Course Introduction

Engineering Project Management equips students with essential principles and tools for planning, executing, and controlling technical projects within engineering environments. The course covers project life cycles, resource allocation, risk management, budgeting, scheduling, team leadership, and communication strategies. Students learn to apply industry-standard project management methodologies, such as PMBOK and Agile, through real-world case studies and team-based project simulations. Emphasis is placed on critical thinking, problem-solving, and the successful delivery of projects that meet technical, time, and budgetary constraints, preparing graduates for successful leadership roles in engineering industries.

Recommended Textbook

Successful Project Management with Microsoft Project 2010 5th Edition by Jack Gido

Available Study Resources on Quizplus

14 Chapters

1226 Verified Questions

1226 Flashcards

Source URL: https://quizplus.com/study-set/455 Page 2

Chapter 1: Project Management Concepts

Available Study Resources on Quizplus for this Chatper

74 Verified Questions

74 Flashcards

Source URL: https://quizplus.com/quiz/8069

Sample Questions

Q1) The estimated duration of the project is dependent upon the sequence of activities.

A)True

B)False

Answer: True

Q2) Describe what each of the following mean in project planning: what, how, who, how long, and how much.

Answer: Responses will vary.Responses should include the need to describe how the project scope will be accomplished within budget and on schedule and then that plan will be implemented with a project timeline.

Before jumping in and starting the project, the project team or contractor must take sufficient time to properly plan the project.

Q3) The schedule for a project is a timetable with only start times for tasks.

A)True

B)False

Answer: False

Q4) List examples of three projects.

Answer: Answers will vary.Response includes a deliverable, schedule, and budget.

To view all questions and flashcards with answers, click on the resource link above.

3

Chapter 2: Identifying and Selecting Projects

Available Study Resources on Quizplus for this Chatper

70 Verified Questions

70 Flashcards

Source URL: https://quizplus.com/quiz/8070

Sample Questions

Q1) The RFP should state the acceptance criteria the customer will use to determine if the project deliverables are completed according to the customer's requirements.

A)True

B)False

Answer: True

Q2) It is fair to meet with potential contractors and provide information about the potential project while developing the RFP.

A)True

B)False

Answer: True

Q3) The project purpose should

A) summarize the need and justification for the project.

B) state what is expected to be accomplished.

C) state the major end products or items expected to be produced.

D) be concise and create a vision for the end result of the project.

Answer: A

To view all questions and flashcards with answers, click on the resource link above. Page 4

Chapter 3: Developing Project Proposals

Available Study Resources on Quizplus for this Chatper

111 Verified Questions

111 Flashcards

Source URL: https://quizplus.com/quiz/8071

Sample Questions

Q1) Contractors may outsource some of the work to subcontractors or consultants to perform certain project tasks.

A)True

B)False

Answer: True

Q2) The amount of profit on a project is adjusted depending upon the amount of competition for a project.

A)True

B)False

Answer: True

Q3) Quantitative and qualitative benefits to the customer should be stated to help convince the customer of the value of the proposed result.

A)True

B)False

Answer: True

Q4) Successful contract opportunities are grounded in relationships.

A)True

B)False Answer: True

To view all questions and flashcards with answers, click on the resource link above. Page 5

Chapter 4: Defining Scope, Quality, Responsibility, and Activity Sequence

Available Study Resources on Quizplus for this Chatper

129 Verified Questions

129 Flashcards

Source URL: https://quizplus.com/quiz/8072

Sample Questions

Q1) Each box for an activity in a network diagram is assigned

A) the next number after its predecessor's number.

B) a unique activity number.

C) an integral number.

D) a rational number

Q2) The ___________ states the specific deliverable that is expected to be completed from the work activities associated with each lowest level-work package.

A) WBS in an indentured list format

B) WBS in a hierarchical graphic chart format

C) responsibility assignment matrix

D) network diagram

Q3) The __________ defines the major tasks or work elements that will need to be performed to accomplish the work that needs to be done and produce all the project deliverables.

A) statement of work

B) project scope document

C) network diagram

D) work breakdown structure

To view all questions and flashcards with answers, click on the resource link above. Page 6

Chapter 5: Developing the Schedule

Available Study Resources on Quizplus for this Chatper

79 Verified Questions

79 Flashcards

Source URL: https://quizplus.com/quiz/8073

Sample Questions

Q1) Eliminating negative slack by reducing durations of activities will involve a trade-off in the form of

A) no change in costs and an increase in scope.

B) a decrease in costs and an expansion in scope.

C) an increase in costs or a reduction in scope.

D) an decrease in costs and no change in scope.

Q2) It is necessary to monitor the progress to ensure that everything is going according to the plan.

A)True

B)False

Q3) The amount of slack should determine the priority with which these concentrated efforts are applied.

A)True

B)False

Q4) When estimating resources for activities to estimate the activity's duration, the A) availability of each resource has to be taken into account.

B) name of each resource has to be taken into account.

C) cost of each resource has to be taken into account.

D) security clearance of each resource has to be taken into account.

To view all questions and flashcards with answers, click on the resource link above. Page 7

Chapter 6: Resource Utilization

Available Study Resources on Quizplus for this Chatper

21 Verified Questions

21 Flashcards

Source URL: https://quizplus.com/quiz/8074

Sample Questions

Q1) The statement, "Network diagrams illustrate the technical constraints among activities," means the activities are constrained because

A) each of the activities are independent from the other activities.

B) one activity cannot be started until the predecessors are finished.

C) the activities use different resources to be completed.

D) some activities use the same resources that may not be available.

Q2) In addition to showing the technical constraints among activities, how does the network logic also take into account resource constraints?

A) Activities that use the same resource may not be able to occur in parallel to each other.

B) Activities that use different resources may be shown in a serial relationship.

C) The activities could be shown in a loop relationship.

D) Resources that are unlimited are not shown in a resource assignment.

Q3) Resource-limited scheduling will not extend the project completion time if necessary in order to keep within the resource limits.

A)True

B)False

To view all questions and flashcards with answers, click on the resource link above.

Chapter 7: Determining Costs, Budget, and Earned Value

Available Study Resources on Quizplus for this Chatper

69 Verified Questions

69 Flashcards

Source URL: https://quizplus.com/quiz/8075

Sample Questions

Q1) In many cases, there will be a tradeoff-reducing cost variances will involve a reduction in project scope or a delay in the project schedule.

A)True

B)False

Q2) It's crucial that cost variances and inefficiencies be identified early so that A) corrective action can be taken before the situation gets worse.

B) negotiations can take place for the contract.

C) the project can be monitored for self-correction.

D) time is not applied to the project.

Q3) The total project cost is often estimated during the_______ phase of the project or when the project charter or a proposal is prepared

A) initiating

B) planning

C) performing

D) closing

Q4) Committed costs are also known as discharged or postponed costs.

A)True

B)False

To view all questions and flashcards with answers, click on the resource link above.

9

Chapter 8: Managing Risk

Available Study Resources on Quizplus for this Chatper

45 Verified Questions

45 Flashcards

Source URL: https://quizplus.com/quiz/8076

Sample Questions

Q1) _________ includes taking action to prevent or minimize the likelihood of occurrence or the impact of such unfavorable events.

A) Managing risk

B) Taking chances

C) Identifying the trigger point

D) Naming the person responsible for the risk response plan

Q2) Risks_____ should be given higher priority because if the risk occurs, it would have a greater impact on the schedule than if it was associated with activities on a path that has a large positive value of total slack.

A) that occur first in the project

B) that affect the most costly activities

C) on the critical path

D) that affect the activities near the end of the project

Q3) The project manager needs to set the tone for encouraging open and timely discussion of risks among the project team.

A)True

B)False

To view all questions and flashcards with answers, click on the resource link above. Page 10

Chapter 9: Closing the Project

Available Study Resources on Quizplus for this Chatper

42 Verified Questions

42 Flashcards

Source URL: https://quizplus.com/quiz/8077

Sample Questions

Q1) The purposes of __________ should be to determine whether the project provided the customer with the expected benefits, assess the level of customer satisfaction, and obtain any feedback that would be helpful in future business relationships with this customer or with other customers.

A) a post-project evaluation meeting with the customer or sponsor

B) a project progress meeting with project stakeholders

C) an analysis session with the project team

D) a pre-RFP meeting with the customer

Q2) Documentation of lessons learned should be done on an ongoing basis throughout the planning and performing phases of the project.

A)True

B)False

Q3) The open-ended question post-project evaluation meeting should contain an opportunity to talk about possible additional projects and assume permission to use the customer as a reference with potential customers.

A)True

B)False

Q4) What type of knowledge base system should be established by the project organization?

To view all questions and flashcards with answers, click on the resource link above. Page 11

Chapter 10: The Project Manager

Available Study Resources on Quizplus for this Chatper

129 Verified Questions

129 Flashcards

Source URL: https://quizplus.com/quiz/8078

Sample Questions

Q1) The project manager is a key ingredient in the success of a project.

A)True

B)False

Q2) The effective project manager has a commitment to limiting the training and development of people working on the project.

A)True

B)False

Q3) A good project manager believes that all individuals are valuable to the organization and that they can make greater contributions through continuous learning.

A)True

B)False

Q4) Effective and frequent communication is crucial for keeping the project moving, identifying potential problems, soliciting suggestions to improve project performance, keeping abreast of customer satisfaction, and avoiding surprises.

A)True

B)False

Q5) Describe at least three potential subjects of negotiations in which a project manager would participate for a project.

To view all questions and flashcards with answers, click on the resource link above. Page 12

Chapter 11: The Project Team

Available Study Resources on Quizplus for this Chatper

225 Verified Questions

225 Flashcards

Source URL: https://quizplus.com/quiz/8079

Sample Questions

Q1) Brainstorming is a technique used in problem solving in which all members of a group contribute spontaneous ideas.

A)True

B)False

Q2) A punitive process should be established for individuals to report any actions by others that they think is unethical.

A)True

B)False

Q3) Conflict is bad and should be avoided.

A)True

B)False

Q4) Team members can also do things to support valuing diversity and the contributions of all team members.

A)True

B)False

Q5) During the brainstorming sessions, some people will come up with ideas that build on ideas previously mentioned by others.

A)True

B)False

To view all questions and flashcards with answers, click on the resource link above. Page 13

Chapter 12: Project Communication and Documentation

Available Study Resources on Quizplus for this Chatper

121 Verified Questions

121 Flashcards

Source URL: https://quizplus.com/quiz/8080

Sample Questions

Q1) Distribute an agenda well in advance of the project meeting.

A)True

B)False

Q2) It is important to keep in mind that a progress report is not

A) a list of completed milestones.

B) an activity report.

C) the current status of project performance.

D) a list of milestones expected to be achieved by the next meeting.

Q3) Projects that involve a design phase, such as an information system project, may require one or more technical ________ to ensure that the customer agrees with or approves of the design.

A) project status review meetings

B) problem-solving meetings

C) design review meetings

D) post-project evaluation meetings

Q4) Sum up your points on a particular item before moving on to the next item on your outline.

A)True

B)False

Q5) List the most common types of project meetings.

Page 14

To view all questions and flashcards with answers, click on the resource link above.

Chapter 13: Project Management Organizational Structures

Available Study Resources on Quizplus for this Chatper

65 Verified Questions

65 Flashcards

Source URL: https://quizplus.com/quiz/8081

Sample Questions

Q1) _________ allows efficient utilization of resources by having individuals from various functions assigned to work on specific projects.

A) an autonomous project organizational structure

B) a functional organizational structure

C) a matrix organizational structure

D) a project management office

Q2) A disadvantage of a functional organizational structure is that there is a stronger allegiance to the function than to the project or the customer.

A)True

B)False

Q3) In _______, project managers come under the projects component of the organization.

A) an autonomous project organizational structure

B) a functional organizational structure

C) a matrix organizational structure

D) a project management office

To view all questions and flashcards with answers, click on the resource link above. Page 15

Chapter 14: Project Management Information Systems

Available Study Resources on Quizplus for this Chatper

46 Verified Questions

46 Flashcards

Source URL: https://quizplus.com/quiz/8068

Sample Questions

Q1) When selecting a PMIS, the ___________ considerations are the memory required, the amount of hard disk space required, the processing speed and power required, the type of graphics display needed, and operating system requirements.

A) procedure requirements

B) installation requirements

C) adoption requirements

D) integration requirements

Q2) An advantage of a project management information system is the affordability because excellent PC-based project management information systems can be purchased for just a few hundred dollars.

A)True

B)False

Q3) Project management information systems can maintain a resource list consisting of resource names, the maximum amount of time resources are available, standard and overtime rates for resources, accrual methods, and textual descriptions of the resources.

A)True

B)False

To view all questions and flashcards with answers, click on the resource link above.

16

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
Engineering Project Management Mock Exam - 1226 Verified Questions by Quizplus - Issuu