Pleasant Hill Public Safety Facility 6875 Martha L Miller Drive, Pleasant Hill, Iowa 50327
October 25, 2019
• • • • • • •
Team Members Prime Contractors Current Highlights Safe Hours Project Photos Upcoming Highlights Ryan Companies Contact Information
TEAM MEMBERS CITY REPRESENTATIVES:
RYAN COMPANIES:
DESIGN TEAM:
Sara Kurovski, Mayor Ben Champ, City Manager Madeline Sturms, Community Development Director Al Pizzano, Chief of Police Jamie Xayavong, Fire Chief
Russ Lewton, Regional Vice President Brian Clark, Director of Real Estate Development Terry Coomes, Field Coordinator Matt Hillis, Division Manager Matt Van Loon, Project Executive Jill Boetger, Project Manager Nate Frye, Superintendent Tyler Lange, Project Engineer Intern Beth Bertlshofer, Project Coordinator
Cory Sharp, FEH Design Denny Sharp, FEH Design Don Seymour, FEH Design Chris Martin, FEH Design Brady Daniel, FEH Design Michelle Cramblit, FEH Design James Deeds, KCL Engineering Jake Cunliffe, KCL Engineering Chris Davis, KCL Engineering Lucas Wardenburg, KCL Engineering Scott Hinshaw, KCL Engineering Brandon Chandler, KCL Engineering Gordon Lemmel, Confluence Matt Carlile, Confluence Jason Ledden, Snyder & Associates Eric Cannon, Snyder & Associates Dean Roberts, MWL
Prime Contractors • • • • • • • • • •
Absolute Concrete Brockway Mechanical & Roofing De Vries Electric Inc. Reliable 1 Heating | AC | Plumbing Katelman Steel Fabrication Inc. Lang Construction Inc. Mid-American Glazing Systems Inc. Moen Steel Erection PDM Precast Inc. Pezzetti Erosion Control Inc.
• Sandstone Management Ltd. • TNT Tuckpointing & Building Restoration, LLC
CURRENT HIGHLIGHTS • The Southeast detention pond is being excavated. • The North and South parking areas around the Building 1 pad are being graded. • The Building 1 pad has been cut to elevation and proof rolled. • The drainage layer of rock under the Building 1 slab has been placed.
• The gridlines and off-sets for the building pad have been laid out. • Ground Breaking ceremony
553 SAFETY HOURS TO DATE
PROJECT PHOTOS
7
D6 Stripping the Site on the South Side
Earthwork/Strip Site/Grade
.
West Side of Compacted Building 1 Pad
East Side of Compacted Building 1 Pad
.
Dirt Being Stockpiled on the East End of the Property
The Over Excavation at the High Density Storage for the Thickened Slab
Scraper Depositing Fill on the Southeast Parking Area
Sally Port Over Excavation and Rock
Mayor Sara Kurovski speaking at the Ground Breaking
Brian Clark speaking at the Ground Breaking
Ground Breaking
Ground Breaking
Building 1 Pad Being Finish Graded After the Final Loads of Rock Were Placed
Building 1 Pad Completely Rocked
UPCOMING HIGHLIGHTS
• Foundation rebar will be delivered and pre-tying of the bar will commence. • The elevator pit and pit walls will be constructed. • The interior column footings will be installed after the elevator pit. • The interior footing and exterior footings will be installed. • The elevator shaft masonry walls will transpire upon completion of the elevator pit. • The electrical underground raceways for the slab will begin soon.
CONTACT INFORMATION TEAM CONTACT:
FIELD CONTACT:
Matt Hillis
Beth Bertlshofer
Nate Frye
Phone: 515-309-8523
Phone: 515-412-5510
Phone: 515-657-1044
matt.hillis@ryancompanies.com
beth.bertlshofer@ryancompanies.com
nate.frye@ryancompanies.com
Matt Van Loon
Terry Coomes
Phone: 515-309-8535
Phone: 515-309-8513
matthew.vanloon@ryancompanies.com
terry.coomes@ryancompanies.com
Jill Boetger Phone: 515-412-5520 jill.boetger@ryancompanies.com
Tyler Lange Phone: 515-412-5529 tyler.lange@ryancompanies.com