Superintendents’ Report November 2012
Mr. Stanley C. Smith Orleans Parish School Board
Mr. John White Louisiana Department of Education
Mr. Patrick Dobard Recovery School District
Prepared by:
Table of Contents Right-Click on the school name to proceed to that page
TABLE OF CONTENTS ..................................................... 1 OVERVIEW......................................................................... 3 COMMUNITY MEETINGS .................................................. 4 BID OPENINGS .................................................................. 4 NEW & MAJOR RENOVATION ......................................... 6 Audubon School (OPSB).............................................. 6 Stuart R. Bradley School (RSD) .................................. 6 George Washington Carver School (RSD) .................. 7 Charles J. Colton School (RSD) .................................. 7 Drew Elementary School (RSD) ................................. 8 Frederick A. Douglass High School (RSD) ................. 8 Paul L. Dunbar School (RSD) ...................................... 9 Fisk-Howard School (RSD) ......................................... 9 William Frantz School (RSD) ..................................... 10 Alice Harte School (OPSB) ........................................ 10 New Karr High School at the JoEllen Smith Site (OPSB) ............................................................................... 10 New PK-8 School at North Kenilworth Park at Curran Site (OPSB)................................................................ 11 Lake Forest PK-8 at the Greater St. Stephens Site (OPSB) ....................................................................... 11 Alfred Lawless School (RSD) .................................... 12 Little Woods School (RSD) ........................................ 12 Edward Livingston High School (RSD) ..................... 13 McDonogh #35 School (Phillip/Waters Site) (OPSB). 13 McDonogh #42 Elementary School (RSD) ............... 14 Eleanor L. McMain School (OPSB) ........................... 14 Small New Orleans East High School at Abramson (RSD) ....................................................................... 15 Mildred Osborne School (RSD) ................................ 15 Booker T. Washington School (RSD) ........................ 16 Phillis Wheatley Elementary School (RSD) ............... 16 Sophie B. Wright School (RSD) ................................ 17 Bundy Road Space (OPSB) ...................................... 17
REFURBISHMENTS ......................................................... 18 Agnes L. Bauduit Elementary School Refurbishment (RSD) ........................................................................ 18 A. D. Crossman School Refurbishment (RSD) .......... 18 Warren Easton School Refurbishment (OPSB) .......... 19 Dwight D. Eisenhower High School Refurbishment (RSD) ......................................................................... 19 Gentilly Terrace School Refurbishment (RSD) ........... 20 Andrew Jackson School Refurbishment (RSD) .......... 20
1
Status Date: 30 November 2012
Dr. Martin L. King Elementary School Refurbishment (RSD) ......................................................................... 21 Lusher Elementary School Refurbishment (OPSB) ... 21 Lusher (Fortier) High School Refurbishment (OPSB) . 22 McDonogh #28 School Refurbishment (RSD) ............ 22 Nelson Elementary School Refurbishment (OPSB) .... 23 Sarah T. Reed School Refurbishment (RSD)............. 23 Albert Wicker School Refurbishment (RSD)............... 24 Sylvanie F. Williams School Refurbishment (RSD) .... 24 OTHER PROJECTS ......................................................... 25 Benjamin Franklin Senior High School (OPSB) .......... 25 Walter L. Cohen High School (RSD) ......................... 25 Warren Easton School (OPSB) ................................. 26 Andrew Jackson School (RSD) ................................ 26 Mahalia Jackson Elementary School Office Renovation (OPSB) .................................................... 26 Edna Karr High School - Gymnasium Repair (OPSB) ............................................................................... 27 Thomy Lafon School (RSD) ....................................... 27 John McDonogh High School (RSD) ......................... 28 McDonogh #35 High School (OPSB) ......................... 28 Timbers HVAC (OPSB) .............................................. 29 Village de’ Lest Elementary School (RSD) ................ 29 Sylvanie Williams Elementary School (RSD) ............. 30 Building Automation System Integration At Recovery School District Central And Remote Offices (RSD) .. 30 MOTHBALL OR SAFE & SECURE OF SELECTED SCHOOLS ........................................................................ 31 Louis D. Armstrong Elementary School (RSD)) ......... 31 Israel M. Augustine Middle School (RSD)................. 31 Andrew J. Bell Junior High School (RSD) ................. 32 Lorraine Hansberry Elementary School (RSD) ......... 33 Morris F. X. Jeff Elementary School (RSD) .............. 33 Valena C. Jones Elementary School (RSD) ............. 34 DEMOLITION PROJECTS ............................................... 35 Modular Classrooms at Fannie C. Williams Elementary School (RSD) ........................................ 35 Greater St. Stephens School (OPSB) ........................ 35 JoEllen Smith Demolition (OPSB) .............................. 36 L. B. Landry Annex Demolition (RSD) ...................... 36 Mary Church Terrell Elementary School Demolition (RSD) ) ....................................................................... 37 Booker T. Washington High School Partial Demolition (RSD) ..................................................... 37 COMPLETED PROJECTS .............................................. 38
2
Status Date: 30 November 2012
Overview The RSD has $385 million in open contracts for the capital program after issuing $1.9 million in new contracts and $833 thousand in change orders and amendments in November. In addition, the total change orders to date, $7.7 million, account for approximately three percent (2.60%) of the total open construction contracts. RSD anticipates issuing approximately $694 thousand in construction contracts
and
$70
thousand
in
professional
service
contracts/amendments in December.
The OPSB has $96.8 million in open contracts for the capital program after issuing no new contracts and $177 thousand in change orders and amendments in November. In addition, the total change orders to date, $1.09 million, account for approximately two percent (1.59 %) of the total open construction contracts. OPSB anticipates issuing approximately $352 thousand in construction contracts and professional service contracts in December.
3
Status Date: 30 November 2012
Community Meetings No Community Meetings were scheduled for the month of November No Community Meetings are anticipated for the month of December
4
Status Date: 30 November 2012
Bid Openings Bids that were opened in November 2012:
New Gym Addition at Eleanor McMain Secondary High School (OPSB) – November 7, 2012
New PK-8 School at North Kenilworth Park at Curran Site November 8, 2012
New McDonogh #35 School at Phillips /Waters Site (OPSB) – November 15, 2012
Test Pile Program at Bradley (RSD) – November 27, 2012
Test Pile Program at Lake Forest PK-8 at the Greater St. Stephens Site (OPSB) – November 28, 2012
(OPSB)
Over the next sixty days, bids to be opened for the following projects:
Thomy Lafon Interpretive Display (RSD) – December 5, 2012
Timbers HVAC Repairs (OPSB) – December 20, 2012
Village de L’est Elementary School Roof and Modular Demolition (RSD) – January 9, 2013
Test Pile Program at Sophie B. Wright (RSD) – January 23, 2013
Fisk-Howard School (RSD) – January 30, 2013
5
Status Date: 30 November 2012
–
Forecasted dates only include the next project phase
New & Major Renovation – Project Status Audubon School (OPSB) [428 Broadway Avenue, New Orleans, LA 70118]
Scope of work: Renovation & Addition of Existing Elementary School
Funding Source – FEMA
Architect – Blitch/Knevel Architects
Contractor – FHP Tectonics Corporation
Construction Phase
Pile driving began at the end of November
Metal stud framing has started in existing building
Under slab plumbing layout in the existing building is complete
Above ceiling gypsum board assembly is complete
Vertical ductwork is complete, horizontal ductwork is ongoing
The removal of the clay tile roof and installation of new decking has started
Contractual Substantial Completion – September 2013
Forecasted Substantial Completion – February 2014
School Ready for Occupancy – May 2014
Stuart R. Bradley School
(RSD)
[ 2401 Humanity Street, New Orleans, LA 70122]
Scope of work: New 3 – section elementary school for 850 students
Funding Source – FEMA
Architect – Sizeler Thompson Brown Architects
Contractor – TBD
Design Phase – CD
100% Construction Documents are anticipated December 21st
Procurement Phase
Test Pile package Bid Opening – November 27th
Test Pile Bids are being reviewed
Anticipated Construction package 1st Advertisement – January 2013
Anticipated Construction package Bid Opening – March 2013
6
Status Date: 30 November 2012
George Washington Carver School (RSD) [3019 & 3059 Higgins Blvd., New Orleans, LA 70126]
Scope of work: New High School
Funding Source – FEMA
Architect – Trapolin Architects & VMDO Architects, A Joint- Venture
Contractor – TBD
Design Phase
The RSD is working with key stakeholders to value engineer this project in an effort to reduce the cost
Items being explored include: Foundation redesign Reduced ceiling heights Repurpose areas of the building Use of cost effective construction materials Changing the project delivery methods Scaling back on architectural elements
Charles J. Colton School (RSD) [2300 St. Claude Avenue, New Orleans, LA 70117]
Scope of work: Renovation of existing elementary school and new addition
Funding Source – FEMA
Architect – Waggonner & Ball Architects
Contractor – F.H. Paschen, S.N. Nielsen & Associates, LLC
Construction Phase
Roofing material installation is 90% complete
Exterior brick work is complete
Gypsum board installation on interior walls is 85% complete on 2nd and 3rd floors
Pulling of wiring/data lines is ongoing
Window installation is complete, glazing is 70% complete
Exterior wall panels are 15% complete
Patching of terrazzo is 80% complete
VCT floor install has started
The installation of electrical fixtures and raceways has started
Contractual Substantial Completion – November 2012
7
Status Date: 30 November 2012
Forecasted Substantial Completion – March 2013
School Ready for Occupancy – June 2013
Drew Elementary School (RSD) [3819 St. Claude Avenue, New Orleans, LA 70117]
Scope of work: Renovation of existing elementary school and new addition to meet code requirements
Funding Source – FEMA
Architect – Blitch / Knevel Architects, Inc.
Contractor – TBD
Design Phase - CD
50% Construction Documents are anticipated December 10th
100% Construction Documents are anticipated February 14th
Procurement Phase
Anticipated 1st Advertisement – March 2013
Anticipated Bid Opening – April 2013
Frederick A. Douglass High School (RSD) [3820 St. Claude Avenue, New Orleans, LA 70117]
Scope of work: Renovation of existing high school
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – TBD
Design Phase - SD
Design Development is anticipated on December 15th
The building will be used for swing space for the next two years
The student population at Drew is overwhelmingly made up of children living in the neighborhood, so having swing space nearby for those students is crucial while Drew is being renovated
8
Status Date: 30 November 2012
Paul L. Dunbar School (RSD) [9330 Forshey Street, New Orleans, LA 70125]
Scope of work: New 2 - section elementary school for 556 students
Funding Source – FEMA
Architect – Chenevert Architects LLC
Contractor – TBD
Design Phase - CD
100% Construction Documents are anticipated December 18th
Procurement Phase
Anticipated 1st Advertisement – January 2013
Anticipated Bid Opening – February 2013
Fisk-Howard School (RSD) [211 South Lopez Street, New Orleans, LA 70119]
Scope of work: New 3 - section elementary school for 850 students
Funding Source - FEMA
Architect - VergesRome Architects+Fanning Howey
Contractor – TBD
Design Phase - CD
Test Pile reports are anticipated November 30th
100% Construction Documents were received on November 12th
Bid Package is anticipated December 7th
Procurement Phase
1st Advertisement – December 26th
2nd Advertisement – January 2nd
3rd Advertisement – January 9th
Pre-Bid Conference – 9:00 a.m. on January 10tht at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA
Bid Opening – January 30th
9
Status Date: 30 November 2012
William Frantz School (RSD) [3811 North Galvez Street, New Orleans, LA 70117]
Scope of work: Renovation of existing elementary school and new addition
Funding Source – FEMA
Architect – Billes Architecture, LLC
Contractor – The Lathan Company, Inc.
Construction Phase
Contractor has remobilized on site
All major trades to be on site by December 3rd
Contractual Substantial Completion – March 2012
Forecasted Substantial Completion – June 2013
School Ready for Occupancy – August 2013
Alice Harte School
(OPSB)
[5300 Berkley Drive, New Orleans, La 70131]
Scope of work: New 3 - section elementary school for 850 students
Funding Source – CDBG & FEMA
Architect – WDG Architects Engineers
Contractor – Woodrow Wilson Construction Company, Inc.
Construction Phase
Pile driving is ongoing
Contractual Substantial Completion – January 2014 Forecasted Substantial Completion – January 2014 School Ready for Occupancy – June 2014 New Karr High School at the JoEllen Smith Site (OPSB) [4400 General Meyer Avenue, New Orleans, LA 70131]
Scope of work: New medium high school
Funding Source – FEMA
Architect – Lee Ledbetter & Associates / Gould Evans Associates
Contractor – TBD
Design Phase - CD
Due to design issues and additional scope of work, Schematic Design Documents were rejected by the Owner
10
Status Date: 30 November 2012
New PK-8 School at North Kenilworth Park at Curran Site (OPSB) [8500 Curran Boulevard, New Orleans, LA 70127]
Scope of work: New 3 - section elementary school for 850 students
Funding Source – FEMA
Architect – Mathes Brierre Architects
Contractor – TBD
Procurement Phase
Bid Date – November 8th
Owner is reviewing the Bids
Notice to Proceed is anticipated mid-February
Forecasted Substantial Completion – July 2014
School Ready for Occupancy – August 2014
Lake Forest PK-8 at the Greater St. Stephens Site
(OPSB)
[11110 Lake Forest Boulevard 70128]
Scope of work: New 3 - section elementary school for 850 students
Funding Source – FEMA
Architect – Imre Hegedus & Associates Architects
Contractor – TBD
Design Phase - DD
Design Development Documents were received on November 6th
50% Construction Documents are anticipated on January 3rd
Procurement Phase
Test Pile Package
Bid Opening – November 28th
Bids are being reviewed
New Construction
Anticipated 1st Advertisement – April 2013
Anticipated Bid Opening – May 2013
11
Status Date: 30 November 2012
Alfred Lawless School
(RSD)
[5300 Law Street, New Orleans, LA 70117]
Scope of work: New medium high school
Funding Source – FEMA
Architect – Sizeler Thompson Brown Architects
Contractor – TBD
Design Phase - DD
Design Development documents were received on November 15th
50% Construction documents are anticipated to be finished on January 25th
Procurement Phase
Anticipated 1st Advertisement – April 2013
Anticipated Bid Opening – May 2013
Little Woods School (RSD) [10200 Curran Blvd., New Orleans, LA 70127]
Scope of work: New Pre-K – 8 school
Funding Source – FEMA
Architect – Group Novak, LLC
Contractor – MAPP Construction
Construction Phase
Terrazzo flooring will start the beginning of December
CMU walls on 2nd and 3rd floor are painted, gypsum board walls are taped, floated and painted
Installing restroom ceilings on 2nd and 3rd floors
Ceiling grid is being installed in the Cafeteria
Window and glass installation is 90% complete
Sprinkler piping on all floors is 90% complete
Electrical raceways are being installed
Installation of fire alarm is ongoing
12,000 sf of parking has been formed up and will be poured beginning of December
Contractual Substantial Completion – November 2012
Forecasted Substantial Completion – April 2013
School Ready for Occupancy – TBD
12
Status Date: 30 November 2012
Edward Livingston High School
(RSD)
[7301 Dwyer Road, New Orleans, LA 70126]
Scope of work: New small high school
Funding Source – FEMA
Architect – RozasWard / a.i.a. architects, inc.
Contractor – TBD
Design Phase - CD
100% Construction Documents are due on January 21st
Procurement Phase
Anticipated 1st Advertisement – February 2013
Anticipated Bid Opening – April 2013
McDonogh #35 School (Phillip/Waters Site)
(OPSB)
[1200 Senate Street, New Orleans, LA 70122]
Scope of work: New 3-story high school
Funding Source – FEMA
Architect – Sizeler, Thompson, Brown Architects
Contractor - TBD
Site Remediation Project
A Phase II environmental assessment revealed heavy metals and PAHs exist in the fill
Scope of work is to remediate fly-ash materials found in the soil
Remediation work is anticipated to be complete 1st quarter of 2013
New Construction Project
Procurement Phase
Bid Opening – November 15th
Bids are being reviewed by the Owner
Notice to Proceed – February
13
Status Date: 30 November 2012
McDonogh #42 Elementary School (RSD) [1651 North Tonti Street, New Orleans, LA 70119]
Scope of work: Renovation of existing elementary school and new addition to meet code requirements
Funding Source – FEMA
Architect – Eskew+Dumez+Ripple
Contractor - TBD
Design Phase - DD
Design Development Documents were received November 26rd
50% Construction Documents are anticipated January 24th
Procurement Phase
Anticipated 1st Advertisement – April 2013
Anticipated Bid Opening – June 2013
Eleanor L. McMain School
(OPSB)
[5721 S. Claiborne Avenue, New Orleans, LA 70125]
Scope of work: The exterior of the existing building will be stabilized and a new gym will be added to the site with a connecting breezeway to the main building. A portion of the existing building will be renovated for a health clinic.
Exterior Stabilization
Funding Source – FEMA
Architect – Jahncke & Burns Architects
Contractor – TBD
Basis of Design for the windows has been accepted
Design management team is assessing the existing stucco on the building
New Gymnasium
Funding Source – FEMA
Architect – Jahncke & Burns Architects
Contractor – TBD
Procurement Phase
Bid Opening – November 7th
Bids are being reviewed by the Owner
School Based Health Clinic
14
Status Date: 30 November 2012
Funding Source – HRSA Grant
Architect – Jahncke & Burns Architects
Contractor – ETI. Inc.
Procurement Phase
Notice to Proceed was issued November 15th
Contractual Substantial Completion – March 2013 Small New Orleans East High School at Abramson (RSD) [5552 Read Boulevard, New Orleans, LA 70127]
Scope of work: New small high school
Funding Source – FEMA
Architect – RozasWard / a.i.a. architects, inc.
Contractor – TBD
Design Phase - CD
100% Construction Documents are anticipated January 21st
Procurement Phase
Anticipated 1st Advertisement – February 2013
Anticipated Bid Opening – April 2013
Mildred Osborne School (RSD) [6701 Curran Blvd., New Orleans, LA 70126]
Scope of work: New Pre-K– 8 school
Funding Source – FEMA
Architect – Fauntleroy & Latham
Contractor – F.H. Paschen, S.N. Nielsen & Associates, LLC
Construction Phase
Landscaping and the fencing is 95% complete
Media Center and Library are 98% complete
Music Room and Gymnasium are complete and turned over to the charter
Contractual Substantial Completion – January 2012 This school will have a phased delivery schedule from 16th of October to end of December
15
Status Date: 30 November 2012
Booker T. Washington School (RSD) [1201 South Roman Street, New Orleans, LA 70125] Scope of work: The auditorium and entry will be renovated and the remainder of the facility will be demolished and constructed new
Funding Source – FEMA
Architect – Hewitt-Washington & Associates
Contractor – TBD
Design Phase - CD
Upon completion of the Design Phase, the project will be put on hold until a mitigation plan is developed on the environmental issues
Based on current market projections, the RSD is working with key stakeholders to value engineer this project in an effort to reduce the cost
Items being explored include: Reduced ceiling heights Repurpose areas of the building Use of cost effective construction materials Changing the project delivery methodology Scaling back on architectural elements
Phillis Wheatley Elementary School (RSD) [2300 Dumaine Street, New Orleans, LA 70119]
Scope of work: New 2 - section elementary school for 556 students
Funding Source – FEMA
Architect – Holly & Smith Architects
Contractor – Gibbs Construction
Construction Phase
Site clearing is ongoing
Pile layour has begun
Pile driving to begin the 1st week of December
Forecasted Substantial Completion – April 2014
School Ready for Occupancy – June 2014
16
Status Date: 30 November 2012
Sophie B. Wright Middle School Renovation
(RSD)
[1426 Napoleon Avenue, New Orleans, LA 70115]
Scope of work: Renovation of existing middle school
Funding Source – FEMA
Architect – Waggonner & Ball Architects, APC
Contractor – TBD
Design Phase - DD
Design Development Documents are anticipated December 7th
50% Construction Documents are anticipated on February 5th
Procurement Phase
Anticipated 1st Advertisement – May 2013
Anticipated Bid Opening – June 2013
Bundy Road Space (OPSB) [6767 Bundy Road, New Orleans, LA 70127]
Scope of work: Renovation of existing office complex into a school
Architect – VergesRome Architects, APAC
Contractor – TBD
Design Phase - FS
Feasibility study was performed to determine if an office complex can be converted into a school
RSD will work with OPSB to procure the site
The conversion of this site to a school is more cost effective than building a new school
The building will have the flexibility to house a K-12 program
17
Status Date: 30 November 2012
REFURBISHMENTS Agnes L. Bauduit Elementary School Refurbishment
(RSD)
[3649 Laurel Street, New Orleans, LA 70115]
Scope of work: Refurbishment of existing high school, including but not limited to structure, windows, doors, masonry walls and roof
Funding Source – FEMA
Architect – Duplantis Design Group, PC
Contractor - TBD
Design Phase - PC
Program documents are anticipated on December 4th
Schematic Design documents are anticipated on January 3rd
Procurement Phase
Anticipated 1st Advertisement – July 2013
Anticipated Bid Opening – August 2013
A. D. Crossman School Refurbishment
(RSD)
[4407 South Carrollton Avenue, New Orleans, LA 70119]
Scope of work: Refurbishment of existing high school, including but not limited to structure, windows, doors, masonry walls and roof
Funding Source – FEMA
Architect – Perez, APC
Contractor - TBD
Design Phase - PC
Program documents were received on November 26th
Schematic Design documents are anticipated on December 18th
Procurement Phase
Anticipated 1st Advertisement – March 2013
Anticipated Bid Opening – April 2013
18
Status Date: 30 November 2012
Warren Easton School
(OPSB)
[3019 Canal Street, New Orleans, LA 70119]
Scope of work: Refurbishment of existing high school
Funding Source – FEMA
Architect – Chenevert Architects LLC
Contractor - TBD
Design Phase - CD
100% Construction Documents are anticipated on December 16th
Owner requested an increase in the scope of work which will extend the Design Phase
Procurement Phase
Anticipated 1st Advertisement – January 2013
Anticipated Bid Opening – February 2013
Dwight D. Eisenhower High School Refurbishment
(RSD)
[3700 Tall Pines Drive, New Orleans, LA 70131]
Scope of work: Refurbishment of existing high school, including but not limited to structure, windows, doors, masonry walls and roof
Funding Source – FEMA
Architect – Harry Baker Smith Architects II, PLLC
Contractor - TBD
Design Phase - PC
Program documents are anticipated on December 8th
Schematic Design documents are anticipated on January 11th
Procurement Phase
Anticipated 1st Advertisement – August 2013
Anticipated Bid Opening – September 2013
19
Status Date: 30 November 2012
Gentilly Terrace School Refurbishment
(RSD)
[4720 Painters Street, New Orleans, LA 70122]
Scope of work: Refurbishment of existing high school, including but not limited to structure, windows, doors, masonry walls and roof
Funding Source – FEMA
Architect – Byron J. Stewart & Associates, APC Architects & Planners
Contractor - TBD
Design Phase - PC
Program documents were received on November 21st
Schematic Design documents are anticipated on December 17th
Procurement Phase
Anticipated 1st Advertisement – March 2013
Anticipated Bid Opening – April 2013
Andrew Jackson School Refurbishment
(RSD)
[1400 Camp Street, New Orleans, LA 70130]
Scope of work: Refurbishment of existing high school, including but not limited to structure, windows, doors, masonry walls and roof
Funding Source – FEMA
Architect – N-Y Associates, Inc.
Contractor - TBD
Design Phase - PC
Program documents were received on November 27th
Schematic Design documents are anticipated on December 23th
Procurement Phase
Anticipated 1st Advertisement – May 2013
Anticipated Bid Opening – June 2013
20
Status Date: 30 November 2012
Dr. Martin L. King Elementary School Refurbishment
(RSD)
[1617 Caffin Avenue, New Orleans, LA 70117]
Scope of work: Refurbishment of existing high school, including but not limited to structure, windows, doors, masonry walls and roof
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor - TBD
Design Phase - PC
Program documents were received on November 20th
Schematic Design documents are anticipated on January 3rd
Procurement Phase
Anticipated 1st Advertisement – July 2013
Anticipated Bid Opening – August 2013
Lusher Elementary School Refurbishment (OPSB) [7315 Willow Street, New Orleans, LA 70118]
Scope of work: Renovation and repairs to the existing bridge, roof, windows, exterior doors, and restroom accessibility
Funding Source – FEMA
Architect – Meyer Engineers, LTD.
Contractor - TBD
Design Phase - PC
Schematic Design documents were received November 14th
Design Development documents are anticipated on December 29th
Procurement Phase
Anticipated 1st Advertisement – April 2013
Anticipated Bid Opening – May 2013
21
Status Date: 30 November 2012
Lusher (Fortier) High School Refurbishment
(OPSB)
[5624 Freret Street, New Orleans, LA 70115]
Scope of work: Renovation and repairs to the roof, masonry, plaster, windows, exterior doors, canopies, mechanical systems, and electrical systems.
Funding Source – FEMA
Architect – Meyer Engineers, LTD.
Contractor - TBD
Design Phase - PC
Schematic Design documents were received November 14th
Design Development documents are anticipated on December 31st
Procurement Phase
Anticipated 1st Advertisement – April 2013
Anticipated Bid Opening – May 2013
McDonogh #28 School Refurbishment
(RSD)
[2733 Esplanade Avenue, New Orleans, LA 70119]
Scope of work: Refurbishment of existing high school, including but not limited to structure, windows, doors, masonry walls and roof
Funding Source – FEMA
Architect – SCNZ Architects,LLC
Contractor - TBD
Design Phase - PC
Program documents were received on November 26th
Schematic Design documents are anticipated on December 17th
Procurement Phase
Anticipated 1st Advertisement – March 2013
Anticipated Bid Opening – April 2013
22
Status Date: 30 November 2012
Nelson Elementary School Refurbishment
(OPSB)
[3121 St. Bernard Avenue, New Orleans, LA 70119]
Scope of work: Renovation and repairs to the roof, masonry, windows, exterior doors, mechanical systems, and electrical systems.
Funding Source – FEMA
Architect – Harry Baker Smith Architects
ontractor - TBD
Design Phase - PC
Program documents are anticipated December 11th
Schematic Design documents are anticipated January 10th
Procurement Phase
Anticipated 1st Advertisement – June 2013
Anticipated Bid Opening – July 2013
Sarah T. Reed School Refurbishment
(RSD)
[5316 Michoud Boulevard, New Orleans, LA 70129]
Scope of work: Refurbishment of existing high school, including but not limited to structure, windows, doors, masonry walls and roof
Funding Source – FEMA
Architect – Byron J. Stewart & Associates, APC Architects & Planners
Contractor - TBD
Design Phase - PC
Program documents are anticipated on December 6th
Schematic Design documents are anticipated on January 9th
Procurement Phase
Anticipated 1st Advertisement – August 2013
Anticipated Bid Opening – September 2013
23
Status Date: 30 November 2012
Albert Wicker School Refurbishment
(RSD)
[2011 Bienville Street, New Orleans, LA 70112]
Scope of work: Refurbishment of existing high school, including but not limited to structure, windows, doors, masonry walls and roof
Funding Source – FEMA
Architect – SCNZ Architects, LLC
Contractor - TBD
Design Phase - PC
Program documents are anticipated on December 6th
Schematic Design documents are anticipated on January 4th
Procurement Phase
Anticipated 1st Advertisement – July 2013
Anticipated Bid Opening – August 2013
Sylvanie F. Williams School Refurbishment
(RSD)
[3127 Martin Luther KingJr. Boulevard, New Orleans, LA 70125]
Scope of work: Refurbishment of existing high school, including but not limited to structure, windows, doors, masonry walls and roof
Funding Source – FEMA
Architect – Chenevert Architects, LLC
Contractor - TBD
Design Phase - PC
Program documents were received on November 30th
Schematic Design documents are anticipated on January 3rd
Procurement Phase
Anticipated 1st Advertisement – August 2013
Anticipated Bid Opening – September 2013
24
Status Date: 30 November 2012
OTHER PROJECTS Benjamin Franklin Senior High School (OPSB) [2001 Leon C. Simon Drive, New Orleans, LA 70122]
Scope of work: Renovation and repairs to the existing courtyard, exterior lighting, metal roof panels, interior lighting, curtain wall, exterior doors (frames), fencing, scoreboard and goal post
Funding Source – FEMA
Architect – Perez, APC
Contractor – Pete Vicari General Contractors Inc.
Construction Phase
Additional courtyard work is anticipated to be complete in January 2013
Electrical lighting work is 95% complete
Forecasted Contractual Substantial Completion – January 2013
Walter L. Cohen High School (RSD) [3520 Dryades Street, New Orleans, LA 70115]
Scope of work: Correct the HVAC return air / ventilation problems and replace eight (8) chilled water pumps
Funding Source – FEMA
Architect – Infinity Engineering Consultants, LLC
Contractor – TBD
Design Phase - PC
Schematic Design documents are anticipated December 23rd
Procurement Phase
Anticipated 1st Advertisement – March 2013
Anticipated Bid Opening – April 2013
25
Status Date: 30 November 2012
Warren Easton School
(OPSB)
[3019 Canal Street, New Orleans, LA 70119]
Scope of work: Removal and replacement of existing exterior windows and waterproofing of the courtyard masonry
Funding Source – Harrah’s
Architect – VergesRome Architects, apc
Contractor – Barbara Enterprises, Inc.
Final Close-out Phase
Substantial completion September 6th
The Owner has put the contractor in default and will contact the Surety
Contractual Substantial Completion – March 2010
Forecasted Substantial Completion – September 2012
Andrew Jackson School
(RSD)
[1400 Camp Street, New Orleans, LA 70130]
Scope of work: Installation of solar panels at Andrew Jackson School. This will save energy for the school and serve as a teaching aide for students to learn about solar energy
Funding Source – Greater New Orleans Foundation/Entergy Grant
Architect – Perez, APC
Contractor – South Coast Solar
Construction Phase
Contractor has mobilized and is expected to start installation in early December
Forecasted Substantial Completion – January 2013
Mahalia Jackson Elementary School Office Renovation (OPSB) [2101 Freret Street, New Orleans, LA 70113]
Scope of work: Convert the office space on the second floor of Building C into four classrooms
Funding Source – New Orleans Parish School Board General Fund
Architect – VergesRome Architects, APAC
Contractor – ETI, Inc.
Construction Phase
Notice to proceed - November 5th
26
Status Date: 30 November 2012
Contractor has mobilized and has started work
Forecasted Substantial Completion – January 2013
Edna Karr High School - Gymnasium Repair (OPSB) [3332 Huntlee Drive, New Orleans, LA 70131]
Scope of work: Determine what amount and methods need to be used to stabilize gymnasium for use.
Funding Source – FEMA
Architect – Chenevert Architects, LLc
Contractor – Crescent Commercial Construction
Stablization of the Gymnasium
Construction Phase
Entergy insulated the power lines so work could commence
Pile driving is complete
Pile caps have been poured
Forecasted Substantial Completion – February 2013
Thomy Lafon School (RSD) [2601 Seventh St, New Orleans, LA 70115]
Scope of work: Stabilization of sculpture and creation of interperative display
Funding Source – FEMA
Architect – Mahlum / Scairono Marinez Joint Venture
Contractor – TBD
Procurement Phase
1st Advertisement – October 31st
2nd Advertisement – November 7th
3rd Advertisement – November 14th
Pre-Bid Conference – 9:00 a.m. on November 15th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA
Bid Opening – December 5th
Construction Phase
Notice to Proceed is anticipated early January
27
Status Date: 30 November 2012
John McDonogh High School (RSD) [2426 Esplanade Avenue, New Orleans, LA 70119]
Scope of work: Replacement of bleachers and istallation of sprinklers to gymnasium
Funding Source – Harrah’s
Architect – Trapolin Peer Architects, LLC / Fanning Howey
Contractor – TBD
Design Phase - CD
The State Fire Marshal confirmed that with the addition of the new bleachers, a fire sprinkler system will be required in the gymnasium
Notice to Proceed on sprinkler design is anticipated for December
Design is anticipated to be completed in April 2013
Construction Phase
Notice to Proceed is anticipated in July 2013
McDonogh #35 High School (OPSB) [1331 Kerlerec Street, New Orleans, LA 70116]
Scope of work: Stabilization and replacement of elevator
Funding Source – FEMA
Architect – Chenevert Architects LLC
Contractor – TBD
Procurement Phase
Owner reviewing contract
Notice to Proceed is anticipated mid of December
Forecasted Substantial Completion – April 2013
28
Status Date: 30 November 2012
Timbers HVAC (OPSB) [3520 General DeGaulle, New Orleans, LA 70114]
Scope of work: Stabilization and replacement of HVAC
Funding Source – General Fund
Architect – Moses Engineers
Contractor – TBD
Procurement Phase
1st Advertisement – November 21st
2nd Advertisement – November 28th
3rd Advertisement – December 5th
Pre-Bid Conference – 9:00 a.m. on December 6th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA
Bid Opening – December 20th
Forecasted Substantial Completion – July 2013
Village de L’est Elementary School
(RSD)
[5100 Cannes Street, New Orleans, LA 70129]
Scope of work: Roof replacement and modular demolition
Funding Source – FEMA
Architect – Richard C. Lambert Consultants, LLC
Contractor – TBD
Design Phase - CD
100% Construction Documents were received on November 5th
Procurement Phase
1st Advertisement – November 14th
2nd Advertisement – November 21st
3rd Advertisement – November 28th
Pre-Bid Conference – 9:00 a.m. on November 29th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA
Bid Opening – December 19th
Forecasted Substantial Completion – May 2013
29
Status Date: 30 November 2012
Sylvanie Williams Elementary School (RSD) [3127 Martin Luther King Jr. Boulevard, New Orleans, LA 70125]
Scope of work: AHU replacement
Funding Source – FEMA
Architect – Integrated Management Services, Inc.
Contractor – TBD
Procurement Phase
Notice to Proceed is anticipated on January 7th
Forecasted Substantial Completion – June 2013
Building Automation System Integration At Recovery School District Central And Remote Offices (RSD) [Various Addresses]
Scope of work: Implementation of a Central Remote Building Automation System that integrates the existing Building Automation Systems of the 4 Quick Start Schools (Andrew H. Wilson ES, Langston Hughes ES, L.B. Landry HS, and Lake Area HS) and Joseph A. Craig ES into a central remote monitoring workstation that will include Fannie C. Williams ES, Lawrence D. Crocker ES, Mildred Osborne ES, William Frantz ES, Bienville ES, Charles J. Colton ES, Carter G. Woodson ES and Parkview ES
Funding Source – FEMA
Architect – Moses Engineers
Contractor – Synergy Building Solutions, Inc.
Construction Phase
The five Quick Start Schools are complete, with the punch lists anticipated mid of December
Sylvanie Williams and Sarah T. Reed are complete, with the punch lists anticipated mid of December
The remaining integration for schools currently under construction will occur as each school is complete
Contractual Substantial Completion – November 2014
Forecasted Substantial Completion – November 2014
30
Status Date: 30 November 2012
MOTHBALL OR SAFE SELECTED SCHOOLS
&
SECURE
OF
Louis D. Armstrong Elementary School (RSD)) [5909 St. Claude Avenue, New Orleans, LA 70117]
Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – CDW Services, LLC
Mothballing of Closed Schools – Safe & Secure
Construction Phase
Abatement is complete
Project is 53% complete
Forecasted Substantial Completion – February 2013
Israel M. Augustine Middle School
(RSD)
[425 S. Broad St., New Orleans, LA 70119]
Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – CDW Services, LLC
Mothballing of Closed Schools – Safe & Secure
Construction Phase
Project is 68% complete
Structural shoring is ongoing in the stairwell
Contractual Substantial Completion – December 2012
Forecasted Substantial Completion – December 2012
31
Status Date: 30 November 2012
Andrew J. Bell Junior High School
(RSD)
[1010 N. Galvez St., New Orleans, LA 70119]
Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – Cresent Commercial Construction
Emergency Shoring – 100% complete
Shoring will remain in place until roof work is complete
Mothballing of Closed Schools – Safe & Secure
Scope of work: Mothballing of the Gymnasium, Adminstration Building, Building “D”, Chapel, and the E.A.Christy Building
Design Phase - CD
Procurement Phase
Anticipated 1st Advertisement – February 2013
Anticipated Bid Opening – March 2013
Roof Replacement
Construction Phase
100% Construction Documents are anticipated to be complete on November 30th
The contractor has mobilized and the project is 15% complete
Forecasted Substantial Completion – August 2013
32
Status Date: 30 November 2012
Lorraine Hansberry Elementary School
(RSD)
[1339 Clouet Street, New Orleans, LA 70117]
Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – Tuna Construction LLC
Mothballing of Closed Schools – Safe & Secure
Final Close – Out Phase
Punchlist is ongoing
Contractual Substantial Completion – November 2012
Forecasted Substantial Completion – November 2012
Morris F. X. Jeff Elementary School
(RSD)
[800 N. Rendon Street, New Orleans, LA 70119]
Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – CDW Services, LLC
Mothballing of Closed Schools – Safe & Secure
Construction Phase
Project is 82% complete
All fencing work has been completed
Contractual Substantial Completion – January 2013
Forecasted Substantial Completion – January 2013
33
Status Date: 30 November 2012
Valena C. Jones Elementary School
(RSD)
[1901 N. Galvez Street, New Orleans, LA 70119]
Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – CDW Services, LLC
Mothballing of Closed Schools – Safe & Secure
Construction Phase
Project is 62% complete
Replacement of roof is 25% complete
Contractual Substantial Completion – February 2012
Forecasted Substantial Completion – February 2012
34
Status Date: 30 November 2012
Demolition Projects Modular Classrooms at Fannie C. Williams Elementary School
(RSD)
[11755 Dwyer Street, New Orleans, LA 70128]
Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes.
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – Gulfcon LLC
Demolition of the Modular Classrooms
Demolition Phase
Bid Opening – September 18th
Notice to Proceed is anticipated on December 3rd
Forecasted Substantial Completion – February 2013
Greater St. Stephens School (OPSB) [11110 Lake Forest Boulevard 70128]
Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes.
Funding Source – FEMA
Architect – Chenevert Architects LLC
Contractor – Bayou Sheet Metal and Roofing Inc
Demolition Phase
Notice to Proceed - November 19th
Contractor has mobilized and started work
Forecasted Substantial Completion – March 2013
35
Status Date: 30 November 2012
JoEllen Smith Demolition
(OPSB)
[4400 General Meyer Avenue, New Orleans, LA 70131]
Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes.
Funding Source – FEMA
Architect – VergesRome Architects, APAC
Contractor – TBD
Design Phase - CD
50% Construction Documents were received on November 5th
100% Construction Documents are anticipated December 10th
Procurement Phase
Anticipated 1st Advertisement – January 2013
Anticipated Bid Date – February 2013
L. B. Landry Annex Demolition
(RSD)
[1100 Wagner Street, New Orleans, LA 70114]
Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes.
Funding Source – FEMA
Architect – Perez Architects
Contractor – Durr Heavy Construction LLC
Procurement Phase
Notice to Proceed is anticipated December 10th
Forecasted Substantial Completion – April 2013
36
Status Date: 30 November 2012
Mary Church Terrell Elementary School Demolition (RSD) [3411 Broadway, New Orleans, LA 70125]
Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes.
Funding Source – FEMA
Architect – SCNZ Architects
Contractor – Gill Industries, Ltd.
Procurement Phase
Notice to Proceed is anticipated December 10th
Forecasted Substantial Completion – April 2013
Booker T. Washington High School Partial Demolition
(RSD)
[1201 S. Roman Street, New Orleans, LA 70125]
Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes.
Funding Source – FEMA
Architect – Hewitt-Washington & Associates
Contractor – Gulfcon LLC
Partial Demolition
Demolition Phase
Demolition of interior of main building is 85% complete
Owner is reviewing soil remediation proposals
Contractual Substantial Completion – Feburary 2013
Forecasted Substantial Completion – February 2013
37
Status Date: 30 November 2012
Comprehensive List - Completed Projects 1.
Abrams | Morial | Abramson | Coghill Demolition
2.
A. D. Cross Elementary School Energy Conservation (RSD)
3.
A. D. Crossman Elementary School and Benjamin Banneker Elementary School (RSD)
4.
A. P. Tureaud Elementary School Roof Repairs (RSD)
5.
Agnes Bauduit Elementary School Boiler (RSD)
6.
Albert Wicker Elementary School Roof Repairs (RSD)
7.
Alfred Lawless Senior High Security Fencing (RSD)
8.
Alice M. Harte Elementary School Demolition (OPSB)
9.
Andrew Jackson Elementary School Roof Repairs (RSD)
10.
Andrew H. Wilson Elementary School Cottage (RSD)
11.
Arthur Ashe Elementary School Kitchen Renovation (OPSB)
12.
Augustine Elementary School Roof (RSD)
13.
Avery-Alexander Elementary School Demolition (RSD)
14.
Barbara C. Jordan Elementary School Demolition (RSD)
15.
Bell JH Shoring (RSD)
16.
Benjamin Banneker Elementary School Energy Conservation (RSD)
17.
Bienville Elementary School Demolition (RSD)
18.
Carter G. Woodson Middle School Demolition (RSD)
19.
Central Services Warehouse Demolition (OPSB)
20.
Charles J. Colton Elementary Selective Demolition (RSD)
21.
Charles R. Drew Elementary Roof & Installation of Kitchen Hood (RSD)
22.
Cohen High School Health Clinic
23.
Douglass High School Under Floor Utilities (RSD)
24.
Dr. Martin Luther King School Roof Repairs (RSD)
25.
Dr. Martin Luther King Jr. School Renovation (RSD)
26.
Dwight D. Eisenhower Elementary School Roof Repairs (RSD)
27.
East BankSwing Space for Audubon Charter School (OPSB)
28.
Edgar P. Harney Elementary School Roof Repairs (RSD)
29.
Edward Livingston Middle School Demolition(RSD)
30.
Edward Henry Phillips Junior High School Demolition (OPSB)
31.
New Edward Hynes School (OPSB)
32.
Edwards | Hardin | Lockett | Lawless Demolition (RSD)
38
(RSD)
(RSD)
Status Date: 30 November 2012
33.
Eleanor L. McMain School Replacement of Existing Chillers (OPSB)
34.
Ernest N. Morial Elementary Security Fencing (RSD)
35.
Fannie C. Williams Elementary School Demolition (RSD)
36.
Fisk-Howard Elementary School Demolition (RSD)
37.
Florence J. Chester Elementary School Demolition (RSD)
38.
Francis W. Gregory Demolition (RSD)
39.
Frederick A. Douglass High Switchgear (RSD)
40.
Frederick A. Douglass High Emergency Boiler Roof Repairs (RSD)
41.
George Mondy Elementary School Mothball (RSD)
42.
George Washington Carver High School Demolition (RSD)
43.
Henry Allen Elementary School Roof (RSD)
44.
Henry C. Schaumburg – Window/Door, Air Condition, Water Fountain/Sink Installation (RSD)
45.
Holy Cross Modular Relocation (RSD)
46.
Israel M. Augustine Middle School Roof Replacement (RSD)
47.
James Derham Demolition (RSD)
48.
James W. Johnson Elementary School Roof (RSD)
49.
New Jean Batiste de Bienville School (RSD)
50.
Jean Gordon Elementary School Demolition (RSD)
51.
John Dibert Elementary School Roof (RSD)
52.
John W. Hoffman Elementary School Demolition (RSD)
53.
John F. Kennedy Modular Relocation (Schwarz Campus) (RSD)
54.
John F. Kennedy Modular Relocation (Coghill Modular Campus) (RSD)
55.
John F. Kennedy High School Demolition (RSD)
56.
John McDonogh Senior High School Roof (RSD)
57.
John A. Shaw Elementary School Mothball (RSD)
58.
Joseph S. Clark Senior High School Roof Repairs (RSD)
59.
Joseph A. Craig Elementary Canopies (RSD)
60.
Joseph A. Craig Elementary Elevator Installation (RSD)
61.
Joseph A. Hardin Elementary Security Fencing (RSD)
62.
Lafayette Elementary School Roof and Masonry(RSD)
63.
Lake Area | Landry Demolition (RSD)
64.
Langston Hughes Elementary School (Phase I) (RSD)
65.
Langston Hughes Elementary School – New Gymnasium (Phase II) (RSD)
39
Status Date: 30 November 2012
66.
Langston Hughes Elementary School – Dumpster Pad (RSD)
67.
Lawrence D. Crocker Elementary School Demolition (RSD)
68.
Little Woods Elementary School Demolition (RSD)
69.
Live Oak Elementary School Roof (RSD)
70.
Live Oak Elementary School Exterior Door Replacement (RSD)
71.
Mahalia Jackson Elementary School (OPSB)
72.
Mahalia Jackson Elementary School Dumpster / Other Improvements(OPSB)
73.
Martin Behrman Elementary School Roof (RSD)
74.
Martin Luther King Jr. Elementary Canopy System (RSD)
75.
Martin Luther King Jr. School Modular Building, Deck, Canopy (RSD)
76.
Mary M. Bethune Elementary 1st Floor Replacement (OPSB)
77.
Mary M. Bethune Elementary Rear Yard Repair/Resurfacing (OPSB)
78.
McDonogh #15 Elementary Exterior Masonry to SOI Standards (RSD)
79.
McDonogh #28 Elementary School Roof
80.
McDonogh #32 Roof Replacement (RSD)
81.
McDonogh #35 ADA Upgrades to Public Restrooms, Exterior Ramp & Handicap Seating in the Auditorium (OPSB)
82.
McDonogh #42 Elementary School Roof (RSD)
83.
McDonogh #42 Elementary School HVAC Replacement (RSD)
84.
Mildred C. Osborne Elementary School Demolition
85.
Modular Campuses Close Outs (RSD)
86.
Modular Structures at Langston Hughes Elementary School (RSD)
87.
Morris F.X. Jeff Elementary School Demolition (RSD)
88.
Murray G. Henderson Elementary School Roof (RSD)
89.
New Andrew H. Wilson Elementary School (RSD)
90.
New Carter G. Woodson School (RSD)
91.
New Fannie C. Williams School (RSD)
92.
New Joseph A. Craig Elementary School (RSD)
93.
New L.B. Landry High School (RSD)
94.
New Lake Area High School (RSD)
95.
New Lawrence D. Crocker School (RSD)
96.
New Parkview School (RSD)
97.
New Equipment & Upgrades at 8 Central & 25 Satellite Kitchens (RSD)
98.
New Orleans High School Signature Center Study (RSD)
40
(RSD)
(RSD)
Status Date: 30 November 2012
99.
Oretha C. Haley Demo (RSD)
100. Oretha C. Haley Elementary School Mothball 101. Parkview Elementary School Demolition
(RSD)
(RSD)
102. Paul L. Dunbar Elementary School Demolition (RSD) 103. Paul B. Habans Elementary School Roof Repairs (RSD) 104. Phillis Wheatley Elementary School Demolition (RSD) 105. Robert M. Lusher Elementary Roof Removal & Replacement (OPSB)
106. Sarah T. Reed High School Bleachers (RSD) 107. Sarah T. Reed High School Auditorium Wall (RSD) 108. Seabrook Computer Training Center Demolition (OPSB) 109. Schaumburg Chillers (RSD) 110. Schwarz Alternative Repairs
(RSD)
111. Schwarz Alternative Modulars Demolition (RSD) 112. Sherwood Forest Elementary School Demolition (RSD) 113. Sophie B. Wright Various Repairs/Restroom Renovations (OPSB) 114. Stuart R. Bradley Elementary School Demolition
(RSD)
115. Sylvanie Williams Elementary School Play Yard (RSD) 116. Sylvanie Williams Elementary School Roof Repairs (RSD) 117. Sylvanie Williams Elementary School HVAC/Chiller Replacement (RSD)
118. Temporary Campus for McDonogh #11 Expropriation (OPSB) 119. Thomas A. Edison Elementary School Demolition (RSD) 120. Thomy Lafon Elementary School Demolition (RSD) 121. Timbers Park Office Building #1 & #2 Demolition (OPSB) 122. Village de L’est Elementary School Subsidence (RSD) 123. Vorice J. Waters Elementary School Demolition (RSD) 124. West Bank Swing Space for Alice Harte Elementary School (OPSB) 125. New William J. Guste Elementary School (RSD) 126. William J. Guste Elementary School Science Lab (RSD) 127. William Frantz Elementary School Environmental Remediation & Selective Demolition (RSD) 128. William Frantz Elementary School Roof (RSD)
41
Status Date: 30 November 2012