Public Safety Facility Project Update

Page 1

Pleasant Hill Public Safety Facility 6875 Martha L Miller Drive, Pleasant Hill, Iowa 50327

October 25, 2019


• • • • • • •

Team Members Prime Contractors Current Highlights Safe Hours Project Photos Upcoming Highlights Ryan Companies Contact Information


TEAM MEMBERS CITY REPRESENTATIVES:

RYAN COMPANIES:

DESIGN TEAM:

Sara Kurovski, Mayor Ben Champ, City Manager Madeline Sturms, Community Development Director Al Pizzano, Chief of Police Jamie Xayavong, Fire Chief

Russ Lewton, Regional Vice President Brian Clark, Director of Real Estate Development Terry Coomes, Field Coordinator Matt Hillis, Division Manager Matt Van Loon, Project Executive Jill Boetger, Project Manager Nate Frye, Superintendent Tyler Lange, Project Engineer Intern Beth Bertlshofer, Project Coordinator

Cory Sharp, FEH Design Denny Sharp, FEH Design Don Seymour, FEH Design Chris Martin, FEH Design Brady Daniel, FEH Design Michelle Cramblit, FEH Design James Deeds, KCL Engineering Jake Cunliffe, KCL Engineering Chris Davis, KCL Engineering Lucas Wardenburg, KCL Engineering Scott Hinshaw, KCL Engineering Brandon Chandler, KCL Engineering Gordon Lemmel, Confluence Matt Carlile, Confluence Jason Ledden, Snyder & Associates Eric Cannon, Snyder & Associates Dean Roberts, MWL


Prime Contractors • • • • • • • • • •

Absolute Concrete Brockway Mechanical & Roofing De Vries Electric Inc. Reliable 1 Heating | AC | Plumbing Katelman Steel Fabrication Inc. Lang Construction Inc. Mid-American Glazing Systems Inc. Moen Steel Erection PDM Precast Inc. Pezzetti Erosion Control Inc.

• Sandstone Management Ltd. • TNT Tuckpointing & Building Restoration, LLC


CURRENT HIGHLIGHTS • The Southeast detention pond is being excavated. • The North and South parking areas around the Building 1 pad are being graded. • The Building 1 pad has been cut to elevation and proof rolled. • The drainage layer of rock under the Building 1 slab has been placed.

• The gridlines and off-sets for the building pad have been laid out. • Ground Breaking ceremony


553 SAFETY HOURS TO DATE


PROJECT PHOTOS

7


D6 Stripping the Site on the South Side

Earthwork/Strip Site/Grade

.


West Side of Compacted Building 1 Pad

East Side of Compacted Building 1 Pad

.


Dirt Being Stockpiled on the East End of the Property

The Over Excavation at the High Density Storage for the Thickened Slab


Scraper Depositing Fill on the Southeast Parking Area

Sally Port Over Excavation and Rock


Mayor Sara Kurovski speaking at the Ground Breaking

Brian Clark speaking at the Ground Breaking


Ground Breaking


Ground Breaking


Building 1 Pad Being Finish Graded After the Final Loads of Rock Were Placed

Building 1 Pad Completely Rocked


UPCOMING HIGHLIGHTS

• Foundation rebar will be delivered and pre-tying of the bar will commence. • The elevator pit and pit walls will be constructed. • The interior column footings will be installed after the elevator pit. • The interior footing and exterior footings will be installed. • The elevator shaft masonry walls will transpire upon completion of the elevator pit. • The electrical underground raceways for the slab will begin soon.


CONTACT INFORMATION TEAM CONTACT:

FIELD CONTACT:

Matt Hillis

Beth Bertlshofer

Nate Frye

Phone: 515-309-8523

Phone: 515-412-5510

Phone: 515-657-1044

matt.hillis@ryancompanies.com

beth.bertlshofer@ryancompanies.com

nate.frye@ryancompanies.com

Matt Van Loon

Terry Coomes

Phone: 515-309-8535

Phone: 515-309-8513

matthew.vanloon@ryancompanies.com

terry.coomes@ryancompanies.com

Jill Boetger Phone: 515-412-5520 jill.boetger@ryancompanies.com

Tyler Lange Phone: 515-412-5529 tyler.lange@ryancompanies.com