Superintendents’ Report December 2012

Mr. Stanley C. Smith Orleans Parish School Board

Mr. John White Louisiana Department of Education

Mr. Patrick Dobard Recovery School District

Prepared by:


Table of Contents Right-Click on the school name to proceed to that page

TABLE OF CONTENTS ..................................................... 1 OVERVIEW......................................................................... 3 COMMUNITY MEETINGS .................................................. 4 BID OPENINGS .................................................................. 5 NEW & MAJOR RENOVATION ......................................... 6 James Audubon School (OPSB) .................................. 6 Stuart R. Bradley School (RSD) .................................. 6 George Washington Carver School (RSD) .................. 7 Charles J. Colton School (RSD) .................................. 7 Charles R. Drew Elementary School (RSD) ............... 8 Frederick A. Douglass High School (RSD) ................. 8 Paul L. Dunbar School (RSD) ...................................... 9 Fisk-Howard School (RSD) ......................................... 9 William Frantz School (RSD) ..................................... 10 Alice Harte School (OPSB) ........................................ 10 New Karr High School at the JoEllen Smith Site (OPSB) ............................................................................... 11 New PK-8 School at North Kenilworth Park at Curran Site (OPSB)................................................................ 11 Lake Forest PK-8 at the Greater St. Stephens Site (OPSB) ....................................................................... 11 Alfred Lawless School (RSD) .................................... 12 Little Woods School (RSD) ........................................ 12 Edward Livingston High School (RSD) ..................... 13 McDonogh #35 School (Phillip/Waters Site) (OPSB). 13 McDonogh #42 Elementary School (RSD) ............... 14 Eleanor L. McMain School (OPSB) ........................... 14 Small New Orleans East High School at Abramson (RSD) ....................................................................... 15 Mildred Osborne School (RSD) ................................ 15 Booker T. Washington School (RSD) ........................ 16 Phillis Wheatley Elementary School (RSD) ............... 16 Sophie B. Wright School (RSD) ................................ 17 Bundy Road Space (RSD) ........................................ 17

REFURBISHMENTS......................................................... 18 Agnes L. Bauduit Elementary School Refurbishment (RSD) ........................................................................ 18 A. D. Crossman School Refurbishment (RSD) .......... 18 Warren Easton School Refurbishment (OPSB) .......... 19 Dwight D. Eisenhower Elementary School Refurbishment (RSD)................................................. 19 Gentilly Terrace School Refurbishment (RSD) ........... 20 Andrew Jackson School Refurbishment (RSD) .......... 20

1

Status Date: 31 December 2012


Dr. Martin L. King Elementary School Refurbishment (RSD) ......................................................................... 21 Lusher Elementary School Refurbishment (OPSB) ... 21 Fortier (Lusher) High School Refurbishment (OPSB) . 22 McDonogh #28 School Refurbishment (RSD) ............ 22 Nelson Elementary School Refurbishment (OPSB) .... 23 Sarah T. Reed School Refurbishment (RSD)............. 23 Albert Wicker School Refurbishment (RSD)............... 24 Sylvanie F. Williams School Refurbishment (RSD) .... 24 OTHER PROJECTS ......................................................... 25 Benjamin Franklin Senior High School (OPSB) .......... 25 Walter L. Cohen High School (RSD) ......................... 25 Warren Easton School (OPSB) ................................. 26 Andrew Jackson School (RSD) ................................ 26 Mahalia Jackson Elementary School Office Renovation (OPSB) .................................................... 26 Edna Karr High School - Gymnasium Repair (OPSB) ............................................................................... 27 Thomy Lafon School (RSD) ....................................... 27 John McDonogh High School (RSD) ......................... 28 McDonogh #35 High School (OPSB) ......................... 28 Timbers HVAC (OPSB) .............................................. 29 Village de’ Lest Elementary School (RSD) ................ 29 Sylvanie Williams Elementary School (RSD) ............. 30 Building Automation System Integration At Recovery School District Central And Remote Offices (RSD) .. 30 MOTHBALL OR SAFE & SECURE OF SELECTED SCHOOLS ........................................................................ 31 Louis D. Armstrong Elementary School (RSD)) ......... 31 Israel M. Augustine Middle School (RSD)................. 31 Andrew J. Bell Junior High School (RSD) ................. 32 Morris F. X. Jeff Elementary School (RSD) .............. 33 Valena C. Jones Elementary School (RSD) ............. 33 DEMOLITION PROJECTS ............................................... 34 Modular Classrooms at Fannie C. Williams Elementary School (RSD) ........................................ 34 Greater St. Stephens School (OPSB) ........................ 34 JoEllen Smith Demolition (OPSB) .............................. 35 L. B. Landry Annex Demolition (RSD) ...................... 35 Mary Church Terrell Elementary School Demolition (RSD) ) ....................................................................... 36 Booker T. Washington High School Partial Demolition (RSD) ..................................................... 36 COMPLETED PROJECTS .............................................. 37

2

Status Date: 31 December 2012


Overview The RSD has $342 million in open contracts for the capital program after issuing $516 thousand in new contracts and $179 thousand in change orders and amendments in December. In addition, the total change orders to date, $7.6 million, account for approximately two percent (2.65%) of the total open construction contracts. RSD anticipates issuing approximately $169 thousand in construction contracts and $408 thousand in professional service contracts/amendments in January. The RSD requested and received approval from the State’s Superintendent of Education to utilize the Design – Build method of project delivery for the following projects. George Washington Carver School Booker T. Washington School Sherwood Forest School Martin Behrman School Paul Habans School The OPSB has $96.7 million in open contracts for the capital program after issuing no new contracts, change orders and amendments in December. In addition, the total change orders to date, $1.7 million, account for approximately two percent (2.49%) of the total open construction contracts. OPSB anticipates issuing approximately $87.3 million in construction contracts and professional service contracts in January.

3

Status Date: 31 December 2012


Community Meetings No Community Meetings were scheduled for the month of December Community Meetings that are anticipated for the month of January •

January 31st: McDonogh 42 Elementary School– 1651 North Tonti Street, New Orleans, LA 70119

4

Status Date: 31 December 2012


Bid Openings Bids that were opened in December 2012: •

Thomy Lafon Interpretive Display (RSD) – December 5, 2012

Timbers HVAC Repairs (OPSB) – December 20, 2012

Over the next sixty days, bids to be opened for the following projects: •

Village de L’est Elementary School Roof and Modular Demolition – January 9, 2013

(RSD)

Test Pile Program at Sophie B. Wright (RSD) – January 23, 2013

Fisk-Howard School (RSD) – January 30, 2013

5

Status Date: 31 December 2012


Forecasted dates only include the next project phase

New & Major Renovation – Project Status James Audubon School (OPSB) [428 Broadway Avenue, New Orleans, LA 70118]

Scope of work: Renovation & Addition of Existing Elementary School •

Funding Source – FEMA

Architect – Blitch/Knevel Architects

Contractor – FHP Tectonics Corporation

Construction Phase 

Pile driving is complete

Pile caps were formed and will be poured in January

Metal stud framing is 90% complete in the existing building

Steel fabrication has started

Installation of the new roofing on the existing building has started

MEP rough-ins are ongoing on the 1st, 2nd and 3rd floor

Contractual Substantial Completion – September 2013

Forecasted Substantial Completion – February 2014

School Ready for Occupancy – May 2014

Stuart R. Bradley School

(RSD)

[ 2401 Humanity Street, New Orleans, LA 70122]

Scope of work: New 3 – section elementary school for 850 students •

Funding Source – FEMA

Architect – Sizeler Thompson Brown Architects

Contractor – TBD

Design Phase – CD

100% Construction Documents are anticipated January 7th

A time extension was granted to the A&E for design consideration of a new cost effective construction material

Procurement Phase 

Anticipated 1st Advertisement – February 2013

Anticipated Bid Opening – March 2013

6

Status Date: 31 December 2012


George Washington Carver School (RSD) [3019 & 3059 Higgins Blvd., New Orleans, LA 70126]

Scope of work: New High School •

Funding Source – FEMA

Architect – Trapolin Architects & VMDO Architects, A Joint- Venture

Contractor – TBD

Design Phase 

The RSD is working with key stakeholders to value engineer this project in an effort to reduce the cost

Items being explored include: Foundation redesign Reduced ceiling heights Repurpose areas of the building Use of cost effective construction materials Changing the project delivery methods Scaling back on architectural elements

Charles J. Colton School (RSD) [2300 St. Claude Avenue, New Orleans, LA 70117]

Scope of work: Renovation of existing elementary school and new addition •

Funding Source – FEMA

Architect – Waggonner & Ball Architects

Contractor – F.H. Paschen, S.N. Nielsen & Associates, LLC

Construction Phase

Roofing material installation is 95% complete

Gypsum board installation on interior walls is complete on 2nd and 3rd floors

Pulling of wiring/data lines is ongoing

Window installation is complete, glazing is 80% complete

Exterior wall panels are 90% complete

Patching of terrazzo is 80% complete

VCT floor installation is 60% complete

The installation of electrical fixtures and raceways are 65% complete

Contractual Substantial Completion – November 2012

7

Status Date: 31 December 2012


Forecasted Substantial Completion – March 2013

School Ready for Occupancy – June 2013

Charles R. Drew Elementary School (RSD) [3819 St. Claude Avenue, New Orleans, LA 70117]

Scope of work: Renovation of existing elementary school and new addition to meet code requirements •

Funding Source – FEMA

Architect – Blitch / Knevel Architects, Inc.

Contractor – TBD

Design Phase - CD

50% Construction Documents were received December 10th

100% Construction Documents are anticipated February 18th

Procurement Phase 

Anticipated 1st Advertisement – March 2013

Anticipated Bid Opening – April 2013

Frederick A. Douglass High School (RSD) [3820 St. Claude Avenue, New Orleans, LA 70117]

Scope of work: Renovation of existing high school •

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor – TBD

Design Phase - CD 

Design Development were received on December 15th

The building will be used for swing space for the next two years

The student population at Drew is overwhelmingly made up of children living in the neighborhood, so having swing space nearby for those students is crucial while Drew is being renovated

8

Status Date: 31 December 2012


Paul L. Dunbar School (RSD) [9330 Forshey Street, New Orleans, LA 70125]

Scope of work: New 2 - section elementary school for 556 students •

Funding Source – FEMA

Architect – Chenevert Architects LLC

Contractor – TBD

Design Phase - CD 

100% Construction Documents were received December 18th

Procurement Phase 

Anticipated 1st Advertisement – March 2013

Anticipated Bid Opening – April 2013

Fisk-Howard School (RSD) [211 South Lopez Street, New Orleans, LA 70119]

Scope of work: New 3 - section elementary school for 850 students •

Funding Source - FEMA

Architect - VergesRome Architects+Fanning Howey

Contractor – TBD

Design Phase 

Test Pile reports were received the beginning of December

Procurement Phase 

1st Advertisement – December 26th

2nd Advertisement – January 2nd

3rd Advertisement – January 9th

Pre-Bid Conference – 9:00 a.m. on January 10th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA

Bid Opening – January 30th

9

Status Date: 31 December 2012


William Frantz School (RSD) [3811 North Galvez Street, New Orleans, LA 70117]

Scope of work: Renovation of existing elementary school and new addition •

Funding Source – FEMA

Architect – Billes Architecture, LLC

Contractor – The Lathan Company, Inc.

Construction Phase 

Sanding and finishing of wood floors in the existing building will take place in January

Ceramic tile reinstall has begun

MEP subcontractors have returned to site and are proceeding with HVAC start-up and various activities

Courtyard site work is ongoing

The general contractor is working on various areas of nonconforming work

Contractual Substantial Completion – March 2012

Forecasted Substantial Completion – June 2013

School Ready for Occupancy – August 2013

Alice Harte School

(OPSB)

[5300 Berkley Drive, New Orleans, La 70131]

Scope of work: New 3 - section elementary school for 850 students •

Funding Source – CDBG & FEMA

Architect – WDG Architects Engineers

Contractor – Woodrow Wilson Construction Company, Inc.

Construction Phase 

Pile driving is complete

Foundation work continues with pile caps and grade beams

Slab on grade is scheduled to be poured by the end of January

• Contractual Substantial Completion – January 2014 • Forecasted Substantial Completion – January 2014 • School Ready for Occupancy – June 2014

10

Status Date: 31 December 2012


New Karr High School at the JoEllen Smith Site (OPSB) [4400 General Meyer Avenue, New Orleans, LA 70131]

Scope of work: New medium high school •

Funding Source – FEMA

Architect – Lee Ledbetter & Associates / Gould Evans Associates

Contractor – TBD

Design Phase - SD 

Due to design issues and additional scope of work, Schematic Design Documents were rejected by the Owner

New PK-8 School at North Kenilworth Park at Curran Site (OPSB) [8500 Curran Boulevard, New Orleans, LA 70127]

Scope of work: New 3 - section elementary school for 850 students •

Funding Source – FEMA

Architect – Mathes Brierre Architects

Contractor – Woodrow Wilson Construction Company, Inc.

Procurement Phase 

The contract was issued to the general contractor

Notice to Proceed is anticipated mid-February

Forecasted Substantial Completion – August 2014

School Ready for Occupancy – January 2015

Lake Forest PK-8 at the Greater St. Stephens Site

(OPSB)

[11110 Lake Forest Boulevard 70128]

Scope of work: New 3 - section elementary school for 850 students •

Funding Source – FEMA

Architect – Imre Hegedus & Associates Architects

Contractor – TBD

Design Phase - CD

50% Construction Documents are anticipated on January 2nd

100% Construction Documents are anticipated on March 5th

Procurement Phase 

Anticipated 1st Advertisement – April 2013

Anticipated Bid Opening – May 2013

11

Status Date: 31 December 2012


Alfred Lawless School

(RSD)

[5300 Law Street, New Orleans, LA 70117]

Scope of work: New medium high school •

Funding Source – FEMA

Architect – Sizeler Thompson Brown Architects

Contractor – TBD

Design Phase - CD

50% Construction documents are anticipated to be finished on January 25th

100% Construction documents are anticipated to be finished on March 24th

Procurement Phase 

Anticipated 1st Advertisement – April 2013

Anticipated Bid Opening – May 2013

Little Woods School (RSD) [10200 Curran Blvd., New Orleans, LA 70127]

Scope of work: New Pre-K – 8 school •

Funding Source – FEMA

Architect – Group Novak, LLC

Contractor – MAPP Construction

Construction Phase 

Terrazzo flooring is complete on third floor; two crews are working on first and second floors.

Gypsum board walls are being taped, floated and painted on the 1st floor

Installing restroom ceilings on 2nd and 3rd floors

Ceiling grid and raceways are installed in the classrooms

90% of the storefront doors are installed

Millwork is installed in Science Labs

Electrical raceways are being installed

10,000 sf of parking has been formed up and will be poured mid-January. Exterior canopies are installed

Contractual Substantial Completion – November 2012

Forecasted Substantial Completion – April 2013

School Ready for Occupancy – TBD

12

Status Date: 31 December 2012


Edward Livingston High School

(RSD)

[7301 Dwyer Road, New Orleans, LA 70126]

Scope of work: New small high school •

Funding Source – FEMA

Architect – RozasWard / a.i.a. architects, inc.

Contractor – TBD

Design Phase - CD 

100% Construction Documents were received on December 26th

Procurement Phase 

1st Advertisement – February 13th

2nd Advertisement – February 20th

3rd Advertisement – February 27th

Pre-Bid Conference – 9:00 a.m. on February 28th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA

Bid Opening – March 20th

McDonogh #35 School (Phillip/Waters Site)

(OPSB)

[1200 Senate Street, New Orleans, LA 70122]

Scope of work: New 3-story high school •

Funding Source – FEMA

Architect – Sizeler, Thompson, Brown Architects

Contractor – Citadel Builders, LLC

Site Remediation Project 

A Phase II environmental assessment revealed heavy metals and PAHs exist in the fill

Scope of work: Remediate fly-ash materials found in the soil

Remediation work is anticipated to be complete 1st quarter of 2013

New Construction Project

Procurement Phase 

The contract was issued to the general contractor

Notice to Proceed is anticipated upon the completion of the site remediation project

13

Status Date: 31 December 2012


McDonogh #42 Elementary School (RSD) [1651 North Tonti Street, New Orleans, LA 70119]

Scope of work: Renovation of existing elementary school and new addition to meet code requirements •

Funding Source – FEMA

Architect – Eskew+Dumez+Ripple

Contractor – TBD

Design Phase - CD

50% Construction Documents are anticipated January 24th

100% Construction Documents are anticipated March

Procurement Phase 

Anticipated 1st Advertisement – April 2013

Anticipated Bid Opening – June 2013

Eleanor L. McMain School

(OPSB)

[5721 S. Claiborne Avenue, New Orleans, LA 70125]

Scope of work: The exterior of the existing building will be stabilized and a new gym will be added to the site with a connecting breezeway to the main building. A portion of the existing building will be renovated for a health clinic. •

Exterior Stabilization 

Funding Source – FEMA

Architect – Jahncke & Burns Architects

Contractor – TBD

Notice to Proceed for the A&E is anticipated January 14th

New Gymnasium 

Funding Source – FEMA

Architect – Jahncke & Burns Architects

Contractor – Ellis Construction

Procurement Phase •

General contractor has return the signed contract

Notice to Proceed is anticipated mid-February

School Based Health Clinic 

Funding Source – HRSA Grant

Architect – Jahncke & Burns Architects

Contractor – ETI. Inc.

14

Status Date: 31 December 2012


Construction Phase •

Construction is 15% complete

• Contractual Substantial Completion – March 2013 Small New Orleans East High School at Abramson (RSD) [5552 Read Boulevard, New Orleans, LA 70127]

Scope of work: New small high school •

Funding Source – FEMA

Architect – RozasWard / a.i.a. architects, inc.

Contractor – TBD

Design Phase - CD

Project will be delayed due to the City Of New Orleans request for reorientation of the front elevation of the project

100% Construction Documents are anticipated March 2013

Procurement Phase 

Anticipated 1st Advertisement – April 2013

Anticipated Bid Opening – May 2013

Mildred Osborne School (RSD) [6701 Curran Blvd., New Orleans, LA 70126]

Scope of work: New Pre-K– 8 school •

Funding Source – FEMA

Architect – Fauntleroy & Latham

Contractor – F.H. Paschen, S.N. Nielsen & Associates, LLC

Construction Phase

• •

Landscaping and the fencing is 95% complete

Media Center and Library will be completed at the end of January

Contractual Substantial Completion – February 2013 This school will have a phased delivery schedule from 16th of October to end of January 2013

15

Status Date: 31 December 2012


Booker T. Washington School (RSD) [1201 South Roman Street, New Orleans, LA 70125] Scope of work: The auditorium and entry will be renovated and the remainder of the facility will be demolished and constructed new •

Funding Source – FEMA

Architect – Hewitt-Washington & Associates

Contractor – TBD

Design Phase - CD 

Upon completion of the Design Phase, the project will be put on hold until a mitigation plan is developed on the environmental issues

Based on current market projections, the RSD is working with key stakeholders to value engineer this project in an effort to reduce the cost

Items being explored include: Reduced ceiling heights Repurpose areas of the building Use of cost effective construction materials Changing the project delivery methodology Scaling back on architectural elements

Phillis Wheatley Elementary School (RSD) [2300 Dumaine Street, New Orleans, LA 70119]

Scope of work: New 2 - section elementary school for 556 students •

Funding Source – FEMA

Architect – Holly & Smith Architects

Contractor – Gibbs Construction

Construction Phase 

Site clearing is complete

Pile driving has begun

Foundation work is expect to continue thru February with pile caps and grade beams

Will close first New Market Tax Credit transaction in partnership with OPSB on the Wheatley School in Treme in February. We will receive $1.5 million that would have otherwise been unavailable to the RSD/OPSB and our partners through this transaction. Contractual Substantial Completion – May 2014 

16

Status Date: 31 December 2012


Forecasted Substantial Completion – May 2014

School Ready for Occupancy – June 2014

Sophie B. Wright Middle School Renovation

(RSD)

[1426 Napoleon Avenue, New Orleans, LA 70115]

Scope of work: Renovation of existing middle school •

Funding Source – FEMA

Architect – Waggonner & Ball Architects, APC

Contractor – TBD

Design Phase - CD

Design Development Documents were received December 11th

The additional scope of adding a new gymnasium will extend the CD phase of this job

50% Construction Documents are anticipated in March

Procurement Phase 

Anticipated 1st Advertisement – June 2013

Anticipated Bid Opening – July 2013

Bundy Road Space (RSD) [6767 Bundy Road, New Orleans, LA 70127]

Scope of work: Renovation of existing office complex into a school •

Architect – VergesRome Architects, APAC

Contractor – TBD

Design Phase - FS 

Feasibility study was performed to determine if an office complex can be converted into a school

RSD will work with OPSB to procure the site

The conversion of this site to a school is more cost effective than building a new school

The building will have the flexibility to house a K-12 program

17

Status Date: 31 December 2012


REFURBISHMENTS Agnes L. Bauduit Elementary School Refurbishment

(RSD)

[3649 Laurel Street, New Orleans, LA 70115]

Scope of work: Refurbishment of existing elementary school, including but not limited to structure, windows, doors, masonry walls and roof •

Funding Source – FEMA

Architect – Duplantis Design Group, PC

Contractor - TBD

Design Phase - SD

Program documents were received on December 4th

The Owner is reviewing the Program Documents scope of work

Schematic Design documents are anticipated on February 21st

Procurement Phase 

Anticipated 1st Advertisement – July 2013

Anticipated Bid Opening – August 2013

A. D. Crossman School Refurbishment

(RSD)

[4407 South Carrollton Avenue, New Orleans, LA 70119]

Scope of work: Refurbishment of existing elementary school, including but not limited to structure, windows, doors, masonry walls and roof •

Funding Source – FEMA

Architect – Perez, APC

Contractor - TBD

Design Phase - CD

Schematic Design documents were received on December 18th

100% Construction Documents are anticipated February 13th

Procurement Phase 

Anticipated 1st Advertisement – March 2013

Anticipated Bid Opening – April 2013

18

Status Date: 31 December 2012


Warren Easton School

(OPSB)

[3019 Canal Street, New Orleans, LA 70119]

Scope of work: Refurbishment of existing high school •

Funding Source – FEMA

Architect – Chenevert Architects LLC

Contractor - TBD

Design Phase - CD

100% Construction Documents are anticipated in February

Owner requested an increase in the scope of work which will extend the Design Phase

Procurement Phase 

Anticipated 1st Advertisement – March 2013

Anticipated Bid Opening – April 2013

Dwight D. Eisenhower Elementary School Refurbishment

(RSD)

[3700 Tall Pines Drive, New Orleans, LA 70131]

Scope of work: Refurbishment of existing elementary school, including but not limited to structure, windows, doors, masonry walls and roof •

Funding Source – FEMA

Architect – Harry Baker Smith Architects II, PLLC

Contractor - TBD

Design Phase - PC

Program documents are anticipated on January 11th

Schematic Design documents are anticipated on February 21th

Procurement Phase 

Anticipated 1st Advertisement – August 2013

Anticipated Bid Opening – September 2013

19

Status Date: 31 December 2012


Gentilly Terrace School Refurbishment

(RSD)

[4720 Painters Street, New Orleans, LA 70122]

Scope of work: Refurbishment of existing elementary school, including but not limited to structure, windows, doors, masonry walls and roof •

Funding Source – FEMA

Architect – Byron J. Stewart & Associates, APC Architects & Planners

Contractor - TBD

Design Phase - PC

Program documents are to be revised and resubmitted on January 9th

Schematic Design documents are anticipated on February 24th

Procurement Phase 

Anticipated 1st Advertisement – June 2013

Anticipated Bid Opening – July 2013

Andrew Jackson School Refurbishment

(RSD)

[1400 Camp Street, New Orleans, LA 70130]

Scope of work: Refurbishment of existing elementary school, including but not limited to structure, windows, doors, masonry walls and roof •

Funding Source – FEMA

Architect – N-Y Associates, Inc.

Contractor - TBD

Design Phase - SD

The Owner is reviewing the Program Documents scope of work

Schematic Design documents are anticipated on February 3rd

Procurement Phase 

Anticipated 1st Advertisement – June 2013

Anticipated Bid Opening – July 2013

20

Status Date: 31 December 2012


Dr. Martin L. King Elementary School Refurbishment

(RSD)

[1617 Caffin Avenue, New Orleans, LA 70117]

Scope of work: Refurbishment of existing elementary school, including but not limited to structure, windows, doors, masonry walls and roof •

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor - TBD

Design Phase - SD

The Owner is reviewing the Program Documents scope of work

Schematic Design documents are anticipated on February 14th

Procurement Phase 

Anticipated 1st Advertisement – July 2013

Anticipated Bid Opening – August 2013

Lusher Elementary School Refurbishment (OPSB) [7315 Willow Street, New Orleans, LA 70118]

Scope of work: Renovation and repairs to the existing bridge, roof, windows, exterior doors, and restroom accessibility •

Funding Source – FEMA

Architect – Meyer Engineers, LTD.

Contractor - TBD

Design Phase - CD

Design Development documents were received on December 27th

50% Construction Documents are anticipated on January 28th

Procurement Phase 

Anticipated 1st Advertisement – April 2013

Anticipated Bid Opening – May 2013

21

Status Date: 31 December 2012


Fortier (Lusher) High School Refurbishment

(OPSB)

[5624 Freret Street, New Orleans, LA 70115]

Scope of work: Renovation and repairs to the roof, masonry, plaster, windows, exterior doors, canopies, mechanical systems, and electrical systems. •

Funding Source – FEMA

Architect – Meyer Engineers, LTD.

Contractor - TBD

Design Phase - DD

Design Development documents were received on December 21st

The Owner is reviewing the Design Development documents scope of work

Procurement Phase 

Anticipated 1st Advertisement – June 2013

Anticipated Bid Opening – July 2013

McDonogh #28 School Refurbishment

(RSD)

[2733 Esplanade Avenue, New Orleans, LA 70119]

Scope of work: Refurbishment of existing elementary school, including but not limited to structure, windows, doors, masonry walls and roof •

Funding Source – FEMA

Architect – SCNZ Architects,LLC

Contractor - TBD

Design Phase - CD

Schematic Design documents were received on December 17th

100% Construction Documents are anticipated on April following a delay for the Owner to define scope

Procurement Phase 

Anticipated 1st Advertisement – May 2013

Anticipated Bid Opening – June 2013

22

Status Date: 31 December 2012


Nelson Elementary School Refurbishment

(OPSB)

[3121 St. Bernard Avenue, New Orleans, LA 70119]

Scope of work: Renovation and repairs to the roof, masonry, windows, exterior doors, mechanical systems, and electrical systems. •

Funding Source – FEMA

Architect – Harry Baker Smith Architects

Contractor - TBD

Design Phase - PC

Program documents are anticipated January 11th

Schematic Design documents are anticipated January 20th

Procurement Phase 

Anticipated 1st Advertisement – June 2013

Anticipated Bid Opening – July 2013

Sarah T. Reed School Refurbishment

(RSD)

[5316 Michoud Boulevard, New Orleans, LA 70129]

Scope of work: Refurbishment of existing high school, including but not limited to structure, windows, doors, masonry walls and roof •

Funding Source – FEMA

Architect – Byron J. Stewart & Associates, APC Architects & Planners

Contractor - TBD

Design Phase - SD

Program documents were received on December 6th

The Owner is reviewing the Program Documents scope of work

Schematic Design documents are anticipated on February 14th

Procurement Phase 

Anticipated 1st Advertisement – August 2013

Anticipated Bid Opening – September 2013

23

Status Date: 31 December 2012


Albert Wicker School Refurbishment

(RSD)

[2011 Bienville Street, New Orleans, LA 70112]

Scope of work: Refurbishment of existing elementary school, including but not limited to structure, windows, doors, masonry walls and roof •

Funding Source – FEMA

Architect – SCNZ Architects, LLC

Contractor - TBD

Design Phase - SD

Program documents were received on December 1st

Schematic Design documents are anticipated on January 1st

Procurement Phase 

Anticipated 1st Advertisement – July 2013

Anticipated Bid Opening – August 2013

Sylvanie F. Williams School Refurbishment

(RSD)

[3127 Martin Luther King Jr. Boulevard, New Orleans, LA 70125]

Scope of work: Refurbishment of existing elementary school, including but not limited to structure, windows, doors, masonry walls and roof •

Funding Source – FEMA

Architect – Chenevert Architects, LLC

Contractor - TBD

Design Phase - PC

Program documents are anticipated January 11th

Schematic Design documents are anticipated on February 21st

Procurement Phase 

Anticipated 1st Advertisement – August 2013

Anticipated Bid Opening – September 2013

24

Status Date: 31 December 2012


OTHER PROJECTS Benjamin Franklin Senior High School (OPSB) [2001 Leon C. Simon Drive, New Orleans, LA 70122]

Scope of work: Stabilization and repairs to the existing courtyard, exterior lighting, metal roof panels, interior lighting, curtain wall, exterior doors (frames), fencing, scoreboard and goal post •

Funding Source – FEMA

Architect – Perez, APC

Contractor – Pete Vicari General Contractors Inc.

Construction Phase 

Additional courtyard work is anticipated to be complete in January 2013

Electrical lighting work is complete

Contractual Substantial Completion – January 2013

Forecasted Substantial Completion – January 2013

Walter L. Cohen High School (RSD) [3520 Dryades Street, New Orleans, LA 70115]

Scope of work: Correct the HVAC return air / ventilation problems and replace eight (8) chilled water pumps •

Funding Source – FEMA

Architect – Infinity Engineering Consultants, LLC

Contractor – TBD

Design Phase - CD

Schematic Design documents were received December 23rd

50% Construction Documents are anticipated on January 16th

Procurement Phase 

Anticipated 1st Advertisement – March 2013

Anticipated Bid Opening – April 2013

25

Status Date: 31 December 2012


Warren Easton School

(OPSB)

[3019 Canal Street, New Orleans, LA 70119]

Scope of work: Removal and replacement of existing exterior windows and waterproofing of the courtyard masonry •

Funding Source – Harrah’s

Architect – VergesRome Architects, apc

Contractor – Barbara Enterprises, Inc.

Final Close-out Phase 

Substantial completion September 6th

The Owner has put the contractor in default

The Surety was contacted and is developing a plan to complete the project

Contractual Substantial Completion – March 2010

Actual Substantial Completion – September 2012

Andrew Jackson School

(RSD)

[1400 Camp Street, New Orleans, LA 70130]

Scope of work: Installation of solar panels at Andrew Jackson School. This will save energy for the school and serve as a teaching aide for students to learn about solar energy •

Funding Source – Greater New Orleans Foundation/Entergy Grant

Architect – Perez, APC

Contractor – South Coast Solar

Construction Phase 

Contractor is 50% complete with the installation of the solar panels

Forecasted Substantial Completion – January 2013

Mahalia Jackson Elementary School Office Renovation (OPSB) [2101 Freret Street, New Orleans, LA 70113]

Scope of work: Convert the office space on the second floor of Building C into four classrooms •

Funding Source – New Orleans Parish School Board General Fund

Architect – VergesRome Architects, APAC

Contractor – ETI, Inc.

Construction Phase

26

Status Date: 31 December 2012


Demolition is complete

Gypsum board and metal stud framing has started

Contractual Substantial Completion – February 2013

Forecasted Substantial Completion – February 2013

Edna Karr High School - Gymnasium Repair (OPSB) [3332 Huntlee Drive, New Orleans, LA 70131]

Scope of work: Determine what amount and methods need to be used to stabilize gymnasium for use. •

Funding Source – FEMA

Architect – Chenevert Architects, LLc

Contractor – Crescent Commercial Construction

Stablization of the Gymnasium 

Construction Phase •

An assement of the structure revield additional structural dammage.

Construction is 40% complete

Contractual Substantial Completion – February 2013

Forecasted Substantial Completion – February 2013

Thomy Lafon School (RSD) [2601 Seventh St, New Orleans, LA 70115]

Scope of work: Stabilization of sculpture and creation of interperative display •

Funding Source – FEMA

Architect – Mahlum / Scairono Marinez Joint Venture

Contractor – Clay Construction

Procurement Phase

Bid Opening – December 5th

The signed contract was received from the general contractor

Construction Phase 

Notice to Proceed is anticipated mid-February

27

Status Date: 31 December 2012


John McDonogh High School (RSD) [2426 Esplanade Avenue, New Orleans, LA 70119]

Scope of work: Replacement of bleachers and installation of sprinklers to gymnasium •

Funding Source – Harrah’s

Architect – Trapolin Peer Architects, LLC / Fanning Howey

Contractor – TBD

Design Phase - CD

The State Fire Marshal confirmed that with the addition of the new bleachers, a fire sprinkler system will be required in the gymnasium

Notice to Proceed on sprinkler design – December 7th

Design is anticipated to be completed in April 2013

Procurement Phase 

Anticipated 1st Advertisement – April 2013

Anticipated Bid Opening – June 2013

McDonogh #35 High School (OPSB) [1331 Kerlerec Street, New Orleans, LA 70116]

Scope of work: Stabilization and replacement of elevator •

Funding Source – FEMA

Architect – Chenevert Architects LLC

Contractor – TBD

Procurement Phase 

Construction Phase 

Owner reviewing contract Notice to Proceed is anticipated mid of January

Forecasted Substantial Completion – May 2013

28

Status Date: 31 December 2012


Timbers HVAC (OPSB) [3520 General DeGaulle, New Orleans, LA 70114]

Scope of work: Stabilization and replacement of HVAC •

Funding Source – General Fund

Architect – Moses Engineers

Contractor – TBD

Procurement Phase

Bid Opening – December 20th

Owner reviewing bids

Construction Phase 

Notice to Proceed is anticipated mid of February

Forecasted Substantial Completion – July 2013

Village de L’est Elementary School

(RSD)

[5100 Cannes Street, New Orleans, LA 70129]

Scope of work: Roof replacement and modular demolition •

Funding Source – FEMA

Architect – Richard C. Lambert Consultants, LLC

Contractor – TBD

Procurement Phase

Bid Opening was moved per Owner’s request

Bid Opening – January 9th

Forecasted Substantial Completion – May 2013

29

Status Date: 31 December 2012


Sylvanie Williams Elementary School (RSD) [3127 Martin Luther King Jr. Boulevard, New Orleans, LA 70125]

Scope of work: AHU replacement •

Funding Source – FEMA

Architect – Integrated Management Services, Inc.

Contractor – TBD

Procurement Phase 

Construction Phase 

The signed contract was received from the general contractor Notice to Proceed is anticipated on January 7th

Forecasted Substantial Completion – June 2013

Building Automation System Integration At Recovery School District Central And Remote Offices (RSD) [Various Addresses]

Scope of work: Implementation of a Central Remote Building Automation System that integrates the existing Building Automation Systems of the 4 Quick Start Schools (Andrew H. Wilson ES, Langston Hughes ES, L.B. Landry HS, and Lake Area HS) and Joseph A. Craig ES into a central remote monitoring workstation that will include Fannie C. Williams ES, Lawrence D. Crocker ES, Mildred Osborne ES, William Frantz ES, Bienville ES, Charles J. Colton ES, Carter G. Woodson ES and Parkview ES •

Funding Source – FEMA

Architect – Moses Engineers

Contractor – Synergy Building Solutions, Inc.

Construction Phase 

The five Quick Start Schools are complete, the punch lists anticipated end of January

Sylvanie Williams and Sarah T. Reed are complete, with the punch lists anticipated end of January

Issues with the RSD network has delyed the punch lists

The remaining integration for schools currently under construction will occur as each school is complete

Contractual Substantial Completion – November 2014

Forecasted Substantial Completion – November 2014

30

Status Date: 31 December 2012


MOTHBALL OR SAFE SELECTED SCHOOLS

&

SECURE

OF

Louis D. Armstrong Elementary School (RSD)) [5909 St. Claude Avenue, New Orleans, LA 70117]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications. •

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor – CDW Services, LLC

Mothballing of Closed Schools – Safe & Secure 

Construction Phase •

Installation of security fence is 40% complete

Demolition of canopies will start in January

Project is 63% complete

Contractual Substantial Completion – February 2013

Forecasted Substantial Completion – February 2013

Israel M. Augustine Middle School

(RSD)

[425 S. Broad St., New Orleans, LA 70119]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications. •

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor – CDW Services, LLC

Mothballing of Closed Schools – Safe & Secure 

Construction Phase •

Project is substantially complete

Contractual Substantial Completion – December 2012

Forecasted Substantial Completion – December 2012

31

Status Date: 31 December 2012


Andrew J. Bell Junior High School

(RSD)

[1010 N. Galvez St., New Orleans, LA 70119]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications. •

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor – Cresent Commercial Construction

Emergency Shoring – 100% complete 

Shoring will remain in place until roof work is complete

Mothballing of Closed Schools – Safe & Secure

Scope of work: Mothballing of the Gymnasium, Adminstration Building, Building “D”, Chapel, and the E.A.Christy Building 

Design Phase - CD •

Procurement Phase •

Anticipated 1st Advertisement – February 2013

Anticipated Bid Opening – March 2013

Roof Replacement 

Construction Phase •

100% Construction Documents were received on December 14th

The contractor has mobilized and the project is 20% complete

Forecasted Substantial Completion – August 2013

32

Status Date: 31 December 2012


Morris F. X. Jeff Elementary School

(RSD)

[800 N. Rendon Street, New Orleans, LA 70119]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications. •

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor – CDW Services, LLC

Mothballing of Closed Schools – Safe & Secure 

Construction Phase •

Project is 90% complete

Contractual Substantial Completion – January 2013

Forecasted Substantial Completion – January 2013

Valena C. Jones Elementary School

(RSD)

[1901 N. Galvez Street, New Orleans, LA 70119]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications. •

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor – CDW Services, LLC

Mothballing of Closed Schools – Safe & Secure 

Construction Phase •

Project is 85% complete

Replacement of roof is 95% complete

Contractual Substantial Completion – February 2013

Forecasted Substantial Completion – February 2013

33

Status Date: 31 December 2012


Demolition Projects Modular Classrooms at Fannie C. Williams Elementary School

(RSD)

[11755 Dwyer Street, New Orleans, LA 70128]

Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes. •

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor – Gulfcon LLC

Demolition of the Modular Classrooms 

Demolition Phase •

Notice to Proceed - December 3rd

Canopy removal is complete

Trailers are anticipated to be moved January – February

Contractual Substantial Completion – March 2013

Forecasted Substantial Completion – March 2013

Greater St. Stephens School (OPSB) [11110 Lake Forest Boulevard 70128]

Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes. •

Funding Source – FEMA

Architect – Chenevert Architects LLC

Contractor – Bayou Sheet Metal and Roofing Inc

Demolition Phase 

Entergy to de-energize and remove transformer

The contractor has demobilized from the site while waiting for Entergy to complete their scope of work

Demolition is 90% complete

Contractual Substantial Completion – March 2013

Forecasted Substantial Completion – March 2013

34

Status Date: 31 December 2012


JoEllen Smith Demolition

(OPSB)

[4400 General Meyer Avenue, New Orleans, LA 70131]

Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes. •

Funding Source – FEMA

Architect – VergesRome Architects, APAC

Contractor – TBD

Design Phase - CD

100% Construction Documents are anticipated January 23rd

���

A & E is working to resolve existing servitude issues

Procurement Phase 

Anticipated 1st Advertisement – February 2013

Anticipated Bid Date – March 2013

L. B. Landry Annex Demolition

(RSD)

[1100 Wagner Street, New Orleans, LA 70114]

Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes. •

Funding Source – FEMA

Architect – Perez Architects

Contractor – Durr Heavy Construction LLC

Demolition Phase 

Notice to Proceed - December 10th

Abatement is complete

Demolition to start the beginning of January

Contractual Substantial Completion – April 2013

Forecasted Substantial Completion – April 2013

35

Status Date: 31 December 2012


Mary Church Terrell Elementary School Demolition (RSD) [3411 Broadway, New Orleans, LA 70125]

Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes. •

Funding Source – FEMA

Architect – SCNZ Architects

Contractor – Gill Industries, Ltd.

Demolition Phase 

Notice to Proceed - December 17th

Abatement to start the beginning of January

Contractual Substantial Completion – April 2013

Forecasted Substantial Completion – April 2013

Booker T. Washington High School Partial Demolition

(RSD)

[1201 S. Roman Street, New Orleans, LA 70125]

Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes. •

Funding Source – FEMA

Architect – Hewitt-Washington & Associates

Contractor – Gulfcon LLC

Partial Demolition 

Demolition Phase •

Demolition of interior of main building is 95% complete

Owner is reviewing soil remediation test proposals

Contractual Substantial Completion – Feburary 2013

Forecasted Substantial Completion – February 2013

36

Status Date: 31 December 2012


Comprehensive List - Completed Projects 1.

Abrams | Morial | Abramson | Coghill Demolition

2.

A. D. Cross Elementary School Energy Conservation (RSD)

3.

A. D. Crossman Elementary School and Benjamin Banneker Elementary School (RSD)

4.

A. P. Tureaud Elementary School Roof Repairs (RSD)

5.

Agnes Bauduit Elementary School Boiler (RSD)

6.

Albert Wicker Elementary School Roof Repairs (RSD)

7.

Alfred Lawless Senior High Security Fencing (RSD)

8.

Alice M. Harte Elementary School Demolition (OPSB)

9.

Andrew Jackson Elementary School Roof Repairs (RSD)

10.

Andrew H. Wilson Elementary School Cottage (RSD)

11.

Arthur Ashe Elementary School Kitchen Renovation (OPSB)

12.

Augustine Elementary School Roof (RSD)

13.

Avery-Alexander Elementary School Demolition (RSD)

14.

Barbara C. Jordan Elementary School Demolition (RSD)

15.

Bell JH Shoring (RSD)

16.

Benjamin Banneker Elementary School Energy Conservation (RSD)

17.

Bienville Elementary School Demolition (RSD)

18.

Carter G. Woodson Middle School Demolition (RSD)

19.

Central Services Warehouse Demolition (OPSB)

20.

Charles J. Colton Elementary Selective Demolition (RSD)

21.

Charles R. Drew Elementary Roof & Installation of Kitchen Hood (RSD)

22.

Cohen High School Health Clinic

23.

Douglass High School Under Floor Utilities (RSD)

24.

Dr. Martin Luther King School Roof Repairs (RSD)

25.

Dr. Martin Luther King Jr. School Renovation (RSD)

26.

Dwight D. Eisenhower Elementary School Roof Repairs (RSD)

27.

East BankSwing Space for Audubon Charter School (OPSB)

28.

Edgar P. Harney Elementary School Roof Repairs (RSD)

29.

Edward Livingston Middle School Demolition(RSD)

30.

Edward Henry Phillips Junior High School Demolition (OPSB)

31.

New Edward Hynes School (OPSB)

32.

Edwards | Hardin | Lockett | Lawless Demolition (RSD)

37

(RSD)

(RSD)

Status Date: 31 December 2012


33.

Eleanor L. McMain School Replacement of Existing Chillers (OPSB)

34.

Ernest N. Morial Elementary Security Fencing (RSD)

35.

Fannie C. Williams Elementary School Demolition (RSD)

36.

Fisk-Howard Elementary School Demolition (RSD)

37.

Florence J. Chester Elementary School Demolition (RSD)

38.

Francis W. Gregory Demolition (RSD)

39.

Frederick A. Douglass High Switchgear (RSD)

40.

Frederick A. Douglass High Emergency Boiler Roof Repairs (RSD)

41.

George Mondy Elementary School Mothball (RSD)

42.

George Washington Carver High School Demolition (RSD)

43.

Henry Allen Elementary School Roof (RSD)

44.

Henry C. Schaumburg – Window/Door, Air Condition, Water Fountain/Sink Installation (RSD)

45.

Holy Cross Modular Relocation (RSD)

46.

Israel M. Augustine Middle School Roof Replacement (RSD)

47.

James Derham Demolition (RSD)

48.

James W. Johnson Elementary School Roof (RSD)

49.

New Jean Batiste de Bienville School (RSD)

50.

Jean Gordon Elementary School Demolition (RSD)

51.

John Dibert Elementary School Roof (RSD)

52.

John W. Hoffman Elementary School Demolition (RSD)

53.

John F. Kennedy Modular Relocation (Schwarz Campus) (RSD)

54.

John F. Kennedy Modular Relocation (Coghill Modular Campus) (RSD)

55.

John F. Kennedy High School Demolition (RSD)

56.

John McDonogh Senior High School Roof (RSD)

57.

John A. Shaw Elementary School Mothball (RSD)

58.

Joseph S. Clark Senior High School Roof Repairs (RSD)

59.

Joseph A. Craig Elementary Canopies (RSD)

60.

Joseph A. Craig Elementary Elevator Installation (RSD)

61.

Joseph A. Hardin Elementary Security Fencing (RSD)

62.

Lafayette Elementary School Roof and Masonry(RSD)

63.

Lake Area | Landry Demolition (RSD)

64.

Langston Hughes Elementary School (Phase I) (RSD)

65.

Langston Hughes Elementary School – New Gymnasium (Phase II) (RSD)

38

Status Date: 31 December 2012


66.

Langston Hughes Elementary School – Dumpster Pad (RSD)

67.

Lawrence D. Crocker Elementary School Demolition (RSD)

68.

Little Woods Elementary School Demolition (RSD)

69.

Live Oak Elementary School Roof (RSD)

70.

Live Oak Elementary School Exterior Door Replacement (RSD)

71.

Lorraine Hansberry Elementary School Mothball (RSD)

72.

Mahalia Jackson Elementary School (OPSB)

73.

Mahalia Jackson Elementary School Dumpster / Other Improvements(OPSB)

74.

Martin Behrman Elementary School Roof (RSD)

75.

Martin Luther King Jr. Elementary Canopy System (RSD)

76.

Martin Luther King Jr. School Modular Building, Deck, Canopy (RSD)

77.

Mary M. Bethune Elementary 1st Floor Replacement (OPSB)

78.

Mary M. Bethune Elementary Rear Yard Repair/Resurfacing (OPSB)

79.

McDonogh #15 Elementary Exterior Masonry to SOI Standards (RSD)

80.

McDonogh #28 Elementary School Roof

81.

McDonogh #32 Roof Replacement (RSD)

82.

McDonogh #35 ADA Upgrades to Public Restrooms, Exterior Ramp & Handicap Seating in the Auditorium (OPSB)

83.

McDonogh #42 Elementary School Roof (RSD)

84.

McDonogh #42 Elementary School HVAC Replacement (RSD)

85.

Mildred C. Osborne Elementary School Demolition

86.

Modular Campuses Close Outs (RSD)

87.

Modular Structures at Langston Hughes Elementary School (RSD)

88.

Morris F.X. Jeff Elementary School Demolition (RSD)

89.

Murray G. Henderson Elementary School Roof (RSD)

90.

New Andrew H. Wilson Elementary School (RSD)

91.

New Carter G. Woodson School (RSD)

92.

New Fannie C. Williams School (RSD)

93.

New Joseph A. Craig Elementary School (RSD)

94.

New L.B. Landry High School (RSD)

95.

New Lake Area High School (RSD)

96.

New Lawrence D. Crocker School (RSD)

97.

New Parkview School (RSD)

98.

New Equipment & Upgrades at 8 Central & 25 Satellite Kitchens (RSD)

39

(RSD)

(RSD)

Status Date: 31 December 2012


99.

New Orleans High School Signature Center Study (RSD)

100. Oretha C. Haley Demo (RSD) 101. Oretha C. Haley Elementary School Mothball 102. Parkview Elementary School Demolition

(RSD)

(RSD)

103. Paul L. Dunbar Elementary School Demolition (RSD) 104. Paul B. Habans Elementary School Roof Repairs (RSD) 105. Phillis Wheatley Elementary School Demolition (RSD) 106. Robert M. Lusher Elementary Roof Removal & Replacement (OPSB)

107. Sarah T. Reed High School Bleachers (RSD) 108. Sarah T. Reed High School Auditorium Wall (RSD) 109. Seabrook Computer Training Center Demolition (OPSB) 110. Schaumburg Chillers (RSD) 111. Schwarz Alternative Repairs

(RSD)

112. Schwarz Alternative Modulars Demolition (RSD) 113. Sherwood Forest Elementary School Demolition (RSD) 114. Sophie B. Wright Various Repairs/Restroom Renovations (OPSB) 115. Stuart R. Bradley Elementary School Demolition

(RSD)

116. Sylvanie Williams Elementary School Play Yard (RSD) 117. Sylvanie Williams Elementary School Roof Repairs (RSD) 118. Sylvanie Williams Elementary School HVAC/Chiller Replacement (RSD)

119. Temporary Campus for McDonogh #11 Expropriation (OPSB) 120. Thomas A. Edison Elementary School Demolition (RSD) 121. Thomy Lafon Elementary School Demolition (RSD) 122. Timbers Park Office Building #1 & #2 Demolition (OPSB) 123. Village de L’est Elementary School Subsidence (RSD) 124. Vorice J. Waters Elementary School Demolition (RSD) 125. West Bank Swing Space for Alice Harte Elementary School (OPSB) 126. New William J. Guste Elementary School (RSD) 127. William J. Guste Elementary School Science Lab (RSD) 128. William Frantz Elementary School Environmental Remediation & Selective Demolition (RSD) 129. William Frantz Elementary School Roof (RSD)

40

Status Date: 31 December 2012


41

Status Date: 31 December 2012