1

Sunland Park, Shadow Mountain, Westwind, Redd Road Phase Ii And Executive Center Roadway – Lighting & Solicitation# 2020-004R Landscape Improvements February 4, 2020

Strategic Plan Goal: 7) Enhance and Sustain El Paso’s Infrastructure Network


Project Details Sunland Park, Shadow Mountain, Westwind, Redd Road Phase Ii And

Location: Executive Center Roadway – Lighting & Landscape Improvements District(s): 1, 8 Total Budget: $10,727,200.00 Funding Source: 2019 Capital Plan

2


Project Location

3

 Location Information  Sunland Park 

Landscaping and Illumination-Doniphan to Mesa

Shadow Mt. / Westwind

 Landscaping- Mesa to Enterprise Silver Springs to Redd Road Illumination- Mesa to Redd Road

Redd Road Phase II Landscaping- Doniphan to I-10 Illumination- Montoya to I-10

Executive Center

Landscaping and Illumination-Paisano to I-10


Existing Conditions – Sunland Park Dr.

4


Existing Conditions – Shadow Mountain

5


Existing Conditions – Westwind

6


Existing Conditions – Redd Road Phase II

7


Existing Conditions – Executive Center

8


Scope of Work 

Safety Continuous Arterial Lighting

Median Landscaping

Automatic Drip Irrigation System

Landscape Illumination at focal points

9


Procurement Summary ď‚§ Recommended Actions ď‚§ To award Solicitation #2020-004R Architect and Engineering Design Services to Brock & Bustillos Engineers, LLC., in the amount of $595,113.84.

10


11

Thank You Strategic Plan Goal: 7) Enhance and Sustain El Paso’s Infrastructure Network


Turn static files into dynamic content formats.

Create a flipbook
Street Median and Parkway Landscaping Project: Redd Rd from Desert Blvd North to Westwind Dr. by porraslj - Issuu