Superintendents’ Report December 2012
Mr. Stanley C. Smith Orleans Parish School Board
Mr. John White Louisiana Department of Education
Mr. Patrick Dobard Recovery School District
Prepared by:
Table of Contents Right-Click on the school name to proceed to that page
TABLE OF CONTENTS ..................................................... 1 OVERVIEW......................................................................... 3 COMMUNITY MEETINGS .................................................. 4 BID OPENINGS .................................................................. 5 NEW & MAJOR RENOVATION ......................................... 6 James Audubon School (OPSB) .................................. 6 Stuart R. Bradley School (RSD) .................................. 6 George Washington Carver School (RSD) .................. 7 Charles J. Colton School (RSD) .................................. 7 Charles R. Drew Elementary School (RSD) ............... 8 Frederick A. Douglass High School (RSD) ................. 8 Paul L. Dunbar School (RSD) ...................................... 9 Fisk-Howard School (RSD) ......................................... 9 William Frantz School (RSD) ..................................... 10 Alice Harte School (OPSB) ........................................ 10 New Karr High School at the JoEllen Smith Site (OPSB) ............................................................................... 11 New PK-8 School at North Kenilworth Park at Curran Site (OPSB)................................................................ 11 Lake Forest PK-8 at the Greater St. Stephens Site (OPSB) ....................................................................... 11 Alfred Lawless School (RSD) .................................... 12 Little Woods School (RSD) ........................................ 12 Edward Livingston High School (RSD) ..................... 13 McDonogh #35 School (Phillip/Waters Site) (OPSB). 13 McDonogh #42 Elementary School (RSD) ............... 14 Eleanor L. McMain School (OPSB) ........................... 14 Small New Orleans East High School at Abramson (RSD) ....................................................................... 15 Mildred Osborne School (RSD) ................................ 15 Booker T. Washington School (RSD) ........................ 16 Phillis Wheatley Elementary School (RSD) ............... 16 Sophie B. Wright School (RSD) ................................ 17 Bundy Road Space (RSD) ........................................ 17
REFURBISHMENTS......................................................... 18 Agnes L. Bauduit Elementary School Refurbishment (RSD) ........................................................................ 18 A. D. Crossman School Refurbishment (RSD) .......... 18 Warren Easton School Refurbishment (OPSB) .......... 19 Dwight D. Eisenhower Elementary School Refurbishment (RSD)................................................. 19 Gentilly Terrace School Refurbishment (RSD) ........... 20 Andrew Jackson School Refurbishment (RSD) .......... 20
1
Status Date: 31 December 2012
Dr. Martin L. King Elementary School Refurbishment (RSD) ......................................................................... 21 Lusher Elementary School Refurbishment (OPSB) ... 21 Fortier (Lusher) High School Refurbishment (OPSB) . 22 McDonogh #28 School Refurbishment (RSD) ............ 22 Nelson Elementary School Refurbishment (OPSB) .... 23 Sarah T. Reed School Refurbishment (RSD)............. 23 Albert Wicker School Refurbishment (RSD)............... 24 Sylvanie F. Williams School Refurbishment (RSD) .... 24 OTHER PROJECTS ......................................................... 25 Benjamin Franklin Senior High School (OPSB) .......... 25 Walter L. Cohen High School (RSD) ......................... 25 Warren Easton School (OPSB) ................................. 26 Andrew Jackson School (RSD) ................................ 26 Mahalia Jackson Elementary School Office Renovation (OPSB) .................................................... 26 Edna Karr High School - Gymnasium Repair (OPSB) ............................................................................... 27 Thomy Lafon School (RSD) ....................................... 27 John McDonogh High School (RSD) ......................... 28 McDonogh #35 High School (OPSB) ......................... 28 Timbers HVAC (OPSB) .............................................. 29 Village de’ Lest Elementary School (RSD) ................ 29 Sylvanie Williams Elementary School (RSD) ............. 30 Building Automation System Integration At Recovery School District Central And Remote Offices (RSD) .. 30 MOTHBALL OR SAFE & SECURE OF SELECTED SCHOOLS ........................................................................ 31 Louis D. Armstrong Elementary School (RSD)) ......... 31 Israel M. Augustine Middle School (RSD)................. 31 Andrew J. Bell Junior High School (RSD) ................. 32 Morris F. X. Jeff Elementary School (RSD) .............. 33 Valena C. Jones Elementary School (RSD) ............. 33 DEMOLITION PROJECTS ............................................... 34 Modular Classrooms at Fannie C. Williams Elementary School (RSD) ........................................ 34 Greater St. Stephens School (OPSB) ........................ 34 JoEllen Smith Demolition (OPSB) .............................. 35 L. B. Landry Annex Demolition (RSD) ...................... 35 Mary Church Terrell Elementary School Demolition (RSD) ) ....................................................................... 36 Booker T. Washington High School Partial Demolition (RSD) ..................................................... 36 COMPLETED PROJECTS .............................................. 37
2
Status Date: 31 December 2012
Overview The RSD has $342 million in open contracts for the capital program after issuing $516 thousand in new contracts and $179 thousand in change orders and amendments in December. In addition, the total change orders to date, $7.6 million, account for approximately two percent (2.65%) of the total open construction contracts. RSD anticipates issuing approximately $169 thousand in construction contracts and $408 thousand in professional service contracts/amendments in January. The RSD requested and received approval from the State’s Superintendent of Education to utilize the Design – Build method of project delivery for the following projects. George Washington Carver School Booker T. Washington School Sherwood Forest School Martin Behrman School Paul Habans School The OPSB has $96.7 million in open contracts for the capital program after issuing no new contracts, change orders and amendments in December. In addition, the total change orders to date, $1.7 million, account for approximately two percent (2.49%) of the total open construction contracts. OPSB anticipates issuing approximately $87.3 million in construction contracts and professional service contracts in January.
3
Status Date: 31 December 2012
Community Meetings No Community Meetings were scheduled for the month of December Community Meetings that are anticipated for the month of January •
January 31st: McDonogh 42 Elementary School– 1651 North Tonti Street, New Orleans, LA 70119
4
Status Date: 31 December 2012
Bid Openings Bids that were opened in December 2012: •
Thomy Lafon Interpretive Display (RSD) – December 5, 2012
•
Timbers HVAC Repairs (OPSB) – December 20, 2012
Over the next sixty days, bids to be opened for the following projects: •
Village de L’est Elementary School Roof and Modular Demolition – January 9, 2013
(RSD)
•
Test Pile Program at Sophie B. Wright (RSD) – January 23, 2013
•
Fisk-Howard School (RSD) – January 30, 2013
5
Status Date: 31 December 2012
Forecasted dates only include the next project phase
New & Major Renovation – Project Status James Audubon School (OPSB) [428 Broadway Avenue, New Orleans, LA 70118]
Scope of work: Renovation & Addition of Existing Elementary School •
Funding Source – FEMA
•
Architect – Blitch/Knevel Architects
•
Contractor – FHP Tectonics Corporation
•
Construction Phase
Pile driving is complete
Pile caps were formed and will be poured in January
Metal stud framing is 90% complete in the existing building
Steel fabrication has started
Installation of the new roofing on the existing building has started
MEP rough-ins are ongoing on the 1st, 2nd and 3rd floor
•
Contractual Substantial Completion – September 2013
•
Forecasted Substantial Completion – February 2014
•
School Ready for Occupancy – May 2014
Stuart R. Bradley School
(RSD)
[ 2401 Humanity Street, New Orleans, LA 70122]
Scope of work: New 3 – section elementary school for 850 students •
Funding Source – FEMA
•
Architect – Sizeler Thompson Brown Architects
•
Contractor – TBD
•
Design Phase – CD
•
100% Construction Documents are anticipated January 7th
A time extension was granted to the A&E for design consideration of a new cost effective construction material
Procurement Phase
Anticipated 1st Advertisement – February 2013
Anticipated Bid Opening – March 2013
6
Status Date: 31 December 2012
George Washington Carver School (RSD) [3019 & 3059 Higgins Blvd., New Orleans, LA 70126]
Scope of work: New High School •
Funding Source – FEMA
•
Architect – Trapolin Architects & VMDO Architects, A Joint- Venture
•
Contractor – TBD
•
Design Phase
The RSD is working with key stakeholders to value engineer this project in an effort to reduce the cost
Items being explored include: Foundation redesign Reduced ceiling heights Repurpose areas of the building Use of cost effective construction materials Changing the project delivery methods Scaling back on architectural elements
Charles J. Colton School (RSD) [2300 St. Claude Avenue, New Orleans, LA 70117]
Scope of work: Renovation of existing elementary school and new addition •
Funding Source – FEMA
•
Architect – Waggonner & Ball Architects
•
Contractor – F.H. Paschen, S.N. Nielsen & Associates, LLC
•
Construction Phase
•
Roofing material installation is 95% complete
Gypsum board installation on interior walls is complete on 2nd and 3rd floors
Pulling of wiring/data lines is ongoing
Window installation is complete, glazing is 80% complete
Exterior wall panels are 90% complete
Patching of terrazzo is 80% complete
VCT floor installation is 60% complete
The installation of electrical fixtures and raceways are 65% complete
Contractual Substantial Completion – November 2012
7
Status Date: 31 December 2012
•
Forecasted Substantial Completion – March 2013
•
School Ready for Occupancy – June 2013
Charles R. Drew Elementary School (RSD) [3819 St. Claude Avenue, New Orleans, LA 70117]
Scope of work: Renovation of existing elementary school and new addition to meet code requirements •
Funding Source – FEMA
•
Architect – Blitch / Knevel Architects, Inc.
•
Contractor – TBD
•
Design Phase - CD
•
50% Construction Documents were received December 10th
100% Construction Documents are anticipated February 18th
Procurement Phase
Anticipated 1st Advertisement – March 2013
Anticipated Bid Opening – April 2013
Frederick A. Douglass High School (RSD) [3820 St. Claude Avenue, New Orleans, LA 70117]
Scope of work: Renovation of existing high school •
Funding Source – FEMA
•
Architect – VergesRome Architects, APAC
•
Contractor – TBD
•
Design Phase - CD
Design Development were received on December 15th
The building will be used for swing space for the next two years
The student population at Drew is overwhelmingly made up of children living in the neighborhood, so having swing space nearby for those students is crucial while Drew is being renovated
8
Status Date: 31 December 2012
Paul L. Dunbar School (RSD) [9330 Forshey Street, New Orleans, LA 70125]
Scope of work: New 2 - section elementary school for 556 students •
Funding Source – FEMA
•
Architect – Chenevert Architects LLC
•
Contractor – TBD
•
Design Phase - CD
•
100% Construction Documents were received December 18th
Procurement Phase
Anticipated 1st Advertisement – March 2013
Anticipated Bid Opening – April 2013
Fisk-Howard School (RSD) [211 South Lopez Street, New Orleans, LA 70119]
Scope of work: New 3 - section elementary school for 850 students •
Funding Source - FEMA
•
Architect - VergesRome Architects+Fanning Howey
•
Contractor – TBD
•
Design Phase
•
Test Pile reports were received the beginning of December
Procurement Phase
1st Advertisement – December 26th
2nd Advertisement – January 2nd
3rd Advertisement – January 9th
Pre-Bid Conference – 9:00 a.m. on January 10th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA
Bid Opening – January 30th
9
Status Date: 31 December 2012
William Frantz School (RSD) [3811 North Galvez Street, New Orleans, LA 70117]
Scope of work: Renovation of existing elementary school and new addition •
Funding Source – FEMA
•
Architect – Billes Architecture, LLC
•
Contractor – The Lathan Company, Inc.
•
Construction Phase
Sanding and finishing of wood floors in the existing building will take place in January
Ceramic tile reinstall has begun
MEP subcontractors have returned to site and are proceeding with HVAC start-up and various activities
Courtyard site work is ongoing
The general contractor is working on various areas of nonconforming work
•
Contractual Substantial Completion – March 2012
•
Forecasted Substantial Completion – June 2013
•
School Ready for Occupancy – August 2013
Alice Harte School
(OPSB)
[5300 Berkley Drive, New Orleans, La 70131]
Scope of work: New 3 - section elementary school for 850 students •
Funding Source – CDBG & FEMA
•
Architect – WDG Architects Engineers
•
Contractor – Woodrow Wilson Construction Company, Inc.
•
Construction Phase
Pile driving is complete
Foundation work continues with pile caps and grade beams
Slab on grade is scheduled to be poured by the end of January
• Contractual Substantial Completion – January 2014 • Forecasted Substantial Completion – January 2014 • School Ready for Occupancy – June 2014
10
Status Date: 31 December 2012
New Karr High School at the JoEllen Smith Site (OPSB) [4400 General Meyer Avenue, New Orleans, LA 70131]
Scope of work: New medium high school •
Funding Source – FEMA
•
Architect – Lee Ledbetter & Associates / Gould Evans Associates
•
Contractor – TBD
•
Design Phase - SD
Due to design issues and additional scope of work, Schematic Design Documents were rejected by the Owner
New PK-8 School at North Kenilworth Park at Curran Site (OPSB) [8500 Curran Boulevard, New Orleans, LA 70127]
Scope of work: New 3 - section elementary school for 850 students •
Funding Source – FEMA
•
Architect – Mathes Brierre Architects
•
Contractor – Woodrow Wilson Construction Company, Inc.
•
Procurement Phase
The contract was issued to the general contractor
Notice to Proceed is anticipated mid-February
•
Forecasted Substantial Completion – August 2014
•
School Ready for Occupancy – January 2015
Lake Forest PK-8 at the Greater St. Stephens Site
(OPSB)
[11110 Lake Forest Boulevard 70128]
Scope of work: New 3 - section elementary school for 850 students •
Funding Source – FEMA
•
Architect – Imre Hegedus & Associates Architects
•
Contractor – TBD
•
Design Phase - CD
•
50% Construction Documents are anticipated on January 2nd
100% Construction Documents are anticipated on March 5th
Procurement Phase
Anticipated 1st Advertisement – April 2013
Anticipated Bid Opening – May 2013
11
Status Date: 31 December 2012
Alfred Lawless School
(RSD)
[5300 Law Street, New Orleans, LA 70117]
Scope of work: New medium high school •
Funding Source – FEMA
•
Architect – Sizeler Thompson Brown Architects
•
Contractor – TBD
•
Design Phase - CD
•
50% Construction documents are anticipated to be finished on January 25th
100% Construction documents are anticipated to be finished on March 24th
Procurement Phase
Anticipated 1st Advertisement – April 2013
Anticipated Bid Opening – May 2013
Little Woods School (RSD) [10200 Curran Blvd., New Orleans, LA 70127]
Scope of work: New Pre-K – 8 school •
Funding Source – FEMA
•
Architect – Group Novak, LLC
•
Contractor – MAPP Construction
•
Construction Phase
Terrazzo flooring is complete on third floor; two crews are working on first and second floors.
Gypsum board walls are being taped, floated and painted on the 1st floor
Installing restroom ceilings on 2nd and 3rd floors
Ceiling grid and raceways are installed in the classrooms
90% of the storefront doors are installed
Millwork is installed in Science Labs
Electrical raceways are being installed
10,000 sf of parking has been formed up and will be poured mid-January. Exterior canopies are installed
•
Contractual Substantial Completion – November 2012
•
Forecasted Substantial Completion – April 2013
•
School Ready for Occupancy – TBD
12
Status Date: 31 December 2012
Edward Livingston High School
(RSD)
[7301 Dwyer Road, New Orleans, LA 70126]
Scope of work: New small high school •
Funding Source – FEMA
•
Architect – RozasWard / a.i.a. architects, inc.
•
Contractor – TBD
•
Design Phase - CD
•
100% Construction Documents were received on December 26th
Procurement Phase
1st Advertisement – February 13th
2nd Advertisement – February 20th
3rd Advertisement – February 27th
Pre-Bid Conference – 9:00 a.m. on February 28th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA
Bid Opening – March 20th
McDonogh #35 School (Phillip/Waters Site)
(OPSB)
[1200 Senate Street, New Orleans, LA 70122]
Scope of work: New 3-story high school •
Funding Source – FEMA
•
Architect – Sizeler, Thompson, Brown Architects
•
Contractor – Citadel Builders, LLC
•
Site Remediation Project
A Phase II environmental assessment revealed heavy metals and PAHs exist in the fill
Scope of work: Remediate fly-ash materials found in the soil
Remediation work is anticipated to be complete 1st quarter of 2013
•
New Construction Project
•
Procurement Phase
The contract was issued to the general contractor
Notice to Proceed is anticipated upon the completion of the site remediation project
13
Status Date: 31 December 2012
McDonogh #42 Elementary School (RSD) [1651 North Tonti Street, New Orleans, LA 70119]
Scope of work: Renovation of existing elementary school and new addition to meet code requirements •
Funding Source – FEMA
•
Architect – Eskew+Dumez+Ripple
•
Contractor – TBD
•
Design Phase - CD
•
50% Construction Documents are anticipated January 24th
100% Construction Documents are anticipated March
Procurement Phase
Anticipated 1st Advertisement – April 2013
Anticipated Bid Opening – June 2013
Eleanor L. McMain School
(OPSB)
[5721 S. Claiborne Avenue, New Orleans, LA 70125]
Scope of work: The exterior of the existing building will be stabilized and a new gym will be added to the site with a connecting breezeway to the main building. A portion of the existing building will be renovated for a health clinic. •
•
•
Exterior Stabilization
Funding Source – FEMA
Architect – Jahncke & Burns Architects
Contractor – TBD
Notice to Proceed for the A&E is anticipated January 14th
New Gymnasium
Funding Source – FEMA
Architect – Jahncke & Burns Architects
Contractor – Ellis Construction
Procurement Phase •
General contractor has return the signed contract
•
Notice to Proceed is anticipated mid-February
School Based Health Clinic
Funding Source – HRSA Grant
Architect – Jahncke & Burns Architects
•
Contractor – ETI. Inc.
14
Status Date: 31 December 2012
Construction Phase •
Construction is 15% complete
• Contractual Substantial Completion – March 2013 Small New Orleans East High School at Abramson (RSD) [5552 Read Boulevard, New Orleans, LA 70127]
Scope of work: New small high school •
Funding Source – FEMA
•
Architect – RozasWard / a.i.a. architects, inc.
•
Contractor – TBD
•
Design Phase - CD
•
Project will be delayed due to the City Of New Orleans request for reorientation of the front elevation of the project
100% Construction Documents are anticipated March 2013
Procurement Phase
Anticipated 1st Advertisement – April 2013
Anticipated Bid Opening – May 2013
Mildred Osborne School (RSD) [6701 Curran Blvd., New Orleans, LA 70126]
Scope of work: New Pre-K– 8 school •
Funding Source – FEMA
•
Architect – Fauntleroy & Latham
•
Contractor – F.H. Paschen, S.N. Nielsen & Associates, LLC
•
Construction Phase
• •
Landscaping and the fencing is 95% complete
Media Center and Library will be completed at the end of January
Contractual Substantial Completion – February 2013 This school will have a phased delivery schedule from 16th of October to end of January 2013
15
Status Date: 31 December 2012
Booker T. Washington School (RSD) [1201 South Roman Street, New Orleans, LA 70125] Scope of work: The auditorium and entry will be renovated and the remainder of the facility will be demolished and constructed new •
Funding Source – FEMA
•
Architect – Hewitt-Washington & Associates
•
Contractor – TBD
•
Design Phase - CD
Upon completion of the Design Phase, the project will be put on hold until a mitigation plan is developed on the environmental issues
Based on current market projections, the RSD is working with key stakeholders to value engineer this project in an effort to reduce the cost
Items being explored include: Reduced ceiling heights Repurpose areas of the building Use of cost effective construction materials Changing the project delivery methodology Scaling back on architectural elements
Phillis Wheatley Elementary School (RSD) [2300 Dumaine Street, New Orleans, LA 70119]
Scope of work: New 2 - section elementary school for 556 students •
Funding Source – FEMA
•
Architect – Holly & Smith Architects
•
Contractor – Gibbs Construction
•
Construction Phase
Site clearing is complete
Pile driving has begun
Foundation work is expect to continue thru February with pile caps and grade beams
Will close first New Market Tax Credit transaction in partnership with OPSB on the Wheatley School in Treme in February. We will receive $1.5 million that would have otherwise been unavailable to the RSD/OPSB and our partners through this transaction. Contractual Substantial Completion – May 2014
•
16
Status Date: 31 December 2012
•
Forecasted Substantial Completion – May 2014
•
School Ready for Occupancy – June 2014
Sophie B. Wright Middle School Renovation
(RSD)
[1426 Napoleon Avenue, New Orleans, LA 70115]
Scope of work: Renovation of existing middle school •
Funding Source – FEMA
•
Architect – Waggonner & Ball Architects, APC
•
Contractor – TBD
•
Design Phase - CD
•
Design Development Documents were received December 11th
The additional scope of adding a new gymnasium will extend the CD phase of this job
50% Construction Documents are anticipated in March
Procurement Phase
Anticipated 1st Advertisement – June 2013
Anticipated Bid Opening – July 2013
Bundy Road Space (RSD) [6767 Bundy Road, New Orleans, LA 70127]
Scope of work: Renovation of existing office complex into a school •
Architect – VergesRome Architects, APAC
•
Contractor – TBD
•
Design Phase - FS
Feasibility study was performed to determine if an office complex can be converted into a school
RSD will work with OPSB to procure the site
The conversion of this site to a school is more cost effective than building a new school
The building will have the flexibility to house a K-12 program
17
Status Date: 31 December 2012
REFURBISHMENTS Agnes L. Bauduit Elementary School Refurbishment
(RSD)
[3649 Laurel Street, New Orleans, LA 70115]
Scope of work: Refurbishment of existing elementary school, including but not limited to structure, windows, doors, masonry walls and roof •
Funding Source – FEMA
•
Architect – Duplantis Design Group, PC
•
Contractor - TBD
•
Design Phase - SD
•
Program documents were received on December 4th
The Owner is reviewing the Program Documents scope of work
Schematic Design documents are anticipated on February 21st
Procurement Phase
Anticipated 1st Advertisement – July 2013
Anticipated Bid Opening – August 2013
A. D. Crossman School Refurbishment
(RSD)
[4407 South Carrollton Avenue, New Orleans, LA 70119]
Scope of work: Refurbishment of existing elementary school, including but not limited to structure, windows, doors, masonry walls and roof •
Funding Source – FEMA
•
Architect – Perez, APC
•
Contractor - TBD
•
Design Phase - CD
•
Schematic Design documents were received on December 18th
100% Construction Documents are anticipated February 13th
Procurement Phase
Anticipated 1st Advertisement – March 2013
Anticipated Bid Opening – April 2013
18
Status Date: 31 December 2012
Warren Easton School
(OPSB)
[3019 Canal Street, New Orleans, LA 70119]
Scope of work: Refurbishment of existing high school •
Funding Source – FEMA
•
Architect – Chenevert Architects LLC
•
Contractor - TBD
•
Design Phase - CD
•
100% Construction Documents are anticipated in February
Owner requested an increase in the scope of work which will extend the Design Phase
Procurement Phase
Anticipated 1st Advertisement – March 2013
Anticipated Bid Opening – April 2013
Dwight D. Eisenhower Elementary School Refurbishment
(RSD)
[3700 Tall Pines Drive, New Orleans, LA 70131]
Scope of work: Refurbishment of existing elementary school, including but not limited to structure, windows, doors, masonry walls and roof •
Funding Source – FEMA
•
Architect – Harry Baker Smith Architects II, PLLC
•
Contractor - TBD
•
Design Phase - PC
•
Program documents are anticipated on January 11th
Schematic Design documents are anticipated on February 21th
Procurement Phase
Anticipated 1st Advertisement – August 2013
Anticipated Bid Opening – September 2013
19
Status Date: 31 December 2012
Gentilly Terrace School Refurbishment
(RSD)
[4720 Painters Street, New Orleans, LA 70122]
Scope of work: Refurbishment of existing elementary school, including but not limited to structure, windows, doors, masonry walls and roof •
Funding Source – FEMA
•
Architect – Byron J. Stewart & Associates, APC Architects & Planners
•
Contractor - TBD
•
Design Phase - PC
•
Program documents are to be revised and resubmitted on January 9th
Schematic Design documents are anticipated on February 24th
Procurement Phase
Anticipated 1st Advertisement – June 2013
Anticipated Bid Opening – July 2013
Andrew Jackson School Refurbishment
(RSD)
[1400 Camp Street, New Orleans, LA 70130]
Scope of work: Refurbishment of existing elementary school, including but not limited to structure, windows, doors, masonry walls and roof •
Funding Source – FEMA
•
Architect – N-Y Associates, Inc.
•
Contractor - TBD
•
Design Phase - SD
•
The Owner is reviewing the Program Documents scope of work
Schematic Design documents are anticipated on February 3rd
Procurement Phase
Anticipated 1st Advertisement – June 2013
Anticipated Bid Opening – July 2013
20
Status Date: 31 December 2012
Dr. Martin L. King Elementary School Refurbishment
(RSD)
[1617 Caffin Avenue, New Orleans, LA 70117]
Scope of work: Refurbishment of existing elementary school, including but not limited to structure, windows, doors, masonry walls and roof •
Funding Source – FEMA
•
Architect – VergesRome Architects, APAC
•
Contractor - TBD
•
Design Phase - SD
•
The Owner is reviewing the Program Documents scope of work
Schematic Design documents are anticipated on February 14th
Procurement Phase
Anticipated 1st Advertisement – July 2013
Anticipated Bid Opening – August 2013
Lusher Elementary School Refurbishment (OPSB) [7315 Willow Street, New Orleans, LA 70118]
Scope of work: Renovation and repairs to the existing bridge, roof, windows, exterior doors, and restroom accessibility •
Funding Source – FEMA
•
Architect – Meyer Engineers, LTD.
•
Contractor - TBD
•
Design Phase - CD
•
Design Development documents were received on December 27th
50% Construction Documents are anticipated on January 28th
Procurement Phase
Anticipated 1st Advertisement – April 2013
Anticipated Bid Opening – May 2013
21
Status Date: 31 December 2012
Fortier (Lusher) High School Refurbishment
(OPSB)
[5624 Freret Street, New Orleans, LA 70115]
Scope of work: Renovation and repairs to the roof, masonry, plaster, windows, exterior doors, canopies, mechanical systems, and electrical systems. •
Funding Source – FEMA
•
Architect – Meyer Engineers, LTD.
•
Contractor - TBD
•
Design Phase - DD
•
Design Development documents were received on December 21st
The Owner is reviewing the Design Development documents scope of work
Procurement Phase
Anticipated 1st Advertisement – June 2013
Anticipated Bid Opening – July 2013
McDonogh #28 School Refurbishment
(RSD)
[2733 Esplanade Avenue, New Orleans, LA 70119]
Scope of work: Refurbishment of existing elementary school, including but not limited to structure, windows, doors, masonry walls and roof •
Funding Source – FEMA
•
Architect – SCNZ Architects,LLC
•
Contractor - TBD
•
Design Phase - CD
•
Schematic Design documents were received on December 17th
100% Construction Documents are anticipated on April following a delay for the Owner to define scope
Procurement Phase
Anticipated 1st Advertisement – May 2013
Anticipated Bid Opening – June 2013
22
Status Date: 31 December 2012
Nelson Elementary School Refurbishment
(OPSB)
[3121 St. Bernard Avenue, New Orleans, LA 70119]
Scope of work: Renovation and repairs to the roof, masonry, windows, exterior doors, mechanical systems, and electrical systems. •
Funding Source – FEMA
•
Architect – Harry Baker Smith Architects
•
Contractor - TBD
•
Design Phase - PC
•
Program documents are anticipated January 11th
Schematic Design documents are anticipated January 20th
Procurement Phase
Anticipated 1st Advertisement – June 2013
Anticipated Bid Opening – July 2013
Sarah T. Reed School Refurbishment
(RSD)
[5316 Michoud Boulevard, New Orleans, LA 70129]
Scope of work: Refurbishment of existing high school, including but not limited to structure, windows, doors, masonry walls and roof •
Funding Source – FEMA
•
Architect – Byron J. Stewart & Associates, APC Architects & Planners
•
Contractor - TBD
•
Design Phase - SD
•
Program documents were received on December 6th
The Owner is reviewing the Program Documents scope of work
Schematic Design documents are anticipated on February 14th
Procurement Phase
Anticipated 1st Advertisement – August 2013
Anticipated Bid Opening – September 2013
23
Status Date: 31 December 2012
Albert Wicker School Refurbishment
(RSD)
[2011 Bienville Street, New Orleans, LA 70112]
Scope of work: Refurbishment of existing elementary school, including but not limited to structure, windows, doors, masonry walls and roof •
Funding Source – FEMA
•
Architect – SCNZ Architects, LLC
•
Contractor - TBD
•
Design Phase - SD
•
Program documents were received on December 1st
Schematic Design documents are anticipated on January 1st
Procurement Phase
Anticipated 1st Advertisement – July 2013
Anticipated Bid Opening – August 2013
Sylvanie F. Williams School Refurbishment
(RSD)
[3127 Martin Luther King Jr. Boulevard, New Orleans, LA 70125]
Scope of work: Refurbishment of existing elementary school, including but not limited to structure, windows, doors, masonry walls and roof •
Funding Source – FEMA
•
Architect – Chenevert Architects, LLC
•
Contractor - TBD
•
Design Phase - PC
•
Program documents are anticipated January 11th
Schematic Design documents are anticipated on February 21st
Procurement Phase
Anticipated 1st Advertisement – August 2013
Anticipated Bid Opening – September 2013
24
Status Date: 31 December 2012
OTHER PROJECTS Benjamin Franklin Senior High School (OPSB) [2001 Leon C. Simon Drive, New Orleans, LA 70122]
Scope of work: Stabilization and repairs to the existing courtyard, exterior lighting, metal roof panels, interior lighting, curtain wall, exterior doors (frames), fencing, scoreboard and goal post •
Funding Source – FEMA
•
Architect – Perez, APC
•
Contractor – Pete Vicari General Contractors Inc.
•
Construction Phase
Additional courtyard work is anticipated to be complete in January 2013
Electrical lighting work is complete
•
Contractual Substantial Completion – January 2013
•
Forecasted Substantial Completion – January 2013
Walter L. Cohen High School (RSD) [3520 Dryades Street, New Orleans, LA 70115]
Scope of work: Correct the HVAC return air / ventilation problems and replace eight (8) chilled water pumps •
Funding Source – FEMA
•
Architect – Infinity Engineering Consultants, LLC
•
Contractor – TBD
•
Design Phase - CD
•
Schematic Design documents were received December 23rd
50% Construction Documents are anticipated on January 16th
Procurement Phase
Anticipated 1st Advertisement – March 2013
Anticipated Bid Opening – April 2013
25
Status Date: 31 December 2012
Warren Easton School
(OPSB)
[3019 Canal Street, New Orleans, LA 70119]
Scope of work: Removal and replacement of existing exterior windows and waterproofing of the courtyard masonry •
Funding Source – Harrah’s
•
Architect – VergesRome Architects, apc
•
Contractor – Barbara Enterprises, Inc.
•
Final Close-out Phase
Substantial completion September 6th
The Owner has put the contractor in default
The Surety was contacted and is developing a plan to complete the project
•
Contractual Substantial Completion – March 2010
•
Actual Substantial Completion – September 2012
Andrew Jackson School
(RSD)
[1400 Camp Street, New Orleans, LA 70130]
Scope of work: Installation of solar panels at Andrew Jackson School. This will save energy for the school and serve as a teaching aide for students to learn about solar energy •
Funding Source – Greater New Orleans Foundation/Entergy Grant
•
Architect – Perez, APC
•
Contractor – South Coast Solar
•
Construction Phase
•
Contractor is 50% complete with the installation of the solar panels
Forecasted Substantial Completion – January 2013
Mahalia Jackson Elementary School Office Renovation (OPSB) [2101 Freret Street, New Orleans, LA 70113]
Scope of work: Convert the office space on the second floor of Building C into four classrooms •
Funding Source – New Orleans Parish School Board General Fund
•
Architect – VergesRome Architects, APAC
•
Contractor – ETI, Inc.
•
Construction Phase
26
Status Date: 31 December 2012
Demolition is complete
Gypsum board and metal stud framing has started
•
Contractual Substantial Completion – February 2013
•
Forecasted Substantial Completion – February 2013
Edna Karr High School - Gymnasium Repair (OPSB) [3332 Huntlee Drive, New Orleans, LA 70131]
Scope of work: Determine what amount and methods need to be used to stabilize gymnasium for use. •
Funding Source – FEMA
•
Architect – Chenevert Architects, LLc
•
Contractor – Crescent Commercial Construction
•
Stablization of the Gymnasium
Construction Phase •
An assement of the structure revield additional structural dammage.
•
Construction is 40% complete
•
Contractual Substantial Completion – February 2013
•
Forecasted Substantial Completion – February 2013
Thomy Lafon School (RSD) [2601 Seventh St, New Orleans, LA 70115]
Scope of work: Stabilization of sculpture and creation of interperative display •
Funding Source – FEMA
•
Architect – Mahlum / Scairono Marinez Joint Venture
•
Contractor – Clay Construction
•
Procurement Phase
•
Bid Opening – December 5th
The signed contract was received from the general contractor
Construction Phase
Notice to Proceed is anticipated mid-February
27
Status Date: 31 December 2012
John McDonogh High School (RSD) [2426 Esplanade Avenue, New Orleans, LA 70119]
Scope of work: Replacement of bleachers and installation of sprinklers to gymnasium •
Funding Source – Harrah’s
•
Architect – Trapolin Peer Architects, LLC / Fanning Howey
•
Contractor – TBD
•
Design Phase - CD
•
The State Fire Marshal confirmed that with the addition of the new bleachers, a fire sprinkler system will be required in the gymnasium
Notice to Proceed on sprinkler design – December 7th
Design is anticipated to be completed in April 2013
Procurement Phase
Anticipated 1st Advertisement – April 2013
Anticipated Bid Opening – June 2013
McDonogh #35 High School (OPSB) [1331 Kerlerec Street, New Orleans, LA 70116]
Scope of work: Stabilization and replacement of elevator •
Funding Source – FEMA
•
Architect – Chenevert Architects LLC
•
Contractor – TBD
•
Procurement Phase
•
Construction Phase
•
Owner reviewing contract Notice to Proceed is anticipated mid of January
Forecasted Substantial Completion – May 2013
28
Status Date: 31 December 2012
Timbers HVAC (OPSB) [3520 General DeGaulle, New Orleans, LA 70114]
Scope of work: Stabilization and replacement of HVAC •
Funding Source – General Fund
•
Architect – Moses Engineers
•
Contractor – TBD
•
Procurement Phase
•
Bid Opening – December 20th
Owner reviewing bids
Construction Phase
•
Notice to Proceed is anticipated mid of February
Forecasted Substantial Completion – July 2013
Village de L’est Elementary School
(RSD)
[5100 Cannes Street, New Orleans, LA 70129]
Scope of work: Roof replacement and modular demolition •
Funding Source – FEMA
•
Architect – Richard C. Lambert Consultants, LLC
•
Contractor – TBD
•
Procurement Phase
•
Bid Opening was moved per Owner’s request
Bid Opening – January 9th
Forecasted Substantial Completion – May 2013
29
Status Date: 31 December 2012
Sylvanie Williams Elementary School (RSD) [3127 Martin Luther King Jr. Boulevard, New Orleans, LA 70125]
Scope of work: AHU replacement •
Funding Source – FEMA
•
Architect – Integrated Management Services, Inc.
•
Contractor – TBD
•
Procurement Phase
•
Construction Phase
•
The signed contract was received from the general contractor Notice to Proceed is anticipated on January 7th
Forecasted Substantial Completion – June 2013
Building Automation System Integration At Recovery School District Central And Remote Offices (RSD) [Various Addresses]
Scope of work: Implementation of a Central Remote Building Automation System that integrates the existing Building Automation Systems of the 4 Quick Start Schools (Andrew H. Wilson ES, Langston Hughes ES, L.B. Landry HS, and Lake Area HS) and Joseph A. Craig ES into a central remote monitoring workstation that will include Fannie C. Williams ES, Lawrence D. Crocker ES, Mildred Osborne ES, William Frantz ES, Bienville ES, Charles J. Colton ES, Carter G. Woodson ES and Parkview ES •
Funding Source – FEMA
•
Architect – Moses Engineers
•
Contractor – Synergy Building Solutions, Inc.
•
Construction Phase
The five Quick Start Schools are complete, the punch lists anticipated end of January
Sylvanie Williams and Sarah T. Reed are complete, with the punch lists anticipated end of January
Issues with the RSD network has delyed the punch lists
The remaining integration for schools currently under construction will occur as each school is complete
•
Contractual Substantial Completion – November 2014
•
Forecasted Substantial Completion – November 2014
30
Status Date: 31 December 2012
MOTHBALL OR SAFE SELECTED SCHOOLS
&
SECURE
OF
Louis D. Armstrong Elementary School (RSD)) [5909 St. Claude Avenue, New Orleans, LA 70117]
Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications. •
Funding Source – FEMA
•
Architect – VergesRome Architects, APAC
•
Contractor – CDW Services, LLC
•
Mothballing of Closed Schools – Safe & Secure
Construction Phase •
Installation of security fence is 40% complete
•
Demolition of canopies will start in January
•
Project is 63% complete
•
Contractual Substantial Completion – February 2013
•
Forecasted Substantial Completion – February 2013
Israel M. Augustine Middle School
(RSD)
[425 S. Broad St., New Orleans, LA 70119]
Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications. •
Funding Source – FEMA
•
Architect – VergesRome Architects, APAC
•
Contractor – CDW Services, LLC
•
Mothballing of Closed Schools – Safe & Secure
Construction Phase •
Project is substantially complete
•
Contractual Substantial Completion – December 2012
•
Forecasted Substantial Completion – December 2012
31
Status Date: 31 December 2012
Andrew J. Bell Junior High School
(RSD)
[1010 N. Galvez St., New Orleans, LA 70119]
Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications. •
Funding Source – FEMA
•
Architect – VergesRome Architects, APAC
•
Contractor – Cresent Commercial Construction
•
Emergency Shoring – 100% complete
Shoring will remain in place until roof work is complete
•
Mothballing of Closed Schools – Safe & Secure
•
Scope of work: Mothballing of the Gymnasium, Adminstration Building, Building “D”, Chapel, and the E.A.Christy Building
Design Phase - CD •
•
Procurement Phase •
Anticipated 1st Advertisement – February 2013
•
Anticipated Bid Opening – March 2013
Roof Replacement
Construction Phase •
•
100% Construction Documents were received on December 14th
The contractor has mobilized and the project is 20% complete
Forecasted Substantial Completion – August 2013
32
Status Date: 31 December 2012
Morris F. X. Jeff Elementary School
(RSD)
[800 N. Rendon Street, New Orleans, LA 70119]
Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications. •
Funding Source – FEMA
•
Architect – VergesRome Architects, APAC
•
Contractor – CDW Services, LLC
•
Mothballing of Closed Schools – Safe & Secure
Construction Phase •
Project is 90% complete
•
Contractual Substantial Completion – January 2013
•
Forecasted Substantial Completion – January 2013
Valena C. Jones Elementary School
(RSD)
[1901 N. Galvez Street, New Orleans, LA 70119]
Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire detection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications. •
Funding Source – FEMA
•
Architect – VergesRome Architects, APAC
•
Contractor – CDW Services, LLC
•
Mothballing of Closed Schools – Safe & Secure
Construction Phase •
Project is 85% complete
•
Replacement of roof is 95% complete
•
Contractual Substantial Completion – February 2013
•
Forecasted Substantial Completion – February 2013
33
Status Date: 31 December 2012
Demolition Projects Modular Classrooms at Fannie C. Williams Elementary School
(RSD)
[11755 Dwyer Street, New Orleans, LA 70128]
Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes. •
Funding Source – FEMA
•
Architect – VergesRome Architects, APAC
•
Contractor – Gulfcon LLC
•
Demolition of the Modular Classrooms
Demolition Phase •
Notice to Proceed - December 3rd
•
Canopy removal is complete
•
Trailers are anticipated to be moved January – February
•
Contractual Substantial Completion – March 2013
•
Forecasted Substantial Completion – March 2013
Greater St. Stephens School (OPSB) [11110 Lake Forest Boulevard 70128]
Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes. •
Funding Source – FEMA
•
Architect – Chenevert Architects LLC
•
Contractor – Bayou Sheet Metal and Roofing Inc
•
Demolition Phase
Entergy to de-energize and remove transformer
The contractor has demobilized from the site while waiting for Entergy to complete their scope of work
Demolition is 90% complete
•
Contractual Substantial Completion – March 2013
•
Forecasted Substantial Completion – March 2013
34
Status Date: 31 December 2012
JoEllen Smith Demolition
(OPSB)
[4400 General Meyer Avenue, New Orleans, LA 70131]
Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes. •
Funding Source – FEMA
•
Architect – VergesRome Architects, APAC
•
Contractor – TBD
•
Design Phase - CD
•
100% Construction Documents are anticipated January 23rd
A & E is working to resolve existing servitude issues
Procurement Phase
Anticipated 1st Advertisement – February 2013
Anticipated Bid Date – March 2013
L. B. Landry Annex Demolition
(RSD)
[1100 Wagner Street, New Orleans, LA 70114]
Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes. •
Funding Source – FEMA
•
Architect – Perez Architects
•
Contractor – Durr Heavy Construction LLC
•
Demolition Phase
Notice to Proceed - December 10th
Abatement is complete
Demolition to start the beginning of January
•
Contractual Substantial Completion – April 2013
•
Forecasted Substantial Completion – April 2013
35
Status Date: 31 December 2012
Mary Church Terrell Elementary School Demolition (RSD) [3411 Broadway, New Orleans, LA 70125]
Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes. •
Funding Source – FEMA
•
Architect – SCNZ Architects
•
Contractor – Gill Industries, Ltd.
•
Demolition Phase
Notice to Proceed - December 17th
Abatement to start the beginning of January
•
Contractual Substantial Completion – April 2013
•
Forecasted Substantial Completion – April 2013
Booker T. Washington High School Partial Demolition
(RSD)
[1201 S. Roman Street, New Orleans, LA 70125]
Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes. •
Funding Source – FEMA
•
Architect – Hewitt-Washington & Associates
•
Contractor – Gulfcon LLC
•
Partial Demolition
Demolition Phase •
Demolition of interior of main building is 95% complete
•
Owner is reviewing soil remediation test proposals
•
Contractual Substantial Completion – Feburary 2013
•
Forecasted Substantial Completion – February 2013
36
Status Date: 31 December 2012
Comprehensive List - Completed Projects 1.
Abrams | Morial | Abramson | Coghill Demolition
2.
A. D. Cross Elementary School Energy Conservation (RSD)
3.
A. D. Crossman Elementary School and Benjamin Banneker Elementary School (RSD)
4.
A. P. Tureaud Elementary School Roof Repairs (RSD)
5.
Agnes Bauduit Elementary School Boiler (RSD)
6.
Albert Wicker Elementary School Roof Repairs (RSD)
7.
Alfred Lawless Senior High Security Fencing (RSD)
8.
Alice M. Harte Elementary School Demolition (OPSB)
9.
Andrew Jackson Elementary School Roof Repairs (RSD)
10.
Andrew H. Wilson Elementary School Cottage (RSD)
11.
Arthur Ashe Elementary School Kitchen Renovation (OPSB)
12.
Augustine Elementary School Roof (RSD)
13.
Avery-Alexander Elementary School Demolition (RSD)
14.
Barbara C. Jordan Elementary School Demolition (RSD)
15.
Bell JH Shoring (RSD)
16.
Benjamin Banneker Elementary School Energy Conservation (RSD)
17.
Bienville Elementary School Demolition (RSD)
18.
Carter G. Woodson Middle School Demolition (RSD)
19.
Central Services Warehouse Demolition (OPSB)
20.
Charles J. Colton Elementary Selective Demolition (RSD)
21.
Charles R. Drew Elementary Roof & Installation of Kitchen Hood (RSD)
22.
Cohen High School Health Clinic
23.
Douglass High School Under Floor Utilities (RSD)
24.
Dr. Martin Luther King School Roof Repairs (RSD)
25.
Dr. Martin Luther King Jr. School Renovation (RSD)
26.
Dwight D. Eisenhower Elementary School Roof Repairs (RSD)
27.
East BankSwing Space for Audubon Charter School (OPSB)
28.
Edgar P. Harney Elementary School Roof Repairs (RSD)
29.
Edward Livingston Middle School Demolition(RSD)
30.
Edward Henry Phillips Junior High School Demolition (OPSB)
31.
New Edward Hynes School (OPSB)
32.
Edwards | Hardin | Lockett | Lawless Demolition (RSD)
37
(RSD)
(RSD)
Status Date: 31 December 2012
33.
Eleanor L. McMain School Replacement of Existing Chillers (OPSB)
34.
Ernest N. Morial Elementary Security Fencing (RSD)
35.
Fannie C. Williams Elementary School Demolition (RSD)
36.
Fisk-Howard Elementary School Demolition (RSD)
37.
Florence J. Chester Elementary School Demolition (RSD)
38.
Francis W. Gregory Demolition (RSD)
39.
Frederick A. Douglass High Switchgear (RSD)
40.
Frederick A. Douglass High Emergency Boiler Roof Repairs (RSD)
41.
George Mondy Elementary School Mothball (RSD)
42.
George Washington Carver High School Demolition (RSD)
43.
Henry Allen Elementary School Roof (RSD)
44.
Henry C. Schaumburg – Window/Door, Air Condition, Water Fountain/Sink Installation (RSD)
45.
Holy Cross Modular Relocation (RSD)
46.
Israel M. Augustine Middle School Roof Replacement (RSD)
47.
James Derham Demolition (RSD)
48.
James W. Johnson Elementary School Roof (RSD)
49.
New Jean Batiste de Bienville School (RSD)
50.
Jean Gordon Elementary School Demolition (RSD)
51.
John Dibert Elementary School Roof (RSD)
52.
John W. Hoffman Elementary School Demolition (RSD)
53.
John F. Kennedy Modular Relocation (Schwarz Campus) (RSD)
54.
John F. Kennedy Modular Relocation (Coghill Modular Campus) (RSD)
55.
John F. Kennedy High School Demolition (RSD)
56.
John McDonogh Senior High School Roof (RSD)
57.
John A. Shaw Elementary School Mothball (RSD)
58.
Joseph S. Clark Senior High School Roof Repairs (RSD)
59.
Joseph A. Craig Elementary Canopies (RSD)
60.
Joseph A. Craig Elementary Elevator Installation (RSD)
61.
Joseph A. Hardin Elementary Security Fencing (RSD)
62.
Lafayette Elementary School Roof and Masonry(RSD)
63.
Lake Area | Landry Demolition (RSD)
64.
Langston Hughes Elementary School (Phase I) (RSD)
65.
Langston Hughes Elementary School – New Gymnasium (Phase II) (RSD)
38
Status Date: 31 December 2012
66.
Langston Hughes Elementary School – Dumpster Pad (RSD)
67.
Lawrence D. Crocker Elementary School Demolition (RSD)
68.
Little Woods Elementary School Demolition (RSD)
69.
Live Oak Elementary School Roof (RSD)
70.
Live Oak Elementary School Exterior Door Replacement (RSD)
71.
Lorraine Hansberry Elementary School Mothball (RSD)
72.
Mahalia Jackson Elementary School (OPSB)
73.
Mahalia Jackson Elementary School Dumpster / Other Improvements(OPSB)
74.
Martin Behrman Elementary School Roof (RSD)
75.
Martin Luther King Jr. Elementary Canopy System (RSD)
76.
Martin Luther King Jr. School Modular Building, Deck, Canopy (RSD)
77.
Mary M. Bethune Elementary 1st Floor Replacement (OPSB)
78.
Mary M. Bethune Elementary Rear Yard Repair/Resurfacing (OPSB)
79.
McDonogh #15 Elementary Exterior Masonry to SOI Standards (RSD)
80.
McDonogh #28 Elementary School Roof
81.
McDonogh #32 Roof Replacement (RSD)
82.
McDonogh #35 ADA Upgrades to Public Restrooms, Exterior Ramp & Handicap Seating in the Auditorium (OPSB)
83.
McDonogh #42 Elementary School Roof (RSD)
84.
McDonogh #42 Elementary School HVAC Replacement (RSD)
85.
Mildred C. Osborne Elementary School Demolition
86.
Modular Campuses Close Outs (RSD)
87.
Modular Structures at Langston Hughes Elementary School (RSD)
88.
Morris F.X. Jeff Elementary School Demolition (RSD)
89.
Murray G. Henderson Elementary School Roof (RSD)
90.
New Andrew H. Wilson Elementary School (RSD)
91.
New Carter G. Woodson School (RSD)
92.
New Fannie C. Williams School (RSD)
93.
New Joseph A. Craig Elementary School (RSD)
94.
New L.B. Landry High School (RSD)
95.
New Lake Area High School (RSD)
96.
New Lawrence D. Crocker School (RSD)
97.
New Parkview School (RSD)
98.
New Equipment & Upgrades at 8 Central & 25 Satellite Kitchens (RSD)
39
(RSD)
(RSD)
Status Date: 31 December 2012
99.
New Orleans High School Signature Center Study (RSD)
100. Oretha C. Haley Demo (RSD) 101. Oretha C. Haley Elementary School Mothball 102. Parkview Elementary School Demolition
(RSD)
(RSD)
103. Paul L. Dunbar Elementary School Demolition (RSD) 104. Paul B. Habans Elementary School Roof Repairs (RSD) 105. Phillis Wheatley Elementary School Demolition (RSD) 106. Robert M. Lusher Elementary Roof Removal & Replacement (OPSB)
107. Sarah T. Reed High School Bleachers (RSD) 108. Sarah T. Reed High School Auditorium Wall (RSD) 109. Seabrook Computer Training Center Demolition (OPSB) 110. Schaumburg Chillers (RSD) 111. Schwarz Alternative Repairs
(RSD)
112. Schwarz Alternative Modulars Demolition (RSD) 113. Sherwood Forest Elementary School Demolition (RSD) 114. Sophie B. Wright Various Repairs/Restroom Renovations (OPSB) 115. Stuart R. Bradley Elementary School Demolition
(RSD)
116. Sylvanie Williams Elementary School Play Yard (RSD) 117. Sylvanie Williams Elementary School Roof Repairs (RSD) 118. Sylvanie Williams Elementary School HVAC/Chiller Replacement (RSD)
119. Temporary Campus for McDonogh #11 Expropriation (OPSB) 120. Thomas A. Edison Elementary School Demolition (RSD) 121. Thomy Lafon Elementary School Demolition (RSD) 122. Timbers Park Office Building #1 & #2 Demolition (OPSB) 123. Village de L’est Elementary School Subsidence (RSD) 124. Vorice J. Waters Elementary School Demolition (RSD) 125. West Bank Swing Space for Alice Harte Elementary School (OPSB) 126. New William J. Guste Elementary School (RSD) 127. William J. Guste Elementary School Science Lab (RSD) 128. William Frantz Elementary School Environmental Remediation & Selective Demolition (RSD) 129. William Frantz Elementary School Roof (RSD)
40
Status Date: 31 December 2012
41
Status Date: 31 December 2012