Skip to main content

Pleasant Hill Public Safety Facilities Update 8.21.2020

Page 1

Pleasant Hill Public Safety Facility 6875 Martha L Miller Drive, Pleasant Hill, Iowa 50327

August 21st, 2020


• • • • • • •

Team Members Prime Contractors Current Highlights Safe Hours Project Photos Upcoming Highlights Ryan Companies Contact Information


TEAM MEMBERS CITY REPRESENTATIVES:

RYAN COMPANIES:

DESIGN TEAM:

Sara Kurovski, Mayor Ben Champ, City Manager Madeline Sturms, Community Development Director Al Pizzano, Chief of Police Jamie Xayavong, Fire Chief

Russ Lewton, Regional Vice President Brian Clark, Director of Real Estate Development Terry Coomes, Field Coordinator Matt Hillis, Director of Construction Matt Van Loon, Project Executive Jill Boetger, Project Manager Nate Frye, Superintendent Tyler Lange, Senior Project Engineer Kim Jones, Project Coordinator II Laura Skogman, Project Coordinator

Cory Sharp, FEH Design Denny Sharp, FEH Design Don Seymour, FEH Design Chris Martin, FEH Design Brady Daniel, FEH Design Michelle Cramblit, FEH Design James Deeds, KCL Engineering Jake Cunliffe, KCL Engineering Chris Davis, KCL Engineering Lucas Wardenburg, KCL Engineering Scott Hinshaw, KCL Engineering Brandon Chandler, KCL Engineering Matt Carlile, Confluence Jason Ledden, Snyder & Associates Eric Cannon, Snyder & Associates Dean Roberts, MWL


Prime Contractors • • • • • • • • • •

Absolute Concrete Brockway Mechanical & Roofing De Vries Electric Inc. Reliable 1 Heating | AC | Plumbing Katelman Steel Fabrication Inc. Lang Construction Inc. Mid-American Glazing Systems Inc. Moen Steel Erection PDM Precast Inc. Pezzetti Erosion Control Inc.

• Sandstone Management Ltd. • TNT Tuckpointing & Building Restoration, LLC • Saxton Inc.


MARTHA L MILLER DRIVE

BUILDING 1

BLDG 2

BLDG 3

Overall Project Diagram


MARTHA L MILLER DRIVE

POUR #2

POUR #1

BUILDING 1

BLDG 2

BLDG 3 POUR #1

Exterior Paving Pour Sequence

POUR #4

POUR #3


CURRENT HIGHLIGHTS • The site sidewalks are being placed throughout the campus. • The gypsum board installation at Building 2 (Fire Auxiliary) has commenced. • Re-spreading black dirt throughout the site is ongoing. • Underground wiring for the site light poles has been trenched in. • The south lot and south west drive are being cleaned and sealed. • The wall angle in the detention area ceilings is being installed for the truss deck ceiling panels.


36,607 SAFETY HOURS TO DATE


PROJECT PHOTOS

9


North faรงade of Building 1 (Main Building)


Flagpole base and sidewalk formed

Light pole base awaiting installation


Break room accent wall painted

IT room sheathing completed


The NE faรงade of Building 2 (Fire Auxiliary)


ERV 2 being installed at Building 2 (Fire Auxiliary)

Site sidewalks east of Building 2


The backup generator being installed

Building 2 apparatus bay lighting being installed


UPCOMING HIGHLIGHTS • Gypsum finishing in Building 1 (Main Building) should be completed next week. • Ceiling grid at the upper level of Building 2 (Fire Auxiliary) should be completed next week. • The detention area is being prepped for combo-unit stools. • The panels in all three buildings, Main Building, Fire Auxiliary, and Storage Garage, will have all conductors pulled to them. • The site sidewalks should be completed next week. • The re-spreading of black dirt will be completed.


CONTACT INFORMATION TEAM CONTACT: Jill Boetger

Kim Jones

Project Manager

Project Coordinator II

Phone: 515-412-5520 jill.boetger@ryancompanies.com

Phone: 319-731-2826 kim.jones@ryancompanies.com

Tyler Lange

Laura Skogman

Senior Project Engineer

Project Coordinator

Phone: 515-412-5529 tyler.lange@ryancompanies.com

Phone: 515-309-8500 laura.skogman@ryancompanies.com

Nate Frye Superintendent

Phone: 515-657-1044 nate.frye@ryancompanies.com


Turn static files into dynamic content formats.

Create a flipbook
Pleasant Hill Public Safety Facilities Update 8.21.2020 by pleasanthilliowa - Issuu