ORLEANS PARISH SCHOOL BOARD PROPERTY COMMITTEE Orleans Parish School Board 3520 General DeGaulle Drive, Suite 4050 New Orleans, LA 70114 December 13, 2012 2:00 PM (Notice: This meeting may be convened up to 30 minutes prior to the posted schedule to facilitate the orderly conduct of business)

Committee Members: Mr. Woody Koppel, Chair Mr. Thomas Robichaux, Ex-Officio

Mr. Ira Thomas Mrs. Lourdes Moran

AGENDA Call to Order

Mr. Woody Koppel

Adoption of the Agenda Additions/Deletions/Modifications ACTION ITEM(S) 1. Edward Lusher Charter School Memorandum of Understanding

Kathleen Padian

2. Amendment for the Lake Forest School Project

Herman Taitt

DISCUSSION/INFORMATION ITEM(S) 3. Charter School Code Compliance and Maintenance Summit

Herman Taitt

REPORTS / PRESENTATION(S) 4. Real Estate Consulting Service

Stan Smith

5. Update on Construction Contracts for:  New Gym at Eleanor McMain High School  New PK-8 School at North Kenilworth  New McDonogh 35 High School

Herman Taitt

6. Capital Projects Summary Report

Herman Taitt

Adjournment

In accordance with the Americans with Disabilities Act, if you need special assistance at a public meeting of the Orleans Parish School Board, please contact the Board Office at 504‐304‐5678, or by email at BoardOffice@nops.k12.la.us , describing the assistance that is necessary.


MEMORANDUM OF UNDERSTANDING REGARDING ASSIGNMENT OF ALLEN BUILDING TO LUSHER CHARTER SCHOOL This Memorandum of Understanding (“MOU”) sets forth the understanding and agreement between Advocates for Arts-Based Education Corporation, d/b/a Lusher Charter School (“Lusher”) and Orleans Parish School Board (“OPSB”) for the assignment of the Allen Building to Lusher after it is transferred to OPSB and vacated by the New Orleans Science and Math Charter High School. The Board of New Orleans Science and Math Charter High School is pursuing a new location and has indicated that the school does not plan to stay at the Allen site. In early 2009, then RSD superintendent, Paul Vallas, met with Lusher representatives and stated RSD’s intention to lease the Allen Building to Lusher when the building became available. At that time, RSD controlled the Allen Building. Lusher understands that RSD intends to transfer the Allen Building back to OPSB in the near future. In reliance on Mr. Vallas’ representations in 2009, the Lusher Board began making plans for expansion of its enrollment. In the spring of 2010, Lusher received approval from OPSB to add two kindergarten classes to be temporarily housed at the Jewish Community Center (the “JCC”) as an additional site. The program at the JCC has grown to four classes -- two first grade and two second grade. This site was always deemed temporary because it can serve only four classes of students. Two new kindergarten classes were not added this year because of the lack of acceptable space. Lusher plans to grow the program into an elementary program that feeds into the middle and high school program on Freret Street and complies with Lusher's current student enrollment limit. Assignment of the Allen Building to Lusher is logical and in the interest of students, faculty and staff in that the Allen Building is located directly behind and adjacent to the Lusher Freret Street campus, enabling Lusher to include the Allen Building within a contiguous campus.

2-

Lusher MOU For Allen


The new elementary program will respond to increasing public demand to create more seats in high-performing New Orleans public schools. Lusher currently has long waiting lists at each grade level and is eager to respond to this demand. Lusher’s Board is aware that temporary sites will have to be used until the Allen Building is available. To enable Lusher to permanently house the students temporarily located at the JCC and to move forward with its plans to meet public demand for increased enrollment, Lusher is requesting that OPSB sign this MOU confirming its intention and agreement to assign the Allen Building to Lusher once the building is transferred to OPSB and vacated by the New Orleans Science and Math Charter High School. Lusher’s current Facilities Lease will be amended to reflect that all of the terms, conditions, and provisions of said Facilities Lease will be applicable to the Allen Building. Lusher understands that RSD must transfer the Allen Building to OPSB, and New Orleans Science and Math Charter High School must vacate the Allen Building, before the building can be assigned to Lusher. However, OPSB’s execution of this MOU with Lusher at the present time will better enable Lusher’s Board and staff to move forward with expansion plans and initiatives, including fundraising to support moving costs and future repairs and OPSBapproved improvements to the Allen Building, and related initiatives. OPSB represents that the assignment of the Allen Building to Lusher is in compliance with the dictates of OPSB Policy No. F606. Lusher greatly appreciates OPSB’s execution of this MOU, which will enable Lusher to continue to fulfill its mission of providing an arts-based program of educational excellence to the students and families of Orleans Parish.

-22-

Lusher MOU For Allen


ORLEANS PARISH SCHOOL BOARD BY:__________________________________ Thomas A. Robichaux, President

ADVOCATES FOR ARTS-BASED EDUCATION CORPORATION, d/b/a LUSHER CHARTER SCHOOL BY:_______________________________ Blaine G. LeCesne, President

-32-

Lusher MOU For Allen


December 18, 2012 APPROVAL TO INCREASE BUDGET TO ACCOMMODATE LANDFILL AND ADDITIONAL PARKING Requestor: Herman K. Taitt, Jr. BACKGROUND: At our third community meeting for the Lake Forest Elementary Project, held on September 24, 2012, both the Board Member for that District, and the community solicited the OPSB Administration to accommodate the Lake Forest Administration to provide clearing and fill, on the remaining 9 acres of undeveloped land at the Greater St. Stephen’s Site. Also the concession was made to add an additional 35 parking spaces above and beyond the standard set by the current building code for a new school. The current funding available for construction is for this project is $22,567,408.00. By the additional cost of clearing and fill, with additional parking, this increases the current budget for this project to $23,597,871.00

Survey Work

$ 11,501.00

Geo-tech Work

$ 14,187.00

Latest Estimate to Clear & Fill

$ 518,000.00

Additional Parking Total

Code 116 + 84 = 200 spaces

$420,000.00 $ 963,688.00

Additional A/E associated with increased cost of scope $66,775.00 Total $1,030,463 RECOMMENDATION: That the Orleans Parish School Board approves the additional construction cost of $1,030,463.00 increase in FEMA funding for the Lake Forest Elementary School located at the Greater St. Stephens Site, bringing the total AFC to $23,597,871.00.


December 18, 2012 Charter School Code Compliance and Maintenance Summit Requestor: Herman K. Taitt, Jr. BACKGROUND: On November 14, 2012, the East‐bank Collaborative of Charter Schools and the Louisiana Association of Public Charter Schools, with the assistance of the OPSB Administration, hosted a Charter School Code Compliance and Maintenance Summit to provide an overview to charter operators on critical facility issues and responsibilities. Presentations and group discussions centered on the work that we do and the codes and requirements that keep our children healthy, safe and secure and protect our school physical assets. The half‐day Summit was attended by about 40 charter principals, CFO/business managers, facility managers, and others. All of the OPSB charters were represented as well as representatives from New Beginnings, KIPP, Dr. Martin Luther King, Sophie B. Wright, and other RSD schools. Presentations were made by Dr. Ken Ducote, Frank Goelz, Paul Lucius, Tracy Griffin‐Robertson, Allison Lewis (Gallagher), and Dr. Paul Lo (MMG). Topics included the following:

Compliance Culture Compliance Documentation Required Inspections Life Safety Codes & Fire Drills Underground Storage Tanks Mold & Indoor Air Quality Lead (Paint, Soil, Water) Sanitation Codes Pest Control Playground Safety Landscaping Good Neighborhood Relations Loss Prevention Contracting for Emergency Repairs OPSB Preventative Maintenance Checklist

Emergency Preparation Asbestos PCBs (Caulk, Electrical) Waste & Dumpsters Site Maintenance City Codes & Zoning Public Works Laws Nuisance Businesses

RECOMMENDATION: As information only

Herman K. Taitt. Jr.


December 5, 2012 REAL ESTATE CONSULTING SERVICES Requestor: Stan Smith, Chief Financial Officer On December 14, 2010 the Orleans Parish School Board approved the awarding of the real estate consulting services contract to Latter & Blum, Limited. In accordance with article 3.1 of the contract, the initial contract period was for one (1) year with an option to extend the contract for two (2) additional years. The first option year of the contract will end on December 13, 2012. Latter & Blum has performed satisfactorily during the initial year (see attached vendor evaluation form).

RECOMMENDATION:

That the Orleans Parish School Board accepts the Administration’s recommendation to renew the Latter & Blum, Limited contract for real estate consulting services for the second option year and authorize the OPSB General Counsel to prepare a contract amendment not to exceed $185,000.00, which amount includes reasonable costs and expenses related to marketing and sale of surplus properties.


OPSB Consulting Services Valuation Model Latter Blum 11.10.11 SALES

Building La Sa lle Myrtle Banks Free School Free School Lodge

Address 6048 Perrier Street 1307 Oretha Castle Haley 3601 Camp Street 3619 Camp Street

Price

3% Comm ission

$ 2,450,000.00 $ $ 660,000.00 $ $ 1,200,000.00 $ $

157,500.00

$

1/5 Interest

4822 Chestnut

Fink Center

1300 Richland Road

$ 530,000.00 $ $ 920,000 .00 $ $ 1,190,000.00 $ $ 612,000.00 $ 21,600.00 $ $ 202,500.00 $ $

Lawton

Flanders & Newton

$

Wiltz Gym

3041 N. Rampart

$ $ 8,220,100.00 $ $

McDonogh 16 Morris F.X. Jeff Moss-Bauer

1815 St. Claude Ave . 800 N. Rendon Street

Pierre Capdau

703 Carondelet & 820 Girod 3821 Franklin Avenue

Total

46,500.00 230,000.00

$

4% Commission

$ $ $ 4,725 .00 $

73,500.00

19,800.00 36,000.00 15,900.00 27,600.00

$

$ 35,700.00 $ 18,360.00 648.00 6,075 .00 1,395.00 6,900.00 246,603.00

$

$ $ $ $ 21,200.00 $ 98,000.00

26,400.00 48,000.00 6,300.00

$ $

App lication of full corporate resources to maximize value and opportunity for the Boa rd

71,400.00 Closed 36,720.00 Pending

1,860.00 9,200.00 328,804.00

Evaluation of thirty original sites and up to fifty additional sites for the ThoreenHale appraisal process Ongoing work with several finance firms to leverage renovation values

9,450 .00 Closed 31,800.00 Closed

$ $ 864.00 $

8,100.00

OTHER SERVICES

147,000.00 Closed 39,600.00 Closed 72,000.00 Pend ing

55,200.00 Pending

47,600.00 24,480.00

Coordination of the CRE Eva luation Process for all Surplus Properties Creation of the RFP Process for Appraisal Firm Selection

Date of Auction

$

36,800.00

$ $ $

6% Comm ission

1,296.00 Closed

$ $

12,150.00 Closed

$ $

13,800.00 Closed 493,206.00

2,790.00 Closed

$ 240,000.00 $ 9,600.00


December 12, 2012 NEW GYM ADDITION AT ELEANOR MCMAIN SECONDARY HIGH SCHOOL Requestor: Herman K. Taitt, Jr., Executive Director of Operations Advertisement Dates: The Times Picayune Wednesday, October 3, 2012 Wednesday, October 10, 2012 Wednesday, October 17, 2012 OPSB Website - continuously October 3 through November 7, 2012 Publicly Opened: November 7, 2012 Vendors Receiving Bid Package: 10

Vendors Responding: 5

Principals of the Company: ELLIS CONSTRUCTION, INC. (NEW ORLEANS, LA) President: Bret Ellis Background Information: On October 3, 2012 the OPSB Purchasing Department released Invitation to Bid (ITB) no. 2010-0787-0001 for the New Gym Addition at Eleanor McMain Secondary High School. The ITB was advertised in the Times-Picayune and posted to the OPSB website. A pre-bid conference was held on October 17, 2012 and there were six (6) general contractors represented. On November 7, 2012 at 2:00 P.M. a public bid opening was conducted at the OPSB offices by the Purchasing Department. The bid results were as follows:

Contractor 1 2 3 4 5

Ellis Construction Woodrow Wilson FHP Tectonics FH Myers Ryan Gootee

Total Base + Alternates 9,497,800.00 9,810,000.00 10,127,000.00 10,230,000.00 10,466,000.00

RECOMMENDATION:

Base

1

9,356,000.00 9,648,000.00 9,970,000.00 10,070,000.00 10,275,000.00

14,800.00 13,000.00 13,000.00 15,000.00 8,000.00

Alternates 2 40,500.00 57,000.00 52,000.00 55,000.00 78,000.00

3 86,500.00 92,000.00 92,000.00 90,000.00 105,000.00

That the Orleans Parish School Board accepts the lowest responsive bid from Ellis Construction, Incorporated in the amount of $9,497,800.00 and authorize the OPSB General Counsel to prepare a contract. In addition, OPSB Administration requests that the OPSB approve a 10% contingency for any unforeseen conditions. Additional work will not be performed until approved by the OPSB Executive Director of Operations by way of a field change order.


December 12, 2012 NEW PK-8 SCHOOL AT NORTH KENILWORTH PARK Requestor: Herman K. Taitt, Jr., Executive Director of Operations Advertisement Dates: The Times Picayune Tuesday, September 25, 2012 Wednesday, October 3, 2012 Wednesday, October 10, 2012 OPSB Website - continuously September 25 through November 8, 2012 Publicly Opened: November 8, 2012 Vendors Receiving Bid Package: 9

Vendors Responding: 5

Principals of the Company: WOODROW WILSON CONSTRUCTION CO, INC. (BATON ROUGE, LA) President: Mark A. Wilson Background Information: On September 25, 2012 the OPSB Purchasing Department released Invitation to Bid (ITB) no. 2011-0850-0001 for the New PK-8 School at North Kenilworth Park. The ITB was advertised in the Times-Picayune and posted to the OPSB website. A pre-bid conference was held on October 10, 2012 and there were four (4) general contractors represented. On November 8, 2012 at 2:00 P.M. a public bid opening was conducted at the OPSB offices by the Purchasing Department. The bid results were as follows:

Contractor Woodrow Wilson Citadel Builders Gibbs Construction FHP Tectonics Satterfield & Pontikes

RECOMMENDATION:

Total Base + Alternate 22,476,000.00 22,569,700.00 22,964,000.00 23,000,000.00 24,575,000.00

Base 22,435,000.00 22,528,000.00 22,925,000.00 22,950,000.00 24,499,000.00

Alternate 41,000.00 41,700.00 39,000.00 50,000.00 76,000.00

That the Orleans Parish School Board accepts the lowest responsive bid from Woodrow Wilson Construction Company, Incorporated in the amount of $22,476,000.00 and authorize the OPSB General Counsel to prepare a contract. In addition, OPSB Administration requests that the OPSB approve a 10% contingency for any unforeseen conditions. Additional work will not be performed until approved by the OPSB Executive Director of Operations by way of a field change order.


December 12, 2012 NEW MCDONOGH #35 HIGH SCHOOL AT THE PHILLIPS-WATERS SITE Requestor: Herman K. Taitt, Jr., Executive Director of Operations Advertisement Dates: The Times Picayune Wednesday, October 10, 2012 Wednesday, October 17, 2012 Wednesday, October 24, 2012 OPSB Website - continuously October 10 through November 15, 2012 Publicly Opened: November 15, 2012 Vendors Receiving Bid Package: 7

Vendors Responding: 3

Principals of the Company: CITADEL BUILDERS, LLC (METAIRIE, LA) President/Managing Member: Denzel L. Clark, Jr. Background Information: On October 10, 2012 the OPSB Purchasing Department released Invitation to Bid (ITB) no. 2010-0783-0001 for the New McDonogh #35 High School at the Phillips-Waters Site. The ITB was advertised in the Times-Picayune and posted to the OPSB website. A pre-bid conference was held on September 4, 2012 and there were five (5) contractors represented. On November 15, 2012 at 2:00 P.M. a public bid opening was conducted at the OPSB offices by the Purchasing Department. The bid results were as follows: Contractor Citadel Builders, LLC Gibbs Construction FHP Tectonics

RECOMMENDATION:

Bid 54,984,000.00 58,897,000.00 61,150,000.00

That the Orleans Parish School Board accepts the lowest responsive bid from Citadel Builders, LLC in the amount of $54,984,000.00 and authorize the OPSB General Counsel to prepare a contract. In addition, OPSB Administration requests that the OPSB approve a 10% contingency for any unforeseen conditions. Additional work will not be performed until approved by the OPSB Executive Director of Operations by way of a field change order.


Current Phase - Project is being delayed due to non-resolution of issues.

OPSB Capital Projects Schedule Report

R Y G

Date Updated :

Current Phase - Project has major issues that are in process of being resolved. Current Phase - Project currently has no major issues

12/18/2012 Low Bid

Facility

Name

Description of Work

CM/PM ARCHITECT COMPLETE

or Budget

Capital Projects McDonogh 35 Rebuild Lake Forest Charter School Alice Harte Rebuild K-8 at North Kenilworth Karr High School McMain High School Gym

NEXT STEP

(current) New School

Brown, CSRS Siezler, and Thompson

New School

CSRS

Imre Hededus

FALL 2014

New School

CSRS

WDG/Wink

SPRING 2014

New School

CSRS

MathisBrierre

AUGUST 2014

CSRS

TBD

FEBRUARY 2014

CSRS

Jahncke & Burnes

OCTOBER 2013

New School Renovation

AUGUST 2014 54,984,000.00

Awaiting award

$22,567,408.00

IN DESIGN

$

26,607,000.00

9%

$

22,476,000.00

Awaiting award

$

30,512,616.00

IN DESIGN

$

9,497,800.00

$

Awaiting award 10%

Audubon Elementary Warren Easton

Renovation Window Replacement

Ben Franklin High School repairs

CSRS

Blitch Knevel SPRING 2014

CSRS

Verges-Rome

JUNE 2012

PEREZ APC

FEBRUARY 2013

Chenevert Architects

MARCH 2013

Verges-Rome

CSRS

Project Ongoing

$

11,517,743.00

$

2,300,000.00

$

1,078,511.00

$

280,000.00

70%

FALL 2013

$

309,062.74

IN DESIGN

Hamps

$

4,478,381.00

Chenevert Architects

FEBRUARY 2013

$

273,000.00

contractor in default 68%

Project Ongoing

Demolition Projects K-8 at the Greater St. Stephens Site Jo Allen Smith Demo

Demolition Demolition

McDonogh 35 Rebuild

Remediation

CSRS

Brown, CSRS Siezler, and Thompson

80%

Emergency Repairs Emergency Repairs

CSRS

Bethune Elementary

Stabilization Repairs

CSRS

Chenevert Architects

TBD

$4,094,149.00

HOLD

McDonogh 35

Stabilization Repairs

CSRS

Chenevert Architects

TBD

$323,000.00

HOLD

Warren Easton

Stabilization Repairs

CSRS

Chenevert Architects

TBD

$2,830,114.00

X

Karr High School Gym

5%

Project Ongoing

New Projects


Lusher Elementary Lusher High School Audubon Extention repairs Mahalia Jackson Mednard Nelson Timbers Chiller replacement

Stabilization Repairs

CSRS

Stabilization Repairs Stabilization Repairs additional classrooms Stabilization Repairs Replacement

AHU repair at Mc35

Manning Achitects

TBD

CSRS

SCNZ

TBD

$13,888,241.53

CSRS

Chenevert Architects

TBD

$2,290,000.00

CSRS Verges-Rome

$

X

2,421,837.06

X X 10%

FEBRUARY 2013

$

274,000.00

CSRS

TBD

TBD

$

2,773,713.00

GCA

Moses Engineers

TBD

$

995,000.00

CSRS

GCA

TBD

$

5,000.00

Timber 4th floor DEMO

Renovation

TBD

In-House

TBD

$

20,000.00

Timbers 5th floor reno

Renovation

TBD

Truewall

TBD

$

34,100.00

Timbers 1st floor reno

repairs

TBD

In-House

TBD

$

24,000.00

4460 chiller repair

repairs

GCA

GCA

TBD

$

21,000.00

McDonogh 07

repairs

GCA

GCA

FEBRUARY 2013

$

1,000,000.00

100% CDs

0%

* construction costs do not include A/E and PM fees

Project Ongoing

COMPLETED 0%

$217,875,676.33

Project Ongoing

Project Ongoing


ORLEANS PARISH SCHOOL BOARD CAPITAL PROJECTS UPDATE

December 13, 2012


Alice Harte New PK-8th Grade

Design

Architect:

Construction WDG Architects Engineers

Notice to Proceed:

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

September 16, 2010 April 15, 2011 June 16, 2011 May 25, 2012 June 4, 2012 June 7, 2012 July 12, 2012

Contractor:

Woodrow Wilson

Notice to Proceed:

September 12, 2012

Pile driving nearing completion Concrete pile caps are underway

Substantial Completion January - 2014

School Occupancy June - 2014


Audubon School Renovation & Addition

Design

Architect: Blitch/Knevel Notice to Proceed:

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

September 16, 2010

January 14, 2011 June 2, 2011 September 28, 2011 January 9, 2012 January 12, 2012 March 1, 2012

Building permit received on 10/22

Construction Contractor:

FHP Tectonics Corp.

Notice to Proceed:

May 23, 2012

Pile driving is near completion Underslab plumbing is existing building complete

Substantial Completion February - 2014

School Occupancy May - 2014


Ben Franklin HS Stabilization

Design

Architect: Perez, APC Notice to Proceed:

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

March 10, 2011 N/A July 18, 2011 December 28, 2011 February 17, 2012 February 28, 2012 March 27, 2012

Construction Contractor:

Pete Vicari

Notice to Proceed:

June 20, 2012

Reconstruction of the curtain walls are underway

Substantial Completion January - 2013

School Occupancy March - 2013


Easton HS Window replacement

Design

Architect: Verges/Rome Notice to Proceed:

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

N/A

N/A N/A N/A N/A N/A N/A

Construction Contractor:

BEI

Notice to Proceed:

September 8, 2009

Actual Substantial Completion September 6th Punch Work Remaining OPSB issued default letter to Contractor & Surety /

Substantial Completion September - 2012

School Occupancy N/A


Easton HS Refurbishment

Design

Architect: Chenevert Architects Notice to Proceed:

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

June 18, 2012

N/A N/A December 11, 2012 December 18, 2012 January 22, 2013 February 26, 2013

Adding additional scope; interior stairs & subsurface drainage. When final scope is accepted & approved by OPSB, a new design schedule will be issued.

Construction Contractor:

TBD

Notice to Proceed:

TBD

Substantial Completion August - 2013

School Occupancy N/A


Greater St. Stephens Demolition of Greater St. Stephen’s School

Design

Architect: Chenevert Architects Notice to Proceed:

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

May 21, 2012

N/A N/A July 13, 2012 July 20, 2012 August 9, 2012 September 13, 2012

Construction

Contractor: Bayou Sheet Metal Notice to Proceed:

November 7, 2012

Demolition of all buildings is nearing completion

Substantial Completion March - 2013

School Occupancy N/A


Lake Forest School New PK-8th Grade – Three Section School

Design

Architect: Hegedus & Associates Notice to Proceed:

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date: Test pile bid opened 11/28 Design ongoing

June 14, 2012

August 24, 2012 November 6, 2012 February 18, 2013 March 4, 2013 March 13, 2013 April 23, 2013

Construction Contractor:

TBD

Notice to Proceed:

TBD

Substantial Completion September - 2014

School Occupancy January - 2015


Jo Ellen Hospital Demolition of the hospital buildings & facilities

Design

Architect: Verges/Rome Architects Notice to Proceed:

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

September 12, 2012 TBD TBD December 10, 2012 December 20, 2012 January 15, 2013 February 28, 2013

Construction Contractor:

TBD

Notice to Proceed:

TBD

Substantial Completion September - 2013

School Occupancy TBD


New Edna Karr HS New High School at the Jo Ellen Site

Design

Architect: Lee Ledbetter & Assoc. Notice to Proceed:

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

May 14, 2012

August 17, 2012 November 2, 2012 March 2, 2013 March 16, 2013 April 1, 2013 May 12, 2013

Schematic Design submittal is under review by OPSB

Construction Contractor:

TBD

Notice to Proceed:

TBD

Substantial Completion February - 2015

School Occupancy June - 2015


Edna Karr HS Stabilization – Gym

Design

Architect: Chenevert Architects Notice to Proceed:

April 20, 2012

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

N/A N/A May 20, 2012 May 31, 2012 June 19, 2012 July 24, 2012

Construction Contractor:

Cresent Commercial Const

Notice to Proceed:

October 8, 2012

Pile driving is underway

Substantial Completion February - 2013

School Occupancy March - 2013


Lusher Elementary Refurbishment

Design

Architect: Meyer Engineers Notice to Proceed:

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

October 1, 2012 November 14, 2012 December 26, 2012 March 4, 2013 March 20, 2013 April 12, 2013 May 21, 2013

OPSB is reviewing additional scope & costs

Construction Contractor:

TBD

Notice to Proceed:

TBD

Substantial Completion TBD

School Occupancy TBD


Lusher/Fortier HS Refurbishment

Design

Architect: SCNZ Architects Notice to Proceed:

September 26, 2012

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

November 14, 2012 December 31, 2012 February 26, 2013 March 15, 2013 April 8, 2013 May 7, 2013

OPSB is reviewing additional scope & costs

Construction Contractor:

TBD

Notice to Proceed:

TBD

Substantial Completion TBD

School Occupancy TBD


Mahalia Jackson Renovation – Additional Classrooms

Design

Architect: Verges/Rome Architects Notice to Proceed:

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

April 17, 2012

N/A May 13, 2012 June 12, 2012 June 27, 2012 July 17, 2012 August 21, 2012

Construction Contractor:

ETI

Notice to Proceed:

November 5, 2012

Demolition is underway

Substantial Completion January - 2013

School Occupancy January - 2013


New McDonogh 35 HS New High School

Design

Architect: Sizler/Thompson/Brown Notice to Proceed:

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

June 3, 2010

April 8, 2011 June 30, 2011 June 8, 2012 October 9, 2012 October 11, 2012 November 15, 2012

Bids are under review by DBE Director & Committee

Construction Contractor:

TBD

Notice to Proceed:

TBD

Substantial Completion August - 2014

School Occupancy January - 2015


New McDonogh 35 HS Remediation Phillips/Waters Site

Design

Architect: Sizler/Thompson/Brown Notice to Proceed:

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

June 3, 2010

N/A N/A March 3, 2011 March 10, 2011 March 17, 2011 April 26, 2011

Construction Contractor:

Hamps

Notice to Proceed:

March 8, 2012

Surety has been noticed of OPSB's consideration of default Contractor has filed a lawsuit against OPSB for

Substantial Completion December - 2012

School Occupancy N/A


McDonogh 35 Stabilization - Kerlerec

Design

Architect: Chenevert Architects Notice to Proceed:

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

April 20, 2012

N/A N/A July 23, 2012 August 2, 2012 August 16, 2012 September 20, 2012

Recommendation of award delivered to OPSB 10/11 OPSB is reviewing award of project

Construction Contractor:

TBD

Notice to Proceed:

TBD

Substantial Completion April - 2013

School Occupancy June - 2013


McMain HS New Gymnasium

Design

Architect:

Jahncke & Burns Arch.

Notice to Proceed:

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

September 16, 2010 April 14, 2011 August 25, 2011 August 15, 2012 September 13, 2012 October 2, 2012 November 7, 2012

Made the Gym an individual project OPSB is evaluating bids opened on the 7th

Construction Contractor:

TBD

Notice to Proceed:

TBD

Substantial Completion December - 2013

School Occupancy March - 2014


McMain HS Stabilization

Design

Architect:

Jahncke & Burns Arch.

Notice to Proceed:

TBD

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

TBD TBD TBD TBD TBD TBD

Separated into an individual project Working on cost effective window options & stucco repairs

Construction Contractor:

TBD

Notice to Proceed:

TBD

Substantial Completion TBD

School Occupancy N/A


McMain HS School Based Health Clinic

Design

Architect:

Jahncke & Burns Arch.

Notice to Proceed:

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

August 31, 2011 N/A N/A May 16, 2012 May 30, 2012 May 29, 2012 June 26, 2012

Construction Contractor:

ETI

Notice to Proceed:

November 15, 2012

Pre-construction meeting held November 8th Environmental contractor has mobilized

Substantial Completion Feburary - 2013

School Occupancy April - 2013


Nelson Elementary Refurbishment

Design

Architect: Harry/Baker/Smith Notice to Proceed:

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

October 23, 2012

January 10, 2013 February 15, 2013 April 5, 2013 May 13, 2013 June 3, 2013 July 16, 2013

Professional Services Contract with OSPB 9/7 A/E kick off meeting held 10/23

Construction Contractor:

TBD

Notice to Proceed:

TBD

Substantial Completion TBD

School Occupancy TBD


PK-8 N. Kenilworth New PK-8th Grade – Three Section School

Design

Architect: Mathes Brierre Arch. Notice to Proceed:

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

April 28, 2011

December 27, 2011 April 27, 2012 July 19, 2012 August 2, 2012 September 25, 2012 October 30, 2012

Recommendation of award with OPSB

Construction Contractor:

TBD

Notice to Proceed:

TBD

Substantial Completion July - 2014

School Occupancy August - 2014


McDonogh 7 Refurbishment Swing Space

Design

Architect: N/A - OPSB Notice to Proceed:

TBD

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

TBD TBD TBD TBD TBD TBD

OPSB is developing the scope required to occupy the building

Construction Contractor:

TBD

Notice to Proceed:

TBD

Substantial Completion TBD

School Occupancy TBD


Timbers III HVAC Replacement

Design

Architect: Moses Engineers Notice to Proceed:

Schematic Design: Design Development: Construction Documents: Bid Documents: 1st Advertisement: Bid Date:

June 8, 2012 N/A N/A September 25, 2012 November 7, 2012 November 21, 2012 December 20, 2012

Construction Contractor:

TBD

Notice to Proceed:

TBD

Substantial Completion June - 2013

School Occupancy N/A