortest schedule when the number or amount of available resources is fixed and cannot be exceeded.

Q2) Resource utilization charts based on each activity's latest start time are said to be based

A)on availability times.

B)an as-late-as-possible ALAP) schedule.

C)on an as-soon-as-possible ASAP) schedule.

D)on a limited schedule plan.

Q3) The statement, "Network diagrams illustrate the technical constraints among activities," means the activities are constrained because

A)each of the activities are independent from the other activities.

B)one activity cannot be started until the predecessors are finished.

C)the activities use different resources to be completed.

D)some activities use the same resources that may not be available.

To view all questions and flashcards with answers, click on the resource link above.

Page 8

Chapter 7: Determining Costs, Budget, and Earned Value

Available Study Resources on Quizplus for this Chatper

69 Verified Questions

69 Flashcards

Source URL: https://quizplus.com/quiz/71902

Sample Questions

Q1) Which of the following is not a way to reduce the costs of activities:

A)reduce the scope or requirements.

B)substitute less expensive materials.

C)assign a person with less expertise or less experience to perform or help with the activity.

D)increase productivity through improved methods or technology.

Q2) Contingency costs in the project costs estimate, also referred to as , are to cover unexpected situations that may come up during the project, such as items that may have been overlooked when the initial project scope was defined, activities that may have to be redone because they may not work the first time redesigns), or a high probability or high impact risk that may occur.

A)auxiliary funds

B)withholding

C)reserves

D)capital funds

Q3) Large projects would have charge codes for the work package numbers to

A)have a place for other projects to charge expenses.

B)determine how the actual costs compare to the planned costs.

C)have resources be able to determine what tasks they should complete.

D)allow for cutting of the budget for the activities if need to cut the budget.

To view all questions and flashcards with answers, click on the resource link above. Page 9

Chapter 8: Managing Risk

Available Study Resources on Quizplus for this Chatper

45 Verified Questions

45 Flashcards

Source URL: https://quizplus.com/quiz/71903

Sample Questions

Q1) Establishing risk categories may help to identify and evaluate risks.List some categories to help identify risks.

Q2) is a rating of low, medium, or high based upon the expected probability of a risk occurring during the project.

A)The action trigger

B)The priority order

C)The mitigation plan

D)The likelihood of occurrence

Q3) Project prices and budgets should include to pay for additional costs associated with implementing response plans.

A)a padded budget

B)a contingency or management reserve

C)expenses for other charges in the office to help

D)extra overhead

Q4) A risk is an uncertain event that, if it occurs,

A)must be accepted.

B)can jeopardize accomplishing the project objective.

C)must be avoided.

D)helps to achieve the project objective.

To view all questions and flashcards with answers, click on the resource link above. Page 10

Chapter 9: Closing the Project

Available Study Resources on Quizplus for this Chatper

42 Verified Questions

42 Flashcards

Source URL: https://quizplus.com/quiz/71904

Sample Questions

Q1) The project manager should prepare a written performance evaluation of each member of the project team that mentions how each has

A)made mistakes in the problem and how much that mistake cost the organization.

B)expanded her or his knowledge as a result of the project assignment and identifies areas she or he needs to develop further.

C)interacted with other team members, especially where conflict has caused problems for reaching the final goals of the project.

D)contributed to the project with a list of activities and the time on each and an analysis of what was done Incorrectly on each activity.

Q2) Projects also can be terminated by the sponsor or customer due to a project return on investment increase.

A)True

B)False

Q3) There may be circumstances that require a project to be terminated before it is completed.

A)True

B)False

To view all questions and flashcards with answers, click on the resource link above.

11

Chapter 10: The Project Manager

Available Study Resources on Quizplus for this Chatper

129 Verified Questions

129 Flashcards

Source URL: https://quizplus.com/quiz/71905

Sample Questions

Q1) Despite the best laid plans, changes will still occur.

A)True

B)False

Q2) Volunteer -- contribute to the community or a specific cause and try your hand at developing leadership skills -- to develop the skills necessary to be an effective project manager.

A)True

B)False

Q3) Generally, the in the project that changes are identified, the their effect on accomplishing the project objective.

A)later, greater

B)later, lesser

C)earlier, greater

D)earlier, more severe

Q4) Read -- subscribe to journals or look up articles related to the skills you want to develop -- to develop the skills necessary to be an effective project manager.

A)True

B)False

To view all questions and flashcards with answers, click on the resource link above.

Page 12

Chapter 11: The Project Team

Available Study Resources on Quizplus for this Chatper

225 Verified Questions

225 Flashcards

Source URL: https://quizplus.com/quiz/71906

Sample Questions

Q1) In the stage of team development, members depend on the project manager to provide direction and structure.

A)forming

B)norming

C)storming

D)performing

Q2) It is important for team members or the project manager to communicate information to the customer.

A)True

B)False

Q3) Team members can also do things to support valuing diversity and the contributions of all team members.

A)True

B)False

Q4) The project team can initiate social events to celebrate project events, such as reaching a critical milestone.

A)True

B)False

Q5) List examples of situations that provide an opportunity for unethical behavior:

To view all questions and flashcards with answers, click on the resource link above. Page 13

Chapter 12: Project Communication and Documentation

Available Study Resources on Quizplus for this Chatper

124 Verified Questions

124 Flashcards

Source URL: https://quizplus.com/quiz/71907

Sample Questions

Q1) Written reports are verbal reports in communicating information about a project. A)just as important as B)not as important as C)more important than D)less effective than

Q2) The project manager should turn off his or her cell phone and other distractions.

A)True

B)False

Q3) When communicating verbally, a person must be careful not to use remarks, words, or phrases that can be construed to be sexist, racist, prejudicial, or offensive.

A)True

B)False

Q4) Verbal communication should be straightforward and unambiguous.

A)True

B)False

Q5) Build interest in your presentation.

A)True

B)False

To view all questions and flashcards with answers, click on the resource link above. Page 14

Chapter 13: Project Management Organizational Structures

Available Study Resources on Quizplus for this Chatper

65 Verified Questions

65 Flashcards

Source URL: https://quizplus.com/quiz/71908

Sample Questions

Q1) provides checks-and-balances and a fast response upon problem identification because it has both a horizontal project) and a vertical functional) path for the flow of information.

A)An autonomous project organizational structure

B)A functional organizational structure

C)A matrix organizational structure

D)A project management office

Q2) Companies with are in the projects business; they do not produce standard products.

A)an autonomous project organizational structure

B)a functional organizational structure

C)a matrix organizational structure

D)a project management office

Q3) is typically used in businesses that primarily sell and produce standard products.For example, a company that manufactures and sells video recorders.

A)An autonomous project organizational structure

B)A functional organizational structure

C)A matrix organizational structure

D)A project management office

To view all questions and flashcards with answers, click on the resource link above.

Page 15

Turn static files into dynamic content formats.

Create a flipbook
Operations Management Exam Preparation Guide - 1197 Verified Questions by Quizplus - Issuu