Pleasant Hill Public Safety Facility 6875 Martha L Miller Drive, Pleasant Hill, Iowa 50327
November 25, 2019
• • • • • • •
Team Members Prime Contractors Current Highlights Safe Hours Project Photos Upcoming Highlights Ryan Companies Contact Information
TEAM MEMBERS CITY REPRESENTATIVES:
RYAN COMPANIES:
DESIGN TEAM:
Sara Kurovski, Mayor Ben Champ, City Manager Madeline Sturms, Community Development Director Al Pizzano, Chief of Police Jamie Xayavong, Fire Chief
Russ Lewton, Regional Vice President Brian Clark, Director of Real Estate Development Terry Coomes, Field Coordinator Matt Hillis, Division Manager Matt Van Loon, Project Executive Jill Boetger, Project Manager Nate Frye, Superintendent Tyler Lange, Project Engineer Intern Beth Bertlshofer, Project Coordinator
Cory Sharp, FEH Design Denny Sharp, FEH Design Don Seymour, FEH Design Chris Martin, FEH Design Brady Daniel, FEH Design Michelle Cramblit, FEH Design James Deeds, KCL Engineering Jake Cunliffe, KCL Engineering Chris Davis, KCL Engineering Lucas Wardenburg, KCL Engineering Scott Hinshaw, KCL Engineering Brandon Chandler, KCL Engineering Gordon Lemmel, Confluence Matt Carlile, Confluence Jason Ledden, Snyder & Associates Eric Cannon, Snyder & Associates Dean Roberts, MWL
Prime Contractors • • • • • • • • • •
Absolute Concrete Brockway Mechanical & Roofing De Vries Electric Inc. Reliable 1 Heating | AC | Plumbing Katelman Steel Fabrication Inc. Lang Construction Inc. Mid-American Glazing Systems Inc. Moen Steel Erection PDM Precast Inc. Pezzetti Erosion Control Inc.
• Sandstone Management Ltd. • TNT Tuckpointing & Building Restoration, LLC
CURRENT HIGHLIGHTS • The installation of the structural masonry walls in building one has transpired. • The building three pad has been built and rocked. • The foundation reinforcing bar for buildings two and three have been pre-tied. • The underground storm water structures are being installed. • In-wall electrical raceways in the structural masonry walls are being installed. • Mass grading is nearly complete.
1,966 SAFETY HOURS TO DATE
PROJECT PHOTOS
7
Some reinforcing rebar for footings
Structure 2 with beehive grate .
Building 3 pad rocked and ready for compacting
Installed initial North and South elevator shaft walls
South parking area staked for utility underground work
Structural wall at gridline K laid up
UPCOMING HIGHLIGHTS
• • • • • •
The plumbers will mobilize on Monday November 25. The mass grading will be completed. The geothermal well field installation will begin soon. Building 3 is scheduled to have the gridlines staked. Footings for buildings 2 and 3 will be starting soon. Storm sewer piping and structures will be on-going.