PPP Project Water Resources Sector 2024 | Directorate Water Resources Infrastructure Financing

Page 1


Jambo Aye Irrigation System, Aceh

Project Cost : IDR 1.09 Trillion

: Q3–Q4 2026

Lhok Guci Irrigation System, Aceh

Project Cost : IDR 3,46 Trillion

: Pre-FS

PPP PROJECT WATER RESOURCES SECTOR

Lambakan Dam, East Kalimantan

Project Cost : IDR 7.22 Trilion

: Identification

FC : Q1–Q4 2027

Saddang Dam, South Sulawesi

Project Cost : IDR 3.01 Trilion Status : Identification

Project Cost : IDR 2.07 Trillion

: Readiness Criteria

Merangin Dam, Jambi

PPP PROJECT WATER RESOURCES SECTOR

Jambo Aye Irrigation PPP Project

Location: North Aceh and East Aceh, Aceh Province

Status: Preliminary Study

PROJECT DESCRIPTION

Jambo Aye irrigation system is located in the North and East Aceh Regency, Aceh Province. The exact location of the dam is in the Rumoh Rayeuk Village, Langkahan District, North Aceh Regency. The total potential irrigation area of the Jambo Aye irrigation system is 24,360 Ha which is situated on the left and right banks of Arakundo River.

PPP SCOPE

1. Construction of the Jambo Aye Kanan Irrigation System with a service area of 1,080 Ha out of a total area of 3,028 Ha.

2. Rehabilitation of the Jambo Aye Kiri Irrigation System along 56.857 Km out of a total channel length of 63 kilometers.

3. Maintenance of the Jambo Aye Kanan and Jambo Aye Kiri Irrigation System.

PROJECT PROFILE

GCA Minister of Public Works

Partnership scheme Design-Build-Financing-Rehabilitation-Maintenance-Transfer (DBFRMT)

Project Cost IDR 1.09 Trillion/ USD 68.7 Million

Concession Period 15 years: 2 years of Construction/ Rehabilitation and 13 years of Maintenance

Return of Investment Scheme Availability Payment

IRR Project 9.26 %

Desc:

* Indicative according to the current SP – OBC Draft

PROJECT STRUCTURE

Komering Irrigation System

Bintang Bano Dam Maintenance And Provision Mini Hydropower

Region of East Ogan Komering Ulu and Ogan Komering Komering Ilir, South Sumatera Province Region of Way Kanan, Lampung Province

Revitalization and Modernization of High Level Diversion (HLD) Interconnection Channel

Unsolicited PPP Project

Location:

Rehabilitation of irrigation networks spread across Komering irrigation area of 59,148 Ha and OM of 59,148 Ha + 8,500 Ha (JICA Loan, OM year 2028). The project includes implementation of Smart Irrigation Asset Management System

Lhok Guci Irrigation PPP Project

Location:

Lambakan Dam

Location:

Lambakan Dam

Location:

Merangin Dam is located in Batanghari River Basin. The benefits of the dam are for irrigattion of 12.000 Ha; raw water supply for drinking to 2 m3/s; to reduce flooding to 200 m3/s; Hydropower to 90-107,5 MW; and tourism

Saddang Dam

The location of the dam project is situated in the Saddang River Basin (DAS Saddang), Enrekang Regency, while the reservoir inundation area is located in Enrekang Regency and Tana Toraja The primary objectives of this project are to support the provision of an additional production of 2 million tons of rice for food security and 1.5 million tons of corn. As well as for tourism and raw water supply. The dam has an average annual flow potential of 566 2 million m³ and an irrigation area potential of 63,000 hectares, while the hydropower potential is 75 MW The Saddang Dam can fulfill up to 2 6 m³/second of raw water demand of the area

Leuwikeris Hydropower Plant

Location: Ciamis Regency, West Java

The Project is located on Leuwikeris Dam, Ciamis Regency, West Java The PPP Project of Leuwikeris Minihydro Power Plant (HPP)

Hydropower Plant Infrastructure

Delivery on Tiga Dihaji Dam

Location: South Ogan Komering Ulu, Regency South Sumatera Province

The Project is located on Tiga Dihaji Dam, South Ogan Komering Ulu Regency, South Sumatera Province. The PPP Project of Tiga Dihaji Hydro Power Plant (HPP) is proposed through Unsolicited with Design, Build, Finance, Operate, Maintain and Transfer (DBFOMT) scheme. It is estimated will generate electricity 40 MW

Minihydropower Plant Infrastructure

Delivery on Bener Dam

Location: Purworejo Regency, Central Java Province

The Project is located on Bener Dam, Purworejo Regency, Central Java Province The Unsolicited

Project of Bener Minihydro Power Plant (MHPP) is proposed through Design,

Operate, Maintain and

PROFILE * GCA Minister of Public Works Partnership scheme

(DBFOMT)

5,79 MW

Bintang Bano Dam Maintenance And Provision Mini Hydropower

Plant Infrastructure

Location: West Sumbawa Regency, West Nusa Tenggara Province

The Project is located on Bintang Bano Dam, West Sumbawa Regency, West Nusa Tenggara Province The PPP Project of Bintang Bano Minihydro Power Plant (MHPP) is proposed through Unsolicited with Design, Build, Finance, Operate, Maintain and Transfer (DBFOMT) scheme It is estimated will

6.3 MW for MHPP.

The Project is located on Bulango Ulu Dam, Bone Bolangu Regency, Gorontalo

Floating Photovoltaic and Minihydropower Plant Infrastructure

Delivery on Lau Simeme Dam

Location: Deli Serdang, North Sumatera Province

The Project is located on Lau Simeme Dam, Deli Serdang Regency, North Sumatera Province. The Unsolicited PPP Project of Lau Simeme Floating Photovoltaic (FPV) Minihydro Power Plant (MHPP) is proposed through Design, Build, Finance, Operate, Maintain and Transfer (DBFOMT) scheme It is estimated will generate electricity 7,79 MWp for FPV and 3 MW for MHPP.

Capacity FPV: 7,79 MWp MHPP: 3 MW

Cost

IDR 108,18 Billion

IDR 71, 1 Billion

Floating

Photovoltaic and Minihydropower Plant Infrastructure

Delivery on Way Apu Dam

Location: Buru Regency, Maluku Province

The Project is located on Way Apu Dam, Buru Regency, Maluku Province The Unsolicitied PPP Project of Way Apu Floating Photovoltaic (FPV) and Minihydro Power Plant (MHPP) is proposed through Design, Build, Finance, Operate, Maintain and Transfer (DBFOMT) scheme. It is estimated will

Operate-MaintenanceTransfer (DBFOMT) Electricity Capacity FPV: 10 MWp MHPP: 4,05 MW

Project Cost

FPV: IDR 146,66 Billion MHPP: IDR 105,75 Billion

Concession Period 18 Months of Construction and 25 Years of Service Period Return of Investment Scheme User Charge IRR Project

13,13% MHPP: 13,95%

Location: North Aceh Regency, Province of Aceh

The Project is located on Keureuto Dam, North Aceh Regency, Province of Aceh The PPP Project of Keureuto Floating Photovoltaic (FPV) and Minihydro Power Plant (MHPP) is proposed through Unsolicited with Design, Build, Finance, Operate, Maintain and Transfer (DBFOMT) scheme. It is estimated will generate electricity 35 MWp for FPV and 4,8 MW for MHPP

Minihydropower Plant Infrastructure

Delivery on Tapin Dam

Location: Tapin Regency, South Kalimantan Province

Project is located on Tapin Dam, Tapin Regency, South Kalimantan Province. The Unsolicitied PPP Project of Tapin Minihydro Power Plant (MHPP) is proposed through Design, Build, Finance, Operate, Maintain and Transfer (DBFOMT) scheme It is

Minihydro Power Plant Infrastructure Delivery on Way Sekampung

Location: Pringsewu Regency,

Minihydropower Plant

Infrastructure Delivery on Karalloe Dam

Location: Gowa Regency, South Sulawesi

National Capital Integrated Coastal Development (NCICD)

Location: North Jakarta

NCICD project has several benefits, including reducing the flood-affected area in North Jakarta by 112,417,700 square meters, eliminating potential flood-related losses amounting to USD 42.25 billion from 2033 to 2071, and saving travel time, vehicle operational costs, and emission costs

PPP Project Construction and Development of the Estuary Dam in Bintan Bay and the Drinking Water Supply System

Location: Riau Islands

PPP Project Construction and Development of the Estuary Dam in Bintan Bay and the Drinking Water Supply System aims to serve the drinking water needs of the community and industries in the Riau Islands and contribute to the increase in piped drinking water nationally by 0.07% and in the Riau Islands Province by 9 33%

The scope of the project includes:

1. Construction of dam infrastructure (Estuary DAM) and a reservoir integrated with a road on top of the dam.Construction of raw water units, including intake and raw water transmission pipes.

2. The transmission pipes are limited to the area between the intake and the clean water treatment plant (IPA) located near the estuary dam

3. Construction of production units, including water treatment buildings (IPA), clean water reservoirs, main clean water distribution networks, pumps, and other related buildings

PROJECT PROFILE

14.4 Trillion

Period 56 years: 6 years of Construction and 50 years of Service