PPP Project Water Resources Sectors 2023 | Directorate Water Resources Infrastructure Financing

Page 1

PPP PROJECT WATER

SCOPE OF PROJECT ON WATER R


RESOURCES SECTOR

RESOURCES INFRASTRUCTURE


Lhok Guci Irrigation

Location: West Aceh R

Status: Preliminary Study - OBC

Location of Lhok Guci Irrigation System

PROJECT PROFILE GCA

Minister of Public Works & Housing

Partnership scheme

Design-Build-Rehabilitation-Finance-OperateMaintenance-Transfer (DBRFOMT)

Project Cost *

IDR 4.09 Trillion/ USD 263.25 Million

Concession Period

16 years: 3 years of Construction and 13 years of Operation and Maintenance

Return of Investment Scheme

Availability Payment

IRR Project

9.33%

Desc: * Indicative according to the current SP – OBC Draft

INDICATIVE PROJECT TIMELINE

P

1. Development secondary m networks, Maintenance ( 2. Design and r Guci irrigatio built; 3. Management irrigation net maintenance, 4. Preparation Maintenance Irrigation Area and 5. Provision of equipment for


System PPP Project

Region, Aceh Province

PPP SCOPE

of both primary and main networks, tertiary and Operation and (OM) facilities; rehabilitation of the Lhok on network that has been

of the entire 12,700 Ha twork, including operation, and monitoring activities; of Operation and Documents and the a Data Book for Lhok Guci;

personnel and supporting r OM.

PROJECT DESCRIPTION The Lhok Guci Irrigation Area belongs to the National Strategic Projects and it located in West Aceh, Aceh Province. The following are some of the benefit of the development of Lhok Guci Irrigation: (i) Potential irrigation for up to 18,542 Ha, (ii) Incrase of agricultural productivity and Crop Index (CI) for food security. The current existing design for Lhok Guci irrigation system can irrigate up to 12,700 Ha in the left and right bank of the Krueng Meurebo River. The irrigation system covers a potential area of 11,700 Ha on the right bank and 1,000 Ha on the left bank of the Krueng Meureubo River. The Lhok Guci irrigation project is the first proposed irrigation system project to be constructed, operated, and maintained through PPP scheme in the Aceh Province.

PROJECT STRUCTURE


Komering Irrigation System Unsolicited PPP Project Location: Region of East Ogan Komering Ulu and Ogan Komering Komering Ilir, South Sumatera Province Region of Way Kanan, Lampung Province

PROJECT DESCRIPTION Rehabilitation of irrigation networks spread across Komering irrigation area of 53,148 Ha and OM of 59,148 Ha + 8,500 Ha (JICA Loan, OM year 2028). The project includes implementation of Smart Irrigation Asset Management System. PROJECT STRUCTURE

PROJECT PROFILE Minister of Public Works & Housing

GCA

Sharia Regress Agreement

Design-RehabilitationBuild-Finance-OperateMaintenance-Transfer (DRBFOMT)

Partnership scheme Project Cost*

IDR 1.65 Trillion / USD 106.22 Million

Concession Period

16 years: 3 years of Construction/ Rehabilitation and 13 years of OM

Return of Investment Scheme

Availability Payment

IRR Project

10.83%

MPWH

Availability Payment

Sharia PPP Agreement Sharia Guarantee Agreement Investor

Sharia Lenders

Empowerment of Existing OM Personnel

SPV

Equity

Evaluation of Service Level Agreement

Debt

Rehabilitazion

OM

Irrigation Service

INDICATIVE PROJECT TIMELINE Current Status

Q2 2022

Q2 2022

Submission of LoI and Pre-FS

Pre-FS Evaluation and Issuance of Letter to Proceed

Q3 2022 – Q1 2023

FS by Project Initiator

Q3-Q4 2022

Q2 2023

Q4 2023 – Q1 2024

Q2-Q3 2024

Coordination for Syariah Scheme

Evaluation of FS Document

Tender Preparation and PQ

RfP

Q3 2024

Bid Award and Signing

Q4 2024 – Q1 2025

Q1 2025Q4 2027

Financial Close

Rehabilitati on and Services


Revitalization and Modernization of High Level Diversion (HLD) Interconnection Channel Unsolicited PPP Project Location: Region of West Lombok, Central Lombok, and East Lombok, West Nusa Tenggara Province

PROJECT DESCRIPTION The revitalization, Operation and Maintenance of HLD interconnection channel includes the upper HLD (Babak-Renggung-Rutus) & the lower HLD (Jangkok-Jurang Sate-Jurang Batu).

PROJECT PROFILE

PROJECT STRUCTURE

GCA

Minister of Public Works & Housing

Partnership scheme

Rehabilitation-DesignBuild-Finance-OperateMaintenance-Transfer (RDBFOMT)

Investment Cost

IDR 1.57 Trillion / USD 101.07 Million

Concession Period

16 years (3 years construction + 13 years operation and maintenance)

Sharia Regress Agreement

MPWH

Availability Payment

Sharia PPP Agreement Sharia Guarantee Agreement

Return of Investment Scheme

Availability Payment

IRR Project

10.74%

Investor

Sharia Lenders

Empowerment of Existing OM Personnel

SPV

Equity

Evaluation of Service Level Agreement

Debt

Rehabilitazion

OM

Irrigation Service

INDICATIVE PROJECT TIMELINE Current Status Q2 2022

Q2 2022

Submission of LoI and Pre-FS

Pre-FS Evaluation and Issuance of Letter to Proceed

Q3 2022 – Q1 2023

FS by Project Initiator

Q1 - Q4 2023

Q4 2023 – Q1 2024

Evaluation of FS Document

Tender Preparation and PQ

Q2–Q4 2024

Q4 2024

RfP

Bid Award and Signing

Q1-Q2 2025

Financial Close

Q3 2025 – Q3 2028

Rehabilitati on and Services


Merangin Dam Location: Region of Merangin, Jambi Province

PROJECT DESCRIPTION Merangin Dam is located in Batanghari River Basin. The benefits of the dam are for irrigattion of 12.000 Ha; raw water supply for drinking to 2 m3/s; to reduce flooding to 200 m3/s; Hydropower to 90-107,5 MW; and tourism. PROJECT STRUCTURE

PROJECT PROFILE GCA

Minister of Public Works & Housing

Partnership scheme

Design-Build-FinanceOperate-MaintenanceTransfer (DBFOMT)

PPP Project Scope

Multipurpose Dam

Project Cost *) Indication

IDR 6.58 Trillion* / USD 438.36 Million

Concession Period

6 years of construction and inundation period, 30 years of operation

Return of Investment Scheme

Availability Payment

Equity IRR *) Indication

14.1%*

INDICATIVE PROJECT TIMELINE Current Status Q2 2022

Preliminary Study

Q4 2019

Q2 – Q4 2021

Q2 2022 – Q4 2023

Q1-Q2 2024

Q3 – Q4 2024

Q2-Q3 2024

Outline Business Case

Preparation of Project Development Facility

Final Business Case

PQ

RfP

Bid Award

Q3 2024

Signing

Q4 2024 – Q1 2025

Q1 2025Q4 2027

Financial Close

Construction and Impounding


Bodri Dam Location: Region of Kendal, Central Java Province

PROJECT DESCRIPTION The Bodri Dam is located in Kendal Regency, Central Java, and is connected to 12 rivers. The benefits of the dam include potential irrigation area for up to 8,861 Ha, raw water supply for Kendal Regency of up to 0.497 m3/s, increase in crop intensity from 262.35% to 300%, potential power generation of up to 3.2 MW, reduction in flooding by 10.26% (Q1000), as well as recreational and tourism opportunities.

PROJECT STRUCTURE

PROJECT PROFILE GCA

Minister of Public Works & Housing

Partnership scheme

Design-Build-FinanceOperate-MaintenanceTransfer (DBFOMT)

Project Cost

IDR 1.74 Trillion / USD 112,28 Million

Concession Period

4 years of construction, 2 years of dam impounding, and 12 years of maintenance

Return of Investment Scheme

Availability Payment

IRR Project

10.13%

INDICATIVE PROJECT TIMELINE Current Status 2020

Preliminary Study

2020

Outline Business Case

Q4 2021

FBC

Q1 2022Q2 2024

Q3 2024

Q3 2024

Q3 2024

Readiness Criteria (Environmental impact assessment & Location determination)

PQ

RfP

Bid Award

Q2 2025

Q2 – Q4 2025

Q4 2025Q4 2031

Signing

Financial Close

Construction and Impounding


Jambo Aye Irrigation System PPP Project Location: North Aceh and East Aceh, Aceh Province

PROJECT DESCRIPTION Jambo Aye irrigation system is located in the North and East Aceh Regency, Aceh Province. The exact location of the dam is in the Rumoh Rayeuk Village, Langkahan District, North Aceh Regency. The total potential irrigation area of the Jambo Aye irrigation system is 24,360 Ha which is situated on the left and right banks of Arakundo River. PROJECT STRUCTURE

PROJECT PROFILE GCA

Minister of Public Works & Housing

Partnership scheme

Design-Build-FinanceOperate-MaintenanceTransfer (DBFOMT) *

Project Cost*

• Indicative CAPEX: IDR 263 Billion * • Indicative OPEX: TBD

Concession Period

TBD

Return of Investment Scheme

Availability Payment

IRR Project

TBD

INDICATIVE PROJECT TIMELINE Current Status Q4 2023Q1 2024

Q2-Q3 2022

Preliminary Study

FBC

Q4 2024

Tender Preparation

Q4 2024

PQ

Q4 2024

Q4 2024

Q1 2025

Q2-Q3 2025

RfP

Bid Award

Signing

Financial Close

Q4 2025 – Q4 2028

Construction


Bintang Bano Dam Maintenance And Provision Mini Hydropower Plant Infrastructure Location: Region of West Sumbawa, West Nusa Tenggara Province

PROJECT DESCRIPTION DMPH Bintang Bano is the first Unsolicited Water Resource PPP Project that planned to be transacted on this year using a user charge return on investment scheme. PPP project scope are BWS NT-1 Sumbawa (MPWH) will be responsible for dam operation, while dam maintenance will be the responsible of SPC and DBFOMT Mini Hydropower Plant Potential Electricity from MHPP: 6.3 MW (3 x 2.1 MW). PROJECT PROFILE

PROJECT STRUCTURE

GCA

Minister of Public Works & Housing

Partnership scheme

Design-Build-FinanceOperate-MaintenanceTransfer (DBFOMT)

Electricity Capacity

6,3 MW

Project Cost

IDR 170,02 Billion / USD 10.95 Million

Concession Period

27 years and 2 months, consist of: 2 years and 2 months construction period, 25 Years take or pay

Return of Investment Scheme

User Charge

Project IRR

12.50%

INDICATIVE PROJECT TIMELINE Current Status

2020

Q1-Q2 2021

Q1 2021

Q4 2021 – Q3 2022

Pre-FS

Evaluation of FS

Issuance of Initiator’s Approval Letter

Tender Preparation

Q4 2022

Q1 – Q4 2023

Q4 2023

PreQualification

Tender Process

Bid Award

Q2 2024

PPA and PPP Signing Agreement

Q2 2025

Q2 2025Q3 2026

Financial Close

Construction


Hydropower Plant Infrastructure Delivery on Tiga Dihaji Dam Location: South Ogan Komering Ulu, Regency South Sumatera Province PROJECT DESCRIPTION The Project is located on Tiga Dihaji Dam, South Ogan Komering Ulu Regency, South Sumatera Province. The PPP Project of Tiga Dihaji Hydro Power Plant (HPP) is proposed through Unsolicited with Design, Build, Finance, Operate, Maintain and Transfer (DBFOMT) scheme. It is estimated will generate electricity 40 MW. PROJECT PROFILE

GCA

Minister of Public Works & Housing

Partnership scheme

Design-Build-FinanceOperate-MaintenanceTransfer (DBFOMT)

Electricity Capacity

40 MW

Project Cost

IDR 1.12 Trillion / USD 74.97 Million

Concession Period

2 Years of Construction and 25 Years of Service Period

Return of Investment Scheme

User Charge

IRR Project

12.50%

INDICATIVE PROJECT TIMELINE

PROJECT STRUCTURE


Jenelata Mini Hydropower Plant Location: Region of Gowa Regency, South Sulawesi

PROJECT DESCRIPTION

Jenelata Dam is located in Jeneberang River. This project is utilization of PUPR dam asset and also became PPP pilot project in application of Environmental, Social and Governance (ESG) concept. PROJECT STRUCTURE

PROJECT PROFILE GCA

Minister of Public Works & Housing

Partnership scheme

Design-Build-FinanceOperate-MaintenanceTransfer (DBFOMT) of hydropower

Electricity Capacity

7 MW

Project Cost

IDR 134 Billion / USD 8.9 Million

Concession Period

2 years of Construction and 25 Years of Operation Period

Return of Investment Scheme

User Charge

IRR Project

12.50%

INDICATIVE PROJECT TIMELINE Current Status

Q1 Q4 2022

Q1-Q4 2023

Q1 –Q4 2024

Q1-Q4 2025

Q1-Q2 2026

Q3 –Q4 2026

Q1-Q4 2027

Outline Business Case

Final Business Case

Tender Document Preparation

Update FBC & Tender Preparation

PQ & RFP

PPP & PPA Signing

Financial Close

Q1 2028 – Q4 2029

Construction & Test Commisioning

Q1 2030

COD


Leuwikeris Hydropower Plant Location: Ciamis Regency, West Java Province

PROJECT DESCRIPTION The Project is located on Leuwikeris Dam, Ciamis Regency, West Java. The PPP Project of Leuwikeris Minihydro Power Plant (HPP) is proposed through Unsolicited with Design, Build, Finance, Operate, Maintain and Transfer (DBFOMT) scheme. It is estimated will generate electricity 7,4 MW. PROJECT PROFILE GCA

Minister of Public Works & Housing

Partnership scheme

Design-Build-FinanceOperate-MaintenanceTransfer (DBFOMT)

Electricity Capacity

7,4 MW

Project Cost

IDR 225.38 Billion / USD 14.51 Million

Concession Period

2 Years of Construction and 25 Years of Service Period

Return of Investment Scheme

User Charge

IRR Project

12.50%

INDICATIVE PROJECT TIMELINE

PROJECT STRUCTURE


Karalloe Mini Hydropower Plant Location: Gowa Regency, South Sulawesi

PROJECT DESCRIPTION Karalloe Dam is located in Jeneberang River. The benefits of the dam are for irrigattion of 7.007 Ha; raw water supply for drinking to 0,4 m3/s; reducing flood up to 49 m3/s; and Mini Hydropower with capacity 4,32 MW. PROJECT PROFILE

PROJECT STRUCTURE

GCA

Minister of Public Works & Housing

Partnership scheme

Design-Build-FinanceOperate-MaintenanceTransfer (DBFOMT)

Electricity Capacity

4.32 MW

Project Cost

IDR 126.68 Billion / USD 8.15 Million

Concession Period

1 Years of Construction and 25 Years of Operation Period

Return of Investment Scheme

User Charge

IRR Project

12.36%

INDICATIVE PROJECT TIMELINE Current Status Q1-Q4 2023

Pre-FS

Q4 2023– Q2 024

Q3 –Q4 2024

Q4 2024

Q2 2024

Q2 2025

Q2 2025

FS

GCA Approval & Preparation of Procurement

PreQualification

Bid Award

PPP Signing

PPA Signing

Q4 2025 – Q4 2026

Q4 2026 – Q4 2027

Construction Financial Close


Temef Mini Hydropower Plant Location: Region of South Timor Tengah, East Nusa Tenggara

PROJECT DESCRIPTION

Temef Dam is located in Benanain River. The benefits of the dam are for irrigattion of 4.500 Ha; raw water supply for drinking to 0,13 m3/s; reducing flood up to 230 m3/s; and Hydropower with capacity 1, 68 MW. PROJECT PROFILE

PROJECT STRUCTURE

GCA

Minister of Public Works & Housing

Partnership scheme

Design-Build-FinanceOperate-MaintenanceTransfer (DBFOMT)

Electricity Capacity

1.68 MW

Project Cost

IDR 55 Billion / USD 3.54 Million

Concession Period

8 Months of Construction and 25 Years of Operation Period

Return of Investment Scheme

User Charge

IRR Project

12.2%

INDICATIVE PROJECT TIMELINE Current Status Q1-Q4 2023

Pre-FS

Q4 2023– Q2 024

Q3 –Q4 2024

Q4 2024

Q2 2024

Q2 2025

Q2 2025

FS

GCA Approval & Preparation of Procurement

PreQualification

Bid Award

PPP Signing

PPA Signing

Q4 2025 – Q4 2026

Q4 2026 – Q4 2027

Construction Financial Close


Construction of Hydropower Dam in Papua Province Location: Region of Mimika Regency, Central Papua Province

PROJECT DESCRIPTION Yachiyo Engineering Co, LTD, a company from Japan, expressed interest in investing in dam and hydropower projects in Central Papua Province by sending a Letter of Intent to the Minister of Public Works and Public Housing. It is planned that this project will be able to produce a dam and a hydropower plant that will generate 639 MW of electricity. PROJECT PROFILE

PROJECT STRUCTURE

GCA

Minister of Public Works and Housing

Partnership scheme

Build-OperateTransfer (BOT)

Electricity Capacity

639 MW

Project Cost

IDR 18.29 Trillion / USD 1.18 Billion

Concession Period

36 years including 6 years for construction and 30 years for O&M

Return of Investment Scheme

User Charge (power sales to PT. FI)

Project IRR

12.02%

INDICATIVE PROJECT TIMELINE Current Status

Q4 2022Q1 2024

Q1 2024

Q1 2024

Q2 2024

Q2 2024

Q2 2024

Q3 2024

Q3 2024

Preparation of FS

Evaluation of FS and Preparation of Procurement

Issuance of Initiator’s Approval Letter

Prequalification

Tender process

Bid Award

SPV Establishment

PPP Signing Agreement

Q3 2024 – Q1 2025

Financial Close

Q1 2025Q1 2031

Construction


Turn static files into dynamic content formats.

Create a flipbook