UNIVERSITY OF PITTSBURGH • GRO SEMINAR SERIES
From Greenfield to Grid Josh Higgins Development Manager, Oriden • Wednesday, November 11, 2026
Agenda
01
02
03
04
05
About me
About Oriden
What a developer does
Active Oriden projects
Key Takeaways
Questions are welcome at any point!
oridenpower.com • University of Pittsburgh GRO Seminar
02
Personal Background
oridenpower.com • University of Pittsburgh GRO Seminar
03
Professional Background
EDUCATION
CAREER
2021
2024 – Present
Bachelor’s, Chemical Engineering
Development Manager, Oriden
University of Pittsburgh
“Project execution” - project finance, commercial contracts, regulatory compliance, deal execution, construction support
2022
Master’s, Petroleum Engineering University of Pittsburgh
2022-2024
Consultant, Deloitte Risk and Financial Advisory Valuation in renewable/oil and gas sectors, renewable energy tax credit analyses, engineering adjacent work 2021-2022
Student Research, Pitt Hydraulic Fracturing Lab Worked with Dr. Bunger on developing testing methods for in-situ stress in sub-surface rock formations
oridenpower.com • University of Pittsburgh GRO Seminar
04
Oriden at a glance WHO WE ARE
Oriden is a renewable energy developer. We take utility-scale solar and storage projects from concept to completion, and we have the financial backing to see them through. NEW CHAPTER, 2026 Acquired in April 2026 by I Squared Capital’s Energy Transition Fund, with about $300M committed to grow the platform. HQ: North Shore, Pittsburgh, PA
oridenpower.com • University of Pittsburgh GRO Seminar
2019
~200 MW
Founded in Pittsburgh as a Mitsubishi Power venture
Actively in construction right now
5+ GW
MISO & PJM
Solar & battery storage development pipeline
Core markets across the Midwest and Mid-Atlantic
30
IPP Transition
Employees across development, finance and engineering
Oriden will own operating assets going forward
05
What Oriden does
Site Selection & Origination
Permitting & Regulatory
Land, market and stakeholder fit
Studies, approvals and compliance
Interconnection
EPC & Operations
Queue strategy and utility studies
Build oversight and asset management
ONE TEAM
Strategic Partnerships
Project Financing
Project Marketing
Landowners, utilities, offtakers, suppliers
Capital structure and tax credits
Selling power to offtakers and investors
oridenpower.com • University of Pittsburgh GRO Seminar
Concept to completion The same people carry a project from first lease to COD
06
The developer’s role in the industry Landowners & communities
Permitting authorities
Grid operators & utilities
Site control through leases; local support
County zoning, state siting, environmental agencies
MISO, PJM and the interconnecting utility
Offtakers
Investors & lenders
Utilities and corporate buyers of power and RECs
Tax equity, debt and sponsor equity The developer coordinates every party and owns the plant
EPC contractors
Equipment suppliers
Regulators
Engineering, procurement and construction
Modules, inverters, trackers, transformers
FERC, NERC and state commissions
oridenpower.com • University of Pittsburgh GRO Seminar
07
The development process
1
4
Site & land Find land with good sun, flat terrain and nearby transmission; sign leases
Offtake Sell the output: a PPA or virtual PPA, plus capacity and renewable energy credits
2
5
Permits & studies Environmental, cultural and wetland studies; local zoning and state approvals
Financing Raise tax equity, construction debt and sponsor equity; reach financial close
3
6
Interconnection Enter the ISO queue, fund system impact studies, sign the interconnection agreement
Construction & COD EPC builds, tests and commissions the plant to commercial operation (COD)
Then decades of operations: asset management, O&M and performance optimization
oridenpower.com • University of Pittsburgh GRO Seminar
08
How to get a project financed
REVENUE
CAPITAL
CONTRACTS
Who pays for the power?
Who funds the build?
Who carries which risk?
PPA or virtual PPA
Tax equity or credit transfer
EPC agreement
A fixed price for the energy
Monetizes federal tax credits
Price, schedule and performance guarantees
Capacity revenue
Construction & term debt
Interconnection agreement
Paid by the ISO for being available at peak
Lenders sized to contracted cash flow
Grid access and upgrade costs
RECs
Sponsor equity
O&M and asset management
Renewable energy credits sold to buyers
The developer’s and owner’s own capital
Keeps the plant performing for decades
Good deals hand each risk to the party best able to manage it, and the contracts must line up with each other.
oridenpower.com • University of Pittsburgh GRO Seminar
09
Common risks all renewable developers face
Policy deadlines Tax credit rules can move a project’s whole schedule and determine if it has viable economics or not.
Trade & equipment rules Manufactured products’ country of origin can qualify/disqualify an entire plant for tax credits.
Study results can determine whether or not a project is economical. Many projects competing for the same transmission capacity drives up costs.
Market rule changes
Community & permits
Offtake risk Signing a solid offtake agreement with a reputable offtaker is one of the most important things a developer can do. There are many ways a bad offtake can ruin project economics.
Interconnection
ISO rule updates can change what power is worth before or after a project comes online.
oridenpower.com • University of Pittsburgh GRO Seminar
Local support is earned early, in person, and kept for the life of the project. A project can be perfect, but if the community is opposed, it will never get built.
10
The 2026 development landscape
Tax credit deadlines
Supply chain & FEOC rules
Under the 2025 One Big Beautiful Bill Act, solar must have “”Begun Construction” by July 4, 2026, or be placed in service by Dec. 31, 2027, to earn the §48E / §45Y credits.
Foreign-entity-of-concern limits now apply to projects starting construction after 2025, raising the bar on equipment sourcing and documentation.
Grid access & market rules
Demand growth
Long interconnection queues in MISO and PJM, and changing capacity accreditation rules, shape which sites are worth pursuing.
New large loads such as data centers are pushing utilities and corporate buyers to contract for new generation.
oridenpower.com • University of Pittsburgh GRO Seminar
11
Projects in the field Three Oriden projects at three different stages
Staunton Solar
Vermillion Rise
Abe’s Run
47 MWac • Virginia
185 MWac • Indiana • MISO
20 MWac • Pennsylvania • PJM
Pre-construction Advancing toward construction with its EPC partner under an early, limited notice to proceed.
COD 2027 Our largest active project: Oriden’s first transmission scale project
oridenpower.com • University of Pittsburgh GRO Seminar
Approaching COD Moving from construction into operations: regulatory registrations, tax equity funding and asset management.
12
Vermillion Rise 185 MWac of solar in western Indiana, our largest active project
KEY FACTS ENGINEERING & COMMERCIAL CHALLENGES
Item
Detail
Capacity
185 MWac solar
Location
Vermillion County, Indiana
Market
MISO Indiana Hub
Offtake
Hub-settled virtual PPA with a corporate buyer
Construction
Single general contractor
Target COD
Late 2027
oridenpower.com • University of Pittsburgh GRO Seminar
Equipment selection Choosing equipment that is compliant with many different federal restrictions/guidelines to maximize tax credit capability
Labor monitoring All wages must be paid at the appropriate rate to qualify for tax credits
Basis analysis Price differences between the plant’s node and the Indiana Hub
Gen-tie permitting Routing the line across a state highway and a creek
13
Spotlight: Abe’s Run 20 MWac of solar in Pennsylvania (PJM), approaching commercial operation
FERC/NERC certifications Federal market and security registrations which take time and communication
THE LAST MILE
Building the plant is half the job. Reaching COD means satisfying regulators, investors, contractors, and offtakers
Interconnection commissioning Communicating with PJM and First Energy to safely bring the plant online
Tax equity funding Capital released in stages as conditions are met by the party that claims tax credits
EPC change orders & closeout Construction issues arise unexpectedly and require collaboration
Asset manager selection Who runs the plant for the next several decades
oridenpower.com • University of Pittsburgh GRO Seminar
14
Where GRO engineers fit The skills you’re building translate directly to power development
What you’re learning
How a developer uses it
Resource characterization
→
Determining if the resource available is worth the investment
Facilities & pipeline design
→
Preliminary site layouts, civil works and high voltage design
Power & process systems
→
Interconnection studies and grid integration
Project economics
→
Financial models, PPA pricing and tax credits
Regulation & permitting
→
FERC, ISO and state siting compliance
Co-op & internship opportunities Oriden is considering co-op and internship roles for GRO students. Reach out: info@oridenpower.com
oridenpower.com • University of Pittsburgh GRO Seminar
15
Conclusions 01 Developers are integrators
We bring land, grid, buyers, capital and builders together, and carry the risk until they align.
and markets move 03 Policy fast
2026 tax credit deadlines and grid rules are reshaping strategy in real time.
oridenpower.com • University of Pittsburgh GRO Seminar
is managing 02 Development risk
Value is created milestone by milestone, long before construction starts.
are central 04 Engineers GRO skills in resources, facilities,
economics and regulation transfer directly to energy development.
16
THANK YOU