September 2013 Program Update OPSB & RSD Phase 2 Projects Program Financial Status The OPSB has $7 million in open contracts for the Phase 2 capital program projects after issuing $0 thousand in new contracts and $0 thousand in change orders and amendments in September. In addition, the total change orders to date, $448 thousand, account for eighteen percent (18%) of the total open Phase 2 construction contracts. OPSB anticipates issuing no new contracts in Phase 2 construction and $22 thousand in professional services in October. Value of Projects by Phase

The RSD has $159 million in open contracts for the Phase 2 capital program projects after issuing $41 million in new contracts and -$2.0 million in change orders and amendments in September. Additionally, the total change orders to date, -$2.0 million, account for approximately less than one percent (-1.49%) of the total open Phase 2 construction contracts. The RSD anticipates issuing $36 million in Phase 2 construction contracts and $5.2 million in professional services contracts/amendments in October. Value of Projects by Phase 48%

Design

$

59,535,903

Procurement

$

Construction

$

-

Complete

$

-

Future Projects

$

34,688,238

41,876,650

Design

$

103,210,111

Procurement

$

147,529,213

Construction

$

94,010,709

Complete

$

44%

31%

0% 0%

16%

0%

Future Projects

25%

$

319,315,456

22% 14%

Note-The value in each phase represents the total of full project budgets.

Program Schedule Status OPSB Phase 2 Projects

RSD Phase 2 Projects

New Schools

Full Renovations

Project Lake Forest PK-8 @ GSt Stephens New Karr HS @ JoEllen Smith Site Bio District HS

Design

Procurement

Construction

Complete

Design

Procurement

Construction

Complete

Design

Procurement

Construction

Complete

Full Renovations Project Franklin ES Refurbished/Renovations Project Warren Easton Fortier (Lusher) HS Ben Franklin HS Lusher ES Bethune ES Nelson ES

Project Drew ES Priestley JH / Johnson ES McDonogh 42 ES Sophie B Wright ES John McDonogh HS Clark HS Tubman ES Live Oak ES Lafayette ES

Design

Procurement

Construction

Complete

Design

Procurement

Construction

Complete

Refurbished/Renovations

RSD Phase 2 Projects New Schools Project Dunbar ES Morial New Algiers PreK-8 Alfred Lawless Fisk-Howard Alexander ES Abrams HS New Orleans East (Abramson) Bradley Sherwood Forest ES Behrman ES Habans ES Edward Livingston Gaudet ES Fischer

Design

Procurement

Construction

Status Date: 30 September 2013

Complete

Project Allen ES Jackson ES Crossman ES Eisenhower HS Gentilly Terrace ES Rosenwald ES O Perry Walker HS Martin L King ES Reed HS Green MS Sylvanie Williams Bauduit ES Laurel ES McDonogh 28 ES McDonogh 7 ES Schwarz HS Village de L'Est ES Wicker ES Marshall ES Schaumburg ES Harney ES McDonogh 32 ES Douglass HS


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
rsd-opsb-monthly-phase-2-summary-2013-09 by Peggy Abadie - Issuu