Superintendents’ Report October 2012

Mr. Stanley C. Smith Orleans Parish School Board

Mr. John White Louisiana Department of Education

Mr. Patrick Dobard Recovery School District

Prepared by:


Table of Contents TABLE OF CONTENTS ..................................................... 1 OVERVIEW......................................................................... 3 COMMUNITY MEETINGS .................................................. 4 BID OPENINGS .................................................................. 5 NEW & MAJOR RENOVATION ......................................... 6 Audubon School (OPSB).............................................. 6 Stuart R. Bradley School (RSD) .................................. 6 George Washington Carver School (RSD) .................. 7 Charles J. Colton School (RSD) .................................. 7 Lawrence D. Crocker School (RSD) ............................ 8 Drew Elementary School (RSD) ................................. 8 Frederick A. Douglass High School (RSD) ................. 8 Paul L. Dunbar School (RSD) ...................................... 9 Fisk-Howard School (RSD) ......................................... 9 William Frantz School (RSD) ..................................... 10 Alice Harte School (OPSB) ........................................ 10 (OPSB) New Karr High School at the JoEllen Smith Site ............................................................................... 10 New PK-8 School at North Kenilworth Park at Curran Site (OPSB)................................................................ 11 Lake Forest PK-8 at the Greater St. Stephens Site (OPSB) ....................................................................... 11 Alfred Lawless School (RSD) .................................... 11 Little Woods School (RSD) ........................................ 12 Edward Livingston High School (RSD) ..................... 13 McDonogh #35 School (Phillip/Waters Site) (OPSB). 13 McDonogh #42 Elementary School (RSD) ............... 14 Eleanor L. McMain School (OPSB) ........................... 14 Small New Orleans East High School at Abramson (RSD) ....................................................................... 15 Mildred Osborne School (RSD) ................................ 16 Parkview School (RSD) ............................................. 16 Booker T. Washington School (RSD) ........................ 17 Phillis Wheatley Elementary School (RSD) ............... 17 Fannie C. Williams School (RSD) .............................. 17 Carter G. Woodson School (RSD) ............................. 18 Sophie B. Wright School (RSD) ................................ 18 REFURBISHMENTS ......................................................... 19 Warren Easton School (OPSB) ................................. 19 Lusher Elementary School Refurbishment (Bridge) (OPSB) ....................................................................... 19 Lusher (Fortier) High School Refurbishment (OPSB) . 20 Nelson Elementary School (OPSB) ........................... 20 OTHER PROJECTS ......................................................... 21 Benjamin Franklin Senior High School (OPSB) .......... 21 Walter L. Cohen High School (RSD) ......................... 21

1

Status Date: 31 October 2012


Warren Easton School (OPSB) ................................. 22 Langston Hughes School (RSD)............................... 22 Andrew Jackson School (RSD) ................................ 22 Mahalia Jackson Elementary School Office Renovation (OPSB) .................................................... 23 Edna Karr High School - Gymnasium Repair (OPSB) ............................................................................... 23 Thomy Lafon School (RSD) ....................................... 24 John McDonogh High School (RSD) ...................... 23 McDonogh #35 High School (OPSB) ......................... 25 Timbers HVAC (OPSB) .............................................. 25 Village de’ Lest Elementary School (RSD) ................ 25 Sylvanie Williams Elementary School (RSD) ............. 26 Dwight D. Eisenhower Elementary School (RSD)..... 26 Andrew Jackson Elementary School (RSD) ............. 26 Paul B. Habans Elementary School (RSD) ............... 26 Sylvanie F. Williams Elementary School (RSD) ........ 26 Joseph S. Clark Senior High School (RSD) ............... 26 Building Automation System Integration At Recovery School District Central And Remote Offices (RSD) .. 27 MOTHBALL OR SAFE & SECURE OF SELECTED SCHOOLS ........................................................................ 28 Louis D. Armstrong Elementary School (RSD)) ......... 28 Israel M. Augustine Middle School (RSD)................. 28 Andrew J. Bell Junior High School (RSD) ................. 29 Oretha C. Haley Elementary School (RSD) .............. 30 Lorraine Hansberry Elementary School (RSD) ......... 30 Morris F. X. Jeff Elementary School (RSD) .............. 31 Valena C. Jones Elementary School (RSD) ............. 31 George Mondy Elementary School (RSD) ................. 32 John A. Shaw Elementary School (RSD)................... 32 DEMOLITION PROJECTS ............................................... 33 Modular Classrooms at Fannie C. Williams Elementary School (RSD) ........................................ 33 Greater St. Stephens School (OPSB) ........................ 33 JoEllen Smith Demolition (OPSB) .............................. 34 L. B. Landry Annex Demolition (RSD) ...................... 34 Mary Church Terrell Elementary School Demolition (RSD) ) ....................................................................... 35 Booker T. Washington High School Partial Demolition (RSD) ..................................................... 35 COMPLETED PROJECTS .............................................. 36

2

Status Date: 31 October 2012


Overview The RSD has $383 million in open contracts for the capital program after issuing $26.7 million in new contracts and $1.6 million in change orders and amendments in October. In addition, the total change orders to date, $7.6 million, account for approximately three percent (2.61%) of the total open construction contracts. RSD anticipates issuing approximately $3.3 million in construction contracts and professional service contracts/amendments in November.

The OPSB has $96.8 million in open contracts for the capital program after issuing $1.7 million in new contracts, change orders and amendments in October. In addition, the total change orders to date, $1.08 million, account for approximately two percent (1.57 %) of the total open construction contracts. OPSB anticipates issuing approximately $685 thousand in construction contracts and professional service contracts in November.

3

Status Date: 31 October 2012


Community Meetings 

October 1st: Alfred Lawless School – 1617 Caffin Avenue, New Orleans, LA 70117

October 3rd: Stuart R. Bradley School – 3939 Gentilly Blvd, New Orleans, LA 70126

November 8th: Phillis Wheatley Elementary School – 1426 Napoleon Avenue, New Orleans, LA 70115

4

Status Date: 31 October 2012


Bid Openings Bids that were opened in October 2012: 

No bids were opened in the month of October

Over the next sixty days, bids to be opened for the following projects: 

New Gym Addition at Eleanor McMain Secondary High School (OPSB) – November 7, 2012

New PK-8 School at North Kenilworth Park at Curran Site November 8, 2012

New McDonogh #35 School at Phillips /Waters Site (OPSB) – November 15, 2012

Test Pile Program at Bradley (RSD) – November 27, 2012

Test Pile Program at Lake Forest PK-8 at the Greater St. Stephens Site (OPSB) – November 28, 2012

Thomy Lafon Interpretive Display (RSD) – December 5, 2012

Village de L’est Elementary School Roof and Modular Demolition (RSD) – December 19, 2012

5

Status Date: 31 October 2012

(OPSB)

–


Forecasted dates only include the next project phase

New & Major Renovation – Project Status Audubon School (OPSB) [428 Broadway Avenue, New Orleans, LA 70118]

Scope of work: Renovation & Addition of Existing Elementary School 

Funding Source – FEMA

Architect – Blitch/Knevel Architects

Contractor – FHP Tectonics Corporation

Construction Phase 

Approved permits were received end of October

Pile driving is anticipate to start beginning of November

Wall layout in existing building is ongoing

Under slab plumbing layout in the existing building in ongoing

Above ceiling gypsum board assembly has started

Contractual Substantial Completion – September 2013

Forecasted Substantial Completion – February 2014

School Ready for Occupancy – May 2014

Stuart R. Bradley School

(RSD)

[ 2401 Humanity Street, New Orleans, LA 70122]

Scope of work: New 3 – section elementary school for 850 students 

Funding Source – FEMA

Architect – Sizeler Thompson Brown Architects

Contractor – TBD

Design Phase – CD

50% Construction Documents are due October 23rd

100% Construction Documents are due December 21st

Procurement Phase 

Test Pile package 1st Advertisement – October 24th

Test Pile package Bid Opening – November 27th

Anticipated Construction package 1st Advertisement – January 2013

Anticipated Construction package Bid Opening – March 2013

6

Status Date: 31 October 2012


George Washington Carver School (RSD) [3019 & 3059 Higgins Blvd., New Orleans, LA 70126]

Scope of work: New High School 

Funding Source – FEMA

Architect – Trapolin Architects & VMDO Architects, A Joint- Venture

Contractor – TBD

Procurement Phase 

Bid Opening – July 27th

Bids were not accepted

Project is on hold pending Owner’s decision

Charles J. Colton School (RSD) [2300 St. Claude Avenue, New Orleans, LA 70117]

Scope of work: Renovation of existing elementary school and new addition 

Funding Source – FEMA

Architect – Waggonner & Ball Architects

Contractor – F.H. Paschen, S.N. Nielsen & Associates, LLC

Construction Phase 

Roofing material installation is 90% complete

Exterior brick work is anticipated to be complete the mid of November

Gypsum board installation on interior walls is 85% complete on 2nd and 3rd floors

Mechanical/Electrical/Plumbing rough-in work is 95% complete

Pulling of wiring/data lines is ongoing

Window installation is 75% complete

Exterior wall panels are being installed

Patching of terrazzo is 25% complete

Contractual Substantial Completion – November 2012

Forecasted Substantial Completion – March 2013

School Ready for Occupancy – June 2013

7

Status Date: 31 October 2012


Lawrence D. Crocker School (RSD) [2300 General Taylor Street, New Orleans, LA 70115]

Scope of work: New PK-8 School  

Funding Source – FEMA Architect – Chenevert Architects LLC

Contractor – Satterfield and Pontikes Construction Group, LLC

Final Close-out Phase

Project is Substantially Complete – October 15

The punch list is ongoing

School is Occupied – September 2012

Drew Elementary School (RSD) [3819 St. Claude Avenue, New Orleans, LA 70117]

Scope of work: Renovation of existing elementary school and new addition to meet code requirements 

Funding Source – FEMA

Architect – Blitch / Knevel Architects, Inc.

Contractor – TBD

Design Phase - CD

Design Development Documents were received on October 19th

50% Construction Documents are due December 10th

100% Construction Documents are due February 14th

Procurement Phase 

Anticipated 1st Advertisement – March 2013

Anticipated Bid Opening – April 2013

Frederick A. Douglass High School (RSD) [3820 St. Claude Avenue, New Orleans, LA 70117]

Scope of work: Renovation of existing high school 

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor – TBD

Design Phase - SD 

Schematic Design Documents were received on October 2nd

8

Status Date: 31 October 2012


 

Design Development is anticipated on December 15th

Procurement Phase 

Anticipated 1st Advertisement – May 2013

Anticipated Bid Opening – June 2013

Paul L. Dunbar School (RSD) [9330 Forshey Street, New Orleans, LA 70125]

Scope of work: New 2 - section elementary school for 556 students 

Funding Source – FEMA

Architect – Chenevert Architects LLC

Contractor – TBD

Design Phase - CD

50% Construction Documents were received on October 11th

100% Construction Documents are due December 18th

Procurement Phase 

Anticipated 1st Advertisement – January 2013

Anticipated Bid Opening – February 2013

Fisk-Howard School (RSD) [211 South Lopez Street, New Orleans, LA 70119]

Scope of work: New 3 - section elementary school for 850 students 

Funding Source - FEMA

Architect - VergesRome Architects+Fanning Howey

Contractor – TBD

Design Phase - CD

Mobilization for pile driving is anticipate the beginning of November

100% Construction Documents are anticipated to be submitted on November 12th

Procurement Phase 

Anticipated 1st Advertisement – December 2012

Anticipated Bid Opening – January 2013

9

Status Date: 31 October 2012


William Frantz School (RSD) [3811 North Galvez Street, New Orleans, LA 70117]

Scope of work: Renovation of existing elementary school and new addition 

Funding Source – FEMA

Architect – Billes Architecture, LLC

Contractor – The Lathan Company, Inc.

Construction Phase 

Contractor has abandoned the project

Owner is working with Surety to resume work

Contractual Substantial Completion – March 2012

Forecasted Substantial Completion – TBD

School Ready for Occupancy – TBD

Alice Harte School

(OPSB)

[5300 Berkley Drive, New Orleans, La 70131]

Scope of work: New 3 - section elementary school for 850 students 

Funding Source – CDBG & FEMA

Architect – WDG Architects Engineers

Contractor – Woodrow Wilson Construction Company, Inc.

Construction Phase 

The contractor has mobilized and has begun site preparation

Pile driving has started

 Contractual Substantial Completion – January 2014  Forecasted Substantial Completion – January 2014  School Ready for Occupancy – June 2014 New Karr High School at the JoEllen Smith Site (OPSB) [4400 General Meyer Avenue, New Orleans, LA 70131]

Scope of work: New medium high school 

Funding Source – FEMA

Architect – Lee Ledbetter & Associates / Gould Evans Associates

Contractor – TBD

Design Phase - CD 

Schematic Design Documents were submitted on August 17th

10

Status Date: 31 October 2012


Due to design issues and additional scope of work, Schematic Design Documents are being reviewed by the Owner

New PK-8 School at North Kenilworth Park at Curran Site (OPSB) [8500 Curran Boulevard, New Orleans, LA 70127]

Scope of work: New 3 - section elementary school for 850 students 

Funding Source – FEMA

Architect – Mathes Brierre Architects

Contractor – TBD

Procurement Phase 

1st Advertisement – September 25th

2nd Advertisement – October 2nd

3rd Advertisement – October 9th

Pre-Bid Conference – 9:00 a.m. on October 10th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA

Bid Date – November 8th

Bid Date was extended a week later due to concerns of the Bidders

Forecasted Substantial Completion – July 2014

School Ready for Occupancy – August 2014

Lake Forest PK-8 at the Greater St. Stephens Site

(OPSB)

[11110 Lake Forest Boulevard 70128]

Scope of work: New 3 - section elementary school for 850 students 

Funding Source – FEMA

Architect – Imre Hegedus & Associates Architects

Contractor – TBD

Design Phase - DD 

Design Development Documents are anticipated November 6th

Procurement Phase 

Test Pile Package 

Anticipated 1st Advertisement – October 17th

Anticipated Bid Opening – November 28th

New Construction

11

Status Date: 31 October 2012


Anticipated 1st Advertisement – April 2013

Anticipated Bid Opening – May 2013

Alfred Lawless School

(RSD)

[5300 Law Street, New Orleans, LA 70117]

Scope of work: New medium high school 

Funding Source – FEMA

Architect – Sizeler Thompson Brown Architects

Contractor – TBD

Design Phase - DD

Community Meeting #2 – October 1st

Design Development Documents are due on November 15th

50% Construction Documents are anticipated to be finished on January 21st

Procurement Phase 

Anticipated 1st Advertisement – April 2013

Anticipated Bid Opening – May 2013

Little Woods School (RSD) [10200 Curran Blvd., New Orleans, LA 70127]

Scope of work: New Pre-K – 8 school 

Funding Source – FEMA

Architect – Group Novak, LLC

Contractor – MAPP Construction

Construction Phase 

Interior brick veneer is complete

Fireproofing is complete in all areas

Window and glass installation is 95% complete

Sprinkler piping on all floors is 90% complete

Interior metal stud framing is complete

Installation of gypsum board has started

Classroom walls are finished on all floors

Installing restroom ceilings on 2nd and 3rd floors

Pulling and terminating wire into panel boxes is ongoing throughout the building

12

Status Date: 31 October 2012


Installation of fire alarm is ongoing

Entergy has energized the transformer and the building has permanent power

Contractual Substantial Completion – November 2012

Forecasted Substantial Completion – April 2013

School Ready for Occupancy – TBD

Edward Livingston High School

(RSD)

[7301 Dwyer Road, New Orleans, LA 70126]

Scope of work: New small high school 

Funding Source – FEMA

Architect – RozasWard / a.i.a. architects, inc.

Contractor – TBD

Design Phase - CD 

100% Construction Documents are due on January 21st

Procurement Phase 

Anticipated 1st Advertisement – February 2013

Anticipated Bid Opening – April 2013

McDonogh #35 School (Phillip/Waters Site)

(OPSB)

[1200 Senate Street, New Orleans, LA 70122]

Scope of work: New 3-story high school 

Funding Source – FEMA

Architect – Sizeler, Thompson, Brown Architects

Contractor - TBD

Site Remediation Project

A Phase II environmental assessment revealed heavy metals and PAHs exist in the fill

Scope of work is to remediate fly-ash materials found in the soil

Remediation work is anticipated to be completed by the end of the year

New Construction Project Ownership 

13

The resubdivision request was approved by the City Of New Orleans, recordation is pending

Status Date: 31 October 2012


 

100% Construction Documents were received on October 2nd

Procurement Phase 

1st Advertisement – October 10th

2nd Advertisement – October 17th

3rd Advertisement – October 24th

Pre-Bid Conference – 9:00 a.m. on October 31st at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA

Bid Opening – November 15th

McDonogh #42 Elementary School (RSD) [1651 North Tonti Street, New Orleans, LA 70119]

Scope of work: Renovation of existing elementary school and new addition to meet code requirements 

Funding Source – FEMA

Architect – Eskew+Dumez+Ripple

Contractor - TBD

Design Phase - DD 

Design Development Documents are anticipate November 23rd

Procurement Phase 

Anticipated 1st Advertisement – April 2013

Anticipated Bid Opening – June 2013

Eleanor L. McMain School

(OPSB)

[5721 S. Claiborne Avenue, New Orleans, LA 70125]

Scope of work: The exterior of the existing building will be stabilized and a new gym will be added to the site with a connecting breezeway to the main building. A portion of the existing building will be renovated for a health clinic. 

Exterior Stabilization 

Funding Source – FEMA

Architect – Jahncke & Burns Architects

Contractor – TBD

Design management team is reviewing alternates for window scope

14

Status Date: 31 October 2012


Design management team is assessing the existing stucco on the building

Notice to Proceed for A & E contract is anticipate November 9th

New Gymnasium and Breezway 

Funding Source – FEMA

Architect – Jahncke & Burns Architects

Contractor – TBD

Design Phase – CD 

100% Construction Documents were received on September 21st

Procurement Phase 

1st Advertisement – October 3rd

2nd Advertisement – October 10th

3rd Advertisement – October 17th

Pre-Bid Conference – 9:00 a.m. on October 17th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA

Bid Opening – November 7th

School Based Health Clinic 

Funding Source – HRSA Grant

Architect – Jahncke & Burns Architects

Contractor – TBD

Procurement Phase 

Notice to Proceed is anticipated November 14th

 Contractual Substantial Completion – 120 days after contract award Small New Orleans East High School at Abramson (RSD) [5552 Read Boulevard, New Orleans, LA 70127]

Scope of work: New small high school 

Funding Source – FEMA

Architect – RozasWard / a.i.a. architects, inc.

Contractor – TBD

Design Phase - CD 

100% Construction Documents are due on January 21st

15

Status Date: 31 October 2012


Procurement Phase 

Anticipated 1st Advertisement – February 2013

Anticipated Bid Opening – April 2013

Mildred Osborne School (RSD) [6701 Curran Blvd., New Orleans, LA 70126]

Scope of work: New Pre-K– 8 school 

Funding Source – FEMA

Architect – Fauntleroy & Latham

Contractor – F.H. Paschen, S.N. Nielsen & Associates, LLC

Construction Phase

 

Finish trades are working in the gymnasium

Landscaping is nearly complete and the fencing is ongoing

Media Center and Music Room are 95% complete

Library is 98% complete

Gymnasium is 90% complete

Contractual Substantial Completion – January 2012 This school will have a phased delivery schedule from 16th of October to end of November

Parkview School (RSD) [4617 Mirabeau Avenue, New Orleans, LA 70126]

Scope of work: New Pre-K– 8 school 

Funding Source – FEMA

Architect – Rozas-Ward

Contractor – Citadel Builders, LLC

Final Close-out Phase

Project is complete

Commissioning will begin in November

School was Occupied – 6 August 2012

16

Status Date: 31 October 2012


Booker T. Washington School (RSD) [1201 South Roman Street, New Orleans, LA 70125] Scope of work: The auditorium and entry will be renovated and the remainder of the facility will be demolished and constructed new 

Funding Source – FEMA

Architect – Hewitt-Washington & Associates

Contractor – TBD

Design Phase - CD 

100% Construction Documents are anticipated on November 13th

Upon completion of the Design Phase, the project will be put on hold until a mitigation plan is developed on the environmental issues

Phillis Wheatley Elementary School (RSD) [2300 Dumaine Street, New Orleans, LA 70119]

Scope of work: New 2 - section elementary school for 556 students 

Funding Source – FEMA

Architect – Holly & Smith Architects

Contractor – Gibbs Construction

Construction Phase 

Notice to proceeded was sent October 17th

Contractor is mobilizing

Permits are anticipated for the beginning of November

Forecasted Substantial Completion – April 2014

School Ready for Occupancy – June 2014

Fannie C. Williams School (RSD) [11755 Dwyer Road, New Orleans, LA 70128]

Scope of work: New Pre-K – 8 school 

Funding Source – FEMA

Architect – Yeates & Yeates Architects

Contractor – Brice Building Company, LLC

Final Close-out Phase 

School is complete and occupied

Substantial Completion - August 24th

17

Status Date: 31 October 2012


Carter G. Woodson School (RSD) [2514 Third Street, New Orleans, LA 70113]

Scope of work: New Pre-K – 8 school 

Funding Source – FEMA

Architect – Byron J. Stewart & Associates

Contractor – Brice Building Company, LLC

Final Close-out Phase

Project is complete

Commissioning will begin in November

School was Occupied – 17 September 2012

Sophie B. Wright Middle School Renovation

(RSD)

[1426 Napoleon Avenue, New Orleans, LA 70115]

Scope of work: Renovation of existing middle school 

Funding Source – FEMA

Architect – Waggonner & Ball Architects, APC

Contractor – TBD

Design Phase - DD  

Schematic Design Documents were delivered on September 24th Design Development Documents are anticipated December 7th

 Procurement Phase 

Anticipated 1st Advertisement – May 2013

Anticipated Bid Opening – June 2013

18

Status Date: 31 October 2012


REFURBISHMENTS Warren Easton School

(OPSB)

[3019 Canal Street, New Orleans, LA 70119]

Scope of work: Refurbishment of existing high school 

Funding Source – FEMA

Architect – Chenevert Architects LLC

Contractor - TBD

Design Phase - CD

100% Construction Documents are anticipated on December 16th

Owner requested increase in the scope of work will extend the Design Phase

Procurement Phase 

Anticipated 1st Advertisement – January 2013

Anticipated Bid Opening – February 2013

Lusher Elementary School Refurbishment (Bridge) (OPSB) [7315 Willow Street, New Orleans, LA 70118]

Scope of work: Renovation of existing bridge and restrooms to meet code requirements 

Funding Source – FEMA

Architect – Meyer Engineers, LTD.

Contractor - TBD

Design Phase - PC

Program documents were received on October 17th

Schematic Design documents are anticipated November 14th

Procurement Phase 

Anticipated 1st Advertisement – April 2013

Anticipated Bid Opening – May 2013

19

Status Date: 31 October 2012


Lusher (Fortier) High School Refurbishment

(OPSB)

[5624 Freret Street, New Orleans, LA 70115]

Scope of work: Renovation and repairs to the roof, masonry, plaster, windows, exterior doors, canopies, mechanical systems, and electrical systems. 

Funding Source – FEMA

Architect – Meyer Engineers, LTD.

Contractor - TBD

Design Phase - PC

Program documents were received on October 15th

Schematic Design documents are anticipated November 14th

Procurement Phase 

Anticipated 1st Advertisement – April 2013

Anticipated Bid Opening – May 2013

Nelson Elementary School Refurbishment

(OPSB)

[3121 St. Bernard Avenue, New Orleans, LA 70119]

Scope of work: Renovation and repairs to the roof, masonry, windows, exterior doors, mechanical systems, and electrical systems. 

Funding Source – FEMA

Architect – Harry Baker Smith Architects

ontractor - TBD

Design Phase - PC

Program documents are anticipated December 11th

Schematic Design documents are anticipated January 10th

Procurement Phase 

Anticipated 1st Advertisement – June 2013

Anticipated Bid Opening – July 2013

20

Status Date: 31 October 2012


OTHER PROJECTS Benjamin Franklin Senior High School (OPSB) [2001 Leon C. Simon Drive, New Orleans, LA 70122]

Scope of work: Renovation and repairs to the existing courtyard, exterior lighting, metal roof panels, interior lighting, curtain wall, exterior doors (frames), fencing, scoreboard and goal post 

Funding Source – FEMA

Architect – Perez, APC

Contractor – Pete Vicari General Contractors Inc.

Construction Phase

Additional courtyard work is anticipated to be complete in January

Exterior roof is complete

Electrical lighting work is 90% complete

Forecasted Contractual Substantial Completion – January 2013

Walter L. Cohen High School (RSD) [3520 Dryades Street, New Orleans, LA 70115]

Scope of work: Correct the HVAC return air / ventilation problems and replace eight (8) chilled water pumps 

Funding Source – FEMA

Architect – Infinity Engineering Consultants, LLC

Contractor – TBD

Design Phase 

A / E contract was approved at the October BESE board Meeting

Anticipated notice to procced – Late November

21

Status Date: 31 October 2012


Warren Easton School

(OPSB)

[3019 Canal Street, New Orleans, LA 70119]

Scope of work: Removal and replacement of existing exterior windows and waterproofing of the courtyard masonry 

Funding Source – Harrah’s

Architect – VergesRome Architects, apc

Contractor – Barbara Enterprises, Inc.

Final Close-out Phase 

Substantial completion September 6th

Punch list is ongoing

Contractual Substantial Completion – March 2010

Forecasted Substantial Completion – September 2012

Langston Hughes School

(RSD)

[3519 Trafalgar Street, New Orleans, LA 70119]

Scope of work: Remove abandoned dumpster pad and grease trap; replace on classroom door/hardware; correct duct system in the IT room; install fencing in place of the dumpster pad; provide and install a fence around the backflow preventer 

Funding Source – FEMA

Architect – Lachin Oubre & Associates

Contractor – Tuna Construction, LLC

Final Close-out Phase 

Project is complete

Substantial Completion – October 12, 2012

Andrew Jackson School

(RSD)

[1400 Camp Street, New Orleans, LA 70130]

Scope of work: Installation of solar panels at Andrew Jackson School. This will save energy for the school and serve as a teaching aide for students to learn about solar energy 

Funding Source – Greater New Orleans Foundation/Entergy Grant

Architect – Perez, APC

Contractor – Gulf Coast Solar

Construction Phase 

Lead time of solar panels has extended the schedule by a month

22

Status Date: 31 October 2012


 

Notice to Proceed - September 17th

Forecasted Substantial Completion – January 2013

Mahalia Jackson Elementary School Office Renovation (OPSB) [2101 Freret Street, New Orleans, LA 70113]

Scope of work: Convert the office space on the second floor of Building C into four classrooms 

Funding Source – New Orleans Parish School Board General Fund

Architect – VergesRome Architects, APAC

Contractor – TBD

Procurement Phase

The lowest bidder was non-responsive, the Owner awarded the contract to the next lowest responsive bidder.

Notice to proceeded is anticipated November 5th

Permits are in place

Forecasted Substantial Completion – January 2013

Edna Karr High School - Gymnasium Repair (OPSB) [3332 Huntlee Drive, New Orleans, LA 70131]

Scope of work: Determine what amount and methods need to be used to stabilize gymnasium for use. 

Funding Source – FEMA

Architect – Chenevert Architects, LLc

Contractor – Crescent Commercial Construction

Stablization of the Gymnasium 

Construction Phase 

Notice to proceeded is anticipated October 8th

Project is being delayed due to Entergy having to insualte the power lines

Forecasted Substantial Completion – February 2013

23

Status Date: 31 October 2012


Thomy Lafon School (RSD) [2601 Seventh St, New Orleans, LA 70115]

Scope of work: Stabilization of sculpture and creation of interperative display 

Funding Source – FEMA

Architect – Mahlum / Scairono Marinez Joint Venture

Contractor – TBD

Procurement Phase

1st Advertisement – October 31st

2nd Advertisement – November 7th

3rd Advertisement – November 14th

Pre-Bid Conference – 9:00 a.m. on November 15th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA

Bid Opening – December 5th

Construction Phase 

Notice to Proceed is anticipated early January

John McDonogh High School (RSD) [2426 Esplanade Avenue, New Orleans, LA 70119]

Scope of work: Replacement of bleachers 

Funding Source – Harrah’s

Architect – Trapolin Peer Architects, LLC

Contractor – TBD

Design Phase - CD 

The State Fire Marshal confirmed that with the addition of the new bleachers, a fire sprinkler system will be required in the gymnasium

Notice to Proceed on sprinkler design is anticipated for the beginning of November

Design is anticipated to be completed in March 2013

24

Status Date: 31 October 2012


McDonogh #35 High School (OPSB) [1331 Kerlerec Street, New Orleans, LA 70116]

Scope of work: Stabilization and replacement of elevator 

Funding Source – FEMA

Architect – Chenevert Architects LLC

Contractor – TBD

Procurement Phase

Bid Opening – September 20th

Bids were higher than expected

Project is being reviewed by the Owner

Forecasted Substantial Completion – April 2013

Timbers HVAC (OPSB) [3520 General DeGaulle, New Orleans, LA 70114]

Scope of work: Stabilization and replacement of HVAC 

Funding Source – General Fund

Architect – Moses Engineers

Contractor – TBD

Design Phase - CD 

100% Construction Documents were received on September 28th

Procurement Phase 

Anticipated 1st Advertisement – November 2012

Anticipated Bid Date – December 2012

Village de L’est Elementary School

(RSD)

[5100 Cannes Street, New Orleans, LA 70129]

Scope of work: Roof replacement and modular demolition 

Funding Source – FEMA

Architect – Richard C. Lambert Consultants, LLC

Contractor – TBD

Design Phase - CD 

100% Construction Documents are anticipated on November 5ths

Procurement Phase

25

Status Date: 31 October 2012


1st Advertisement – November 14th

2nd Advertisement – November 21st

3rd Advertisement – November 28th

Pre-Bid Conference – 9:00 a.m. on November 29th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA

Bid Opening – December 19th

Sylvanie Williams Elementary School (RSD) [3127 Martin Luther King Jr. Boulevard, New Orleans, LA 70125]

Scope of work: AHU replacement 

Funding Source – FEMA

Architect – Integrated Management Services, Inc.

Contractor – TBD

Procurement Phase

Bid Opening – September 11th

Notice to Proceed is anticipated on November 12th

Forecasted Substantial Completion – April 2013

Dwight D. Eisenhower Elementary School

(RSD)

[3700 Tall Pines Drive, New Orleans, LA 70131]

Andrew Jackson Elementary School

(RSD)

[1400 Camp Street, New Orleans, LA 70130]

Paul B. Habans Elementary School

(RSD)

[3819 Herschel Street, New Orleans, LA 70114]

Sylvanie F. Williams Elementary School

(RSD)

[3127 Martin Luther King Jr. Blvd, New Orleans, LA 70113]

Joseph S. Clark Senior High School (RSD) [1301 North Derbigny Street, New Orleans, LA 70116]

Scope of work: Roof repairs and replacement 

Funding Source – FEMA

Architect – HMS Architects, Inc.

Contractor – Hamp’s Construction, LLC

Final Close-out Phase 

Project is complete

26

Status Date: 31 October 2012


Building Automation System Integration At Recovery School District Central And Remote Offices (RSD) [Various Addresses]

Scope of work: Implementation of a Central Remote Building Automation System that integrates the existing Building Automation Systems of the 4 Quick Start Schools (Andrew H. Wilson ES, Langston Hughes ES, L.B. Landry HS, and Lake Area HS) and Joseph A. Craig ES into a central remote monitoring workstation that will include Fannie C. Williams ES, Lawrence D. Crocker ES, Mildred Osborne ES, William Frantz ES, Bienville ES, Charles J. Colton ES, Carter G. Woodson ES and Parkview ES 

Funding Source – FEMA

Architect – Moses Engineers

Contractor – Synergy Building Solutions, Inc.

Construction Phase 

The five Quick Start Schools are 95% complete, with work expected to be complete in November pending change order #2

Sylvanie Williams and Sarah T. Reed are 90% complete

The remaining integration for schools currently under construction will occur as each school is complete

Contractual Substantial Completion – November 2014

Forecasted Substantial Completion – November 2014

27

Status Date: 31 October 2012


MOTHBALL OR SAFE SELECTED SCHOOLS

&

SECURE

OF

Louis D. Armstrong Elementary School (RSD)) [5909 St. Claude Avenue, New Orleans, LA 70117]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications. 

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor – CDW Services, LLC

Mothballing of Closed Schools – Safe & Secure 

Construction Phase 

Abatement is 90% complete

Project is 28% complete

Forecasted Substantial Completion – January 2013

Israel M. Augustine Middle School

(RSD)

[425 S. Broad St., New Orleans, LA 70119]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications. 

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor – CDW Services, LLC

Mothballing of Closed Schools – Safe & Secure 

Construction Phase 

Project is 38% complete

Structural shoring is ongoing in the stairwell

Contractual Substantial Completion – November 2012

Forecasted Substantial Completion – December 2012

28

Status Date: 31 October 2012


Andrew J. Bell Junior High School

(RSD)

[1010 N. Galvez St., New Orleans, LA 70119]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications. 

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor – Cresent Commercial Construction

Emergency Shoring – 100% complete 

Shoring will remain in place until roof work is complete

Mothballing of Closed Schools – Safe & Secure

Scope of work: Mothballing of the Gymnasium, Adminstration Building, Building “D”, Chapel, and the E.A.Christy Building 

Design Phase - CD 

50% Construction Documents were received on October 25th

100% Construction Documents are anticipated to be complete on November 28th

Roof Structure Replacement 

Procurement Phase 

The contractor has mobilized and the project is 10% complete

Forecasted Substantial Completion – May 2013

29

Status Date: 31 October 2012


Oretha C. Haley Elementary School

(RSD)

[2515 N. Robertson Street, New Orleans, LA 70117]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications. 

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor – CDW Servcies, LLC

Mothballing of Closed Schools – Safe & Secure 

Final Close – out Phase 

Punchlist is 90% complete

 Contractual Substantial Completion – September 2012  Forecasted Substantial Completion – September 2012 Lorraine Hansberry Elementary School

(RSD)

[1339 Clouet Street, New Orleans, LA 70117]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications. 

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor – Tuna Construction LLC

Mothballing of Closed Schools – Safe & Secure 

Construction Phase 

Metal panels over exterior windows is 90% complete

Contractor is installing metal panels over exterior windows on the cottage

Contractual Substantial Completion – November 2012

Forecasted Substantial Completion – November 2012

30

Status Date: 31 October 2012


Morris F. X. Jeff Elementary School

(RSD)

[800 N. Rendon Street, New Orleans, LA 70119]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications. 

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor – CDW Services, LLC

Mothballing of Closed Schools – Safe & Secure 

Construction Phase 

Project is 52% complete

Contractual Substantial Completion – December 2012

Forecasted Substantial Completion – December 2012

Valena C. Jones Elementary School

(RSD)

[1901 N. Galvez Street, New Orleans, LA 70119]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications. 

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor – CDW Services, LLC

Mothballing of Closed Schools – Safe & Secure 

Construction Phase 

Project is 24% complete

Replacement of roof is ongoing

Contractual Substantial Completion – December 2012

Forecasted Substantial Completion – December 2012

31

Status Date: 31 October 2012


George Mondy Elementary School (RSD) [2327 St. Phillip Street, New Orleans, LA 70119]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications. 

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor – TBD

Project has been Canceled

John A. Shaw Elementary School (RSD) [2518 Arts Street, New Orleans, LA 70117]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications. 

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor – Zimmer-Eschette Services II, LLC

Mothballing of Closed Schools – Safe & Secure 

Final Close – Out Phase 

Punchlist is 90% complete

Contractual Substantial Completion – August 2012

Forecasted Substantial Completion – October 2012

32

Status Date: 31 October 2012


Demolition Projects Modular Classrooms at Fannie C. Williams Elementary School

(RSD)

[11755 Dwyer Street, New Orleans, LA 70128]

Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes. 

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor – Gulfcon LLC

Demolition of the Modular Classrooms 

Procurement Phase 

Bid Opening – September 18th

Notice to Proceed is anticipated early December

Owner is actively working on the property title issues and the removal of the F.F. & E.

Forecasted Substantial Completion – February 2013

Greater St. Stephens School (OPSB) [11110 Lake Forest Boulevard 70128]

Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes. 

Funding Source – FEMA

Architect – Chenevert Architects LLC

Contractor – Bayou Sheet Metal and Roofing Inc

Procurement Phase

Bid Opening – September 13th

Notice to Proceed is anticipated November 7th

Forecasted Substantial Completion – February 2013

33

Status Date: 31 October 2012


JoEllen Smith Demolition

(OPSB)

[4400 General Meyer Avenue, New Orleans, LA 70131]

Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes. 

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor – TBD

Design Phase - CD

50% Construction Documents are anticipated November 5th

100% Construction Documents are anticipated December 10th

Procurement Phase 

Anticipated 1st Advertisement – January 2013

Anticipated Bid Date – February 2013

L. B. Landry Annex Demolition

(RSD)

[1100 Wagner Street, New Orleans, LA 70114]

Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes. 

Funding Source – FEMA

Architect – Perez Architects

Contractor – Durr Heavy Construction LLC

Procurement Phase

Bid Opening – August 14th Contractor was non responsive, and the Owner is going to award the contract to the lowest responsive bidder

Notice to Proceed is anticipated middle of November

Forecasted Substantial Completion – February 2013

34

Status Date: 31 October 2012


Mary Church Terrell Elementary School Demolition (RSD) [3411 Broadway, New Orleans, LA 70125]

Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes. 

Funding Source – FEMA

Architect – SCNZ Architects

Contractor – Gill Industries, Ltd.

Procurement Phase

Bid Opening – July 31st Contractor was non responsive, and the Owner is going to award the contract to the lowest responsive bidder

Notice to Proceed is anticipated middle of November

Forecasted Substantial Completion – March 2013

Booker T. Washington High School Partial Demolition

(RSD)

[1201 S. Roman Street, New Orleans, LA 70125]

Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes. 

Funding Source – FEMA

Architect – Hewitt-Washington & Associates

Contractor – Gulfcon LLC

Partial Demolition 

Demolition Phase 

Demolition of interior of main building is 80% complete

Remediation proposals were received October 26th and are being reviewed

Contractual Substantial Completion – Feburary 2013

Forecasted Substantial Completion – February 2013

35

Status Date: 31 October 2012


Comprehensive List - Completed Projects 1.

Abrams | Morial | Abramson | Coghill Demolition

2.

A. D. Cross Elementary School Energy Conservation (RSD)

3.

A. D. Crossman Elementary School and Benjamin Banneker Elementary School (RSD)

4.

A. P. Tureaud Elementary School Roof Repairs (RSD)

5.

Agnes Bauduit Elementary School Boiler (RSD)

6.

Albert Wicker Elementary School Roof Repairs (RSD)

7.

Alfred Lawless Senior High Security Fencing (RSD)

8.

Alice M. Harte Elementary School Demolition (OPSB)

9.

Andrew H. Wilson Elementary School Cottage (RSD)

10.

Arthur Ashe Elementary School Kitchen Renovation (OPSB)

11.

Augustine Elementary School Roof (RSD)

12.

Avery-Alexander Elementary School Demolition (RSD)

13.

Barbara C. Jordan Elementary School Demolition (RSD)

14.

Bell JH Shoring (RSD)

15.

Benjamin Banneker Elementary School Energy Conservation (RSD)

16.

Bienville Elementary School Demolition (RSD)

17.

Carter G. Woodson Middle School Demolition (RSD)

18.

Central Services Warehouse Demolition (OPSB)

19.

Charles J. Colton Elementary Selective Demolition (RSD)

20.

Charles R. Drew Elementary Roof & Installation of Kitchen Hood (RSD)

21.

Cohen High School Health Clinic

22.

Douglass High School Under Floor Utilities (RSD)

23.

Dr. Martin Luther King School Roof Repairs(RSD)

24.

Dr. Martin Luther King Jr. School Renovation(RSD)

25.

East BankSwing Space for Audubon Charter School (OPSB)

26.

Edgar P. Harney Elementary School Roof Repairs (RSD)

27.

Edward Livingston Middle School Demolition(RSD)

28.

Edward Henry Phillips Junior High School Demolition (OPSB)

29.

New Edward Hynes School (OPSB)

30.

Edwards | Hardin | Lockett | Lawless Demolition (RSD)

31.

Eleanor L. McMain School Replacement of Existing Chillers (OPSB)

32.

Ernest N. Morial Elementary Security Fencing (RSD)

36

(RSD)

(RSD)

Status Date: 31 October 2012


33.

Fannie C. Williams Elementary School Demolition (RSD)

34.

Fisk-Howard Elementary School Demolition (RSD)

35.

Florence J. Chester Elementary School Demolition (RSD)

36.

Francis W. Gregory Demolition (RSD)

37.

Frederick A. Douglass High Switchgear (RSD)

38.

Frederick A. Douglass High Emergency Boiler Roof Repairs (RSD)

39.

George Washington Carver High School Demolition (RSD)

40.

Henry Allen Elementary School Roof (RSD)

41.

Henry C. Schaumburg – Window/Door, Air Condition, Water Fountain/Sink Installation (RSD)

42.

Holy Cross Modular Relocation (RSD)

43.

Israel M. Augustine Middle School Roof Replacement (RSD)

44.

James Derham Demolition (RSD)

45.

James W. Johnson Elementary School Roof (RSD)

46.

New Jean Batiste de Bienville School (RSD)

47.

Jean Gordon Elementary School Demolition (RSD)

48.

John Dibert Elementary School Roof (RSD)

49.

John W. Hoffman Elementary School Demolition (RSD)

50.

John F. Kennedy Modular Relocation (Schwarz Campus) (RSD)

51.

John F. Kennedy Modular Relocation (Coghill Modular Campus) (RSD)

52.

John F. Kennedy High School Demolition (RSD)

53.

John McDonogh Senior High School Roof (RSD)

54.

Joseph A. Craig Elementary Canopies (RSD)

55.

Joseph A. Craig Elementary Elevator Installation (RSD)

56.

Joseph A. Hardin Elementary Security Fencing (RSD)

57.

Lafayette Elementary School Roof and Masonry(RSD)

58.

Lake Area | Landry Demolition (RSD)

59.

Langston Hughes Elementary School (Phase I) (RSD)

60.

Langston Hughes Elementary School – New Gymnasium (Phase II) (RSD)

61.

Lawrence D. Crocker Elementary School Demolition (RSD)

62.

Little Woods Elementary School Demolition (RSD)

63.

Live Oak Elementary School Roof (RSD)

64.

Live Oak Elementary School Exterior Door Replacement (RSD)

65.

Mahalia Jackson Elementary School (OPSB)

37

Status Date: 31 October 2012


66.

Mahalia Jackson Elementary School Dumpster / Other Improvements(OPSB)

67.

Martin Behrman Elementary School Roof (RSD)

68.

Martin Luther King Jr. Elementary Canopy System (RSD)

69.

Martin Luther King Jr. School Modular Building, Deck, Canopy (RSD)

70.

Mary M. Bethune Elementary 1st Floor Replacement (OPSB)

71.

Mary M. Bethune Elementary Rear Yard Repair/Resurfacing (OPSB)

72.

McDonogh #15 Elementary Exterior Masonry to SOI Standards (RSD)

73.

McDonogh #28 Elementary School Roof

74.

McDonogh #32 Roof Replacement (RSD)

75.

McDonogh #35 ADA Upgrades to Public Restrooms, Exterior Ramp & Handicap Seating in the Auditorium (OPSB)

76.

McDonogh #42 Elementary School Roof (RSD)

77.

McDonogh #42 Elementary School HVAC Replacement (RSD)

78.

Mildred C. Osborne Elementary School Demolition

79.

Modular Campuses Close Outs (RSD)

80.

Modular Structures at Langston Hughes Elementary School (RSD)

81.

Morris F.X. Jeff Elementary School Demolition (RSD)

82.

Murray G. Henderson Elementary School Roof (RSD)

83.

New Andrew H. Wilson Elementary School (RSD)

84.

New Joseph A. Craig Elementary School (RSD)

85.

New Lake Area High School

86.

New L.B. Landry High School (RSD)

87.

New Equipment & Upgrades at 8 Central & 25 Satellite Kitchens (RSD)

88.

New Orleans High School Signature Center Study (RSD)

89.

Oretha C. Haley Demo (RSD)

90.

Parkview Elementary School Demolition

91.

Paul L. Dunbar Elementary School Demolition (RSD)

92.

Phillis Wheatley Elementary School Demolition (RSD)

93.

Robert M. Lusher Elementary Roof Removal & Replacement

(RSD)

(RSD)

(RSD)

(RSD)

(OPSB)

94.

Sarah T. Reed High School Bleachers (RSD)

95.

Sarah T. Reed High School Auditorium Wall (RSD)

96.

Seabrook Computer Training Center Demolition (OPSB)

97.

Schaumburg Chillers (RSD)

38

Status Date: 31 October 2012


98.

Schwarz Alternative Repairs

99.

Schwarz Alternative Modulars Demolition (RSD)

(RSD)

100. Sherwood Forest Elementary School Demolition (RSD) 101. Sophie B. Wright Various Repairs/Restroom Renovations (OPSB) 102. Stuart R. Bradley Elementary School Demolition

(RSD)

103. Sylvanie Williams Elementary School Play Yard (RSD) 104. Sylvanie Williams Elementary School HVAC/Chiller Replacement (RSD)

105. Temporary Campus for McDonogh #11 Expropriation (OPSB) 106. Thomas A. Edison Elementary School Demolition (RSD) 107. Thomy Lafon Elementary School Demolition (RSD) 108. Timbers Park Office Building #1 & #2 Demolition (OPSB) 109. Village de L’est Elementary School Subsidence (RSD) 110. Vorice J. Waters Elementary School Demolition (RSD) 111. West Bank Swing Space for Alice Harte Elementary School (OPSB) 112. New William J. Guste Elementary School (RSD) 113. William J. Guste Elementary School Science Lab (RSD) 114. William Frantz Elementary School Environmental Remediation & Selective Demolition (RSD) 115. William Frantz Elementary School Roof (RSD)

39

Status Date: 31 October 2012