Table of Contents TABLE OF CONTENTS ..................................................... 1 OVERVIEW......................................................................... 3 COMMUNITY MEETINGS .................................................. 4 BID OPENINGS .................................................................. 5 NEW & MAJOR RENOVATION ......................................... 6 Audubon School (OPSB).............................................. 6 Stuart R. Bradley School (RSD) .................................. 6 George Washington Carver School (RSD) .................. 7 Charles J. Colton School (RSD) .................................. 7 Lawrence D. Crocker School (RSD) ............................ 8 Drew Elementary School (RSD) ................................. 8 Frederick A. Douglass High School (RSD) ................. 8 Paul L. Dunbar School (RSD) ...................................... 9 Fisk-Howard School (RSD) ......................................... 9 William Frantz School (RSD) ..................................... 10 Alice Harte School (OPSB) ........................................ 10 (OPSB) New Karr High School at the JoEllen Smith Site ............................................................................... 10 New PK-8 School at North Kenilworth Park at Curran Site (OPSB)................................................................ 11 Lake Forest PK-8 at the Greater St. Stephens Site (OPSB) ....................................................................... 11 Alfred Lawless School (RSD) .................................... 11 Little Woods School (RSD) ........................................ 12 Edward Livingston High School (RSD) ..................... 13 McDonogh #35 School (Phillip/Waters Site) (OPSB). 13 McDonogh #42 Elementary School (RSD) ............... 14 Eleanor L. McMain School (OPSB) ........................... 14 Small New Orleans East High School at Abramson (RSD) ....................................................................... 15 Mildred Osborne School (RSD) ................................ 16 Parkview School (RSD) ............................................. 16 Booker T. Washington School (RSD) ........................ 17 Phillis Wheatley Elementary School (RSD) ............... 17 Fannie C. Williams School (RSD) .............................. 17 Carter G. Woodson School (RSD) ............................. 18 Sophie B. Wright School (RSD) ................................ 18 REFURBISHMENTS ......................................................... 19 Warren Easton School (OPSB) ................................. 19 Lusher Elementary School Refurbishment (Bridge) (OPSB) ....................................................................... 19 Lusher (Fortier) High School Refurbishment (OPSB) . 20 Nelson Elementary School (OPSB) ........................... 20 OTHER PROJECTS ......................................................... 21 Benjamin Franklin Senior High School (OPSB) .......... 21 Walter L. Cohen High School (RSD) ......................... 21
1
Status Date: 31 October 2012
Warren Easton School (OPSB) ................................. 22 Langston Hughes School (RSD)............................... 22 Andrew Jackson School (RSD) ................................ 22 Mahalia Jackson Elementary School Office Renovation (OPSB) .................................................... 23 Edna Karr High School - Gymnasium Repair (OPSB) ............................................................................... 23 Thomy Lafon School (RSD) ....................................... 24 John McDonogh High School (RSD) ...................... 23 McDonogh #35 High School (OPSB) ......................... 25 Timbers HVAC (OPSB) .............................................. 25 Village de’ Lest Elementary School (RSD) ................ 25 Sylvanie Williams Elementary School (RSD) ............. 26 Dwight D. Eisenhower Elementary School (RSD)..... 26 Andrew Jackson Elementary School (RSD) ............. 26 Paul B. Habans Elementary School (RSD) ............... 26 Sylvanie F. Williams Elementary School (RSD) ........ 26 Joseph S. Clark Senior High School (RSD) ............... 26 Building Automation System Integration At Recovery School District Central And Remote Offices (RSD) .. 27 MOTHBALL OR SAFE & SECURE OF SELECTED SCHOOLS ........................................................................ 28 Louis D. Armstrong Elementary School (RSD)) ......... 28 Israel M. Augustine Middle School (RSD)................. 28 Andrew J. Bell Junior High School (RSD) ................. 29 Oretha C. Haley Elementary School (RSD) .............. 30 Lorraine Hansberry Elementary School (RSD) ......... 30 Morris F. X. Jeff Elementary School (RSD) .............. 31 Valena C. Jones Elementary School (RSD) ............. 31 George Mondy Elementary School (RSD) ................. 32 John A. Shaw Elementary School (RSD)................... 32 DEMOLITION PROJECTS ............................................... 33 Modular Classrooms at Fannie C. Williams Elementary School (RSD) ........................................ 33 Greater St. Stephens School (OPSB) ........................ 33 JoEllen Smith Demolition (OPSB) .............................. 34 L. B. Landry Annex Demolition (RSD) ...................... 34 Mary Church Terrell Elementary School Demolition (RSD) ) ....................................................................... 35 Booker T. Washington High School Partial Demolition (RSD) ..................................................... 35 COMPLETED PROJECTS .............................................. 36
2
Status Date: 31 October 2012
Overview The RSD has $383 million in open contracts for the capital program after issuing $26.7 million in new contracts and $1.6 million in change orders and amendments in October. In addition, the total change orders to date, $7.6 million, account for approximately three percent (2.61%) of the total open construction contracts. RSD anticipates issuing approximately $3.3 million in construction contracts and professional service contracts/amendments in November.
The OPSB has $96.8 million in open contracts for the capital program after issuing $1.7 million in new contracts, change orders and amendments in October. In addition, the total change orders to date, $1.08 million, account for approximately two percent (1.57 %) of the total open construction contracts. OPSB anticipates issuing approximately $685 thousand in construction contracts and professional service contracts in November.
3
Status Date: 31 October 2012
Community Meetings
October 1st: Alfred Lawless School – 1617 Caffin Avenue, New Orleans, LA 70117
October 3rd: Stuart R. Bradley School – 3939 Gentilly Blvd, New Orleans, LA 70126
November 8th: Phillis Wheatley Elementary School – 1426 Napoleon Avenue, New Orleans, LA 70115
4
Status Date: 31 October 2012
Bid Openings Bids that were opened in October 2012:
No bids were opened in the month of October
Over the next sixty days, bids to be opened for the following projects:
New Gym Addition at Eleanor McMain Secondary High School (OPSB) – November 7, 2012
New PK-8 School at North Kenilworth Park at Curran Site November 8, 2012
New McDonogh #35 School at Phillips /Waters Site (OPSB) – November 15, 2012
Test Pile Program at Bradley (RSD) – November 27, 2012
Test Pile Program at Lake Forest PK-8 at the Greater St. Stephens Site (OPSB) – November 28, 2012
Thomy Lafon Interpretive Display (RSD) – December 5, 2012
Village de L’est Elementary School Roof and Modular Demolition (RSD) – December 19, 2012
5
Status Date: 31 October 2012
(OPSB)
–
Forecasted dates only include the next project phase
New & Major Renovation – Project Status Audubon School (OPSB) [428 Broadway Avenue, New Orleans, LA 70118]
Scope of work: Renovation & Addition of Existing Elementary School
Funding Source – FEMA
Architect – Blitch/Knevel Architects
Contractor – FHP Tectonics Corporation
Construction Phase
Approved permits were received end of October
Pile driving is anticipate to start beginning of November
Wall layout in existing building is ongoing
Under slab plumbing layout in the existing building in ongoing
Above ceiling gypsum board assembly has started
Contractual Substantial Completion – September 2013
Forecasted Substantial Completion – February 2014
School Ready for Occupancy – May 2014
Stuart R. Bradley School
(RSD)
[ 2401 Humanity Street, New Orleans, LA 70122]
Scope of work: New 3 – section elementary school for 850 students
Funding Source – FEMA
Architect – Sizeler Thompson Brown Architects
Contractor – TBD
Design Phase – CD
50% Construction Documents are due October 23rd
100% Construction Documents are due December 21st
Procurement Phase
Test Pile package 1st Advertisement – October 24th
Test Pile package Bid Opening – November 27th
Anticipated Construction package 1st Advertisement – January 2013
Anticipated Construction package Bid Opening – March 2013
6
Status Date: 31 October 2012
George Washington Carver School (RSD) [3019 & 3059 Higgins Blvd., New Orleans, LA 70126]
Scope of work: New High School
Funding Source – FEMA
Architect – Trapolin Architects & VMDO Architects, A Joint- Venture
Contractor – TBD
Procurement Phase
Bid Opening – July 27th
Bids were not accepted
Project is on hold pending Owner’s decision
Charles J. Colton School (RSD) [2300 St. Claude Avenue, New Orleans, LA 70117]
Scope of work: Renovation of existing elementary school and new addition
Funding Source – FEMA
Architect – Waggonner & Ball Architects
Contractor – F.H. Paschen, S.N. Nielsen & Associates, LLC
Construction Phase
Roofing material installation is 90% complete
Exterior brick work is anticipated to be complete the mid of November
Gypsum board installation on interior walls is 85% complete on 2nd and 3rd floors
Mechanical/Electrical/Plumbing rough-in work is 95% complete
Pulling of wiring/data lines is ongoing
Window installation is 75% complete
Exterior wall panels are being installed
Patching of terrazzo is 25% complete
Contractual Substantial Completion – November 2012
Forecasted Substantial Completion – March 2013
School Ready for Occupancy – June 2013
7
Status Date: 31 October 2012
Lawrence D. Crocker School (RSD) [2300 General Taylor Street, New Orleans, LA 70115]
Scope of work: New PK-8 School
Funding Source – FEMA Architect – Chenevert Architects LLC
Contractor – Satterfield and Pontikes Construction Group, LLC
Final Close-out Phase
Project is Substantially Complete – October 15
The punch list is ongoing
School is Occupied – September 2012
Drew Elementary School (RSD) [3819 St. Claude Avenue, New Orleans, LA 70117]
Scope of work: Renovation of existing elementary school and new addition to meet code requirements
Funding Source – FEMA
Architect – Blitch / Knevel Architects, Inc.
Contractor – TBD
Design Phase - CD
Design Development Documents were received on October 19th
50% Construction Documents are due December 10th
100% Construction Documents are due February 14th
Procurement Phase
Anticipated 1st Advertisement – March 2013
Anticipated Bid Opening – April 2013
Frederick A. Douglass High School (RSD) [3820 St. Claude Avenue, New Orleans, LA 70117]
Scope of work: Renovation of existing high school
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – TBD
Design Phase - SD
Schematic Design Documents were received on October 2nd
8
Status Date: 31 October 2012
Design Development is anticipated on December 15th
Procurement Phase
Anticipated 1st Advertisement – May 2013
Anticipated Bid Opening – June 2013
Paul L. Dunbar School (RSD) [9330 Forshey Street, New Orleans, LA 70125]
Scope of work: New 2 - section elementary school for 556 students
Funding Source – FEMA
Architect – Chenevert Architects LLC
Contractor – TBD
Design Phase - CD
50% Construction Documents were received on October 11th
100% Construction Documents are due December 18th
Procurement Phase
Anticipated 1st Advertisement – January 2013
Anticipated Bid Opening – February 2013
Fisk-Howard School (RSD) [211 South Lopez Street, New Orleans, LA 70119]
Scope of work: New 3 - section elementary school for 850 students
Funding Source - FEMA
Architect - VergesRome Architects+Fanning Howey
Contractor – TBD
Design Phase - CD
Mobilization for pile driving is anticipate the beginning of November
100% Construction Documents are anticipated to be submitted on November 12th
Procurement Phase
Anticipated 1st Advertisement – December 2012
Anticipated Bid Opening – January 2013
9
Status Date: 31 October 2012
William Frantz School (RSD) [3811 North Galvez Street, New Orleans, LA 70117]
Scope of work: Renovation of existing elementary school and new addition
Funding Source – FEMA
Architect – Billes Architecture, LLC
Contractor – The Lathan Company, Inc.
Construction Phase
Contractor has abandoned the project
Owner is working with Surety to resume work
Contractual Substantial Completion – March 2012
Forecasted Substantial Completion – TBD
School Ready for Occupancy – TBD
Alice Harte School
(OPSB)
[5300 Berkley Drive, New Orleans, La 70131]
Scope of work: New 3 - section elementary school for 850 students
Funding Source – CDBG & FEMA
Architect – WDG Architects Engineers
Contractor – Woodrow Wilson Construction Company, Inc.
Construction Phase
The contractor has mobilized and has begun site preparation
Pile driving has started
Contractual Substantial Completion – January 2014 Forecasted Substantial Completion – January 2014 School Ready for Occupancy – June 2014 New Karr High School at the JoEllen Smith Site (OPSB) [4400 General Meyer Avenue, New Orleans, LA 70131]
Scope of work: New medium high school
Funding Source – FEMA
Architect – Lee Ledbetter & Associates / Gould Evans Associates
Contractor – TBD
Design Phase - CD
Schematic Design Documents were submitted on August 17th
10
Status Date: 31 October 2012
Due to design issues and additional scope of work, Schematic Design Documents are being reviewed by the Owner
New PK-8 School at North Kenilworth Park at Curran Site (OPSB) [8500 Curran Boulevard, New Orleans, LA 70127]
Scope of work: New 3 - section elementary school for 850 students
Funding Source – FEMA
Architect – Mathes Brierre Architects
Contractor – TBD
Procurement Phase
1st Advertisement – September 25th
2nd Advertisement – October 2nd
3rd Advertisement – October 9th
Pre-Bid Conference – 9:00 a.m. on October 10th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA
Bid Date – November 8th
Bid Date was extended a week later due to concerns of the Bidders
Forecasted Substantial Completion – July 2014
School Ready for Occupancy – August 2014
Lake Forest PK-8 at the Greater St. Stephens Site
(OPSB)
[11110 Lake Forest Boulevard 70128]
Scope of work: New 3 - section elementary school for 850 students
Funding Source – FEMA
Architect – Imre Hegedus & Associates Architects
Contractor – TBD
Design Phase - DD
Design Development Documents are anticipated November 6th
Procurement Phase
Test Pile Package
Anticipated 1st Advertisement – October 17th
Anticipated Bid Opening – November 28th
New Construction
11
Status Date: 31 October 2012
Anticipated 1st Advertisement – April 2013
Anticipated Bid Opening – May 2013
Alfred Lawless School
(RSD)
[5300 Law Street, New Orleans, LA 70117]
Scope of work: New medium high school
Funding Source – FEMA
Architect – Sizeler Thompson Brown Architects
Contractor – TBD
Design Phase - DD
Community Meeting #2 – October 1st
Design Development Documents are due on November 15th
50% Construction Documents are anticipated to be finished on January 21st
Procurement Phase
Anticipated 1st Advertisement – April 2013
Anticipated Bid Opening – May 2013
Little Woods School (RSD) [10200 Curran Blvd., New Orleans, LA 70127]
Scope of work: New Pre-K – 8 school
Funding Source – FEMA
Architect – Group Novak, LLC
Contractor – MAPP Construction
Construction Phase
Interior brick veneer is complete
Fireproofing is complete in all areas
Window and glass installation is 95% complete
Sprinkler piping on all floors is 90% complete
Interior metal stud framing is complete
Installation of gypsum board has started
Classroom walls are finished on all floors
Installing restroom ceilings on 2nd and 3rd floors
Pulling and terminating wire into panel boxes is ongoing throughout the building
12
Status Date: 31 October 2012
Installation of fire alarm is ongoing
Entergy has energized the transformer and the building has permanent power
Contractual Substantial Completion – November 2012
Forecasted Substantial Completion – April 2013
School Ready for Occupancy – TBD
Edward Livingston High School
(RSD)
[7301 Dwyer Road, New Orleans, LA 70126]
Scope of work: New small high school
Funding Source – FEMA
Architect – RozasWard / a.i.a. architects, inc.
Contractor – TBD
Design Phase - CD
100% Construction Documents are due on January 21st
Procurement Phase
Anticipated 1st Advertisement – February 2013
Anticipated Bid Opening – April 2013
McDonogh #35 School (Phillip/Waters Site)
(OPSB)
[1200 Senate Street, New Orleans, LA 70122]
Scope of work: New 3-story high school
Funding Source – FEMA
Architect – Sizeler, Thompson, Brown Architects
Contractor - TBD
Site Remediation Project
A Phase II environmental assessment revealed heavy metals and PAHs exist in the fill
Scope of work is to remediate fly-ash materials found in the soil
Remediation work is anticipated to be completed by the end of the year
New Construction Project Ownership
13
The resubdivision request was approved by the City Of New Orleans, recordation is pending
Status Date: 31 October 2012
100% Construction Documents were received on October 2nd
Procurement Phase
1st Advertisement – October 10th
2nd Advertisement – October 17th
3rd Advertisement – October 24th
Pre-Bid Conference – 9:00 a.m. on October 31st at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA
Bid Opening – November 15th
McDonogh #42 Elementary School (RSD) [1651 North Tonti Street, New Orleans, LA 70119]
Scope of work: Renovation of existing elementary school and new addition to meet code requirements
Funding Source – FEMA
Architect – Eskew+Dumez+Ripple
Contractor - TBD
Design Phase - DD
Design Development Documents are anticipate November 23rd
Procurement Phase
Anticipated 1st Advertisement – April 2013
Anticipated Bid Opening – June 2013
Eleanor L. McMain School
(OPSB)
[5721 S. Claiborne Avenue, New Orleans, LA 70125]
Scope of work: The exterior of the existing building will be stabilized and a new gym will be added to the site with a connecting breezeway to the main building. A portion of the existing building will be renovated for a health clinic.
Exterior Stabilization
Funding Source – FEMA
Architect – Jahncke & Burns Architects
Contractor – TBD
Design management team is reviewing alternates for window scope
14
Status Date: 31 October 2012
Design management team is assessing the existing stucco on the building
Notice to Proceed for A & E contract is anticipate November 9th
New Gymnasium and Breezway
Funding Source – FEMA
Architect – Jahncke & Burns Architects
Contractor – TBD
Design Phase – CD
100% Construction Documents were received on September 21st
Procurement Phase
1st Advertisement – October 3rd
2nd Advertisement – October 10th
3rd Advertisement – October 17th
Pre-Bid Conference – 9:00 a.m. on October 17th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA
Bid Opening – November 7th
School Based Health Clinic
Funding Source – HRSA Grant
Architect – Jahncke & Burns Architects
Contractor – TBD
Procurement Phase
Notice to Proceed is anticipated November 14th
Contractual Substantial Completion – 120 days after contract award Small New Orleans East High School at Abramson (RSD) [5552 Read Boulevard, New Orleans, LA 70127]
Scope of work: New small high school
Funding Source – FEMA
Architect – RozasWard / a.i.a. architects, inc.
Contractor – TBD
Design Phase - CD
100% Construction Documents are due on January 21st
15
Status Date: 31 October 2012
Procurement Phase
Anticipated 1st Advertisement – February 2013
Anticipated Bid Opening – April 2013
Mildred Osborne School (RSD) [6701 Curran Blvd., New Orleans, LA 70126]
Scope of work: New Pre-K– 8 school
Funding Source – FEMA
Architect – Fauntleroy & Latham
Contractor – F.H. Paschen, S.N. Nielsen & Associates, LLC
Construction Phase
Finish trades are working in the gymnasium
Landscaping is nearly complete and the fencing is ongoing
Media Center and Music Room are 95% complete
Library is 98% complete
Gymnasium is 90% complete
Contractual Substantial Completion – January 2012 This school will have a phased delivery schedule from 16th of October to end of November
Parkview School (RSD) [4617 Mirabeau Avenue, New Orleans, LA 70126]
Scope of work: New Pre-K– 8 school
Funding Source – FEMA
Architect – Rozas-Ward
Contractor – Citadel Builders, LLC
Final Close-out Phase
Project is complete
Commissioning will begin in November
School was Occupied – 6 August 2012
16
Status Date: 31 October 2012
Booker T. Washington School (RSD) [1201 South Roman Street, New Orleans, LA 70125] Scope of work: The auditorium and entry will be renovated and the remainder of the facility will be demolished and constructed new
Funding Source – FEMA
Architect – Hewitt-Washington & Associates
Contractor – TBD
Design Phase - CD
100% Construction Documents are anticipated on November 13th
Upon completion of the Design Phase, the project will be put on hold until a mitigation plan is developed on the environmental issues
Phillis Wheatley Elementary School (RSD) [2300 Dumaine Street, New Orleans, LA 70119]
Scope of work: New 2 - section elementary school for 556 students
Funding Source – FEMA
Architect – Holly & Smith Architects
Contractor – Gibbs Construction
Construction Phase
Notice to proceeded was sent October 17th
Contractor is mobilizing
Permits are anticipated for the beginning of November
Forecasted Substantial Completion – April 2014
School Ready for Occupancy – June 2014
Fannie C. Williams School (RSD) [11755 Dwyer Road, New Orleans, LA 70128]
Scope of work: New Pre-K – 8 school
Funding Source – FEMA
Architect – Yeates & Yeates Architects
Contractor – Brice Building Company, LLC
Final Close-out Phase
School is complete and occupied
Substantial Completion - August 24th
17
Status Date: 31 October 2012
Carter G. Woodson School (RSD) [2514 Third Street, New Orleans, LA 70113]
Scope of work: New Pre-K – 8 school
Funding Source – FEMA
Architect – Byron J. Stewart & Associates
Contractor – Brice Building Company, LLC
Final Close-out Phase
Project is complete
Commissioning will begin in November
School was Occupied – 17 September 2012
Sophie B. Wright Middle School Renovation
(RSD)
[1426 Napoleon Avenue, New Orleans, LA 70115]
Scope of work: Renovation of existing middle school
Funding Source – FEMA
Architect – Waggonner & Ball Architects, APC
Contractor – TBD
Design Phase - DD
Schematic Design Documents were delivered on September 24th Design Development Documents are anticipated December 7th
Procurement Phase
Anticipated 1st Advertisement – May 2013
Anticipated Bid Opening – June 2013
18
Status Date: 31 October 2012
REFURBISHMENTS Warren Easton School
(OPSB)
[3019 Canal Street, New Orleans, LA 70119]
Scope of work: Refurbishment of existing high school
Funding Source – FEMA
Architect – Chenevert Architects LLC
Contractor - TBD
Design Phase - CD
100% Construction Documents are anticipated on December 16th
Owner requested increase in the scope of work will extend the Design Phase
Procurement Phase
Anticipated 1st Advertisement – January 2013
Anticipated Bid Opening – February 2013
Lusher Elementary School Refurbishment (Bridge) (OPSB) [7315 Willow Street, New Orleans, LA 70118]
Scope of work: Renovation of existing bridge and restrooms to meet code requirements
Funding Source – FEMA
Architect – Meyer Engineers, LTD.
Contractor - TBD
Design Phase - PC
Program documents were received on October 17th
Schematic Design documents are anticipated November 14th
Procurement Phase
Anticipated 1st Advertisement – April 2013
Anticipated Bid Opening – May 2013
19
Status Date: 31 October 2012
Lusher (Fortier) High School Refurbishment
(OPSB)
[5624 Freret Street, New Orleans, LA 70115]
Scope of work: Renovation and repairs to the roof, masonry, plaster, windows, exterior doors, canopies, mechanical systems, and electrical systems.
Funding Source – FEMA
Architect – Meyer Engineers, LTD.
Contractor - TBD
Design Phase - PC
Program documents were received on October 15th
Schematic Design documents are anticipated November 14th
Procurement Phase
Anticipated 1st Advertisement – April 2013
Anticipated Bid Opening – May 2013
Nelson Elementary School Refurbishment
(OPSB)
[3121 St. Bernard Avenue, New Orleans, LA 70119]
Scope of work: Renovation and repairs to the roof, masonry, windows, exterior doors, mechanical systems, and electrical systems.
Funding Source – FEMA
Architect – Harry Baker Smith Architects
ontractor - TBD
Design Phase - PC
Program documents are anticipated December 11th
Schematic Design documents are anticipated January 10th
Procurement Phase
Anticipated 1st Advertisement – June 2013
Anticipated Bid Opening – July 2013
20
Status Date: 31 October 2012
OTHER PROJECTS Benjamin Franklin Senior High School (OPSB) [2001 Leon C. Simon Drive, New Orleans, LA 70122]
Scope of work: Renovation and repairs to the existing courtyard, exterior lighting, metal roof panels, interior lighting, curtain wall, exterior doors (frames), fencing, scoreboard and goal post
Funding Source – FEMA
Architect – Perez, APC
Contractor – Pete Vicari General Contractors Inc.
Construction Phase
Additional courtyard work is anticipated to be complete in January
Exterior roof is complete
Electrical lighting work is 90% complete
Forecasted Contractual Substantial Completion – January 2013
Walter L. Cohen High School (RSD) [3520 Dryades Street, New Orleans, LA 70115]
Scope of work: Correct the HVAC return air / ventilation problems and replace eight (8) chilled water pumps
Funding Source – FEMA
Architect – Infinity Engineering Consultants, LLC
Contractor – TBD
Design Phase
A / E contract was approved at the October BESE board Meeting
Anticipated notice to procced – Late November
21
Status Date: 31 October 2012
Warren Easton School
(OPSB)
[3019 Canal Street, New Orleans, LA 70119]
Scope of work: Removal and replacement of existing exterior windows and waterproofing of the courtyard masonry
Funding Source – Harrah’s
Architect – VergesRome Architects, apc
Contractor – Barbara Enterprises, Inc.
Final Close-out Phase
Substantial completion September 6th
Punch list is ongoing
Contractual Substantial Completion – March 2010
Forecasted Substantial Completion – September 2012
Langston Hughes School
(RSD)
[3519 Trafalgar Street, New Orleans, LA 70119]
Scope of work: Remove abandoned dumpster pad and grease trap; replace on classroom door/hardware; correct duct system in the IT room; install fencing in place of the dumpster pad; provide and install a fence around the backflow preventer
Funding Source – FEMA
Architect – Lachin Oubre & Associates
Contractor – Tuna Construction, LLC
Final Close-out Phase
Project is complete
Substantial Completion – October 12, 2012
Andrew Jackson School
(RSD)
[1400 Camp Street, New Orleans, LA 70130]
Scope of work: Installation of solar panels at Andrew Jackson School. This will save energy for the school and serve as a teaching aide for students to learn about solar energy
Funding Source – Greater New Orleans Foundation/Entergy Grant
Architect – Perez, APC
Contractor – Gulf Coast Solar
Construction Phase
Lead time of solar panels has extended the schedule by a month
22
Status Date: 31 October 2012
Notice to Proceed - September 17th
Forecasted Substantial Completion – January 2013
Mahalia Jackson Elementary School Office Renovation (OPSB) [2101 Freret Street, New Orleans, LA 70113]
Scope of work: Convert the office space on the second floor of Building C into four classrooms
Funding Source – New Orleans Parish School Board General Fund
Architect – VergesRome Architects, APAC
Contractor – TBD
Procurement Phase
The lowest bidder was non-responsive, the Owner awarded the contract to the next lowest responsive bidder.
Notice to proceeded is anticipated November 5th
Permits are in place
Forecasted Substantial Completion – January 2013
Edna Karr High School - Gymnasium Repair (OPSB) [3332 Huntlee Drive, New Orleans, LA 70131]
Scope of work: Determine what amount and methods need to be used to stabilize gymnasium for use.
Funding Source – FEMA
Architect – Chenevert Architects, LLc
Contractor – Crescent Commercial Construction
Stablization of the Gymnasium
Construction Phase
Notice to proceeded is anticipated October 8th
Project is being delayed due to Entergy having to insualte the power lines
Forecasted Substantial Completion – February 2013
23
Status Date: 31 October 2012
Thomy Lafon School (RSD) [2601 Seventh St, New Orleans, LA 70115]
Scope of work: Stabilization of sculpture and creation of interperative display
Funding Source – FEMA
Architect – Mahlum / Scairono Marinez Joint Venture
Contractor – TBD
Procurement Phase
1st Advertisement – October 31st
2nd Advertisement – November 7th
3rd Advertisement – November 14th
Pre-Bid Conference – 9:00 a.m. on November 15th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA
Bid Opening – December 5th
Construction Phase
Notice to Proceed is anticipated early January
John McDonogh High School (RSD) [2426 Esplanade Avenue, New Orleans, LA 70119]
Scope of work: Replacement of bleachers
Funding Source – Harrah’s
Architect – Trapolin Peer Architects, LLC
Contractor – TBD
Design Phase - CD
The State Fire Marshal confirmed that with the addition of the new bleachers, a fire sprinkler system will be required in the gymnasium
Notice to Proceed on sprinkler design is anticipated for the beginning of November
Design is anticipated to be completed in March 2013
24
Status Date: 31 October 2012
McDonogh #35 High School (OPSB) [1331 Kerlerec Street, New Orleans, LA 70116]
Scope of work: Stabilization and replacement of elevator
Funding Source – FEMA
Architect – Chenevert Architects LLC
Contractor – TBD
Procurement Phase
Bid Opening – September 20th
Bids were higher than expected
Project is being reviewed by the Owner
Forecasted Substantial Completion – April 2013
Timbers HVAC (OPSB) [3520 General DeGaulle, New Orleans, LA 70114]
Scope of work: Stabilization and replacement of HVAC
Funding Source – General Fund
Architect – Moses Engineers
Contractor – TBD
Design Phase - CD
100% Construction Documents were received on September 28th
Procurement Phase
Anticipated 1st Advertisement – November 2012
Anticipated Bid Date – December 2012
Village de L’est Elementary School
(RSD)
[5100 Cannes Street, New Orleans, LA 70129]
Scope of work: Roof replacement and modular demolition
Funding Source – FEMA
Architect – Richard C. Lambert Consultants, LLC
Contractor – TBD
Design Phase - CD
100% Construction Documents are anticipated on November 5ths
Procurement Phase
25
Status Date: 31 October 2012
1st Advertisement – November 14th
2nd Advertisement – November 21st
3rd Advertisement – November 28th
Pre-Bid Conference – 9:00 a.m. on November 29th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA
Bid Opening – December 19th
Sylvanie Williams Elementary School (RSD) [3127 Martin Luther King Jr. Boulevard, New Orleans, LA 70125]
Scope of work: AHU replacement
Funding Source – FEMA
Architect – Integrated Management Services, Inc.
Contractor – TBD
Procurement Phase
Bid Opening – September 11th
Notice to Proceed is anticipated on November 12th
Forecasted Substantial Completion – April 2013
Dwight D. Eisenhower Elementary School
(RSD)
[3700 Tall Pines Drive, New Orleans, LA 70131]
Andrew Jackson Elementary School
(RSD)
[1400 Camp Street, New Orleans, LA 70130]
Paul B. Habans Elementary School
(RSD)
[3819 Herschel Street, New Orleans, LA 70114]
Sylvanie F. Williams Elementary School
(RSD)
[3127 Martin Luther King Jr. Blvd, New Orleans, LA 70113]
Joseph S. Clark Senior High School (RSD) [1301 North Derbigny Street, New Orleans, LA 70116]
Scope of work: Roof repairs and replacement
Funding Source – FEMA
Architect – HMS Architects, Inc.
Contractor – Hamp’s Construction, LLC
Final Close-out Phase
Project is complete
26
Status Date: 31 October 2012
Building Automation System Integration At Recovery School District Central And Remote Offices (RSD) [Various Addresses]
Scope of work: Implementation of a Central Remote Building Automation System that integrates the existing Building Automation Systems of the 4 Quick Start Schools (Andrew H. Wilson ES, Langston Hughes ES, L.B. Landry HS, and Lake Area HS) and Joseph A. Craig ES into a central remote monitoring workstation that will include Fannie C. Williams ES, Lawrence D. Crocker ES, Mildred Osborne ES, William Frantz ES, Bienville ES, Charles J. Colton ES, Carter G. Woodson ES and Parkview ES
Funding Source – FEMA
Architect – Moses Engineers
Contractor – Synergy Building Solutions, Inc.
Construction Phase
The five Quick Start Schools are 95% complete, with work expected to be complete in November pending change order #2
Sylvanie Williams and Sarah T. Reed are 90% complete
The remaining integration for schools currently under construction will occur as each school is complete
Contractual Substantial Completion – November 2014
Forecasted Substantial Completion – November 2014
27
Status Date: 31 October 2012
MOTHBALL OR SAFE SELECTED SCHOOLS
&
SECURE
OF
Louis D. Armstrong Elementary School (RSD)) [5909 St. Claude Avenue, New Orleans, LA 70117]
Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – CDW Services, LLC
Mothballing of Closed Schools – Safe & Secure
Construction Phase
Abatement is 90% complete
Project is 28% complete
Forecasted Substantial Completion – January 2013
Israel M. Augustine Middle School
(RSD)
[425 S. Broad St., New Orleans, LA 70119]
Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – CDW Services, LLC
Mothballing of Closed Schools – Safe & Secure
Construction Phase
Project is 38% complete
Structural shoring is ongoing in the stairwell
Contractual Substantial Completion – November 2012
Forecasted Substantial Completion – December 2012
28
Status Date: 31 October 2012
Andrew J. Bell Junior High School
(RSD)
[1010 N. Galvez St., New Orleans, LA 70119]
Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – Cresent Commercial Construction
Emergency Shoring – 100% complete
Shoring will remain in place until roof work is complete
Mothballing of Closed Schools – Safe & Secure
Scope of work: Mothballing of the Gymnasium, Adminstration Building, Building “D”, Chapel, and the E.A.Christy Building
Design Phase - CD
50% Construction Documents were received on October 25th
100% Construction Documents are anticipated to be complete on November 28th
Roof Structure Replacement
Procurement Phase
The contractor has mobilized and the project is 10% complete
Forecasted Substantial Completion – May 2013
29
Status Date: 31 October 2012
Oretha C. Haley Elementary School
(RSD)
[2515 N. Robertson Street, New Orleans, LA 70117]
Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – CDW Servcies, LLC
Mothballing of Closed Schools – Safe & Secure
Final Close – out Phase
Punchlist is 90% complete
Contractual Substantial Completion – September 2012 Forecasted Substantial Completion – September 2012 Lorraine Hansberry Elementary School
(RSD)
[1339 Clouet Street, New Orleans, LA 70117]
Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – Tuna Construction LLC
Mothballing of Closed Schools – Safe & Secure
Construction Phase
Metal panels over exterior windows is 90% complete
Contractor is installing metal panels over exterior windows on the cottage
Contractual Substantial Completion – November 2012
Forecasted Substantial Completion – November 2012
30
Status Date: 31 October 2012
Morris F. X. Jeff Elementary School
(RSD)
[800 N. Rendon Street, New Orleans, LA 70119]
Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – CDW Services, LLC
Mothballing of Closed Schools – Safe & Secure
Construction Phase
Project is 52% complete
Contractual Substantial Completion – December 2012
Forecasted Substantial Completion – December 2012
Valena C. Jones Elementary School
(RSD)
[1901 N. Galvez Street, New Orleans, LA 70119]
Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – CDW Services, LLC
Mothballing of Closed Schools – Safe & Secure
Construction Phase
Project is 24% complete
Replacement of roof is ongoing
Contractual Substantial Completion – December 2012
Forecasted Substantial Completion – December 2012
31
Status Date: 31 October 2012
George Mondy Elementary School (RSD) [2327 St. Phillip Street, New Orleans, LA 70119]
Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – TBD
Project has been Canceled
John A. Shaw Elementary School (RSD) [2518 Arts Street, New Orleans, LA 70117]
Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – Zimmer-Eschette Services II, LLC
Mothballing of Closed Schools – Safe & Secure
Final Close – Out Phase
Punchlist is 90% complete
Contractual Substantial Completion – August 2012
Forecasted Substantial Completion – October 2012
32
Status Date: 31 October 2012
Demolition Projects Modular Classrooms at Fannie C. Williams Elementary School
(RSD)
[11755 Dwyer Street, New Orleans, LA 70128]
Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes.
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – Gulfcon LLC
Demolition of the Modular Classrooms
Procurement Phase
Bid Opening – September 18th
Notice to Proceed is anticipated early December
Owner is actively working on the property title issues and the removal of the F.F. & E.
Forecasted Substantial Completion – February 2013
Greater St. Stephens School (OPSB) [11110 Lake Forest Boulevard 70128]
Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes.
Funding Source – FEMA
Architect – Chenevert Architects LLC
Contractor – Bayou Sheet Metal and Roofing Inc
Procurement Phase
Bid Opening – September 13th
Notice to Proceed is anticipated November 7th
Forecasted Substantial Completion – February 2013
33
Status Date: 31 October 2012
JoEllen Smith Demolition
(OPSB)
[4400 General Meyer Avenue, New Orleans, LA 70131]
Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes.
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – TBD
Design Phase - CD
50% Construction Documents are anticipated November 5th
100% Construction Documents are anticipated December 10th
Procurement Phase
Anticipated 1st Advertisement – January 2013
Anticipated Bid Date – February 2013
L. B. Landry Annex Demolition
(RSD)
[1100 Wagner Street, New Orleans, LA 70114]
Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes.
Funding Source – FEMA
Architect – Perez Architects
Contractor – Durr Heavy Construction LLC
Procurement Phase
Bid Opening – August 14th Contractor was non responsive, and the Owner is going to award the contract to the lowest responsive bidder
Notice to Proceed is anticipated middle of November
Forecasted Substantial Completion – February 2013
34
Status Date: 31 October 2012
Mary Church Terrell Elementary School Demolition (RSD) [3411 Broadway, New Orleans, LA 70125]
Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes.
Funding Source – FEMA
Architect – SCNZ Architects
Contractor – Gill Industries, Ltd.
Procurement Phase
Bid Opening – July 31st Contractor was non responsive, and the Owner is going to award the contract to the lowest responsive bidder
Notice to Proceed is anticipated middle of November
Forecasted Substantial Completion – March 2013
Booker T. Washington High School Partial Demolition
(RSD)
[1201 S. Roman Street, New Orleans, LA 70125]
Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes.
Funding Source – FEMA
Architect – Hewitt-Washington & Associates
Contractor – Gulfcon LLC
Partial Demolition
Demolition Phase
Demolition of interior of main building is 80% complete
Remediation proposals were received October 26th and are being reviewed
Contractual Substantial Completion – Feburary 2013
Forecasted Substantial Completion – February 2013
35
Status Date: 31 October 2012
Comprehensive List - Completed Projects 1.
Abrams | Morial | Abramson | Coghill Demolition
2.
A. D. Cross Elementary School Energy Conservation (RSD)
3.
A. D. Crossman Elementary School and Benjamin Banneker Elementary School (RSD)
4.
A. P. Tureaud Elementary School Roof Repairs (RSD)
5.
Agnes Bauduit Elementary School Boiler (RSD)
6.
Albert Wicker Elementary School Roof Repairs (RSD)
7.
Alfred Lawless Senior High Security Fencing (RSD)
8.
Alice M. Harte Elementary School Demolition (OPSB)
9.
Andrew H. Wilson Elementary School Cottage (RSD)
10.
Arthur Ashe Elementary School Kitchen Renovation (OPSB)
11.
Augustine Elementary School Roof (RSD)
12.
Avery-Alexander Elementary School Demolition (RSD)
13.
Barbara C. Jordan Elementary School Demolition (RSD)
14.
Bell JH Shoring (RSD)
15.
Benjamin Banneker Elementary School Energy Conservation (RSD)
16.
Bienville Elementary School Demolition (RSD)
17.
Carter G. Woodson Middle School Demolition (RSD)
18.
Central Services Warehouse Demolition (OPSB)
19.
Charles J. Colton Elementary Selective Demolition (RSD)
20.
Charles R. Drew Elementary Roof & Installation of Kitchen Hood (RSD)
21.
Cohen High School Health Clinic
22.
Douglass High School Under Floor Utilities (RSD)
23.
Dr. Martin Luther King School Roof Repairs(RSD)
24.
Dr. Martin Luther King Jr. School Renovation(RSD)
25.
East BankSwing Space for Audubon Charter School (OPSB)
26.
Edgar P. Harney Elementary School Roof Repairs (RSD)
27.
Edward Livingston Middle School Demolition(RSD)
28.
Edward Henry Phillips Junior High School Demolition (OPSB)
29.
New Edward Hynes School (OPSB)
30.
Edwards | Hardin | Lockett | Lawless Demolition (RSD)
31.
Eleanor L. McMain School Replacement of Existing Chillers (OPSB)
32.
Ernest N. Morial Elementary Security Fencing (RSD)
36
(RSD)
(RSD)
Status Date: 31 October 2012
33.
Fannie C. Williams Elementary School Demolition (RSD)
34.
Fisk-Howard Elementary School Demolition (RSD)
35.
Florence J. Chester Elementary School Demolition (RSD)
36.
Francis W. Gregory Demolition (RSD)
37.
Frederick A. Douglass High Switchgear (RSD)
38.
Frederick A. Douglass High Emergency Boiler Roof Repairs (RSD)
39.
George Washington Carver High School Demolition (RSD)
40.
Henry Allen Elementary School Roof (RSD)
41.
Henry C. Schaumburg – Window/Door, Air Condition, Water Fountain/Sink Installation (RSD)
42.
Holy Cross Modular Relocation (RSD)
43.
Israel M. Augustine Middle School Roof Replacement (RSD)
44.
James Derham Demolition (RSD)
45.
James W. Johnson Elementary School Roof (RSD)
46.
New Jean Batiste de Bienville School (RSD)
47.
Jean Gordon Elementary School Demolition (RSD)
48.
John Dibert Elementary School Roof (RSD)
49.
John W. Hoffman Elementary School Demolition (RSD)
50.
John F. Kennedy Modular Relocation (Schwarz Campus) (RSD)
51.
John F. Kennedy Modular Relocation (Coghill Modular Campus) (RSD)
52.
John F. Kennedy High School Demolition (RSD)
53.
John McDonogh Senior High School Roof (RSD)
54.
Joseph A. Craig Elementary Canopies (RSD)
55.
Joseph A. Craig Elementary Elevator Installation (RSD)
56.
Joseph A. Hardin Elementary Security Fencing (RSD)
57.
Lafayette Elementary School Roof and Masonry(RSD)
58.
Lake Area | Landry Demolition (RSD)
59.
Langston Hughes Elementary School (Phase I) (RSD)
60.
Langston Hughes Elementary School – New Gymnasium (Phase II) (RSD)
61.
Lawrence D. Crocker Elementary School Demolition (RSD)
62.
Little Woods Elementary School Demolition (RSD)
63.
Live Oak Elementary School Roof (RSD)
64.
Live Oak Elementary School Exterior Door Replacement (RSD)
65.
Mahalia Jackson Elementary School (OPSB)
37
Status Date: 31 October 2012
66.
Mahalia Jackson Elementary School Dumpster / Other Improvements(OPSB)
67.
Martin Behrman Elementary School Roof (RSD)
68.
Martin Luther King Jr. Elementary Canopy System (RSD)
69.
Martin Luther King Jr. School Modular Building, Deck, Canopy (RSD)
70.
Mary M. Bethune Elementary 1st Floor Replacement (OPSB)
71.
Mary M. Bethune Elementary Rear Yard Repair/Resurfacing (OPSB)
72.
McDonogh #15 Elementary Exterior Masonry to SOI Standards (RSD)
73.
McDonogh #28 Elementary School Roof
74.
McDonogh #32 Roof Replacement (RSD)
75.
McDonogh #35 ADA Upgrades to Public Restrooms, Exterior Ramp & Handicap Seating in the Auditorium (OPSB)
76.
McDonogh #42 Elementary School Roof (RSD)
77.
McDonogh #42 Elementary School HVAC Replacement (RSD)
78.
Mildred C. Osborne Elementary School Demolition
79.
Modular Campuses Close Outs (RSD)
80.
Modular Structures at Langston Hughes Elementary School (RSD)
81.
Morris F.X. Jeff Elementary School Demolition (RSD)
82.
Murray G. Henderson Elementary School Roof (RSD)
83.
New Andrew H. Wilson Elementary School (RSD)
84.
New Joseph A. Craig Elementary School (RSD)
85.
New Lake Area High School
86.
New L.B. Landry High School (RSD)
87.
New Equipment & Upgrades at 8 Central & 25 Satellite Kitchens (RSD)
88.
New Orleans High School Signature Center Study (RSD)
89.
Oretha C. Haley Demo (RSD)
90.
Parkview Elementary School Demolition
91.
Paul L. Dunbar Elementary School Demolition (RSD)
92.
Phillis Wheatley Elementary School Demolition (RSD)
93.
Robert M. Lusher Elementary Roof Removal & Replacement
(RSD)
(RSD)
(RSD)
(RSD)
(OPSB)
94.
Sarah T. Reed High School Bleachers (RSD)
95.
Sarah T. Reed High School Auditorium Wall (RSD)
96.
Seabrook Computer Training Center Demolition (OPSB)
97.
Schaumburg Chillers (RSD)
38
Status Date: 31 October 2012
98.
Schwarz Alternative Repairs
99.
Schwarz Alternative Modulars Demolition (RSD)
(RSD)
100. Sherwood Forest Elementary School Demolition (RSD) 101. Sophie B. Wright Various Repairs/Restroom Renovations (OPSB) 102. Stuart R. Bradley Elementary School Demolition
(RSD)
103. Sylvanie Williams Elementary School Play Yard (RSD) 104. Sylvanie Williams Elementary School HVAC/Chiller Replacement (RSD)
105. Temporary Campus for McDonogh #11 Expropriation (OPSB) 106. Thomas A. Edison Elementary School Demolition (RSD) 107. Thomy Lafon Elementary School Demolition (RSD) 108. Timbers Park Office Building #1 & #2 Demolition (OPSB) 109. Village de L’est Elementary School Subsidence (RSD) 110. Vorice J. Waters Elementary School Demolition (RSD) 111. West Bank Swing Space for Alice Harte Elementary School (OPSB) 112. New William J. Guste Elementary School (RSD) 113. William J. Guste Elementary School Science Lab (RSD) 114. William Frantz Elementary School Environmental Remediation & Selective Demolition (RSD) 115. William Frantz Elementary School Roof (RSD)
39
Status Date: 31 October 2012