Engineering Project Management

Final Test Solutions

Course Introduction

Engineering Project Management introduces students to the essential principles and practices involved in planning, organizing, and executing engineering projects. The course covers topics such as project lifecycle management, scheduling, budgeting, resource allocation, risk assessment, quality control, and team leadership. Through a combination of theoretical concepts and practical case studies, students learn to apply project management tools and techniques specific to engineering environments, emphasizing effective communication, problem-solving, and decision-making skills. By the end of the course, students are equipped to manage complex engineering projects from conception through completion, ensuring successful delivery within scope, time, and budget constraints.

Recommended Textbook

Project Management in Practice 5th Edition by Jack R. Meredith

Available Study Resources on Quizplus

8 Chapters

533 Verified Questions

533 Flashcards

Source URL: https://quizplus.com/study-set/1630

Page 2

Chapter 1: The World of Project Management

Available Study Resources on Quizplus for this Chatper

70 Verified Questions

70 Flashcards

Source URL: https://quizplus.com/quiz/32366

Sample Questions

Q1) Project budgets are primarily modifications of budgets for the same activity in the previous period.

A)True

B)False

Answer: False

Q2) A disadvantage of using the payback period method for selecting projects is that it cannot reflect the time-value of money.

A)True

B)False

Answer: True

Q3) One reason for the emphasis on project management is that tasks fit neatly into business-as-usual.

A)True

B)False

Answer: False

Q4) Explain what the third alternative is in negotiation.

Answer: Not Answered

Q5) Briefly explain the project portfolio process.

Answer: Not Answered

To view all questions and flashcards with answers, click on the resource link above. Page 3

Chapter 2: The Manager, the Organization, and the Team

Available Study Resources on Quizplus for this Chatper

68 Verified Questions

68 Flashcards

Source URL: https://quizplus.com/quiz/32367

Sample Questions

Q1) Which of the following is not true concerning the difference between the project manager (PM) and the traditional manager TM)?

A) the PM is a facilitator the TM is a technical supervisor

B) the PM is a generalist the TM is a specialist

C) the PM must be able to integrate tasks; the TM must be able to analyze tasks

D) the PM uses an analytical approach the TM uses a systems approach

E) all of the above are true

Answer: D

Q2) The three primary goals of any project are:

A) profit, schedule, quality

B) schedule, budget, quality

C) performance, budget, schedule

D) performance, quality, schedule

E) budget, quality, profit

Answer: C

Q3) An advantage of pure project organization is its great depth of technical knowledge.

A)True

B)False

Answer: False

To view all questions and flashcards with answers, click on the resource link above.

Page 4

Chapter 3: Planning the Project

Available Study Resources on Quizplus for this Chatper

63 Verified Questions

63 Flashcards

Source URL: https://quizplus.com/quiz/32368

Sample Questions

Q1) A limitation of traditional project management planning tools is that they do not address the flow of information.

A)True

B)False

Answer: True

Q2) Which of the following is not an important advantage of empowerment?

A) high quality solutions

B) micromanagement avoided

C) high degree of worker specialization

D) synergistic solutions

E) timely feedback

Answer: C

Q3) The details of the project work force are discussed in the Resource Requirements section of the project master plan.

A)True

B)False

Answer: False

Q4) Explain the process of developing a WBS.

Answer: Not Answered

To view all questions and flashcards with answers, click on the resource link above. Page 5

Chapter 4: Budgeting the Project

Available Study Resources on Quizplus for this Chatper

64 Verified Questions

64 Flashcards

Source URL: https://quizplus.com/quiz/32369

Sample Questions

Q1) Organizations can use both top-down and bottom-up budgeting.

A)True

B)False

Q2) After major risk are identified which of the following data should NOT be obtained for analysis

A) probability of each risk occurring

B) Range or distribution of possible outcomes

C) probability of each outcome

D) the expected time of each outcome

E) the person responsible for each outcome

Q3) The PMI does not devote much coverage to risk management in the PMBOK

A)True

B)False

Q4) Briefly contrast the three different perspectives cost can be viewed from.

Q5) List the steps in performing FMEA.

Q6) A key advantage of top-down budgeting is that the overall budget costs can be estimated quite accurately.

A)True

B)False

Q7) Define Top-down and Bottom-Up budgeting.

To view all questions and flashcards with answers, click on the resource link above. Page 6

Chapter 5: Scheduling the Project

Available Study Resources on Quizplus for this Chatper

63 Verified Questions

63 Flashcards

Source URL: https://quizplus.com/quiz/32370

Sample Questions

Q1) Milestones are not depended upon the predecessor activities in the project plan.

A)True

B)False

Q2) The amount of time an activity can be delayed without affecting the start time of any successor activity is known as free slack.

A)True

B)False

Q3) Networks are usually drawn with a "Start" node to the right and a "Finish" node to the left.

A)True

B)False

Q4) A big advantage of AON networks is that they are easier to draw.

A)True

B)False

Q5) To manage a project successfully, the project manager need only pay close attention to tasks on the critical path.

A)True

B)False

Q6) What is a merger and what problems do mergers create?

Page 7

To view all questions and flashcards with answers, click on the resource link above.

Chapter 6: Allocating Resources to the Project

Available Study Resources on Quizplus for this Chatper

66 Verified Questions

66 Flashcards

Source URL: https://quizplus.com/quiz/32371

Sample Questions

Q1) The as late as possible priority rule is considered the standard scheduling rule.

A)True

B)False

Q2) Projects often compete with each other for the same resources.

A)True

B)False

Q3) Allocating specific, limited resources to specific activities is called

A) resource allocation

B) resource leveling

C) resource tracking

D) expediting a project

E) crashing a project

Q4) Crashing non-critical activities will influence project duration.

A)True

B)False

Q5) One limitation of Microsoft Project is that all resources must share the same availability calendar.

A)True

B)False

To view all questions and flashcards with answers, click on the resource link above. Page 8

Chapter 7: Monitoring and Controlling the Project

Available Study Resources on Quizplus for this Chatper

72 Verified Questions

72 Flashcards

Source URL: https://quizplus.com/quiz/32372

Sample Questions

Q1) Statistical quality control techniques can be helpful for determining what size variances are significant.

A)True

B)False

Q2) Define the terms monitoring and control.

Q3) Everyone associated with the project should receive the same information.

A)True

B)False

Q4) Which of the following is not an objective mentioned in the text for data gathered from monitoring?

A) promoting team members

B) keeping management informed

C) auditing

D) learning from mistakes

E) control

Q5) One way of linking planning and control is to monitor project progress on the MSP Gantt chart.

A)True

B)False

Q6) Why is control difficult?

Page 9

To view all questions and flashcards with answers, click on the resource link above.

Chapter 8: Evaluating and Terminating the Project

Available Study Resources on Quizplus for this Chatper

67 Verified Questions

67 Flashcards

Source URL: https://quizplus.com/quiz/32373

Sample Questions

Q1) According to research, future potential is an important dimension of project success.

A)True

B)False

Q2) Project audits are typically very useful in the initiation project state.

A)True

B)False

Q3) The general audit is usually performed by a person or team with special technical skills.

A)True

B)False

Q4) Which of the following is not a type of project termination mentioned in the text?

A) project extinction

B) termination-by-addition

C) termination-by-integration

D) termination-by-starvation

E) termination-by-elimination

Q5) What content should be included in the audit report?

Q6) What criteria should be included in evaluating a project?

To view all questions and flashcards with answers, click on the resource link above. Page 10

Turn static files into dynamic content formats.

Create a flipbook
Engineering Project Management Final Test Solutions - 533 Verified Questions by Quizplus - Issuu