2012 3rd QUARTER REPORT Prepared for Orleans Parish School Board and Louisiana Department of Education Committed to creating a world-class public education system that is child centered and supports the rebuilding of the City of New Orleans
Charles J. Colton Renovation Exterior Work Nearly Completed
Alice Harte Elementary Construction Begun
Lawrence D. Crocker Elementary Classes Begun in August
Parkview Elementary Classes Begun in August, 2012
Booker T. Washington High School Design Phase Completed
Carter G. Woodson Elementary Substantial Completion in September, 2012
TABLE OF CONTENTS Crocker Construction Douglass HS – Reno Drew ES – Reno Dunbar ES - New Fannie C Williams – Modular Demo Fannie C. Williams Construction Fisk-Howard ES - New Frantz Renovation and Addition Gaudet/Lake Forest ES (Roof) Guste ES (New Roof and Elevator) Haley (Mothballing) Hansberry (Mothballing) Jackson K-8 Solar Panels Jeff (Mothballing) John McDonogh HS (Bleachers) Jones (Mothballing) Lafon Display Langston Hughes - Dumpster Pad Lawless HS - New LB Landry HS Annex - Demo Little Woods (New Construction) Livingston HS - New Martin L. King ES - Modul Bldg McDonogh 15 ES - Masonry Repair McDonogh 32 (Roof) McDonough 42 ES – Reno Mondy (Mothballing) NO East Abramson HS - New Osborne (New Construction) Parkview (New Construction) Roof Repair-Various Sites (HMS) Roof Repair-Various Sites (RCL) Shaw (Mothballing) Sophie B. Wright ES – Reno Sylvanie Williams AHU Terrell ES - Demo
Executive Summary Financial Overview -- 3rd Quarter Activities New & Major Renovation Other Projects Mothball or Safe & Secure of Selected Schools Demolition Projects
4 5 17 23 27
Community Outreach Reports July, 2012 August, 2012 September, 2012
31 35 41
Cost Reports Program Summary Report Program Cost Status Report
50 51
Individual Project Summaries Recovery School District Armstrong (Mothballing) Augustine (Mothballing) Augustine (Roof) BAS Integration Bell JH (Mothballing) Bell JH (Phase 1—Roof) Bell JH (Shoring) Bienville Elementary (New Construction) Booker T. Washington (New Construction) Booker T. Washington – Demo Bradley ES - New Carver HS (New Construction) Cohen (HVAC) Colton (Renovation)
60 61 62 63 64 65 66 67 68 69 70 71 72 73 TABLE OF CONTENTS
74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 Status Date: 30-September-2012
TABLE OF CONTENTS Village De L'est (Roof) Village de Lest ES Einstein - Subsidence Wheatley (New Construction) Woodson (New Construction) Orleans Parish School Board Audubon School Renovation Benjamin Franklin HS - Stabilization Easton HS - Refurb GSt Stephens - Demo Harte School (New Construction) JoEllen Smith Med Ctr - Demo Karr HS - Gym Repair Lake Forest PK-8 (GSt Stephens) - New Lusher Fortier HS – Refurb Mahalia Jackson – Off Reno McDonogh 35 (Phillips/Waters) McDonogh 35 HS - Stabilization (Elevator) McMain School – Gymnasium New Karr HS at JE Smith Site New PK-8 at North Kenilworth Park Timbers – HVAC
110 111 112 113
114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129
Appendix A-Funding Analysis Progress Reports…………………… Recovery School District Orleans Parish School Board B-School Map……………………… … … C-Understanding the Quarterly Report…………… …
130 131 174 190 192
TABLE OF CONTENTS
Status Date: 30-September-2012
EXECUTIVE SUMMARY Financial Overview The RSD has $354 million in open contracts including $2.5 million in new contracts issued in September. There are $7.1 million in program related change orders including $39,000 added in September. This equates to a rate of 2.65% of the total open construction contracts. The RSD is forecasting issuing $26 million in construction contracts and $3.4 million in professional service contracts in October. Colton Elementary Complete Renovation Ongoing
The OPSB has $95 million in open contracts including $29 million in new contracts issued in September. There are $1.08 million in program related change orders. This is 1.59% of the total open construction contracts. OPSB is forecasting issuing $1.4 million in construction contracts and $3.4 million in professional service contracts in October.
Mildred Osborne Elementary School Occupation Begun in August, 2012
EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY New & Major Renova on – Project Status Audubon School (OPSB) [428 Broadway Avenue, New Orleans, LA 70118]
Scope of work: Renovation & Addition of Existing Elementary School Audubon School Architect’s Rendering
Construction Phase ▪
Test Pile package is complete
▪
Test Pile report was received September 24th
▪
BZA and Safety / Permits are reviewing the Construction Documents
▪
Pile driving is anticipate to start upon release of the permits
▪
Wall layout in existing building is ongoing
Jean Batiste de Bienville School (RSD) [1456 Gardena Drive, New Orleans, LA 70122]
Scope of work: New Pre-K – 8 School Final Close-out Phase Jean Batiste de Bienville School Substantially Complete
▪
Project is complete – June 15
▪
The punch list is 95% complete
EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY
Stuart R. Bradley School
(RSD)
[ 2401 Humanity Street, New Orleans, LA 70122]
Scope of work: New 3-Section Elementary School Design Phase – CD
Stuart R. Bradley School Design Development Rendering
▪
50% Construction Documents are due October 23rd
▪
100% Construction Documents are due December 23th
Paul L. Dunbar School (RSD) [9330 Forshey Street, New Orleans, LA 70125]
Scope of work: New 2 - section elementary school Design Phase - CD ▪ Design Development documents were received on August 6th
Paul L. Dunbar School Schematic Design Rendering
▪
Community Meeting #4 – September 20th
▪
50% Construction Documents are due October 11th
▪
100% Construction Documents are due December 10th
George Washington Carver School (RSD) [3019 & 3059 Higgins Blvd., New Orleans, LA 70126]
Scope of work: New High School Procurement Phase
George Washington Carver School Entrance Rendering
▪
Bid Opening – July 27th
▪
Bids were not accepted
▪
Project is on hold pending Owner’s decision EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY
Charles J. Colton School (RSD) [2300 St. Claude Avenue, New Orleans, LA 70117]
Scope of work: Renovation of existing elementary school and new addition Construction Phase
Charles J. Colton School Exterior Brickwork Nearly Complete
▪
Roofing material installation is 85% complete
▪
Exterior brick work is anticipated to be complete in mid-November
▪
Gypsum board installation on interior walls is 85% complete on 2nd and 3rd floors
▪
Mechanical/Electrical/Plumbing rough-in work is 85% complete
▪
Pulling of wiring/data lines is in process
▪
Window installation is 30% complete
▪
Exterior wall panels were delivered and are being installed
▪
Patching of existing terrazzo and installation of floor tile has started
Lawrence D. Crocker School (RSD) [2300 General Taylor Street, New Orleans, LA 70115]
Scope of work: New PK-8 School Final Closeout Phase
Lawrence D. Crocker School Windows and Wall Facing in Progress
▪ ▪ ▪
Exterior wall panels are complete, install of metal soffit is ongoing Temporary Certificate of Occupancy from the City of New Orleans was received on August 23rd Temporary Certificate of Occupancy from the State Fire Marshal is anticipated on October 9th for the Gymnasium and Music room
▪
Equipment and systems training is ongoing
▪
Punch list is ongoing
EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY Drew Elementary School (RSD) [3819 St. Claude Avenue, New Orleans, LA 70117]
Scope of work: Renovation of existing elementary school and new addition Design Phase - DD
Drew Elementary School Early Renovation Design Progressing
▪
Community Meeting #2 is anticipated to be held on October 18th
▪
The Design Phase was extended due to Hurricane Isaac and revisions to the HVAC design
▪
Design Development documents are due on October 19th
Warren Easton School
(OPSB)
[3019 Canal Street, New Orleans, LA 70119]
Scope of work: Refurbishment of existing high school Design Phase - CD
Warren Easton High School Renovation Design Underway
▪
95% Construction Documents were received on September 15th
▪
Owner requested increase in the scope of work will extend the Design Phase
Frederick A. Douglass High School (RSD) [3820 St. Claude Avenue, New Orleans, LA 70117]
Scope of work: Renovation of existing high school Design Phase - SD
Frederick A. Douglass High School Renovation Design Has Begun
▪
Community Meeting #1 will be rescheduled at a later date
▪
Program Completion was received July 30th
▪
Schematic Design is anticipated on October 2nd
▪
Design Development is anticipated on December 15th
EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY Fisk-Howard School (RSD) [211 South Lopez Street, New Orleans, LA 70119]
Scope of work: New 3 section ES for 850 students. Design Phase - CD Fisk-Howard School Front Façade Rendering
▪
Community Meeting #4 - August 23rd
▪
Contractor is reviewing the contract for the Test pile program
▪
50% Construction Documents were received September 17th
▪
100% Construction Documents are anticipated to be finished on November 18th
William Frantz School (RSD) [3811 North Galvez Street, New Orleans, LA 70117]
Scope of work: Renovation of existing elementary school and new addition Construction Phase
William Frantz School Exterior Closed In—Interior In Progress
▪
Contractor has abandoned the project
▪
Owner is working with Surety to resume work
Alice Harte School
(OPSB)
[5300 Berkley Drive, New Orleans, La 70131]
Scope of work: New Pre-K – 8 School Construction Phase ▪
Ground Breaking was September 11th
▪
Notice to Proceed was issued September 12th
▪
The contractor has mobilized and has begun site preparation
Alice Harte School Design Completed EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY Lake Forest School at the Greater St. Stephens Site
(OPSB)
[11110 Lake Forest Boulevard 70128]
Scope of work: New Pre-K – 8 School Design Phase - DD
Lake Forest School at Gr. St. Stephens Design Development Site Study
▪
Community Meeting #3 – September 24th
▪
Schematic Design documents were received September 29th
▪
Design Development documents are anticipated October 18th
New PK-8 School at North Kenilworth Park at Curran Site (OPSB) [8500 Curran Boulevard, New Orleans, LA 70127]
Scope of work: New Pre-K– 8 School Procurement Phase
New PK-8 School at North Kenilworth Park At The Curran Site - Design Completed
▪
100% CD Documents were received on September 11th with the incorporated comments
▪
1st Advertisement – September 25th
▪
Pre-Bid Conference – 9:00 a.m. on October 10th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA
▪
Bid Date – November 8th
Alfred Lawless School
(RSD)
[5300 Law Street, New Orleans, LA 70117]
▪
Scope of work: New High School
Design Phase - DD ▪
Schematic Design documents were received on August 23rd
▪
Community Meeting postponed, will be rescheduled at a later date
▪
Design Development documents are due on November 13th
Alfred Lawless High School Design Of New High School Begun EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY
Edward Livingston School
(RSD)
[7301 Dwyer Road, New Orleans, LA 70126]
Scope of work: New High School Edward Livingston High School Early Schematic Design Rendering
Design Phase - CD ▪
50% Construction Documents were received on August 28th
▪
100% Construction Documents are due on November 9th pending approval of owner-requested changes
McDonogh #35 School (Phillip/Waters Site)
(OPSB)
[1200 Senate Street, New Orleans, LA 70122]
Scope of work: New 3-Story High School Site Remediation Project ▪
A Phase II environmental assessment revealed heavy metals and PAHs exist in the fill
▪
Scope of work is to remediate fly-ash materials found in the soil
▪
Remediation work is anticipated to be completed end of November
Ownership
McDonogh #35 School (Phillip/Waters Site) Completed Design Rendering
▪
The resubdivision request was submitted to the City Of New Orleans
▪
100% Construction Documents were received on October 2nd
Procurement Phase ▪
1st Advertisement – October 10th
▪
2nd Advertisement – October 17th
▪
3rd Advertisement – October 24th
▪
Pre-Bid Conference – 9:00 a.m. on October 31st at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA
▪
Bid Opening – November 15th
EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY
Eleanor L. McMain School
(OPSB)
[5721 S. Claiborne Avenue, New Orleans, LA 70125]
Scope of work: The exterior of the existing building will be stabilized and a new gym will be added to the site with a connecting breezeway to the main building Stabilization and Addition ▪
Design management team is reviewing alternates for window scope
▪
Design management team is assessing the existing stucco on the building
School Based Health Clinic Procurement Phase Eleanor L. McMain School Gymnasium Street Elevation
▪
Bid Opening – June 26th
▪
Contract was returned to the Owner, Owner is waiting on insurance certificates from the contractor
New Gymnasium and Breezeway Design Phase – CD ▪
100% Construction Documents were received on September 21st
Procurement Phase ▪
First Advertisement—October 3rd
▪
Bid Opening—November 7th
New Orleans East Abramson School
(RSD)
[7301 Dwyer Road, New Orleans, LA 70126]
Scope of work: New High School New Orleans East High School Abramson Site Location
Design Phase - CD ▪
Design will follow Edward Livingston High School. EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY
Mildred Osborne School (RSD) [6701 Curran Blvd., New Orleans, LA 70126]
Scope of work: New Pre-K– 8 School Construction Phase
Mildred Osborne School School Being Occupied
▪
Finish trades are working in the gymnasium
▪
Landscaping is nearly complete and the fencing is ongoing
▪
Media Center and Music Room are 85% complete
▪
Library is 90% complete
▪
Gymnasium is 80% complete
▪
School was Occupied – 15 August 2012
Parkview School (RSD) [4617 Mirabeau Avenue, New Orleans, LA 70126]
Scope of work: New Pre-K – 8 School Final Closeout Phase ▪
Punch list is 90% complete
▪
Owner requested additional hardscape to the exterior of the building
▪
Commissioning will begin in November
▪
School was Occupied – 6 August 2012
Parkview School Construction Complete
EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY
New Karr High School at the JoEllen Smith Site (OPSB) [4400 General Meyer Avenue, New Orleans, LA 70131]
Scope of work: New High School Design Phase - SD ▪
Community Meeting #3 is anticipated to be held in November
▪
Schematic Design Documents were submitted on August 17th
▪
Due to design issues and additional scope of work, Schematic Design Documents will be resubmitted
New Karr High School At The JoEllen Smith Site Early Site Study
Booker T. Washington School (RSD) [1201 South Roman Street, New Orleans, LA 70125] Scope of work: The auditorium and entry will be renovated and the remainder of the facility will be demolished and constructed new Design Phase - CD ▪
95% Construction Documents were received on September 26th
▪
Upon completion of the Design Phase, the project will be put on hold until a mitigation plan is developed on the environmental issues
Booker T. Washington School Architect’s Rendering of the Redesigned Entry
Phillis Wheatley Elementary School (RSD) [2300 Dumaine Street, New Orleans, LA 70119]
Scope of work: New Elementary School Procurement Phase
Phillis Wheatley Elementary School Design Completed and Ready To Build
▪
Bid Date – August 9th
▪
Contracts were returned by the contractor
▪
Notice to proceeded is anticipated October 17th
▪
Preconstruction meeting will be held October 16th EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY
Fannie C. Williams School (RSD) [11755 Dwyer Road, New Orleans, LA 70128]
Scope of work: New Pre-K – 8 School Final Closeout Phase
Fannie C. Williams School Classes Begin In October
▪
Certificate of Occupancy was issued on August 21st
▪
Substantial Completion achieved on August 24th
▪
Teachers will move in October 15th
▪
Classes to begin on October 22nd
Little Woods School (RSD) [10200 Curran Blvd., New Orleans, LA 70127]
Scope of work: New Pre-K – 8 School Construction Phase
Little Woods School Mechanical Systems Being Installed
▪
CMU installation is complete in all areas
▪
Installing brick veneer on interior of 1st floor and exterior of gymnasium is ongoing
▪
Fireproofing is complete in all areas
▪
Window and glass installation is 90% complete
▪
Sprinkler piping is complete on 3rd floor and 80% complete on the 1st and 2nd floors
▪
Interior metal stud framing is 95% complete
▪
Installation of gypsum board has started
▪
Pulling and terminating wire into panel boxes is ongoing throughout the building
▪
Roof deck, insulation and roof membrane is complete
▪
Permanent power is anticipate by the end of November
EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY
Carter G. Woodson School (RSD) [2514 Third Street, New Orleans, LA 70113]
Scope of work: New Pre-K – 8 School Construction Phase ▪
Substantial Completion – September 14th
▪
Punch list is 85% complete
▪
School occupied and classes began on September 17th
▪
Commissioning will start in November
Carter G. Woodson School Classes Begun on September 17, 2012
Sophie B. Wright Middle School Renovation
(RSD)
[1426 Napoleon Avenue, New Orleans, LA 70115]
Scope of work: Renovation Design Phase - DD
Sophie B. Wright Middle School Renovation Early Design Work In Progress
▪ ▪
Schematic Design Documents were delivered on September 24th Community Meeting #1 is anticipated to be held on October 4th
▪
Design Development Documents are anticipated December 7th
EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY OTHER PROJECTS Benjamin Franklin Senior High School (OPSB) [2001 Leon C. Simon Drive, New Orleans, LA 70122]
Scope of work: Renovation and Repairs to the existing courtyard, exterior lighting, metal roof panels, interior lighting, curtain wall, exterior doors (frames), fencing, scoreboard and goal post ▪Construction Phase ▪
Courtyard work will be complete in January
▪
Exterior roof and lighting work is 90% complete
Benjamin Franklin Senior High School Courtyard Repair Underway
Walter L. Cohen High School (RSD) [3520 Dryades Street, New Orleans, LA 70115]
Scope of work: Correct the HVAC Return Air/Ventilation problems and replace eight (8) chilled water pumps Design Phase Walter L. Cohen High School HVAC Repairs On the Way
▪
A / E contract to be approved at the October BESE board Meeting
EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY
Warren Easton School
(OPSB)
[3019 Canal Street, New Orleans, LA 70119]
Scope of work: Removal and replacement of existing exterior windows and waterproofing of the courtyard masonry Final Closeout Phase ▪
Substantial completion September 6th
▪
Punch list is ongoing
Warren Easton School Replacement Window Installation Complete
Langston Hughes School
(RSD)
[3519 Trafalgar Street, New Orleans, LA 70119]
Scope of work: Remove abandoned dumpster pad and grease trap; replace classroom door/hardware; correct duct system in the IT room; install fencing in place of the dumpster pad; provide and install a fence around the backflow preventer Final Closeout Phase ▪
95% of contractual items are complete
▪
Project completion will be extended due to the lead-time of a new classroom door
▪
Forecasted Substantial Completion – October 2012
Langston Hughes School All Work To Be Completed In October
EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY Andrew Jackson School
(RSD)
[1400 Camp Street, New Orleans, LA 70130]
Scope of work: To install solar panels at Andrew Jackson School. This will serve as a teaching aide for students to learn about solar energy Construction Phase
Andrew Jackson School General Contractor Selected
▪
Bid Opening – June 26th
▪
Lead time of solar panels has extended the schedule by a month
▪
Notice to Proceed on September 17th
Mahalia Jackson Elementary School Office Renovation (OPSB) [2101 Freret Street, New Orleans, LA 70113]
Scope of work: Convert the office space on the second floor of Building C into four classrooms Funding Source – New Orleans Parish School Board General Fund Procurement Phase
Mahalia Jackson ES School Office Renovation Design Complete
▪
Bid Opening – August 21st
▪
Contract was re-awarded after protest
▪
Notice to proceeded is anticipated October 18th
▪
Permits are in place
John McDonogh High School (RSD) [2426 Esplanade Avenue, New Orleans, LA 70119]
Scope of work – Replacement of Bleachers Design Phase - CD
John McDonogh High School Bleachers and Sprinklers To Be Installed
▪
The State Fire Marshal confirmed that with the addition of the new bleachers, a fire sprinkler system will be required in the gymnasium
▪
New bleachers and a new fire sprinkler system will be installed in the gymnasium
▪
Design is expected to be completed in December EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY Edna Karr High School - Gymnasium Repair (OPSB) [3332 Huntlee Drive, New Orleans, LA 70131]
Scope of work: Reinforce structural system in Gymnasium damaged due to termites Procurement Phase
Edna Karr High School - Gymnasium Repair Construction To Begin In October
▪
Bid Opening date – July 24th
▪
Owner returned signed contract September 26th
▪
Notice to proceeded is anticipated October 8th
Thomy Lafon School (RSD) [2601 Seventh St, New Orleans, LA 70115]
Scope of work: Stabilization of sculpture and installation of interpretive display Procurement Phase
Thomy Lafon School Sculpture To BeStabilized
▪
Bids received in September were not accepted
▪
1st Advertisement scheduled for October 31st
▪
Bid Opening will be December 5th
Lusher Elementary School Refurbishment (Bridge) (OPSB) [7315 Willow Street, New Orleans, LA 70118]
Scope of work: Renovation of existing bridge and restrooms to meet code requirements Design Phase - PC ▪
Program Documents are anticipated on October 15th
▪
Community Meeting postponed and will be rescheduled at a later date
Lusher Elementary School Bridge and Restrooms To Be Renovated EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY
Lusher (Fortier) High School Refurbishment (OPSB) [5624 Freret Street, New Orleans, LA 70115]
Scope of work: Renovation and repairs to the roof, masonry, plaster, windows, exterior doors, canopies, mechanical systems, and electrical systems. Design Phase - PC
Lusher (Fortier) High School Exterior Refurbishment Planning In Progress
▪
Program Documents are anticipated on October 10th
▪
Community Meeting postponed and will be rescheduled at a later date
McDonogh #35 High School Stabilization (OPSB) [1331 Kerlerec Street, New Orleans, LA 70116 ]
Scope of work: Stabilization and replacement of elevator systems, and electrical systems. Procurement Phase ▪
Bid Opening – September 20th
▪
Bids were higher than expected
▪
Project is being reviewed by the Owner
McDonogh #35 High School Elevator & Electrical Design Completed
Timbers HVAC (OPSB) [3520 General DeGaulle, New Orleans, LA 70114 ]
Scope of work: Stabilization and replacement of HVAC Design Phase - CD ▪
100% Construction Documents were received on September 28th
▪
Anticipated 1st Advertisement – November 2012
Timbers School Office HVAC System Replacement Ongoing EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY Village de L’est Elementary School (RSD) [5100 Cannes Street, New Orleans, LA 70129 ]
Scope of work: Roof replacement and demolition of four modular buildings Design Phase - CD ▪
95% Construction Documents are anticipated on October 4th
▪
100% Construction Documents are anticipated on October 26th
Village de L’Est Elementary School Roofing Design Work Nearly Complete
Sylvanie Williams Elementary School (RSD) [3127 Martin Luther King Jr. Boulevard, New Orleans, LA 70125]
Scope of work: AHU Replacement Procurement Phase ▪
Bid opening delayed 13 days due to Hurricane Isaac
▪
Bid Opening – September 11th
▪
Reccomendation letter was sent out September 25th
Sylvanie Williams Elementary School Air Handling Unit To Be Replaced
Dwight D. Eisenhower Elementary School (RSD) Andrew Jackson Elementary School (RSD) Paul B. Habans Elementary School (RSD) Sylvanie F. Williams Elementary School (RSD) Joseph S. Clark Senior High School (RSD) Scope of work: Roof Repairs and Replacement Final Closeout Phase ▪
Punch list will be complete November 2012
Various Roof Repairs In Final Closeout Phase Now EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY Building Automation System Integration At Recovery School District Central And Remote Offices
(RSD)
Scope of work: Implementation of a Central Remote Building Automation System that integrates the existing Building Automation Systems of the 4 Quick Start Schools (Andrew H. Wilson ES, Langston Hughes ES, L.B. Landry HS, and Lake Area HS) and Joseph A. Craig ES into a central remote monitoring workstation that will include Fannie C. Williams ES, Lawrence D. Crocker ES, Mildred Osborne ES, William Frantz ES, Bienville ES, Charles J. Colton ES, Carter G. Woodson ES and Parkview ES Construction Phase
BAS Integration System Installation Ongoing
▪
The five Quick Start Schools are 95% complete, with the punch list to be complete on in late October
▪
Sylvanie Williams and Sarah T. Reed are 90% complete
▪
The remaining integration for schools currently under construction will occur as each school is complete
MOTHBALL OR SAFE & SECURE OF SELECTED SCHOOLS Louis D. Armstrong Elementary School (RSD)) [5909 St. Claude Avenue, New Orleans, LA 70117]
Scope of work: Determine what methods need to be used to stabilize each school; Develop a plan for securing the exterior envelope from moisture, vandals and natural disasters; Implement the plan to stabilize and safeguard the school. Procurement Phase ▪
Preconstruction meeting is anticipated October 9th
▪
Notice to Proceed is anticipated October 11st
Louis D. Armstrong Elementary School Safe & Secure Design Complete
EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY
Israel M. Augustine Middle School
(RSD)
[425 S. Broad St., New Orleans, LA 70119]
Scope of work: Determine what methods need to be used to stabilize each school; Develop a plan for securing the exterior envelope from moisture, vandals and natural disasters; Implement the plan to stabilize and safeguard the school.
Israel M. Augustine Middle School Interior Shoring In Progress
Construction Phase ▪
Project is 20% complete
▪
Structural shoring is ongoing in the stairwell
Andrew J. Bell Junior High School
(RSD)
[1010 N. Galvez St., New Orleans, LA 70119]
Scope of work: Replace Roof. Determine what methods need to be used to stabilize each school; Develop a plan for securing the exterior envelope from moisture, vandals and natural disasters; Implement the plan to stabilize and safeguard the school. Mothballing of Closed Schools—Safe & Secure Andrew J. Bell Junior High School Stabilization Design Underway
Design Phase—CD ▪
50% Construction Documents are anticipated to be complete on October 25th
▪
100% Construction Documents are anticipated to be complete in November
Roof Structure Replacement Construction Phase ▪
Notice to Proceed was issued September 27th
▪
Substantial Completion scheduled for May, 2013
EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY
Oretha C. Haley Elementary School
(RSD)
[2515 N. Robertson Street, New Orleans, LA 70117]
Scope of work: Determine what methods need to be used to stabilize each school; Develop a plan for securing the exterior envelope from moisture, vandals and natural disasters; Implement the plan to stabilize and safeguard the school. Final Closeout Phase ▪
Punchlist is ongoing
Oretha C. Haley Elementary School Stabilization Completed
Lorraine Hansberry Elementary School
(RSD)
[1339 Clouet Street, New Orleans, LA 70117]
Scope of work: Determine what methods need to be used to stabilize each school; Develop a plan for securing the exterior envelope from moisture, vandals and natural disasters; Implement the plan to stabilize and safeguard the school. Construction Phase ▪
Metal panels over exterior windows is 75% complete
Lorraine Hansberry Elementary School Stabilization Begun In June, 2012
Morris F. X. Jeff Elementary School
(RSD)
[800 N. Rendon Street, New Orleans, LA 70119]
Scope of work: Determine what methods need to be used to stabilize each school; Develop a plan for securing the exterior envelope from moisture, vandals and natural disasters; Implement the plan to stabilize and safeguard the school. Construction Phase ▪
Notice to Proceed was issued September 17th
▪
Project is 10% complete
Morris F. X. Jeff Elementary School General Contractor Being Selected EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY Valena C. Jones Elementary School
(RSD)
[1901 N. Galvez Street, New Orleans, LA 70119]
Scope of work: Determine what methods need to be used to stabilize each school; Develop a plan for securing the exterior envelope from moisture, vandals and natural disasters; Implement the plan to stabilize and safeguard the school. Construction Phase Valena C. Jones Elementary School Stabilization Contractor Selection Underway
▪
Notice to Proceed was issued on September 12th
▪
Project is 10% complete
George Mondy Elementary School (RSD) [2327 St. Phillip Street, New Orleans, LA 70119]
Scope of work: Determine what methods need to be used to stabilize each school; Develop a plan for securing the exterior envelope from moisture, vandals and natural disasters; Implement the plan to stabilize and safeguard the school. Procurement Phase ▪
Bid Opening – October 30th
▪
Notice to Proceed is anticipated the end of November
George Mondy Elementary School Stabilization
John A. Shaw Elementary School (RSD) [2518 Arts Street, New Orleans, LA 70117]
Scope of work: Determine what methods need to be used to stabilize each school; Develop a plan for securing the exterior envelope from moisture, vandals and natural disasters; Implement the plan to stabilize and safeguard the school. Construction Phase ▪ John A. Shaw Elementary School Stabilization Work In Progress
Metal panels over exterior windows are 65% complete
EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY Demoli on Projects Fannie C. Williams Modular Campus
(RSD)
[11755 Dwyer Street, New Orleans, LA 70128]
Scope of work: Demolition of the existing modular classrooms Procurement Phase
Fannie C. Williams Elementary School Demolition of Modulars To Begin
▪
Bid Opening – September 18th
▪
The contract is being reviewed by the contractor
Greater St. Stephens School (OPSB) Scope of work: Demolition of the existing buildings Procurement Phase ▪
Bid Opening – September 13th
▪
The Owner is reviewing the bids
Greater St. Stephens School Demolition Bids Received
EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY JoEllen Smith Demolition (OPSB) [4400 General Meyer Avenue, New Orleans, LA 70131]
Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes. Design Phase - CD
JoEllen Smith School Demolition Planning Underway
▪
Notice to proceed was issued September 12th
▪
50% Construction Documents are anticipated October 31st
▪
100% Construction Documents are anticipated December 10th
L. B. Landry Annex Demolition
(RSD)
[1100 Wagner Street, New Orleans, LA 70114]
Scope of work: Develop a plan for the demolition of the existing annex building Procurement Phase ▪
Bid Opening – August 14th
▪
Contractor was non responsive, and the Owner is going to award the contract to the lowest responsive bidder
L.B. Landry Annex Demolition Procurement In Progress
Mary Church Terrell Elementary School Demolition (RSD) ) [3411 Broadway, New Orleans, LA 70125]
Scope of work: Develop a plan for the demolition of the existing buildings Procurement Phase ▪
Bid Opening – July 31st
▪
LDOE will issue a revised Notice of Intent to Award
Mary Church Terrell Elementary School Contract Award Forthcoming EXECUTIVE SUMMARY
Status Date: 30-September-2012
EXECUTIVE SUMMARY Booker T. Washington High School Partial Demolition
(RSD)
[1201 S. Roman Street, New Orleans, LA 70125]
Scope of work: Partial demolition of the existing building Procurement Phase ▪
Demolition of interior of main building is 70% complete
▪
First draft of the Environmental Plan was submitted on September 18th
Booker T. Washington HS Partial Demolition Demolition Underway
EXECUTIVE SUMMARY
Status Date: 30-September-2012
Community Outreach Reports
COMMUNITY OUTREACH REPORTS
Status Date: 30-September-2012
COMMUNITY OUTREACH JULY 2012 (Community Outreach Report) During the month of July in addition to monitoring construction activity and participating in school design community meetings, Bright Moments also worked with the Program Director and Outreach Manager for CSRS/Jacobs on the effort to increase minority participation in the rebuilding of schools. Both the RSD and the OPSB have adopted new DBE policies with the intent of increasing minority participation. In an effort to communicate the new policies and to foster partnerships between local general and minority contractors, meetings were held with the RSD and OPSB DBE program directors and representatives from contractor associations to begin planning for a major event to announce the new policies and forge relationships for future contract competition. With the school year beginning in August, several school projects are nearing completion.
CONSTRUCTION SITE MONITORING (Demolitions ‐ Renovations ‐ New School Buildings): Bienville Elementary – New School The school is near total completion. Students will start school August 6, 2012. Parkview Elementary ‐ New School This school will open its doors during the irst week of August. There is still a lot of work around the outside of this school that needs to be inished. There was one problem reported to the Outreach Team during the month. Ms. Sheleta Campbell of 4858 Piety St. reported that her foundation is cracking. The Outreach Team informed her that she needs to send a letter to the Citadel Builders and inform them that the problem at her home is believed to be as a result from the construction of the new school. The Outreach Team attended three project update meetings. Osborne Elementary ‐ New School Students are scheduled to move into building the 1st week in August, 2012. There is still landscaping work that needs to be completed. The charter operator Pride will be moving the staff into the building in early August 2012. There were no problems reported and the Outreach Team attended three project up date meetings during the month. COMMUNITY OUTREACH REPORTS
Status Date: 30-September-2012
COMMUNITY OUTREACH Crocker–New School This school site has progressed well this month. There weren’t many community issues throughout July. Early in the month, the outreach team was informed of a verbal altercation between two workers at the construction site and Steve Byrd, a nearby resident. (Based on our investigation, a barricade that was blocking the street off was moved by a worker in order for a construction vehicle to go down the street. Without knowing the street was blocked off, Steve Byrd, a nearby resident followed the construction vehicle down the street. Since the street was blocked off, the workers requested Mr. Byrd to reverse down the street. Mr. Byrd then informed the workers his vehicle does not drive in reverse. The workers then offered to push it back down the street. Mr. Byrd was upset by this gesture and declined their offer. This led into a verbal altercation. Mr. Byrd claims derogatory words were used towards him during this altercation.) The outreach team member recommended that the project manager, Randy Mullis of Satterfield and Pontikes, contact Mr. Byrd to apologize and explain that due diligence was taken. Mr. Byrd accepted the apology. There were no other major community issues reported this month. The general contractor continues to block off streets adjacent to the site in order to work on the building. In past months, the main concern from the community has been the litter around the site. Litter was not an issue this month. Workers clean the streets near the site daily. The outreach team will continue to monitor the site and follow‐up on complaints. Woodson Elementary – New School The work on this school site has progressed toward completion. There has not been any major community issues reported. The streets were slightly muddy this month due to the heavy amounts of rain. The workers continue to clean the streets after the mud builds up. Since concrete is being laid this upcoming month, the muddy streets should be less of a concern in the near future. The outreach team will continue to monitor the site. Little Woods Elementary ‐ New School On July 25, 2012 the Outreach Team received a telephone call from Ms. Cynthia Rouselle of 10717 Curran Rd. Ms Rouselle stated that work at this site began at 3:30 a.m.. The resident was very upset and complained that she could not get any rest. The Outreach Team went to the site and talked with MAPP Construction Project Superintendent. Wade Frey the superintendent reported that the gates to the site did not open until 6:00 A.M. Ms. Rouselle stated that if the problem comes up again, she will take pictures and send them to the Outreach Team. There were no other problems reported. F. C. Williams ‐ New School There is a lot of work going on around the outside of this school. All the driveways and sidewalks have been completed. The new trees have been planted and the grass is down. The school staff and a number of neighborhood members have been passing by and commenting on how good the school looks and how well it its in the community. There were no problems reported during the month.
COMMUNITY OUTREACH REPORTS
Status Date: 30-September-2012
COMMUNITY OUTREACH Frantz ‐ New and Renovated There was a problem with a truck leveling the site that pulled down some wires off a house. The Lathan Construction Company called out All Star Electric along with the Power Company Entergy and they were able to get the power back into the home. The resident was upset because the power box off the house hit her car and made a dent. Phillip Dekeyser the project manager gave the resident all the insurance information to ile a claim. The house is located at 2208 Alvar St. There is nothing new regarding Ms. Annie Falls’ problem. Larry Jordan of CSRS is still trying to contact the owner of Lathan Construction to get some answers to this problem. Colton – Major Renovation The work on this school site is coming along well. In past months, there have been several complaints received concerning this site. This month a complaint was received from Bill Lewin in regards to dirt being in the surrounding streets as well as airborne dust emissions from the construction site. The speci ic streets the complaint was pertaining to are Mandeville St., N. Rampart St., and Spain St. Dust was on vehicles parked on the streets adjacent to the site. Anytime a vehicle would drive down one of the adjacent streets dust emissions would become airborne. This is the cause for dust being on the vehicles. In response to the complaint, the Louisiana Department of Environmental Quality inspected the construction site and nearby streets. The inspector con irmed that were dust emissions from the site as well as dirt in the streets and on vehicles. To solve this issue, F. H. Paschen hired laborers to clean the street daily. F.H. Paschen also scheduled a street sweeper from Metro Disposal to clean the affected streets. In addition, the contractor had stone placed around the site to control track out. The outreach team will continue to monitor site for any further dust issues or any other community issues concerning the site. Audubon – Major Renovation The cottage has been completely demolished. Work is continuing inside the main building. There have not been any community issues around this site. The outreach team will continue to monitor the site and follow up on complaints. Lorraine Hansberry ‐ Mothballing There was one problem reported at this site during the month. The resident at 3134 North Villere Street reported that his garage was damaged when the new fence went up and all the vines and tree roots were removed. An Outreach Team member made a visit to Mr. Mike at the above address and informed him that Tuna Construction will replace the damaged wood on the garage. The construction company will also put up a little fence between the school property and his garage to prevent anyone from getting on his property from the back. The Outreach Team will work with Mr. Mike until the problem is resolved.
COMMUNITY OUTREACH REPORTS
Status Date: 30-September-2012
COMMUNITY OUTREACH O. C. Haley � Mothballing During the month there were no problems reported to the Outreach Team. The construction company has completed the work on the inside of the school. The workers are covering up the windows on the second and third loor. The Outreach Team did some community networking at this school. There had not been any more problems with the resident parking his car on the school property. The project should be completed at the end of the month. The Outreach Team attended two project update meetings. Shaw Elementary � Mothballing There were no major problems reported during the month. The Outreach Team networked with a resident who worked at this site for over 30 years. At the present time more of the inside work has been completed. Mike Dunn reported once again, that the community members are always stopping by and talking with him and the crew. The Outreach Team attended two project up date meetings.
COMMUNITY OUTREACH REPORTS
Status Date: 30-September-2012
COMMUNITY OUTREACH AUGUST 2012 (Community Outreach Report) During the month of August, in addition to the work on School / Community Design Input meetings and monitoring community issues at construction sites, Bright Moments worked with the OPSB and the RSD in planning a major outreach effort to inform the community about the new DBE policies and to build relationships between local General Contractors and DBE Sub-Contractors. Several pre-meetings with various constituencies were held and the promotion of the Construction Industry Day event began. The event is scheduled for Saturday, September 22, 2012.
CONSTRUCTION SITE MONITORING (Demolitions - Renovations - New School Buildings): Crocker–New School The construction on this school is close to completion and should be ready before the end of the year. There were no major community issues reported this month. The workers continue to block off adjacent streets to work on the building. In recent weeks, fewer streets have been blocked off due to the progress of construction. The contractor continues to have workers clean the streets near the site daily. The outreach team will continue to monitor the site and follow-up complaints. Bienville Elementary – New School Arthur Ashe Charter School started August 6, 2012. Woodson Elementary – New School This school is near completion. The school should be complete the end of the year if not sooner. There were no community issues reported this month. Most of the concrete has been laid around the school. In the past months, there has been a lot of mud in the streets near the site after heavy rainfall. Since the concrete has been laid around the site, there is a lot less mud in the streets in recent weeks. The outreach team will continue to monitor the site. Parkview Elementary - New School The doors opened at this school and the kids are in. The Citadel Builders continue to work inside and outside the school. The team did not hear any more from Ms. Sheila Campbell about her damages. The Outreach Team will no longer be spending time around this site. The Superintendent has been informed to contact the Outreach Team if any community issues come up.
COMMUNITY OUTREACH REPORTS
Status Date: 30-September-2012
COMMUNITY OUTREACH Osborne Elementary - New School The Outreach Team did not have any problems reported during the month. The site has opened for the school year. The P. H. Paschen Construction Company will be doing some work on the outside during the day and some work on the inside at night. There were a number of community members passing by stating how good the school looks. An Outreach Team member informed them that the community will be able to use some parts of the school. The Outreach Team will continue to monitor the site until all of the work is completed. F. C. Williams - New School The community around this site worked very well with the Brice / Roy Anderson Construction Company. There were no problems reported during the month. Tom Royle of Jacobs/ CSRS reported the students will be moving into the school in mid-September. Community members are excited about the new school. The neighborhood reported that the school fits well in the community. The site was checked pre and post Hurricane Isaac. Colton – Major Renovation The work on this school site has progressed. In past months, there have been several complaints received concerning this site. Towards the end of last month a complaint was received from Bill Lewin in regards to dirt being in the surrounding streets as well as airborne dust emissions from the construction site. The specific streets the complaint was pertaining to are Mandeville St., N. Rampart St., and Spain St. Dust was on vehicles parked on the streets adjacent to the site. To solve this issue, F. H. Paschen hired laborers to clean the street daily. F.H. Paschen also scheduled a street sweeper from Metro Disposal to clean the affected streets. This month, another complaint was received from Lord David concerning the airborne dust emissions. The complaint was mainly referring to a dust cloud that was created from the Metro Disposal street sweeper who was hired by Paschen. The outreach team and Jacobs/CSRS met with Paschen to discuss how to resolve the issue. In the meeting, Thomas Ryan, Paschen project superintendent, informed the outreach team and Jacobs/CSRS that the cause of the dust cloud was a faulty operator of the street sweeper. The street sweeper operator forgot to spray the water before sweeping the street. A big dust cloud was formed since there was no water to saturate the dust and keep it grounded. Metro Disposal ensured Paschen this would not happen again. Paschen hired a Metro Disposal street sweeper to sweep the streets a couple times a week. Paschen also has a cleaning crew cleaning the streets with push brooms and pressure washers near the site throughout each day. After receiving another complaint concerning the dust and dirt in the streets, Paschen hired the Metro Disposal street sweeper to sweep around the site daily. An additional cleaning crew was hired to wash the bobcats and any other construction vehicles that may be tracking dirt throughout the day. In addition, the contractor has placed stone around the site to control track out. There will be less work being done on the exterior of the building in the near future which will affect the community less. The outreach team will continue to monitor site for any further dust issues or any other community issues concerning the site.
COMMUNITY OUTREACH REPORTS
Status Date: 30-September-2012
COMMUNITY OUTREACH Audubon – Major Renovation The cottage has been completely demolished. Work is continuing inside the main building. Construction has not started on this site. There have not been community issues around this site. The outreach team will continue to monitor the site and follow up on complaints. Frantz Elementary - New and Renovated School Once again an Outreach Team member spoke with Larry Jordan of Jacobs / CSRS about Ms. Annie Falls. She reported her home was damaged by the work going on at the school over a year ago. There are very few workers on this site during the day. There have been a few neighborhood members asking why it is taking so long for the school to be completed. There were no new problems reported during the month. The Outreach Team spoke with the Superintendent of this site regarding keeping the streets around the school clean. The team checked the site before and after Hurricane Isaac and there were no neighborhood problems found. O. C. Haley - Mothballing This site is about 96% completed and all of the windows have been covered up. There were no major problems reported around this site. The construction company had a very good working relationship with the community. The Outreach Team attended two project update meetings. The team checked the site before and after Hurricane Isaac and found no community issues. L. Hansberry - Mothballing During the month the Outreach Team did not hear anything from Mr. Mike who resides at 3134 North Villere, regarding damages to his garage. There were no problems reported to the team during the month. The TUWA Construction Company began to cover up the windows at this school. The Outreach Team attended two project update meetings during the month. The team did check the site before and after Hurricane Isaac and there were no problems found by the team. Shaw Elementary - Mothballing The work at this site is moving slowly. Mike Dunn of Zimmer Eschette reported that he is waiting on material to begin doing the windows. Once again, there were no problems reported during the month. The team attended one project update meeting. The site was checked pre and post Hurricane Isaac.
COMMUNITY OUTREACH REPORTS
Status Date: 30-September-2012
COMMUNITY OUTREACH Israel M. Augustine - Mothballing The work began at this site during the month. At the present time there were no neighborhood issues reported to the team. There are only a few homes around this site. The Outreach Team did network with a family around the site. The family was excited that something is being done to the school and reported that people had been trying to get in the school. An Outreach Team member attended the project's first update meeting. The team is looking forward to working with the community. Booker T. Washington - Demolition The RSL Construction Company is presently removing all of the debris from the main building. The Outreach Team spent a number of hours networking with community members that passed by the site. The team explained that the main building will be renovated with an addition. There was a problem with some members of the neighborhood coming on the site to steal iron. The iron is being cut into big pieces so it cannot be removed. The team attended one demolition meeting during the month. 5th Community Meeting Fisk Howard School Building (Morris Jeff Community School) Date: Thursday, August 23, 2012 Location: First Grace United Church Start Time: 6:00 pm End Time: 7:15 pm Number in Attendance: 16 Overall: The meeting was productive. The participants were satisfied with the design of the school. The architect presented samples of the exterior material for the community to see. The field turf that would be used for the play area was also presented. The community was receptive of the selection of materials. A main concern from the school community was the size of the stage. Principal Perkins wanted to know the capabilities of such a small stage. She was concerned because Morris Jeff has a focus on the performing arts. In response, Lona Hankins of the RSD stated that the stage is a size ideal for presentations and award ceremonies. She also stated that it is big enough to hold one class. She informed Principal Perkins that a portable stage may be a possible solution to increase stage size. A community member who just moved in the area was also present. His main concern was about the traffic flow. He was informed the traffic will mostly be on S. Lopez St. Principal Perkins ensured him that they will be sensitive when it comes to the traffic flow around the school. She also informed him that the school will have crossing guards and she will do her best to work with the community. Overall, the community was excited about the school design.
COMMUNITY OUTREACH REPORTS
Status Date: 30-September-2012
COMMUNITY OUTREACH Questions, Answers, Comments Q: Was there a solution to the bus drop? A: The bus drop will be located near S. Lopez and Palmyra. Q: Is possible to post the 3d pictures on our website? R: Yes. Q: Where is the mechanical equipment? A: Some is on the second floor. It will also be hidden by the gym. There will be none on the ground. You will not be able to see it. Q: How many faculty members? A: 75 R: That's only 30 parking spaces. What about the church parking lot you all were trying to acquire. R: We are still looking into that. Q: What are the school hours? A: 8am – 3:30pm- Most of us will already be gone by the time you get home. R: I agree Q: What about energy efficiency and certification? A: LEED silver Q: What other schools have you all designed? A: Lake Area, Douglas, and a few high schools in Plaquemines Parish
Q: What about the shading on the stairwell? A: The shading on the stairwell is essential for the energy efficiency. It depends on the orientation of the sun and how much shade is needed. Q: What is the bus route? A: The bus route is all left turns. We didn't want to inconvenience the community by switching the directions of the streets.
COMMUNITY OUTREACH REPORTS
Status Date: 30-September-2012
COMMUNITY OUTREACH Q: When will the construction process begin? A: In roughly a month or two. We will begin knocking on doors to survey your home in late September or early October. Q: Will utilities improve surrounding the school? C: There is a lack of proper draining on Palmyra. A: We hope so. We are trying to work with the city to do so.
COMMUNITY OUTREACH REPORTS
Status Date: 30-September-2012
COMMUNITY OUTREACH SEPTEMBER 2012 (Community Outreach Report) During the month of September, Bright Moments worked with the Jacobs/CSRS management team, the Urban League, the DBE Di‐ rectors from the RSD and the OPSB, and with the Associated General Contractors to produce a successful "Construction Industry Day". The event was designed to provide information the new DBE policies enacted by the two school authorities and to urge local participation in the school rebuilding program. One hundred, ifty eight people (158) attended the event and from early reports, it appears that some relationships are being formed between GC's and minority contractors. The Outreach Team will follow‐up and continue to work for more local inclusion. Additionally, Bright Moments produced "Community Hot Line" signs to be posted at each school construction site to inform the neighborhoods who to contact if they have issues during the construction of the school. Bright Moments also began discussion in September to take on the task of developing "Interpretive Displays" at FEMA selected schools to commemorate the sites, which have historical signi icance. CONSTRUCTION SITE MONITORING (Demolitions ‐ Renovations ‐ New School Buildings ‐ Mothballing): Crocker–New School This school is near total completion. The students started attending the school building in the irst week of September. Although the school has started to use the building, construction work continues to be done on the side of the building located on LaSalle St. The community has not reported any major issues. A community outreach member spoke with Mike Burnett about the completion of the school. He expressed that he was excited about the look of the school and the completion of construction. The outreach team will continue to monitor the site until construction is completed. Woodson Elementary – New School This school is near total completion. There is minor construction and landscaping work still being done near the streets surrounding the school. The students began to use the building in the irst week of September. In the earlier weeks of the month, the school ad‐ ministration had a concern regarding pot holes near the school entrance. The contractor illed the major pot holes that were a cause of concern. There has been no community issues reported. The outreach team will continue to monitor until construction is totally completed.
COMMUNITY OUTREACH REPORTS
Status Date: 30-September-2012
COMMUNITY OUTREACH Fannie C. Williams ‐ New School The students are moving into this school in the middle of the month. The Brice Construction Company has moved off the site. The Outreach Team reported that this community around the school worked very well with the construction of the school. The Outreach Team has completed their assignment at this site. Parkview ‐ New School The Outreach Team had one problem reported during the month. Ms. Sheleta Campbell reported that she did not hear from the Citadel Builders. Ms. Campbell failed to send a letter to the construction company to report the damages to her home. This is the second time the Outreach Team reported to Ms. Campbell that she needs to send a letter. There were no other problems reported during the month. The Outreach Team has completed its assignment at this site. McDonogh 35 ‐ New School During the month the Hemp’s Construction Company stopped working for a few days. Ms. Sonji White of Jacobs /CSRS reported that the Hamp’s Company needs to work out a few problems. The major problem around this site is the streets. All the streets have big holes in them. Hamp’s Company has illed the holes a few times but they always come back. There have not been any community complaints about the holes in the street during the month. The Outreach Team will stay on top of this problem as the work moves forward. There have been a few former students of the school stopping by the site to see what is going on and why is it taking so long to begin new construction of the school. The Hamp’s Company is not on schedule and has missed its completion date. Audubon – Major Renovation Construction on this site is still on hold. A few test piles have been driven in the ground but there has been no other construction ac‐ tivity. The outreach team will continue to monitor the site and follow up on complaints. Colton – Major Renovation The work on this school site is coming along well. We have received several complaints in the recent couple of months concerning dust issues. This month the outreach team did not receive any complaints concerning dust issues. Although there were no issues concerning dust, the outreach team received multiple complaints from Craig Nero, owner of the Who Dat Café . On Thursday, Sep‐ tember 27, 2012 Bright Moments received a call from Craig Nero, owner of the “Who Dat” Cafe, concerning workers parking near the café which is a block away from the Colton construction site. Mr. Nero stated he does not want workers parking near his café be‐ cause his customers have no where to park. Mr. Nero has previously called regarding this issue. In May, Mr. Nero called ive times concerning this issue. The outreach member informed F.H. Paschen of the complaints. In response, F.H. Paschen informed all the sub ‐contractors not to park near the café . One week this month, Mr. Nero called twice to inform Willis Carter, Bright Moments outreach
COMMUNITY OUTREACH REPORTS
Status Date: 30-September-2012
COMMUNITY OUTREACH member, of these parking issues. As a result, Mr. Carter informed Thomas Ryan from F.H. Paschen of Mr. Nero’s complaints. Mr. Ryan stated that every week the contractor reminds the sub‐contractors not to park near the café . The outreach member informed Mr. Ne‐ ro of this information. However, he continues to be upset about the situation because he views the results as unsatisfactory. In clos‐ ing the conversation, Mr. Nero threatened to sue for loss of business due to these parking issues. There have been no other commu‐ nity issues reported this month. The outreach team will continue to monitor site for any community issues concerning the site. Frantz ‐ New school and renovation There are big problems at this site, The Lathan Company Inc. packed up and moved off the site in the middle of the night. The project manager of this site at Jacob/ CSRS reported to the Outreach Team members that it will take about six months to get this site moving forward again. A team member made a number of phone calls to Phillip Dekeyser of the Lathan Company to ind out about the problems with Annie Falls home. Mr. Dekeyser failed to get back with the Outreach Team. The team will keep checking on this site in the coming weeks. Oretha Castle Haley ‐ Mothballing This site is completed. The CDW Construction Company worked well with the community. During the time the mothballing was going on, there was not one neighborhood issue reported. The Outreach Team has completed the assignment at this site. Loraine Hansberry ‐ Mothballing The work at this site is moving forward. The TUNA Construction Company has done a good job. The Outreach Team has not had any neighborhood problems reported during the month. The resident at 3134 North Villere Street who had complained about his garage being damaged by the contractor did not pursue his claim. The team attended three project update meetings during the month. The Outreach Team will keep working in this neighborhood until the site is completed. Shaw Elementary‐ Mothballing The Zimmer Eschette Construction Company has failed to complete this job on its due date. At this site there have been some community members stopping by to share stories about their times at the school. There have not been any community problems reported during the month. This site has been assigned a new superintendent. The Outreach Team attended two project up date meetings during the month.
COMMUNITY OUTREACH REPORTS
Status Date: 30-September-2012
COMMUNITY OUTREACH Valena C. Jones ‐ Mothballing The asbestos and lead abatement has started. The Outreach Team walked around the neighborhood talking with the community and they were excited that something was going on with this school. The Outreach Team attended two project up date meetings during the month. Israel M. Augustine‐ Mothballing The work at this site is moving forward. There is a problem on the South Side of the school. The power lines will not let the CDW Construction Company perform work on the third loor windows. CDW is also concerned about people parking cars by the south side of the school and going into the courthouse and the bail bonds of ice. The construction company did not want the debris to fall on the cars parked on the south side of the school. The power Company is asking about $5,000.00 to remove the lines. The construction company put up some new fences around the site. Some community members were taking the shortcut through the site to get to Banks Street. The Outreach Team attended two project up date meetings during the month. Booker T. Washington ‐ Demolition During the month the RSL Construction Company has not reported anyone coming on site and stealing the iron. At the present time RSL is still removing debris from the site. Once again a number of alumni have passed by the site to check on the progress of the work and talk about their past days at the school. There is so much misinformation about this site. The team has to always explain that the school is coming back. The team attended one demolition meeting during the month. Alice M. Harte Ground Breaking Bright Moments coordinated the groundbreaking for Alice M. Harte Elementary School, which was held on Tuesday, September 11, 2012. After conversations with OPSB District 4 Board Member, Lourdes Moran, and Interim Superintendent Stan Smith; Bright Mo‐ ments identi ied and con irmed the participation of key elected of icials and city representatives. Bright Moments developed the run of show and physical program for the event, speci ically recommending content information and providing talking points to speak‐ ers for the event. In addition, Bright Moments coordinated all logistical aspects of the event, including the special shovel and hat sou‐ venirs for elected of icials. Bright Moments promoted the event by contacting individuals who attended the planning and design team meetings for the school, as well as the school, and other community members and residents. At the request of OPSB, Bright Mo‐ ments also served as media relations for the event, which included writing the draft press release and submitting it to OPSB for re‐ view and approval; sending the release to the media; and providing follow‐up calls to the media to determine their attendance at the event. Two television stations – ABC26 and WWL TV 4 – came to the event.
COMMUNITY OUTREACH REPORTS
Status Date: 30-September-2012
COMMUNITY OUTREACH Paul L. Dunbar 4th Community Meeting Date: Thursday, September 20, 2012 Bright Moments Staff: Willis Carter & Tom Martin Location: Cypress Manor Community Center Start Time: 6:00pm End Time: 7:00pm Number in Attendance: 5 Overall: The meeting was productive. There were no major concerns with the design from the community. The community was pleased with the location of the bus drop which will be off Forshey St. The community was also informed that the main entrance to the school will be on Live Oak St. Knowing the sensitivity of the matter, the contractor explained to the community that a request has been submitted for street parking on Live Oak St. and Cherry St. After receiving this information, the community had no issues with the requested street parking. Another participant present was a representative from Tulane University tutoring program housed at the present Benjamin Banneker. She expressed her concern about a space for the tutoring program. Ms. Lona Hankins explained to her that there is space available but it will be an administrative decision. In the end, the community was satis ied with the design. Comments, Questions, & Answers Q: Pre – K thru 2nd grade will be on the 1st loor? A: Yes. 3rd thru 5th grade will be on 2nd loor and 6th thru 8th will on the 3rd loor. The school counselor will be on the 2nd loor. Q: When will the contractor be selected? A: Late March or early April 2013 C: We do have test piles that will start in November. There will be a break from test pile to actual construction starts (Ms. Butler)C: I just don’t want the community to think that the school isn’t going to be built when they see the work has stopped af‐ ter the test piles are driven. The community still thinks the school will not be built. In the past, I have tried to post the presentations in the neighborhood but people continually take it down. R: We can give you multiple copies of the presentation. So you can post another copy if people continue to take the presentation. Q: Will there be space for the Tulane University tutoring program at the school?
COMMUNITY OUTREACH REPORTS
Status Date: 30-September-2012
COMMUNITY OUTREACH A: There is space for the program. Spaces or classrooms that could be used are the media center outdoor classroom, gym, or the pro‐ fessional development area. But that decision is up to the school's administration. Lake Forest Charter School ‐ Community Design Coordination Meeting #3 Monday, September 24, 2012 Greater St. Stephens, 5700 Read Boulevard, Morton Hall Meeting Notes The Lake Forest School Community Design Coordination Meeting #3 was held on Monday, September 24, 2012. This meeting is the third meeting in a series of ive meetings that will be held with the community to share with them the plans for the construction. Attendance: 105 Attendees Mr. Rouselle began the meeting with introductions. School principal Maudelle Cade welcomed the group and acknowledged the public of icials that were present. Mr. Steve Jones and Kevin Chenevert presented the attendees with a PPT presentation that out‐ lined the following: Activities Update: Demolition of Existing Building: Architect: Hegedus Grade Levels: PK‐8 Location: 11110 Lk. Forest Blvd. Funding Source: FEMA Available Funds for Construction: $22,080,000 Bid: Sept. 13, 2012 Notice to Proceed: October 24th Demolition from: Nov. ‘12 to Jan. ‘13 Test Pile Program: Advertise for Bids: Nov. 2012 Contract Awarded: Dec. 2013 Test Pile Work: Jan. to Feb. 2013
Geotechnical Soils Testing; RFP: Early July 2012 Proposals Received: Mid July 2012 NTP: Early Aug. 2012 Drilling: Delayed in August due to inclement weather Soil Boring: Completed – Sept. 21, 2012 Final Soils Report: Oct. 3, 2012
Design & Construction Schedule: Architect NTP: June 14, 2012 Advertise for Bids: March 2013 Bid Date: April 2013
COMMUNITY OUTREACH REPORTS
Status Date: 30-September-2012
COMMUNITY OUTREACH
Contractor NTP: Construction: Completion Date:
May 2013 487 Days January 2015
General Discussion: The demolition contract has been approved and the recommendation has been made to OPSB. A contractor will be identi ied at a Property Committee meeting scheduled to take place in mid‐October. Attendees were pleased that the school would be built on 8 acres of land and have access to all 16 acres of the site. The announcement of an option to have a total of 200 parking spaces at the school was received positively by all. Test pilings advertise for bids would begin in November 2012 and it is expected that the con‐ tract will be awarded in early December. The work would begin in early January 2013. After all of the test piling and structural is‐ sues have been addressed and the NTP has been issued it would be 90‐120 days before construction would begin. The design team met with City Planning representatives to map out the street traf ic low. Estimated construction completion date is January 2015. Following the presentation the meeting attendees were asked to state their questions or concerns to the project manager and archi‐ tects. The following is a recap of what the community concerns/questions/statements. Q. Does the school have the exact amount of fees for the architect for Lake Forest as for Hynes? A. Reduced fee 20‐30%. Will consult with the architect and get back with an answer. Q. Do not want the school to look exactly like Hynes. A. All that has been seen tonight is conceptual. The architects will bring back to the community for review and input so they can get an idea of concepts from this meeting as decisions are being made. The building will have its own identify and its own amenities. When the revisions are made they will get to see a true consensus of what the building will actually look like. Q. A resident who lives at the back yard of the school and whose property faces the playground area, wanted to know what type of fence would be built around the school. A. 8’ wood privacy fence. Will look at whether it would be wood or chain link. The fence would be maintained by the school. Design team will follow up on that. Q. Wanted to know how many feet from the property line would the fence be pitched. A. A possibility of a meeting being held with the property owners to discuss this matter. Q. What is the number of buildings will this school have?
COMMUNITY OUTREACH REPORTS
Status Date: 30-September-2012
COMMUNITY OUTREACH A. The school is a two story structure building which will function as ive different buildings. The Design will segregate into as‐ sembly spaces. Most of space designed will allow access to public for the use of school functions. Q. Roof – will it be pitched or will it be lat? Concerned that roof would experience leakage problems. A. Will follow up on that question. Compliment: Attendee expressed appreciation regarding the dialogue between the project manager/design team.
COMMUNITY OUTREACH REPORTS
Status Date: 30-September-2012
Cost Reports
PROGRAM COST SUMMARY AND STATUS REPORTS
Status Date: 30-September-2012
Program Summary
Schedule Status: Number of Projects by Phase
Not Started
42
Not Started
$474,095,355
Design
22
Design
$384,657,058
Procurement
18
Procurement
$183,270,918
Construction
15
Construction
$133,119,595
Final Completion Complete
Cost Description Not Started Design Procurement Construction Final Completion Complete Totals:
Value of Projects by Phase
5
Final Completion
129
Complete
$72,158,612 $366,933,380
Estimated Budget
Estimated Adjustments
Project Budget
Committed Costs
Cost to Date
Uncommitted Costs
Projected Costs
Projected Ovr/(Undr)
$473,397,159 $383,541,451 $174,946,968 $128,141,979 $71,490,403 $369,845,626
$430,500 $528 $36,185 $434,018 $405,147 ($3,520,469)
$473,827,659 $383,541,979 $174,983,152 $128,575,997 $71,895,550 $366,325,160
$7,208,265 $29,825,153 $46,742,667 $98,297,695 $70,546,159 $348,150,934
$430,230 $6,496,533 $12,710,558 $61,741,131 $66,229,377 $340,946,359
$466,887,090 $354,831,905 $136,528,251 $34,821,901 $1,612,453 $18,782,442
$474,095,355 $384,657,058 $183,270,918 $133,119,595 $72,158,612 $366,933,380
$267,696 $1,115,078 $8,287,766 $4,543,598 $263,062 $608,226
($2,214,091) $1,599,149,497
$600,770,873
$488,554,188 $1,013,464,042 $1,614,234,918
$15,085,426
$1,601,363,586
Program Summary
Status Date: 30-Sep-2012
Program Cost Status
Estimated Budget
Cost Description
Estimated Adjustments
Project Budget
Committed Costs
Cost to Date
Uncommitted Projected Costs Costs
Projected Ovr/(Undr)
$1,800,000,000 $1,620,000,000 $1,440,000,000 $1,260,000,000 $1,080,000,000 $900,000,000 $720,000,000 $540,000,000 $360,000,000 $180,000,000 $0 Project Budget
Cost Description 1-RSD Abrams HS - New Allen ES - Refurb Armstrong (Mothballing) Augustine (Mothballing) Augustine (Roof) Avery Alexander ES - New BAS Integration Bauduit ES - Refurb Behrman ES - New Bell JH (Mothballing) Bell JH (Phase 1-Roof) Bell JH (Shoring) Bell JH-Demo Bienville Elementary (New Construction) Booker T. Washington - HABS Booker T. Washington (New Construction) Booker T. Washington-Demo Bradley ES - New Carbon Credit Energy Conservation Measures Carver HS (New Construction) Clark HS - Reno Cohen (HVAC) Colton (Renovation)
Projected Costs
Committed Costs
Cost to Date
Estimated Budget
Estimated Adjustments
Project Budget
Committed Costs
Cost to Date
$25,507,738 $1,199,006 $276,023 $821,059 $495,101 $25,507,738 $229,369 $3,569,712 $25,507,738 $842,568 $2,140,855 $1,256,095 $98,522 $21,647,863 $35,804 $55,144,993 $960,633 $24,657,771 $373,166 $54,303,350 $20,228,401 $338,928 $32,846,878
$0 $16,001 $11,880 $13,200 $0 $0 $372,197 $19,549 $0 $0 $1,054 $0 $187 ($142,709) $0 $0 $0 $0 $522 $0 $0 $0 $0
$25,507,738 $1,215,007 $287,903 $834,259 $495,101 $25,507,738 $601,566 $3,589,261 $25,507,738 $842,568 $2,141,909 $1,256,095 $98,709 $21,505,154 $35,804 $55,144,993 $960,633 $24,657,771 $373,688 $54,303,350 $20,228,401 $338,928 $32,846,878
$0 $25,999 $483,752 $873,019 $398,057 $1,588,167 $502,605 $332,012 $0 $92,568 $1,408,896 $1,254,520 $10,334 $20,886,293 $35,804 $4,522,928 $1,039,547 $1,842,071 $387,728 $4,551,464 $0 $113,663 $29,293,261
$0 $16,001 $116,644 $321,824 $396,131 $0 $273,522 $19,549 $0 $0 $123,620 $1,359,467 $6,276 $19,465,329 $21,358 $1,951,267 $539,800 $507,954 $385,167 $2,843,755 $0 $18,243 $20,482,915
Program Cost Status
Uncommitted Projected Costs Costs
$25,507,738 $1,199,006 $0 ($196) $97,044 $23,919,571 $107,998 $3,267,888 $25,507,738 $753,131 $733,013 $106,575 $88,375 $851,009 $0 $50,635,892 ($78,914) $22,828,152 $0 $49,751,886 $20,228,401 $300,522 $3,538,772
$25,507,738 $1,225,005 $483,752 $872,823 $495,101 $25,507,738 $610,603 $3,599,900 $25,507,738 $845,699 $2,141,909 $1,361,095 $98,709 $21,737,302 $35,804 $55,158,820 $960,633 $24,670,223 $387,728 $54,303,350 $20,228,401 $414,185 $32,832,033
Projected Ovr/(Undr)
$0 $9,998 $195,849 $38,564 $0 $0 $9,037 $10,639 $0 $3,131 $0 $105,000 $0 $232,148 $0 $13,827 $0 $12,452 $14,040 $0 $0 $75,257 ($14,845)
Status Date: 30-Sep-2012
Program Cost Status
Cost Description Crocker Construction Crossman ES - Refurb Derham-Demo Douglass HS - Reno Drew ES - Reno Dunbar ES - New Eisenhower HS - Refurb Fannie C Williams - Modular Demolition Fannie C. Williams Construction Fischer ES - New Fisk-Howard ES - New Frantz Roof Replacement Frantz Renovation and Addition Gaudet ES - New Gaudet/Lake Forest ES (Roof) Gentilly Terrace ES - Refurb Green MS - Refurb Guste ES (New Roof and Elevator) Habans ES - New Haley (Mothballing) Haley-Demo Hansberry (Mothballing) Harney ES - Refurb Henderson (Roof) Jackson ES - Refurb Jackson K-8 Solar Panels Jeff (Mothballing) John McDonogh HS - Reno John McDonogh HS (Bleachers) Jones (Mothballing) Kennedy Modular Relocation-Coghill Campus Kennedy Modular Relocation-Schwarz Campus Kennedy-Demo Lafayette (New Roof and Masonry Repairs) Lafayette ES - Reno Lafon Interpretive Display Langston Hughes - Dumpster Pad
Estimated Budget
Estimated Adjustments
Project Budget
Committed Costs
Cost to Date
$21,344,462 $460,742 $1,000,000 $36,559,207 $19,661,993 $22,377,778 $1,738,309 $363,633 $24,271,336 $25,899,660 $25,145,449 $905,403 $24,675,669 $25,912,121 $416,274 $1,528,614 $6,104,559 $815,624 $25,836,662 $276,023 $98,754 $276,023 $316,775 $276,023 $1,310,788 $250,000 $276,023 $34,242,249 $124,844 $276,023 $549,927 $2,176,044 $1,000,000 $1,071,174 $22,222,469 $57,571 $91,522
$0 $16,001 $0 $0 $0 $0 $16,001 $0 $113,172 $0 $0 ($632,258) $1 $0 $522 $16,001 $19,549 $385,378 $0 $291,975 $188 $13,200 $21,206 $0 $16,001 $0 $11,220 $0 $0 $12,430 $336,751 ($902,847) $0 $0 $0 $0 $0
$21,344,462 $476,743 $1,000,000 $36,559,207 $19,661,993 $22,377,778 $1,754,310 $363,633 $24,384,508 $25,899,660 $25,145,449 $273,145 $24,675,670 $25,912,121 $416,796 $1,544,615 $6,124,108 $1,201,002 $25,836,662 $567,998 $98,942 $289,223 $337,981 $276,023 $1,326,789 $250,000 $287,243 $34,242,249 $124,844 $288,453 $886,678 $1,273,197 $1,000,000 $1,071,174 $22,222,469 $57,571 $91,522
$21,184,357 $71,211 $922,312 $3,426,806 $1,660,269 $1,791,650 $180,482 $31,113 $24,489,031 $0 $1,918,417 $273,146 $22,588,948 $0 $320,225 $163,098 $30,188 $1,201,002 $0 $567,998 $88,889 $654,839 $33,537 $96,611 $144,871 $168,284 $328,676 $0 $61,106 $904,093 $886,678 $1,273,197 $785,520 $945,902 $0 $8,120 $49,031
$18,382,289 $16,001 $863,177 $491,237 $218,482 $695,614 $16,001 $18,883 $23,927,788 $0 $744,026 $273,146 $18,803,976 $0 $304,423 $16,001 $19,549 $1,102,287 $0 $561,896 $88,768 $244,456 $21,206 $84,856 $16,001 $12,944 $156,507 $0 $6,579 $335,474 $886,678 $1,273,197 $777,097 $919,485 $0 $5,092 $42,775
Program Cost Status
Uncommitted Projected Costs Costs $206,243 $415,530 $77,688 $33,132,401 $18,001,724 $20,609,720 $1,583,826 $333,058 ($104,521) $25,899,660 $23,247,616 $0 $2,167,704 $25,912,121 $96,577 $1,391,515 $6,104,559 $0 $25,836,662 $0 $10,582 $0 $316,775 $179,412 $1,191,916 $74,951 $0 $34,242,249 $113,022 $0 $0 $0 $214,479 $125,272 $22,222,469 $50,000 $40,262
$21,390,600 $486,741 $1,000,000 $36,559,207 $19,661,993 $22,401,370 $1,764,308 $364,171 $24,384,509 $25,899,660 $25,166,033 $273,146 $24,756,652 $25,912,121 $416,802 $1,554,613 $6,134,747 $1,201,002 $25,836,662 $567,998 $99,471 $654,839 $350,312 $276,023 $1,336,787 $243,235 $328,676 $34,242,249 $174,128 $904,093 $886,678 $1,273,197 $1,000,000 $1,071,174 $22,222,469 $58,120 $89,292
Projected Ovr/(Undr) $46,138 $9,998 $0 $0 $0 $23,592 $9,998 $538 $1 $0 $20,584 $1 $80,982 $0 $6 $9,998 $10,639 $0 $0 $0 $530 $365,616 $12,331 $0 $9,998 ($6,765) $41,433 $0 $49,283 $615,640 $0 $0 $0 $0 $0 $549 ($2,230)
Status Date: 30-Sep-2012
Program Cost Status
Cost Description Laurel ES - Refurb Lawless HS - New LB Landry HS Annex - Demo Little Woods (New Construction) Live Oak ES - Reno Live Oak ES (Door Replacement) Live Oak ES (Roof) Livingston HS - New Marshall ES - Refurb Martin L King ES - Refurb Martin L. King (Canopy System) Martin L. King ES - Modular Buillding McDonogh 15 ES - Masonry Repair McDonogh 28 (Roof) McDonogh 28 ES - Refurb McDonogh 32 (Roof) McDonogh 42 (Roof) McDonogh 42 ES - Reno McDonogh 7 ES - Refurb Mondy (Mothballing) Mondy-Demo Morial ES - New New Algiers ES - New NO East HS @Abramson - New NO Signature Ctr Derham ES HS - New O Perry Walker HS - Refurb Osborne (New Construction) Parkview (New Construction) Priestley JH - Reno Reed HS - Refurb Reed HS (Bleachers) Roof Repair-Various Sites (HMS) Roof Repair-Various Sites (RCL) Rosenwald ES - Refurb Schaumburg ES - Refurb Schwarz HS - Refurb Shaw (Mothballing)
Estimated Budget
Estimated Adjustments
Project Budget
Committed Costs
Cost to Date
$6,703,881 $32,406,567 $190,458 $25,159,683 $23,804,832 $330,023 $812,349 $23,643,317 $894,838 $766,159 $125,087 $158,835 $240,106 $121,584 $2,442,527 $121,584 $471,859 $18,151,123 $4,024,854 $276,023 $22,133 $25,417,080 $25,507,738 $23,453,718 $7,268,586 $2,230,113 $24,447,403 $19,800,000 $14,808,612 $1,152,650 $124,844 $261,843 $282,249 $219,723 $208,570 $1,583,637 $276,023
$19,549 $0 $529 $0 $0 $34,239 $272,414 $0 $21,551 $19,549 ($9,147) $0 $0 $0 $19,549 $338,096 $0 $0 $19,549 $11,220 $187 $0 $0 $0 $0 $34,156 $0 $3,871,640 $0 $31,001 $528 $0 $0 $23,041 $22,516 $19,549 $11,770
$6,723,430 $32,406,567 $190,987 $25,159,683 $23,804,832 $364,262 $1,084,763 $23,643,317 $916,389 $785,708 $115,940 $158,835 $240,106 $121,584 $2,462,076 $459,680 $471,859 $18,151,123 $4,044,403 $287,243 $22,320 $25,417,080 $25,507,738 $23,453,718 $7,268,586 $2,264,269 $24,447,403 $23,671,640 $14,808,612 $1,183,651 $125,373 $261,843 $282,249 $242,764 $231,086 $1,603,186 $287,793
$30,188 $2,369,062 $27,062 $23,917,926 $0 $364,262 $1,084,763 $1,347,035 $33,882 $102,483 $115,940 $162,424 $203,348 $56,098 $229,436 $459,680 $418,613 $1,576,422 $30,188 $86,195 $2,816 $1,151,421 $1,151,421 $1,328,558 $268,586 $48,944 $23,505,805 $23,429,889 $29,032 $151,303 $89,050 $79,794 $119,964 $35,372 $34,847 $30,188 $691,591
$19,549 $297,202 $20,885 $15,812,597 $0 $296,340 $1,084,763 $276,958 $21,551 $19,549 $115,940 $159,698 $148,979 $52,504 $19,549 $446,896 $416,752 $205,749 $19,549 $75,786 $1,767 $0 $0 $289,000 $102,976 $34,156 $20,204,266 $23,261,328 $0 $31,001 $76,335 $6,594 $18,870 $23,041 $22,246 $19,549 $544,600
Program Cost Status
Uncommitted Projected Costs Costs $6,703,881 $30,051,255 $163,925 $1,332,253 $23,804,832 ($33,000) $0 $22,296,282 $894,838 $693,864 $0 $706 $40,688 $66,725 $2,243,279 $0 $35,719 $16,582,181 $4,024,854 $201,323 $19,500 $24,265,659 $24,356,317 $22,156,116 $7,000,000 $2,230,113 $941,597 $241,750 $14,808,612 $1,047,136 $32,484 $182,049 $168,275 $219,723 $208,570 $1,583,637 $0
$6,734,069 $32,420,317 $190,987 $25,250,179 $23,804,832 $331,262 $1,084,763 $23,643,317 $928,720 $796,347 $115,940 $163,131 $244,036 $122,824 $2,472,715 $459,680 $454,331 $18,158,603 $4,055,042 $287,518 $22,316 $25,417,080 $25,507,738 $23,484,674 $7,268,586 $2,279,057 $24,447,402 $23,671,639 $14,837,644 $1,198,439 $121,534 $261,843 $288,239 $255,095 $243,417 $1,613,825 $691,591
Projected Ovr/(Undr) $10,639 $13,750 $0 $90,496 $0 ($33,000) $0 $0 $12,331 $10,639 $0 $4,296 $3,930 $1,240 $10,639 $0 ($17,527) $7,480 $10,639 $275 ($4) $0 $0 $30,956 $0 $14,788 ($1) $0 $29,032 $14,788 ($3,838) $0 $5,990 $12,331 $12,331 $10,639 $403,798
Status Date: 30-Sep-2012
Program Cost Status
Cost Description Sherwood Forest ES - New Sophie B Wright ES - Reno Sylvanie Williams - Refurb Sylvanie Williams (HVAC and Chiller) Sylvanie Williams AHU Terrell ES - Demo Tubman ES - Reno Village De L'est (Roof) Village de L'Est ES - Refurb Village de Lest ES - Subsidence Wheatley (New Construction) Wheatley-Demo Wicker ES - Refurb Woodson (New Construction) Sub-Total: 1-RSD 2-OPSB Ashe Kitchen - Reno Audubon School Renovation Ben Franklin ES - Reno Ben Franklin HS - Refurb Benjamin Franklin HS - Stabilization Bethune ES - Addition BioMed District HS - New Central Services-Demo Eastbank Swing Space - Modules Easton HS - Refurb Easton HS (Window Replacement) GSt Stephens - Demo Harte - Demo Harte School (New Construction) Hynes ES (New Construction) JoEllen Smith Med Ctr Demo Karr HS - Gym Repair Lake Forest ES (New Construction) Lake Forest School @ Greater St. Stephens Site
Estimated Budget
Estimated Adjustments
Project Budget
Committed Costs
Cost to Date
$25,507,738 $24,815,434 $936,959 $449,939 $404,055 $320,943 $22,222,469 $89,716 $598,863 $115,283 $22,497,999 $500,000 $764,081 $22,233,798
$0 $0 $19,549 $0 $0 $0 $0 $528 $20,931 $0 $0 $0 $19,701 $0
$25,507,738 $24,815,434 $956,508 $449,939 $404,055 $320,943 $22,222,469 $90,244 $619,794 $115,283 $22,497,999 $500,000 $783,782 $22,233,798
$1,151,421 $2,060,248 $117,278 $448,873 $40,286 $51,470 $0 $92,694 $33,262 $117,153 $27,502,128 $239,216 $104,146 $21,903,531
$0 $277,151 $19,549 $437,086 $26,371 $41,748 $0 $19,534 $20,931 $81,310 $1,475,428 $239,216 $19,701 $21,528,833
$4,848,567 $1,042,115,494
$295,517,589
$208,508,096
$589,153 $13,776,116 $0 $0 $1,193,240 $14,287 $0 $1,147,718 $2,999,167 $214,773 $0 $56,529 $375,966 $2,316,519 $23,756,840 $0 $22,943 $0 $1,382,303
$149,654 $2,301,626 $0 $0 $413,387 $8,093 $0 $1,184,608 $2,999,167 $8,093 $0 $34,992 $405,097 $1,454,728 $23,028,287 $0 $8,093 $0 $207,345
$1,037,266,926
$593,224 $12,562,739 $14,369,521 $3,770,528 $1,202,557 $282,372 $23,453,718 $2,207,344 $2,705,681 $2,830,114 $2,380,000 $325,028 $382,738 $28,237,778 $26,304,056 $3,278,197 $282,372 $22,567,408 $24,993,905
$0 $0 $0 $0 $0 $0 $0 $31,201 $293,486 $0 $0 $11,502 $0 $0 $0 $0 $0 $0 $0
$593,224 $12,562,739 $14,369,521 $3,770,528 $1,202,557 $282,372 $23,453,718 $2,238,545 $2,999,167 $2,830,114 $2,380,000 $336,529 $382,738 $28,237,778 $26,304,056 $3,278,197 $282,372 $22,567,408 $24,993,905
Program Cost Status
Uncommitted Projected Costs Costs $24,356,317 $22,755,186 $849,869 $33,470 $364,298 $270,000 $22,222,469 $80,192 $598,863 $27,499 $1,876,832 $259,884 $691,967 $593,328
Projected Ovr/(Undr)
$25,507,738 $24,815,434 $967,147 $482,344 $404,584 $321,470 $22,222,469 $172,886 $632,125 $144,652 $29,378,960 $499,101 $796,113 $22,496,860
$0 $0 $10,639 $32,405 $529 $527 $0 $82,642 $12,331 $29,369 $6,880,961 ($899) $12,331 $263,062
$756,582,390 $1,052,099,982
$9,984,491
$4,071 $1,470,616 $14,369,521 $3,770,528 $4,565 $250,000 $23,453,718 $1,090,827 $0 $2,615,852 $2,380,000 $280,000 $65,947 $26,163,890 $2,744,306 $3,278,197 $250,000 $22,567,408 $23,611,602
$593,224 $15,246,732 $14,369,521 $3,770,528 $1,197,805 $264,287 $23,453,718 $2,238,545 $2,999,167 $2,830,625 $2,380,000 $336,529 $441,913 $28,480,409 $26,501,146 $3,278,197 $272,943 $22,567,408 $24,993,905
$0 $2,683,993 $0 $0 ($4,752) ($18,085) $0 $0 $0 $511 $0 $0 $59,174 $242,631 $197,090 $0 ($9,429) $0 $0
Status Date: 30-Sep-2012
Program Cost Status
Cost Description Lusher Bridge - Refurb Lusher Fortier HS – Refurb Mahalia Jackson - Off Reno McDonogh 35 (Phillips/Waters) McDonogh 35 HS - Stabilization (Elevator) McMain School - Gymnasium Nelson ES - Refurb New Karr HS (JE Smith) New PK-8 at North Kenilworth Park Sophie B. Wright (Repairs) Timbers - HVAC Sub-Total: 2-OPSB 3-RSD Completed Agnes Bauduit (Boiler) Allen Elementary (Roof) Avery-Alexander-Demo Behrman (Roof) Bienville School-Demo Booker T. Washington (Lockout/Tagout) Bradley ES-Demo Carver - Demo Chester-Demo Clark High School Cohen HS (Early Childhood Center) Cohen HS Health Clinic Colton (Select and Exploratory Demo) Craig (Canopies) Craig Construction Craig Demolition Craig ES Elevator Crocker Demolition * Crocker Reno and Select Demo Demolition 1 (Abrams ES, Abramson HS, Coghill ES, Morial ES)
Uncommitted Projected Costs Costs
Estimated Budget
Estimated Adjustments
Project Budget
Committed Costs
Cost to Date
$282,372 $13,675,666 $200,000 $57,072,600 $282,372 $12,975,643 $2,347,379 $29,952,863 $22,695,671 $587,430 $1,114,928
$0 $0 $0 $0 $0 $0 $0 $0 $0 ($217,244) $0
$282,372 $13,675,666 $200,000 $57,072,600 $282,372 $12,975,643 $2,347,379 $29,952,863 $22,695,671 $370,186 $1,114,928
$147,653 $1,128,827 $18,658 $9,008,816 $23,815 $1,360,038 $173,888 $2,633,172 $2,047,095 $370,186 $114,928
$15,090 $60,986 $11,195 $5,852,465 $15,658 $855,171 $0 $148,559 $1,176,679 $370,186 $57,464
$250,000 $12,585,430 $181,342 $48,461,697 $250,000 $11,834,265 $2,173,491 $27,947,432 $21,276,612 $0 $1,000,000
$397,653 $13,714,257 $200,000 $57,470,513 $273,815 $13,194,303 $2,347,379 $30,580,604 $23,323,707 $370,186 $1,114,928
$115,281 $38,591 $0 $397,913 ($8,557) $218,660 $0 $627,741 $628,036 $0 $0
$313,916,204
$118,945
$314,035,148
$64,872,630
$40,766,623
$254,331,317
$319,203,947
$5,168,798
$75,000 $433,326 $500,000 $1,400,000 $353,931 $5,000 $500,000 $500,000 $500,000 $34,316 $338,406 $622,466 $847,318 $46,522 $14,110,548 $1,173,116 $69,436 $661,961 $1,184,853 $2,119,395
($8,177) $175,464 $58,209 ($621,681) ($41,672) $2,000 ($177,635) $1,547,871 ($257,210) ($11,446) ($338,406) ($38,240) $1,730 ($380) $1,789,089 ($448,122) $79,428 $522 ($41,604) ($136,606)
$66,823 $608,790 $558,209 $778,319 $312,259 $7,000 $322,365 $2,047,871 $242,790 $22,870 $0 $584,226 $849,048 $46,142 $15,899,637 $724,994 $148,864 $662,483 $1,143,249 $1,982,789
$66,823 $608,790 $558,210 $778,319 $312,259 $7,000 $322,365 $2,047,871 $242,790 $22,870 $38,406 $584,226 $847,318 $46,142 $15,899,637 $724,994 $148,864 $499,418 $1,143,249 $1,982,789
$66,823 $608,790 $558,210 $778,319 $312,259 $7,000 $322,365 $2,047,871 $242,790 $22,870 $0 $584,226 $847,318 $46,142 $15,899,637 $724,994 $148,864 $451,943 $1,143,249 $1,982,789
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 ($38,406) $0 $0 $0 $0 $0 $0 $120,585 $0 $0
$66,823 $608,790 $558,210 $778,319 $312,259 $7,000 $322,365 $2,047,871 $242,790 $22,870 $0 $584,226 $847,318 $46,142 $15,899,637 $724,994 $148,864 $620,003 $1,143,249 $1,982,789
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 ($1,730) $0 $0 $0 $0 ($42,480) $0 $0
Program Cost Status
Projected Ovr/(Undr)
Status Date: 30-Sep-2012
Program Cost Status
Cost Description Demolition 2 (Edwards ES, Hardin ES, Lawless ES, Lockett ES) Demolition 3 (Lake Area MS, LB Landry HS) Demolition 4 (Temporary and Modular Buildings) Dibert ES (Roof)* Douglass (Room 214 Remodel) * Douglass HS (Boiler Roof) Douglass HS (Replace Under Floor Utilities) Douglass HS (Switchgear) Drew ES (Roof) Dunbar-Demo Edison ES-Demo Environmental Testing At 13 Schools Fannie C. Williams Reno and Demo Fisk-Howard-Demo Frantz Environmental and Demolition Gentilly Terrace ES (Roof)* Gordon-Demo Gregory-Demo * Guste ES Guste Science Lab Hardin and Morial (Fence) Hoffman-Demo Holy Cross Modular Relocation INT Baccalaureate John McDonogh Senior High (Roof) Johnson Elementary (Roof) Jordan-Demo* Lafon-Demo Lake Area HS* Lake Area MS - Demo Langston Hughes ES* Langston Hughes Mod Rmvl and Restore Lawless (Fence) LB Landry HS * LB Landry HS - Demo Little Woods ES-Demo
Uncommitted Projected Costs Costs
Estimated Budget
Estimated Adjustments
Project Budget
Committed Costs
Cost to Date
$1,910,553
($138,190)
$1,772,363
$1,772,363
$1,772,363
$0
$1,772,363
$0
$1,648,188 $564,909 $111,556 $85,942 $2,354 $32,529 $588,000 $413,901 $500,000 $500,000 $52,130 $819,389 $550,000 $603,495 $56,198 $500,000 $1,000,000 $2,840,872 $250,298 $133,895 $500,000 $2,178,783 $0 $778,490 $464,880 $500,000 $500,000 $38,923,536 $0 $29,915,546 $1,101,260 $78,749 $56,530,760 $0 $500,000
($148,775) ($23,051) $522 $522 $0 ($3,909) ($264,900) ($27,970) ($227,396) $72,229 $46,632 ($92,573) ($80,424) ($163,385) $20,379 ($246,889) $0 $9,803,082 $69,084 ($64,095) ($169,914) $1,932,274 $0 ($239,646) $35,902 $28,007 ($218,470) $1,139,650 $0 $219,410 ($385,731) ($20,817) $3,750,941 $0 ($200,692)
$1,499,413 $541,858 $112,078 $86,464 $2,354 $28,620 $323,100 $385,931 $272,604 $572,229 $98,762 $726,817 $469,576 $440,110 $76,577 $253,111 $1,000,000 $12,643,953 $319,382 $69,800 $330,086 $4,111,057 $0 $538,845 $500,782 $528,007 $281,530 $40,063,186 $0 $30,134,956 $715,529 $57,932 $60,281,701 $0 $299,308
$1,499,413 $541,858 $47,710 $10,942 $2,354 $28,620 $323,100 $385,931 $272,604 $572,229 $98,762 $726,817 $469,576 $440,110 $76,575 $253,111 $412,923 $12,643,953 $319,382 $69,800 $330,086 $4,111,056 $0 $538,845 $500,781 $236,339 $281,530 $39,622,512 $0 $30,034,537 $715,529 $57,932 $60,365,554 $0 $299,308
$1,499,413 $541,858 $29,120 $0 $2,354 $28,620 $323,100 $385,931 $272,604 $572,229 $98,762 $726,817 $469,576 $440,110 $69,575 $253,111 $204,972 $12,643,953 $319,382 $69,800 $330,086 $4,111,056 $0 $538,845 $500,781 $214,631 $281,530 $39,229,066 $0 $29,815,134 $715,529 $57,932 $60,351,796 $0 $299,308
$0 $0 $64,368 $75,522 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2 $0 $587,077 $0 $0 $0 $0 $0 $0 $0 $1 $291,668 $0 $424,674 $0 $115,253 $0 $0 ($83,853) $0 $0
$1,499,413 $541,858 $112,078 $86,464 $2,354 $28,620 $323,100 $385,931 $272,604 $572,229 $98,762 $726,817 $469,576 $440,110 $76,577 $253,111 $1,000,000 $12,643,953 $319,382 $69,800 $330,086 $4,111,056 $0 $538,845 $500,782 $528,007 $281,530 $40,047,186 $0 $30,149,790 $715,529 $57,932 $60,281,701 $0 $299,308
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 ($16,000) $0 $14,834 $0 $0 $0 $0 $0
Program Cost Status
Projected Ovr/(Undr)
Status Date: 30-Sep-2012
Program Cost Status
Cost Description Live Oak (Chimney) Livingston - Demo Livingston Multiplex (New Construction) McDonogh 15 ES (Waterproofing) McDonogh 42 (HVAC Replacement) New Orleans Free School (Study) O Perry Walker HS (Auditorium Reno) OE Federal City Osborne ES-Demo Parkview School-Demo Reed HS (Auditorium Wall)* Schaumburg School Chillers Schaumburg Window Replacement Schwarz Alternative Schwarz Modular-Demo Shaw-Demo Sherwood Forest ES - Demo Sylvanie Williams ES (Play Yard) Waters/Hughes-Demo Wilson Cottage Wilson ES Woodson MS-Demo* Sub-Total: 3-RSD Completed 4-OPSB Completed Audubon Ext (Roof @ Carrolton) * Banks ES-Demo Bethune ES (Floor Replacement) Bethune ES (Yard) Lusher ES (Roof) Mahalia Jackson Mahalia Jackson (Dumpster) McDonogh 35 (ADA Upgrades) McMain (Chiller Replacement) Phillips - Demo Seabrook Computer Training Center-Demo
Uncommitted Projected Costs Costs
Estimated Budget
Estimated Adjustments
Project Budget
Committed Costs
Cost to Date
$0 $500,000 $25,643,317 $221,646 $46,696 $50,000 $674,278 $0 $500,000 $500,000 $11,864 $442,000 $713,656 $229,532 $59,875 $337,285 $500,000 $188,677 $500,000 $283,144 $27,381,787 $500,000
$0 $170,058 ($23,134,469) ($34,846) $60,221 ($35,396) ($485,079) $0 $17,100 ($54,516) $1,510 ($241,105) $306,058 $93,231 ($31,883) $0 ($179,720) $29,541 ($148,625) $149,611 $1,687,871 $56,675
$0 $670,058 $2,508,848 $186,800 $106,917 $14,604 $189,199 $0 $517,100 $445,484 $13,374 $200,895 $1,019,714 $322,763 $27,992 $337,285 $320,280 $218,218 $351,375 $432,755 $29,069,659 $556,675
$0 $670,058 $2,508,848 $186,800 $106,917 $14,604 $189,199 $0 $517,100 $445,483 $13,372 $200,895 $1,019,714 $322,763 $27,992 $0 $320,279 $218,218 $351,375 $139,149 $29,069,660 $554,261
$0 $670,058 $2,470,111 $186,800 $106,917 $14,604 $189,199 $0 $517,100 $445,483 $13,372 $200,895 $1,019,714 $322,763 $27,992 $0 $320,279 $218,218 $351,375 $139,149 $29,069,660 $525,211
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2 $0 $0 $0 $0 $337,285 $0 $0 $0 $293,605 $0 ($20,586)
$0 $670,058 $2,508,848 $186,800 $106,917 $14,604 $189,199 $0 $517,100 $445,483 $13,374 $200,895 $1,019,714 $322,763 $27,992 $337,285 $320,280 $218,218 $351,375 $432,755 $29,069,659 $533,675
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1 ($23,000)
$229,895,564
($5,838,822)
$224,056,744
$221,821,169
$220,774,703
$2,167,197
$223,988,367
($68,374)
$282,372 $300,823 $300,000 $200,000 $460,379 $14,730,000 $78,190 $248,021 $626,000 $714,284 $61,500
$0 ($270,788) $57,424 $10,856 $157,160 $265,362 $0 ($65,264) ($114,977) ($45,509) ($25,000)
$282,372 $30,035 $357,424 $210,856 $617,539 $14,995,362 $78,190 $182,757 $511,023 $668,775 $36,500
$32,883 $30,035 $357,424 $210,856 $617,539 $14,865,825 $74,590 $182,757 $511,023 $668,775 $36,500
$8,604 $30,035 $357,424 $210,856 $617,539 $14,832,557 $77,929 $182,757 $511,023 $668,775 $36,500
$250,000 $0 $0 $0 $0 $129,538 $3,600 $0 $0 $0 $0
$282,883 $30,035 $357,424 $210,856 $617,539 $14,995,362 $78,190 $182,757 $511,023 $668,775 $36,500
$511 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Program Cost Status
Projected Ovr/(Undr)
Status Date: 30-Sep-2012
Program Cost Status
Uncommitted Projected Costs Costs
Cost Description
Estimated Budget
Estimated Adjustments
Project Budget
Committed Costs
Cost to Date
Timbers Office-Demo
$2,283,323
($1,312,045)
$971,278
$971,278
$971,278
$0
$971,278
$0
$20,284,892
($1,342,781)
$18,942,111
$18,559,485
$18,505,277
$383,138
$18,942,622
$511
($2,214,091) $1,599,149,497
$600,770,873
$488,554,699 $1,013,464,042 $1,614,234,918
$15,085,426
Sub-Total: 4-OPSB Completed
Totals:
$1,601,363,586
Projected Ovr/(Undr)
NOTE: All work has been completed for projects indicated by an asterisk (*). However, for financial or contractual reasons, they cannot yet be closed out.
Program Cost Status
Status Date: 30-Sep-2012
Individual Project Summaries
INDIVIDUAL PROJECT SUMMARIES
Status Date: 30-September-2012
Louis D. Armstrong Elementary School (RSD) 5909 St. Claude Avenue, New Orleans, LA 70117 Scope of Work: Stabilize and Secure the Building Funding Source - FEMA Architect - VergesRome Architects, APAC Contractor - CDW Services, LLC
Schedule Phase
Forecast Start
Forecast Finish
Armstrong (Mothballing)
Plan Start
Plan Finish
Design
12/16/2010
06/15/2012
12/16/2010
04/13/2012
Procurement
05/26/2012
09/21/2012
04/14/2012
07/22/2012
Construction
09/21/2012
01/19/2013
07/23/2012
11/19/2012
Final Completion
01/19/2013
03/05/2013
11/20/2012
01/03/2013
Cost Description
2010
2011
2012
2013
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$250,000 $0 $26,023 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $11,880 $0 $0 $0 $0 $0 $0
$250,000 $0 $26,023 $11,880 $0 $0 $0 $0 $0 $0
$445,593 $0 $26,023 $11,880 $0 $0 $0 $0 $256 $0
$87,593 $0 $16,915 $11,880 $0 $0 $0 $0 $256 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$445,593 $0 $26,023 $11,880 $0 $0 $0 $0 $256 $0
$195,593 $0 $0 $0 $0 $0 $0 $0 $256 $0
Totals:
$276,023
$11,880
$287,903
$483,752
$116,644
$0
$483,752
$195,849
$500,000 $450,000 $400,000 $350,000 $300,000 $250,000 $200,000 $150,000 $100,000 $50,000 $0
Project Update: - Preconstruction meeting is anticipated October 9th - Notice to Proceed is anticipated October 11st
Project Budget
Armstrong (Mothballing)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Israel M. Augustine Middle School (RSD) 425 South Broad Street, New Orleans, LA 70119 Scope of Work: Stabilize and Secure the Building Funding Source - FEMA Architect - VergesRome Architects, APAC Contractor - CDW Services, LLC
Schedule Phase
Forecast Start
Forecast Finish
Augustine (Mothballing)
Plan Start
Plan Finish
Design
10/20/2011
04/18/2012
10/20/2011
11/04/2011
Procurement
04/19/2012
07/27/2012
11/05/2011
02/12/2012
Construction
07/31/2012
12/27/2012
02/13/2012
06/11/2012
Final Completion
12/28/2012
02/10/2013
06/12/2012
07/26/2012
Cost Description
2011
2012
2013
2014
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Owner Costs Misc
$750,000 $0 $71,059 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $12,650 $0 $0 $0 $0 $0 $550
$750,000 $0 $71,059 $12,650 $0 $0 $0 $0 $0 $550
$791,139 $0 $69,230 $12,650 $0 $0 $0 $0 $0 $0
$266,539 $0 $42,635 $12,650 $0 $0 $0 $0 $0 $0
$0 $0 ($746) $0 $0 $0 $0 $0 $0 $550
$791,139 $0 $68,484 $12,650 $0 $0 $0 $0 $0 $550
$41,139 $0 ($2,575) $0 $0 $0 $0 $0 $0 $0
Totals:
$821,059
$13,200
$834,259
$873,019
$321,824
($196)
$872,823
$38,564
$900,000 $810,000 $720,000 $630,000 $540,000 $450,000 $360,000 $270,000 $180,000 $90,000 $0
Project Update: - Stabilization is 20% complete - Structural shoring is ongoing in the stairwell
Project Budget
Augustine (Mothballing)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Augustine Elementary School (RSD) 425 South Broad Street, New Orleans, LA 70119 Scope of Work: Roof Repairs Funding Source - FEMA Architect - VergesRome Architects, apc Contractor - CAMCO
Schedule Phase
Forecast Start
Forecast Finish
Augustine (Roof)
Plan Start
Plan Finish
Design
09/23/2010
04/20/2011
09/23/2010
02/24/2011
Procurement
04/21/2011
09/07/2011
02/25/2011
07/24/2011
Construction
09/08/2011
04/13/2012
07/25/2011
12/16/2011
Final Completion
04/14/2012
07/02/2012
12/17/2011
01/30/2012
Cost Description
2010
2011
2012
2013
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Project Budget
Estimated Estimated Budget Adjustments
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
Program Contingency A/E Fees & Reimbursables Demolition Environmental General Construction Modular Classrooms Other Costs Other Professional Services Permits & Fees Miscellaneous
$64,578 $38,523 $0 $0 $392,000 $0 $0 $0 $0 $0
($3,195) $0 $0 $0 $0 $0 $3,195 $0 $0 $0
$61,383 $38,523 $0 $0 $392,000 $0 $3,195 $0 $0 $0
$0 $38,523 $0 $0 $356,339 $0 $3,195 $0 $0 $0
$0 $36,597 $0 $0 $356,339 $0 $3,195 $0 $0 $0
$61,383 $0 $0 $0 $35,661 $0 $0 $0 $0 $0
$61,383 $38,523 $0 $0 $392,000 $0 $3,195 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$495,101
$0
$495,101
$398,057
$396,131
$97,044
$495,101
$0
$500,000 $450,000 $400,000 $350,000 $300,000 $250,000 $200,000 $150,000 $100,000 $50,000 $0
Project Update: - Project is substantially complete
Project Budget
Augustine (Roof)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Building Automation System At RSD Offices Scope of Work: BAS at Offices & 4 New Schools Funding Source - FEMA Architect - Moses Engineers Contractor - Synergy Building Solutions, Inc.
Schedule Phase
Forecast Start
Forecast Finish
BAS Integration
Plan Start
Plan Finish
Design
01/11/2011
05/26/2011
07/16/2010
05/09/2011
Procurement
05/27/2011
11/27/2011
05/10/2011
08/17/2011
Construction
11/28/2011
11/26/2014
08/18/2011
12/30/2011
Final Completion
11/27/2014
01/10/2015
12/31/2011
02/13/2012
Cost Description
2010
2011
2012
2013
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$175,000 $0 $54,369 $0 $0 $0 $0 $0 $0 $0
$345,440 $0 $26,229 $0 $0 $0 $0 $0 $528 $0
$520,440 $0 $80,598 $0 $0 $0 $0 $0 $528 $0
$421,479 $0 $80,598 $0 $0 $0 $0 $0 $528 $0
$205,630 $0 $67,364 $0 $0 $0 $0 $0 $528 $0
$98,962 $0 $9,036 $0 $0 $0 $0 $0 $0 $0
$520,441 $0 $89,634 $0 $0 $0 $0 $0 $528 $0
$1 $0 $9,036 $0 $0 $0 $0 $0 $0 $0
Totals:
$229,369
$372,197
$601,566
$502,605
$273,522
$107,998
$610,603
$9,037
$630,000 $567,000 $504,000 $441,000 $378,000 $315,000 $252,000 $189,000 $126,000 $63,000 $0
Project Update: - The five Quick Start Schools are 95% complete, with work expected to be complete on in late October - Sylvanie Williams and Sarah T. Reed are 90% complete - The remaining integration for schools currently under construction will occur as each school is complete
Project Budget
BAS Integration
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Andrew J. Bell Junior High School (RSD) 1010 N. Galvez Street, New Orleans, LA 70119 Scope of Work: Stabilize/Secure Selected Buildings Funding Source - FEMA Architect - VergesRome Architects, APAC Contractor - Cresent Commercial Construction
Schedule Phase
Forecast Start
Forecast Finish
Bell JH (Mothballing)
Plan Start
Plan Finish
Design
07/13/2011
10/29/2012
09/21/2010
03/31/2011
Procurement
10/30/2012
02/06/2013
04/01/2011
07/09/2011
Construction
02/07/2013
07/16/2013
07/10/2011
11/06/2011
Final Completion
07/17/2013
08/30/2013
11/07/2011
12/21/2011
Cost Description
2010
2011
2012
2013
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Owner Costs Misc
$750,000 $0 $92,568 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$750,000 $0 $92,568 $0 $0 $0 $0 $0 $0 $0
$0 $0 $92,568 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$750,000 $0 ($21,509) $24,640 $0 $0 $0 $0 $0 $0
$750,000 $0 $71,059 $24,640 $0 $0 $0 $0 $0 $0
$0 $0 ($21,509) $24,640 $0 $0 $0 $0 $0 $0
Totals:
$842,568
$0
$842,568
$92,568
$0
$753,131
$845,699
$3,131
$900,000 $810,000 $720,000 $630,000 $540,000 $450,000 $360,000 $270,000 $180,000 $90,000 $0
Project Update: - 50% Construction Documents are anticipated to be complete on October 25th - 100% Construction Documents are anticipated to be complete in November
Project Budget
Bell JH (Mothballing)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Andrew J. Bell Junior High School (RSD) 1010 N. Galvez Street, New Orleans, LA 70119 Scope of Work: Replace Roof and Roof Structure. Funding Source - FEMA Architect - VergesRome Architects, APAC Contractor - Cresent Commercial Construction
Schedule Phase
Forecast Start
Forecast Finish
Bell JH (Phase 1-Roof)
Plan Start
Plan Finish
Design
05/03/2012
05/29/2012
06/20/2011
08/29/2011
Procurement
05/30/2012
09/27/2012
08/30/2011
12/07/2011
Construction
09/28/2012
05/25/2013
12/08/2011
04/05/2012
Final Completion
05/26/2013
07/09/2013
04/06/2012
05/20/2012
Cost Description
2011
2012
2013
2014
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Misc
$1,900,000 $0 $167,303 $0 $0 $0 $0 $0 $0 $73,552
$0 $0 $0 $0 $0 $0 $0 $0 $1,054 $0
$1,900,000 $0 $167,303 $0 $0 $0 $0 $0 $1,054 $73,552
$1,264,000 $0 $70,290 $0 $0 $0 $0 $0 $1,054 $73,552
$0 $0 $49,014 $0 $0 $0 $0 $0 $1,054 $73,552
$636,000 $0 $97,013 $0 $0 $0 $0 $0 $0 $0
$1,900,000 $0 $167,303 $0 $0 $0 $0 $0 $1,054 $73,552
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$2,140,855
$1,054
$2,141,909
$1,408,896
$123,620
$733,013
$2,141,909
$0
$2,400,000 $2,160,000 $1,920,000 $1,680,000 $1,440,000 $1,200,000 $960,000 $720,000 $480,000 $240,000 $0
Project Update: - Notice to Proceed was issued September 27th - Substantial Completion scheduled for May 2013
Project Budget
Bell JH (Phase 1-Roof)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Andrew J. Bell Junior High School (RSD) 1010 N. Galvez Street, New Orleans, LA 70119 Scope of Work: Stabilize and Shoring of the Building Funding Source - FEMA Architect - VergesRome Architects, APAC Contractor - Abry Brothers
Schedule Phase
Forecast Start
Forecast Finish
Bell JH (Shoring)
Plan Start
Plan Finish
Design
09/21/2010
10/16/2010
09/21/2010
03/31/2011
Procurement
10/17/2010
02/11/2011
04/01/2011
07/09/2011
Construction
02/12/2011
05/09/2013
07/10/2011
11/06/2011
Final Completion
05/09/2013
05/09/2013
11/07/2011
12/21/2011
Cost Description
2010
2011
2012
2013
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Project Budget
Estimated Estimated Budget Adjustments
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$1,000,000 $0 $106,095 $0 $0 $0 $150,000 $0 $0 $0
$113,425 $0 $0 $0 $0 $0 ($113,425) $0 $0 $0
$1,113,425 $0 $106,095 $0 $0 $0 $36,575 $0 $0 $0
$1,148,425 $0 $106,095 $0 $0 $0 $0 $0 $0 $0
$1,253,425 $0 $106,042 $0 $0 $0 $0 $0 $0 $0
$70,000 $0 $0 $0 $0 $0 $36,575 $0 $0 $0
$1,218,425 $0 $106,095 $0 $0 $0 $36,575 $0 $0 $0
$105,000 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$1,256,095
$0
$1,256,095
$1,254,520
$1,359,467
$106,575
$1,361,095
$105,000
$1,400,000 $1,260,000 $1,120,000 $980,000 $840,000 $700,000 $560,000 $420,000 $280,000 $140,000 $0
Project Update: - Project was completed on 22 June 2011. - Shoring will remain in place until roof work is complete.
Project Budget
Bell JH (Shoring)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Jean Batiste de Bienville School (RSD) 1456 Gardena Drive, New Orleans, LA 70122 Scope of Work: New Pre-K - 8 School Funding Source - FEMA Architect - Howard Performance Architecture Contractor - Walton Construction
Schedule Phase
Forecast Start
Forecast Finish
Bienville Elementary (New Construction)
Plan Start
Plan Finish
Design
06/22/2009
04/20/2010
06/22/2009
02/14/2010
Procurement
07/22/2010
10/18/2010
02/13/2010
05/06/2010
Construction
10/18/2010
06/15/2012
10/14/2010
02/12/2012
Final Completion
06/16/2012
07/30/2012
02/13/2012
05/13/2012
Cost Description
2009
2010
2011
2012
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$18,880,000 $0 $1,446,554 $20,900 $0 $0 $1,030,850 $63,920 $205,639 $0
($83,525) $0 $149,990 $0 $0 $3,123 ($213,359) $0 $1,061 $0
$18,796,475 $0 $1,596,544 $20,900 $0 $3,123 $817,491 $63,920 $206,700 $0
$18,942,306 $0 $1,596,544 $18,975 $0 $3,123 $70,267 $48,377 $206,700 $0
$17,673,924 $0 $1,524,181 $18,975 $0 $3,123 $0 $48,377 $196,750 $0
($9,145) $0 $0 $1,925 $0 $0 $842,686 $15,543 $0 $0
$18,933,161 $0 $1,596,544 $20,900 $0 $3,123 $912,953 $63,920 $206,700 $0
$136,686 $0 $0 $0 $0 $0 $95,462 $0 $0 $0
Totals:
$21,647,863
($142,709)
$21,505,154
$20,886,293
$19,465,329
$851,009
$21,737,302
$232,148
$24,000,000 $21,600,000 $19,200,000 $16,800,000 $14,400,000 $12,000,000 $9,600,000 $7,200,000 $4,800,000 $2,400,000 $0
Project Update: - Project is complete - June 15 - The punch list is 95% complete
Project Budget
Bienville Elementary (New Construction)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Booker T. Washington School (RSD) 1201 South Roman Street, New Orleans, LA 70125 Scope of Work: Reno of Auditorium & New Const. Funding Source - FEMA Architect - Hewitt-Washington & Associates Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
Booker T. Washington (New Construction)
Plan Start
Plan Finish
Design
05/13/2011
11/05/2012
02/01/2010
12/11/2010
Procurement
11/17/2012
02/04/2013
04/08/2012
07/06/2012
Construction
02/05/2013
02/04/2015
07/07/2012
07/07/2014
Final Completion
02/05/2015
05/05/2015
07/08/2014
10/07/2014
Cost Description
2010
2011
2012
2013
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$46,263,980 $0 $3,501,332 $20,900 $0 $0 $5,100,511 $28,270 $230,000 $0
$0 $0 $614,814 $25,850 $0 $0 ($765,553) $7,500 $117,389 $0
$46,263,980 $0 $4,116,146 $46,750 $0 $0 $4,334,958 $35,770 $347,389 $0
$0 $0 $4,116,146 $46,750 $0 $0 $0 $12,643 $347,389 $0
$0 $0 $1,852,266 $0 $0 $0 $0 $9,755 $89,246 $0
$46,263,980 $0 $3,974 $9,853 $0 $0 $4,334,958 $23,128 $0 $0
$46,263,980 $0 $4,120,120 $56,603 $0 $0 $4,334,958 $35,770 $347,389 $0
$0 $0 $3,974 $9,853 $0 $0 $0 $0 $0 $0
Totals:
$55,144,993
$0
$55,144,993
$4,522,928
$1,951,267
$50,635,892
$55,158,820
$13,827
$60,000,000 $54,000,000 $48,000,000 $42,000,000 $36,000,000 $30,000,000 $24,000,000 $18,000,000 $12,000,000 $6,000,000 $0
Project Update: - 95% Construction Documents were received on September 26th - Upon completion of the Design Phase, the project will be put on hold until a mitigation plan is developed on the environmental issues
Project Budget
Booker T. Washington (New Construction)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Booker T. Washington HS Partial Demolition (RSD) 1201 S. Roman Street, New Orleans, LA 70125 Scope of Work: Partial demo of the existing building Funding Source - FEMA Architect - Hewitt-Washington & Associates Contractor - Gulfcon LLC
Schedule Phase
Forecast Start
Forecast Finish
Booker T. Washington-Demo
Plan Start
Plan Finish
Design
01/03/2011
12/01/2011
09/23/2010
12/31/2010
Procurement
12/02/2011
05/09/2012
01/01/2011
07/01/2011
Construction
05/10/2012
02/03/2013
07/01/2011
10/28/2011
Final Completion
02/04/2013
03/20/2013
10/29/2011
12/13/2011
Cost Description
2010
2011
2012
2013
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$0 $869,500 $91,133 $0 $0 $0 $0 $0 $0 $0
$0 $80,696 ($17,566) $9,115 $0 $3,500 ($78,914) $0 $3,169 $0
$0 $950,196 $73,567 $9,115 $0 $3,500 ($78,914) $0 $3,169 $0
$0 $950,196 $73,567 $9,115 $0 $3,500 $0 $0 $3,169 $0
$0 $462,293 $61,723 $9,115 $0 $3,500 $0 $0 $3,169 $0
$0 $0 $0 $0 $0 $0 ($78,914) $0 $0 $0
$0 $950,196 $73,567 $9,115 $0 $3,500 ($78,914) $0 $3,169 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$960,633
$0
$960,633
$1,039,547
$539,800
($78,914)
$960,633
$0
$1,200,000 $1,080,000 $960,000 $840,000 $720,000 $600,000 $480,000 $360,000 $240,000 $120,000 $0
Project Update: - Demolition of interior of main building is 70% complete - First draft of the Environmental Plan was submitted on September 18th
Project Budget
Booker T. Washington-Demo
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Stuart R. Bradley School (RSD) 2401 Humanity Street, New Orleans, LA 70122 Scope of Work: New 3-Section Elementary School Funding Source - FEMA Architect - Sizeler Thompson Brown Architects Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
Bradley ES - New
Plan Start
Plan Finish
Design
02/27/2012
01/12/2013
02/27/2012
02/23/2013
Procurement
01/19/2013
04/30/2013
01/12/2013
04/23/2013
Construction
04/30/2013
08/30/2014
04/23/2013
08/23/2014
Final Completion
08/30/2014
11/27/2014
08/23/2014
11/20/2014
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Project Budget
Estimated Estimated Budget Adjustments
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$21,330,000 $0 $1,582,878 $20,900 $0 $0 $1,395,723 $98,270 $230,000 $0
$0 $0 $144,710 $0 $0 $0 ($144,710) $0 $0 $0
$21,330,000 $0 $1,727,588 $20,900 $0 $0 $1,251,013 $98,270 $230,000 $0
$0 $0 $1,582,878 $18,920 $0 $0 $0 $16,506 $223,767 $0
$0 $0 $474,893 $17,050 $0 $0 $0 $16,011 $0 $0
$21,330,000 $0 $144,710 $2,530 $0 $4,640 $1,251,015 $89,025 $6,233 $0
$21,330,000 $0 $1,727,588 $21,450 $0 $4,640 $1,251,015 $105,530 $230,000 $0
$0 $0 $0 $550 $0 $4,640 $2 $7,260 $0 $0
Totals:
$24,657,771
$0
$24,657,771
$1,842,071
$507,954
$22,828,152
$24,670,223
$12,452
$27,000,000 $24,300,000 $21,600,000 $18,900,000 $16,200,000 $13,500,000 $10,800,000 $8,100,000 $5,400,000 $2,700,000 $0
Project Update: - 50% Construction Documents are due October 23rd - 100% Construction Documents are due December 23th
Project Budget
Bradley ES - New
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
George Washington Carver School (RSD) 3019 & 3059 Higgins Blvd., New Orleans, LA 70126 Scope of Work: New High School Funding Source - FEMA Architect - Trapolin Architects & VMDO Architects Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
Carver HS (New Construction)
Plan Start
Plan Finish
Design
02/01/2010
05/14/2012
02/01/2010
12/11/2010
Procurement
05/10/2012
09/16/2012
12/12/2010
03/01/2011
Construction
09/17/2012
09/16/2014
03/02/2011
10/29/2012
Final Completion
09/17/2014
12/15/2014
10/30/2012
01/27/2013
Cost Description
2010
2011
2012
2013
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$45,775,180 $0 $3,312,332 $20,900 $0 $0 $4,936,668 $28,270 $230,000 $0
$0 $0 $784,107 $4,290 $0 $1,510 ($974,148) $74,100 $110,141 $0
$45,775,180 $0 $4,096,439 $25,190 $0 $1,510 $3,962,520 $102,370 $340,141 $0
$0 $0 $4,096,439 $24,530 $0 $1,510 $0 $89,104 $339,881 $0
$0 $0 $2,632,131 $24,530 $0 $850 $0 $87,653 $98,591 $0
$45,775,180 $0 $0 $660 $0 $0 $3,962,520 $13,266 $260 $0
$45,775,180 $0 $4,096,439 $25,190 $0 $1,510 $3,962,520 $102,370 $340,141 $0
$0 $0 ($1) $0 $0 $0 $0 $0 $0 $0
Totals:
$54,303,350
$0
$54,303,350
$4,551,464
$2,843,755
$49,751,886
$54,303,350
$0
$60,000,000 $54,000,000 $48,000,000 $42,000,000 $36,000,000 $30,000,000 $24,000,000 $18,000,000 $12,000,000 $6,000,000 $0
Project Update: - Bid Opening - July 27th - Bids were not accepted - Project is on hold pending Owner's decision
Project Budget
Carver HS (New Construction)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Walter L. Cohen High School (RSD) 3520 Dryades Street, New Orleans, LA, 70115 Scope of Work: HVAC Corrections & New Controls Funding Source - FEMA Architect - Infinity Engineering Consultants, LLC Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
Cohen (HVAC)
Plan Start
Plan Finish
Design
10/22/2012
10/16/2014
10/22/2012
10/16/2014
Procurement
10/17/2014
01/24/2015
10/17/2014
01/24/2015
Construction
01/25/2015
05/24/2015
01/25/2015
05/24/2015
Final Completion
05/25/2015
07/08/2015
05/25/2015
07/08/2015
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$300,000 $0 $38,406 $0 $0 $0 $0 $0 $522 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$300,000 $0 $38,406 $0 $0 $0 $0 $0 $522 $0
$0 $0 $113,663 $0 $0 $0 $0 $0 $0 $0
$0 $0 $18,243 $0 $0 $0 $0 $0 $0 $0
$300,000 $0 $0 $0 $0 $0 $0 $0 $522 $0
$300,000 $0 $113,663 $0 $0 $0 $0 $0 $522 $0
$0 $0 $75,257 $0 $0 $0 $0 $0 $0 $0
Totals:
$338,928
$0
$338,928
$113,663
$18,243
$300,522
$414,185
$75,257
$450,000 $405,000 $360,000 $315,000 $270,000 $225,000 $180,000 $135,000 $90,000 $45,000 $0
Project Update: - A / E contract to be approved at the October BESE board Meeting
Project Budget
Cohen (HVAC)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Charles J. Colton School (RSD) 2300 St. Claude Avenue, New Orleans, LA 70117 Scope of Work: Renovation and New Addition Funding Source - FEMA Architect - Waggonner & Ball Architects Contractor - F.H. Paschen, S.N. Nielsen
Schedule Phase
Forecast Start
Forecast Finish
Colton (Renovation)
Plan Start
Plan Finish
Design
06/08/2009
08/21/2010
06/29/2009
03/01/2010
Procurement
09/15/2010
02/11/2011
02/28/2010
05/21/2010
Construction
03/01/2011
03/29/2013
05/22/2010
11/20/2011
Final Completion
03/30/2013
05/28/2013
11/21/2011
01/04/2012
Cost Description
2009
2010
2011
2012
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$26,394,224 $0 $3,120,373 $10,010 $0 $0 $3,061,378 $44,780 $216,113 $0
$0 $0 $13,110 $219,588 $0 $358 ($234,087) $0 $1,031 $0
$26,394,224 $0 $3,133,483 $229,598 $0 $358 $2,827,291 $44,780 $217,144 $0
$26,354,565 $0 $2,466,762 $223,037 $0 $358 $0 $31,395 $217,144 $0
$18,459,977 $0 $1,705,457 $166,988 $0 $358 $0 $31,395 $118,741 $0
$9,194 $0 $666,721 $6,561 $0 $0 $2,827,291 $29,005 $0 $0
$26,363,759 $0 $3,133,483 $229,598 $0 $358 $2,827,291 $60,400 $217,144 $0
($30,465) $0 $0 $0 $0 $0 $0 $15,620 $0 $0
Totals:
$32,846,878
$0
$32,846,878
$29,293,261
$20,482,915
$3,538,772
$32,832,033
($14,845)
$36,000,000 $32,400,000 $28,800,000 $25,200,000 $21,600,000 $18,000,000 $14,400,000 $10,800,000 $7,200,000 $3,600,000 $0
Project Update: - Roofing material installation is 85% complete - Exterior brick work is anticipated to be complete in mid- November - Gypsum board installation on interior walls is 85% complete on 2nd and 3rd floors - Mechanical/Electrical/Plumbing rough-in work is 85% complete - Pulling of wiring/data lines is in process - Window installation is 30% complete - Exterior wall panels were delivered and are being installed - Patching of terrazzo and installation of floor tile has started
Project Budget
Colton (Renovation)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Lawrence D. Crocker School (RSD) 2300 General Taylor St, New Orleans, LA 70115 Scope of Work: New Pre-K - 8 School Funding Source - FEMA Architect - Chenevert Architects LLC Contractor - Satterfield and Pontikes
Schedule Phase
Forecast Start
Forecast Finish
Crocker Construction
Plan Start
Plan Finish
Design
06/15/2009
05/24/2010
06/15/2009
02/09/2010
Procurement
05/18/2010
11/08/2010
02/08/2010
05/01/2010
Construction
11/08/2010
09/08/2012
11/08/2010
03/07/2012
Final Completion
09/09/2012
11/30/2012
11/21/2011
01/04/2012
Cost Description
2009
2010
2011
2012
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$18,598,000 $0 $1,427,250 $20,900 $0 $0 $1,016,403 $76,270 $205,639 $0
$842,907 $0 $23,986 $0 $0 $0 ($867,936) $0 $1,043 $0
$19,440,907 $0 $1,451,236 $20,900 $0 $0 $148,467 $76,270 $206,682 $0
$19,466,669 $0 $1,451,236 $10,780 $0 $0 $0 $48,990 $206,682 $0
$16,841,472 $0 $1,330,584 $10,780 $0 $0 $0 $48,990 $150,463 $0
$20,376 $0 $0 $10,120 $0 $0 $148,467 $27,280 $0 $0
$19,487,046 $0 $1,451,236 $20,900 $0 $0 $148,467 $76,270 $206,682 $0
$46,139 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$21,344,462
$0
$21,344,462
$21,184,357
$18,382,289
$206,243
$21,390,600
$46,138
$24,000,000 $21,600,000 $19,200,000 $16,800,000 $14,400,000 $12,000,000 $9,600,000 $7,200,000 $4,800,000 $2,400,000 $0
Project Update: - Exterior wall panels are complete, install of metal soffit is ongoing - Temporary Certificate of Occupancy from the City of New Orleans was received on August 23rd - Temporary Certificate of Occupancy from the State Fire Marshal is anticipated on October 9th for the Gymnasium and Music room - Equipment and systems training is ongoing - Punch list is ongoing
Project Budget
Crocker Construction
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Frederick A. Douglass High School (RSD) 3820 St. Claude Avenue, New Orleans, LA 70117 Scope of Work: Renovation of Existing Building Funding Source - FEMA Architect - VergesRome Architects, APAC Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
Douglass HS - Reno
Plan Start
Plan Finish
Design
06/25/2012
06/22/2013
06/25/2012
06/22/2013
Procurement
05/05/2013
08/14/2013
05/05/2013
08/19/2013
Construction
08/15/2013
02/14/2015
08/20/2013
02/19/2015
Final Completion
02/15/2015
05/15/2015
02/20/2015
05/20/2015
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$28,867,500 $0 $2,618,653 $20,900 $0 $0 $4,765,618 $28,270 $258,266 $0
$0 $0 $517,296 $11,746 $0 $0 ($540,042) $11,000 $0 $0
$28,867,500 $0 $3,135,949 $32,646 $0 $0 $4,225,576 $39,270 $258,266 $0
$0 $0 $3,135,949 $11,746 $0 $0 $0 $20,845 $258,266 $0
$0 $0 $470,392 $0 $0 $0 $0 $20,845 $0 $0
$28,867,500 $0 $0 $20,900 $0 $0 $4,225,576 $18,425 $0 $0
$28,867,500 $0 $3,135,949 $32,646 $0 $0 $4,225,576 $39,270 $258,266 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$36,559,207
$0
$36,559,207
$3,426,806
$491,237
$33,132,401
$36,559,207
$0
$40,000,000 $36,000,000 $32,000,000 $28,000,000 $24,000,000 $20,000,000 $16,000,000 $12,000,000 $8,000,000 $4,000,000 $0
Project Update: - Community Meeting #1 will be rescheduled at a later date - Program Completion was received July 30th - Schematic Design is anticipated on October 2nd - Design Development is anticipated on December 15th
Project Budget
Douglass HS - Reno
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Drew Elementary School (RSD) 3819 St. Claude Avenue, New Orleans, LA 70117 Scope of Work: Renovation and new addition Funding Source - FEMA Architect - Blitch / Knevel Architects Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
Drew ES - Reno
Plan Start
Plan Finish
Design
04/09/2012
03/22/2013
04/09/2012
04/03/2013
Procurement
03/24/2013
07/03/2013
03/01/2013
06/10/2013
Construction
07/03/2013
01/02/2015
06/10/2013
12/10/2014
Final Completion
01/02/2015
04/01/2015
12/10/2014
03/09/2015
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Project Budget
Estimated Estimated Budget Adjustments
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$15,690,475 $0 $1,456,546 $20,900 $0 $0 $2,235,802 $28,270 $230,000 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$15,690,475 $0 $1,456,546 $20,900 $0 $0 $2,235,802 $28,270 $230,000 $0
$0 $0 $1,456,546 $0 $0 $0 $0 $0 $203,723 $0
$0 $0 $218,482 $0 $0 $0 $0 $0 $0 $0
$15,690,475 $0 $0 $20,900 $0 $0 $2,235,802 $28,270 $26,277 $0
$15,690,475 $0 $1,456,546 $20,900 $0 $0 $2,235,802 $28,270 $230,000 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$19,661,993
$0
$19,661,993
$1,660,269
$218,482
$18,001,724
$19,661,993
$0
$20,000,000 $18,000,000 $16,000,000 $14,000,000 $12,000,000 $10,000,000 $8,000,000 $6,000,000 $4,000,000 $2,000,000 $0
Project Update: - Community Meeting #2 is anticipated to be held on October 18th - The Design Phase was extended due to Hurricane Isaac and revisions to the HVAC design - Design Development documents are due on October 19th
Project Budget
Drew ES - Reno
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Paul L. Dunbar School (RSD) 9330 Forshey Street, New Orleans, LA 70125 Scope of Work: New 2-Section Pre-K - 8. Funding Source - FEMA Architect - Chenevert Architects LLC Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
Dunbar ES - New
Plan Start
Plan Finish
Design
02/22/2012
12/25/2013
02/22/2012
02/18/2013
Procurement
12/26/2012
04/04/2013
12/26/2012
04/18/2013
Construction
04/04/2013
10/04/2014
04/18/2013
08/18/2014
Final Completion
10/05/2014
01/02/2015
08/18/2014
11/15/2014
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Project Budget
Estimated Estimated Budget Adjustments
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$19,230,000 $0 $1,437,088 $20,900 $0 $0 $1,361,520 $98,270 $230,000 $0
$0 $0 $10,453 $0 $0 $0 ($31,494) $8,250 $12,791 $0
$19,230,000 $0 $1,447,541 $20,900 $0 $0 $1,330,026 $106,520 $242,791 $0
$67,600 $0 $1,439,838 $13,530 $0 $4,640 $0 $22,715 $243,327 $0
$0 $0 $646,690 $13,530 $0 $4,640 $0 $19,415 $11,339 $0
$19,162,400 $0 $5,745 $7,370 $0 $325 $1,330,026 $83,805 $20,049 $0
$19,230,000 $0 $1,445,583 $20,900 $0 $4,965 $1,330,026 $106,520 $263,376 $0
$0 $0 ($1,958) $0 $0 $4,965 $0 $0 $20,585 $0
Totals:
$22,377,778
$0
$22,377,778
$1,791,650
$695,614
$20,609,720
$22,401,370
$23,592
$24,000,000 $21,600,000 $19,200,000 $16,800,000 $14,400,000 $12,000,000 $9,600,000 $7,200,000 $4,800,000 $2,400,000 $0
Comments - Design Development documents were received on August 6th - Community Meeting #4 - September 20th - 50% Construction Documents are due October 11th - 100% Construction Documents are due December 10th
Project Budget
Dunbar ES - New
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Fannie C. Williams Elementary School (RSD) 11755 Dwyer Rd, New Orleans, LA 70128 Scope of Work: Demolish Modular Classrooms Funding Source - FEMA Architect - VergesRome Architects, APAC Contractor - Gulfcon LLC
Schedule Phase
Forecast Start
Forecast Finish
Fannie C Williams - Modular Demolition
Plan Start
Plan Finish
Design
06/11/2012
07/30/2012
06/11/2012
07/25/2012
Procurement
07/31/2012
11/30/2012
07/26/2012
09/23/2012
Construction
12/01/2012
02/28/2013
09/24/2012
10/23/2012
Final Completion
03/01/2013
04/14/2013
10/24/2012
12/07/2012
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$0 $300,000 $30,575 $0 $0 $0 $33,058 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $300,000 $30,575 $0 $0 $0 $33,058 $0 $0 $0
$0 $0 $30,575 $0 $0 $0 $0 $0 $538 $0
$0 $0 $18,345 $0 $0 $0 $0 $0 $538 $0
$0 $300,000 $0 $0 $0 $0 $33,058 $0 $0 $0
$0 $300,000 $30,575 $0 $0 $0 $33,058 $0 $538 $0
$0 $0 $0 $0 $0 $0 $0 $0 $538 $0
Totals:
$363,633
$0
$363,633
$31,113
$18,883
$333,058
$364,171
$538
$400,000 $360,000 $320,000 $280,000 $240,000 $200,000 $160,000 $120,000 $80,000 $40,000 $0
Project Update: - Bid Opening - September 18th - The contract is being reviewed by the contractor
Project Budget
Fannie C Williams - Modular Demolition
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Fannie C. Williams School (RSD) 11755 Dwyer Road, New Orleans, LA 70128 Scope of Work: New Pre-K - 8 School Funding Source - FEMA Architect - Yeates & Yeates Architects Contractor - Brice Building Company, LLC
Schedule Phase
Forecast Start
Forecast Finish
Fannie C. Williams Construction
Plan Start
Plan Finish
Design
05/04/2009
07/06/2010
05/04/2009
10/21/2009
Procurement
04/14/2010
11/22/2010
10/03/2009
12/24/2009
Construction
11/22/2010
09/06/2012
11/22/2010
03/22/2012
Final Completion
09/07/2012
10/21/2012
03/23/2012
05/07/2012
Cost Description
2009
2010
2011
2012
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$21,185,000 $0 $1,611,681 $20,900 $0 $0 $1,155,778 $74,733 $223,244 $0
$1,294,278 $0 $418,920 $0 $0 $1,345 ($1,602,634) $0 $1,263 $0
$22,479,278 $0 $2,030,601 $20,900 $0 $1,345 ($446,856) $74,733 $224,507 $0
$22,183,980 $0 $2,030,601 $0 $0 $1,345 $0 $48,597 $224,507 $0
$21,832,098 $0 $1,928,191 $0 $0 $1,345 $0 $48,597 $117,556 $0
$295,299 $0 $0 $20,900 $0 $0 ($446,856) $26,136 $0 $0
$22,479,278 $0 $2,030,601 $20,900 $0 $1,345 ($446,856) $74,733 $224,507 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$24,271,336
$113,172
$24,384,508
$24,489,031
$23,927,788
($104,521)
$24,384,509
$1
$27,000,000 $24,300,000 $21,600,000 $18,900,000 $16,200,000 $13,500,000 $10,800,000 $8,100,000 $5,400,000 $2,700,000 $0
Project Update: - Certificate of Occupancy was issued on August 21st - Substantial Completion achieved on August 24th - Teachers will move in October 15th - Classes to begin on October 22nd
Project Budget
Fannie C. Williams Construction
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Fisk Howard School (RSD) 211 South Lopez Street, New Orleans, LA 70119 Scope of Work: New 3 Section ES Funding Source - FEMA Architect - VergesRome Architects+Fanning Howey Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
Fisk-Howard ES - New
Plan Start
Plan Finish
Design
01/23/2012
12/13/2012
01/22/2012
01/23/2013
Procurement
12/14/2012
03/18/2013
12/02/2012
03/11/2013
Construction
03/19/2013
07/19/2014
03/12/2013
07/12/2014
Final Completion
07/19/2014
10/16/2014
07/12/2014
10/09/2014
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$21,400,000 $0 $1,587,723 $20,900 $0 $0 $1,808,556 $98,270 $230,000 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$21,400,000 $0 $1,587,723 $20,900 $0 $0 $1,808,556 $98,270 $230,000 $0
$64,000 $0 $1,582,878 $16,940 $0 $0 $0 $11,275 $243,324 $0
$0 $0 $712,295 $16,940 $0 $0 $0 $11,275 $3,515 $0
$21,336,000 $0 $4,845 $4,400 $0 $0 $1,808,556 $93,815 $0 $0
$21,400,000 $0 $1,587,723 $21,340 $0 $0 $1,808,556 $105,090 $243,324 $0
$0 $0 $0 $440 $0 $0 $0 $6,820 $13,324 $0
Totals:
$25,145,449
$0
$25,145,449
$1,918,417
$744,026
$23,247,616
$25,166,033
$20,584
$27,000,000 $24,300,000 $21,600,000 $18,900,000 $16,200,000 $13,500,000 $10,800,000 $8,100,000 $5,400,000 $2,700,000 $0
Comments - Community Meeting #4 - August 23rd - Contractor is reviewing the contract for the Test pile program - 50% Construction Documents were received September 17th - 100% Construction Documents are anticipated to be finished on November 18th
Project Budget
Fisk-Howard ES - New
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
William Frantz School (RSD) 3811 North Galvez Street, New Orleans, LA 70117 Scope of Work: Reno of Bldg and New Addition Funding Source: FEMA Architect - Billes Architecture Contractor - The Lathan Company
Schedule Phase
Forecast Start
Forecast Finish
Frantz Renovation and Addition
Plan Start
Plan Finish
Design
05/15/2009
06/28/2010
05/15/2009
11/10/2009
Procurement
06/29/2010
10/08/2010
11/09/2009
01/30/2010
Construction
10/08/2010
06/21/2013
10/08/2010
02/06/2012
Final Completion
06/22/2013
08/05/2013
02/07/2012
03/23/2012
Cost Description
2009
2010
2011
2012
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$20,217,718 $0 $1,958,387 $19,931 $0 $0 $2,256,185 $39,193 $184,255 $0
$77,347 $0 $30,255 $6,750 $0 $1,535 ($117,970) $0 $2,083 $0
$20,295,065 $0 $1,988,642 $26,681 $0 $1,535 $2,138,215 $39,193 $186,338 $0
$20,350,628 $0 $1,988,643 $25,181 $0 $1,535 $0 $36,623 $186,339 $0
$16,841,573 $0 $1,800,408 $25,181 $0 $1,535 $0 $35,963 $99,316 $0
$25,419 $0 $0 $1,500 $0 $0 $2,138,215 $2,570 $0 $0
$20,376,046 $0 $1,988,643 $26,681 $0 $1,535 $2,138,215 $39,193 $186,339 $0
$80,981 $0 $0 $0 $0 $0 $0 $0 $1 $0
Totals:
$24,675,669
$1
$24,675,670
$22,588,948
$18,803,976
$2,167,704
$24,756,652
$80,982
$27,000,000 $24,300,000 $21,600,000 $18,900,000 $16,200,000 $13,500,000 $10,800,000 $8,100,000 $5,400,000 $2,700,000 $0
Project Update: - Contractor has abandoned the project - Owner is working with Surety to resume work
Project Budget
Frantz Renovation and Addition
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Frances Gaudet/Lake Forest ES (RSD) 12000 Hayne Boulevard, New Orleans, LA 70128 Scope of Work: Roof Repairs Funding Source - FEMA Architect - HMS Architects, LLC Contractor - Chatmon Construction, LLC
Schedule Phase
Forecast Start
Forecast Finish
Gaudet/Lake Forest ES (Roof)
Plan Start
Plan Finish
Design
10/25/2010
08/31/2011
02/01/2010
12/11/2010
Procurement
09/01/2011
01/08/2012
12/12/2010
03/01/2011
Construction
01/09/2012
05/08/2012
03/02/2011
06/30/2012
Final Completion
05/09/2012
06/22/2012
07/01/2012
08/14/2012
Cost Description
2010
2011
2012
2013
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$378,307 $0 $37,967 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $522 $0
$378,307 $0 $37,967 $0 $0 $0 $0 $0 $522 $0
$281,730 $0 $37,967 $0 $0 $0 $0 $0 $528 $0
$281,370 $0 $22,780 $0 $0 $0 $0 $0 $273 $0
$96,577 $0 $0 $0 $0 $0 $0 $0 $0 $0
$378,307 $0 $37,967 $0 $0 $0 $0 $0 $528 $0
$0 $0 $0 $0 $0 $0 $0 $0 $6 $0
Totals:
$416,274
$522
$416,796
$320,225
$304,423
$96,577
$416,802
$6
$450,000 $405,000 $360,000 $315,000 $270,000 $225,000 $180,000 $135,000 $90,000 $45,000 $0
Project Update: - Substantial Completion documentation is being processed.
Project Budget
Gaudet/Lake Forest ES (Roof)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
William J. Guste Elementary School (RSD) 2625 Thalia Street, New Orleans, LA 70113 Scope of Work - Replace Roof & Install Elevator Funding Source - FEMA Architect - Richard C. Lambert Consultants, LLC Contractor - CAMCO, LLC
Schedule Phase
Forecast Start
Forecast Finish
Guste ES (New Roof and Elevator)
Plan Start
Plan Finish
Design
01/03/2011
05/27/2011
01/03/2011
05/27/2011
Procurement
05/28/2011
09/21/2011
05/28/2011
09/04/2011
Construction
09/22/2011
06/12/2012
09/05/2011
03/06/2012
Final Completion
06/13/2012
07/27/2012
03/07/2012
06/04/2012
Cost Description
2011
2012
2013
2014
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$745,000 $0 $70,624 $0 $0 $0 $0 $0 $0 $0
$360,000 $0 $24,854 $0 $0 $0 $0 $0 $524 $0
$1,105,000 $0 $95,478 $0 $0 $0 $0 $0 $524 $0
$1,105,000 $0 $95,478 $0 $0 $0 $0 $0 $524 $0
$1,014,644 $0 $87,119 $0 $0 $0 $0 $0 $524 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$1,105,000 $0 $95,478 $0 $0 $0 $0 $0 $524 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$815,624
$385,378
$1,201,002
$1,201,002
$1,102,287
$0
$1,201,002
$0
$1,400,000 $1,260,000 $1,120,000 $980,000 $840,000 $700,000 $560,000 $420,000 $280,000 $140,000 $0
Project Update: - Project is substantially complete - June 12th
Project Budget
Guste ES (New Roof and Elevator)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Oretha C. Haley Elementary School (RSD) 2515 N. Robertson Street, New Orleans, LA 70117 Scope of Work: Stabilize and Secure the Building Funding Source - FEMA Architect - VergesRome Architects, APAC Contractor - CDW Services, LLC
Schedule Phase
Forecast Start
Forecast Finish
Haley (Mothballing)
Plan Start
Plan Finish
Design
08/08/2011
02/01/2012
08/08/2011
09/16/2011
Procurement
02/02/2012
05/23/2012
09/17/2011
12/25/2011
Construction
05/24/2012
09/20/2012
12/26/2011
04/23/2012
Final Completion
09/21/2012
11/04/2012
04/24/2012
06/07/2012
Cost Description
2011
2012
2013
2014
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$250,000 $0 $26,023 $0 $0 $0 $0 $0 $0 $0
$261,778 $0 $17,565 $12,100 $0 $0 $0 $0 $532 $0
$511,778 $0 $43,588 $12,100 $0 $0 $0 $0 $532 $0
$511,778 $0 $43,588 $12,100 $0 $0 $0 $0 $532 $0
$511,778 $0 $37,486 $12,100 $0 $0 $0 $0 $532 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$511,778 $0 $43,588 $12,100 $0 $0 $0 $0 $532 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$276,023
$291,975
$567,998
$567,998
$561,896
$0
$567,998
$0
$600,000 $540,000 $480,000 $420,000 $360,000 $300,000 $240,000 $180,000 $120,000 $60,000 $0
Project Update: - Punchlist is ongoing
Project Budget
Haley (Mothballing)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Lorraine Hansberry Elementary School (RSD) 1339 Clouet Street, New Orleans, LA 70117 Scope of Work: Stabilize and Secure the Building Funding Source - FEMA Architect - VergesRome Architects, APAC Contractor -Tuna Const. LLC
Schedule Phase
Forecast Start
Forecast Finish
Hansberry (Mothballing)
Plan Start
Plan Finish
Design
08/08/2011
03/22/2012
08/08/2011
09/16/2011
Procurement
03/23/2012
06/01/2012
09/17/2011
12/25/2011
Construction
06/02/2012
11/13/2012
12/26/2011
04/23/2012
Final Completion
11/14/2012
12/28/2012
04/24/2012
06/07/2012
Cost Description
2011
2012
2013
2014
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$250,000 $0 $26,023 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $13,200 $0 $0 $0 $0 $0 $0
$250,000 $0 $26,023 $13,200 $0 $0 $0 $0 $0 $0
$592,560 $0 $48,548 $13,200 $0 $0 $0 $0 $531 $0
$192,143 $0 $38,838 $13,200 $0 $0 $0 $0 $275 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$592,560 $0 $48,548 $13,200 $0 $0 $0 $0 $531 $0
$342,560 $0 $22,525 $0 $0 $0 $0 $0 $531 $0
Totals:
$276,023
$13,200
$289,223
$654,839
$244,456
$0
$654,839
$365,616
$700,000 $630,000 $560,000 $490,000 $420,000 $350,000 $280,000 $210,000 $140,000 $70,000 $0
Project Update: - Metal panels over exterior windows is 75% complete
Project Budget
Hansberry (Mothballing)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Andrew Jackson School (RSD) 1400 Camp Street, New Orleans, LA 70130 Scope of Work: Install Solar Panels Funding Source - Greater N.O. Foundation/ Entergy Architect - Perez, APC Contractor - South Coast Solar, LLC
Schedule Phase
Forecast Start
Forecast Finish
Jackson K-8 Solar Panels
Plan Start
Plan Finish
Design
01/18/2012
05/09/2012
02/21/2011
07/21/2011
Procurement
05/10/2012
09/16/2012
07/22/2011
10/29/2011
Construction
09/17/2012
01/14/2013
10/30/2011
04/26/2012
Final Completion
01/15/2013
02/28/2013
04/27/2012
06/10/2012
Cost Description
2011
2012
2013
2014
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Owner Costs Misc
$215,000 $0 $22,578 $0 $0 $0 $12,422 $0 $0 $0
$0 $0 $0 $0 $0 $0 ($526) $0 $0 $526
$215,000 $0 $22,578 $0 $0 $0 $11,896 $0 $0 $526
$145,180 $0 $22,578 $0 $0 $0 $0 $0 $0 $526
$0 $0 $12,418 $0 $0 $0 $0 $0 $0 $526
$69,820 $0 ($6,765) $0 $0 $0 $11,896 $0 $0 $0
$215,000 $0 $15,813 $0 $0 $0 $11,896 $0 $0 $526
$0 $0 ($6,765) $0 $0 $0 $0 $0 $0 $0
Totals:
$250,000
$0
$250,000
$168,284
$12,944
$74,951
$243,235
($6,765)
$270,000 $243,000 $216,000 $189,000 $162,000 $135,000 $108,000 $81,000 $54,000 $27,000 $0
Project Update: - Bid Opening - June 26th - Notice to Proceed issued on September 17th - Lead time of solar panels has extended the schedule by a month
Project Budget
Jackson K-8 Solar Panels
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Morris F. X. Jeff Elementary School (RSD) 800 North Rendon St., New Orleans, LA 70119 Scope of Work: Stabilize and Secure the Building Funding Source - FEMA Architect - VergesRome Architects, APAC Contractor - CDW Services, LLC
Schedule Phase
Forecast Start
Forecast Finish
Jeff (Mothballing)
Plan Start
Plan Finish
Design
10/05/2011
05/21/2012
10/05/2011
10/20/2011
Procurement
05/22/2012
08/31/2012
10/21/2011
01/28/2012
Construction
09/01/2012
12/29/2012
01/29/2012
05/27/2012
Final Completion
12/30/2012
02/12/2013
05/28/2012
07/11/2012
Cost Description
2011
2012
2013
2014
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Project Budget
Estimated Estimated Budget Adjustments
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$250,000 $0 $26,023 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $11,220 $0 $0 $0 $0 $0 $0
$250,000 $0 $26,023 $11,220 $0 $0 $0 $0 $0 $0
$291,622 $0 $25,834 $11,220 $0 $0 $0 $0 $0 $0
$128,372 $0 $16,915 $11,220 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$291,622 $0 $25,834 $11,220 $0 $0 $0 $0 $0 $0
$41,622 $0 ($189) $0 $0 $0 $0 $0 $0 $0
Totals:
$276,023
$11,220
$287,243
$328,676
$156,507
$0
$328,676
$41,433
$360,000 $324,000 $288,000 $252,000 $216,000 $180,000 $144,000 $108,000 $72,000 $36,000 $0
Project Update: - Notice to Proceed was issued September 12th - Project is 10% complete
Project Budget
Jeff (Mothballing)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
John McDonogh High School (RSD) 2426 Esplanade Avenue, New Orleans, LA 70119 Scope of Work - Replacement of Bleachers Funding Source - Harrah's Architect - Trapolin Peer Architects, LLC Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
John McDonogh HS (Bleachers)
Plan Start
Plan Finish
Design
09/26/2011
10/15/2012
01/11/2011
05/10/2011
Procurement
10/16/2012
01/23/2013
05/11/2011
08/18/2011
Construction
01/24/2013
08/01/2013
08/19/2011
12/31/2011
Final Completion
08/02/2013
09/15/2013
01/01/2012
02/14/2012
Cost Description
2011
2012
2013
2014
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Misc
$112,500 $0 $11,823 $0 $0 $0 $0 $0 $522 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$112,500 $0 $11,823 $0 $0 $0 $0 $0 $522 $0
$0 $0 $60,556 $0 $0 $0 $0 $0 $0 $550
$0 $0 $6,029 $0 $0 $0 $0 $0 $0 $550
$112,500 $0 $0 $0 $0 $0 $0 $0 $522 $0
$112,500 $0 $60,556 $0 $0 $0 $0 $0 $522 $550
$0 $0 $48,733 $0 $0 $0 $0 $0 $0 $550
Totals:
$124,844
$0
$124,844
$61,106
$6,579
$113,022
$174,128
$49,283
$180,000 $162,000 $144,000 $126,000 $108,000 $90,000 $72,000 $54,000 $36,000 $18,000 $0
Comments - The State Fire Marshal confirmed that with the addition of the new bleachers, a fire sprinkler system will be required in the gymnasium - New bleachers and a new fire sprinkler system will be installed in the gymnasium - Design is expected to be completed in December
Project Budget
John McDonogh HS (Bleachers)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Valena C. Jones Elementary School (RSD) 1901 N. Galvez Street, New Orleans, LA 70119 Scope of Work: Stabilize and Secure the Building Funding Source - FEMA Architect - VergesRome Architects, APAC Contractor - C.D.W. Services, LLC
Schedule Phase
Forecast Start
Forecast Finish
Jones (Mothballing)
Plan Start
Plan Finish
Design
11/04/2011
05/21/2012
11/04/2011
11/18/2011
Procurement
05/22/2012
08/30/2012
11/19/2011
02/26/2012
Construction
08/31/2012
12/28/2012
02/27/2012
06/25/2012
Final Completion
12/29/2012
02/11/2013
06/26/2012
08/09/2012
Cost Description
2011
2012
2013
2014
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$250,000 $0 $26,023 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $12,430 $0 $0 $0 $0 $0 $0
$250,000 $0 $26,023 $12,430 $0 $0 $0 $0 $0 $0
$826,979 $0 $64,684 $12,430 $0 $0 $0 $0 $0 $0
$306,129 $0 $16,915 $12,430 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$826,979 $0 $64,684 $12,430 $0 $0 $0 $0 $0 $0
$576,979 $0 $38,661 $0 $0 $0 $0 $0 $0 $0
Totals:
$276,023
$12,430
$288,453
$904,093
$335,474
$0
$904,093
$615,640
$1,000,000 $900,000 $800,000 $700,000 $600,000 $500,000 $400,000 $300,000 $200,000 $100,000 $0
Project Update: - Notice to Proceed was issued on September 12th - Project is 10% complete
Project Budget
Jones (Mothballing)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Thomy Lafon School Display (RSD) 2601 Seventh St., New Orleans 70115 Scope of Work: Interpretive Display & Sculpture Funding Source - FEMA Architects: Mahlum/Scairono Martinez Contractor: TBD
Schedule Phase
Forecast Start
Forecast Finish
Lafon Interpretive Display
Plan Start
Plan Finish
Design
03/13/2012
06/19/2012
03/13/2012
06/19/2012
Procurement
06/20/2012
01/08/2013
06/20/2012
09/17/2012
Construction
01/09/2013
04/08/2013
09/18/2012
01/15/2013
Final Completion
04/08/2013
04/17/2013
01/15/2013
01/24/2013
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$50,000 $0 $7,571 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$50,000 $0 $7,571 $0 $0 $0 $0 $0 $0 $0
$0 $0 $7,571 $0 $0 $0 $0 $0 $549 $0
$0 $0 $4,543 $0 $0 $0 $0 $0 $549 $0
$50,000 $0 $0 $0 $0 $0 $0 $0 $0 $0
$50,000 $0 $7,571 $0 $0 $0 $0 $0 $549 $0
$0 $0 $0 $0 $0 $0 $0 $0 $549 $0
Totals:
$57,571
$0
$57,571
$8,120
$5,092
$50,000
$58,120
$549
$60,000 $54,000 $48,000 $42,000 $36,000 $30,000 $24,000 $18,000 $12,000 $6,000 $0
Project Update: - Bids received in September were not accepted - 1st Advertisement scheduled for October 31st - Bid Opening will be December 5th
Project Budget
Lafon Interpretive Display
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Langston Hughes School (RSD) 3519 Trafalgar St, New Orleans, LA 70119 Scope of Work: Remove Dumpster Pad, Replace Fence Funding Source: FEMA Architects: Lachin Oubre & Associates Contractor: Tuna Construction LLC
Schedule Phase
Forecast Start
Forecast Finish
Langston Hughes - Dumpster Pad
Plan Start
Plan Finish
Design
01/12/2012
02/10/2012
01/12/2012
02/10/2012
Procurement
02/11/2012
06/25/2012
02/11/2012
05/10/2012
Construction
06/26/2012
10/08/2012
05/11/2012
08/08/2012
Final Completion
10/09/2012
11/22/2012
08/09/2012
09/22/2012
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$85,000 $0 $6,000 $0 $0 $0 $0 $0 $522 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$85,000 $0 $6,000 $0 $0 $0 $0 $0 $522 $0
$42,500 $0 $6,000 $0 $0 $0 $0 $0 $531 $0
$42,500 $0 $0 $0 $0 $0 $0 $0 $275 $0
$40,262 $0 $0 $0 $0 $0 $0 $0 $0 $0
$82,762 $0 $6,000 $0 $0 $0 $0 $0 $531 $0
($2,238) $0 $0 $0 $0 $0 $0 $0 $9 $0
Totals:
$91,522
$0
$91,522
$49,031
$42,775
$40,262
$89,292
($2,230)
$100,000 $90,000 $80,000 $70,000 $60,000 $50,000 $40,000 $30,000 $20,000 $10,000 $0
Project Update: - 95% of contractual items are complete - Project completion will be extended due to the lead-time of a new classroom door - Forecasted Substantial Completion - October 2012
Project Budget
Langston Hughes - Dumpster Pad
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Alfred Lawless School (RSD) 5300 Law Street, New Orleans, LA 70117 Scope of Work: New High School Funding Source - FEMA Architect - Sizeler Thompson Brown Architects Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
Lawless HS - New
Plan Start
Plan Finish
Design
05/23/2012
05/24/2013
05/23/2012
05/20/2013
Procurement
04/06/2013
07/16/2013
04/02/2013
07/12/2013
Construction
07/17/2013
03/17/2015
07/13/2013
03/13/2015
Final Completion
03/17/2015
06/14/2015
03/13/2015
06/10/2015
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Project Budget
Estimated Estimated Budget Adjustments
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$27,200,000 $0 $1,981,345 $20,900 $0 $0 $2,946,052 $28,270 $230,000 $0
$0 $0 $0 $0 $0 $0 ($117,908) $0 $117,908 $0
$27,200,000 $0 $1,981,345 $20,900 $0 $0 $2,828,144 $28,270 $347,908 $0
$0 $0 $1,981,345 $21,120 $0 $0 $0 $18,689 $347,908 $0
$0 $0 $297,202 $0 $0 $0 $0 $0 $0 $0
$27,200,000 $0 $0 $2,530 $0 $0 $2,828,144 $20,581 $0 $0
$27,200,000 $0 $1,981,345 $23,650 $0 $0 $2,828,144 $39,270 $347,908 $0
$0 $0 $0 $2,750 $0 $0 $0 $11,000 $0 $0
Totals:
$32,406,567
$0
$32,406,567
$2,369,062
$297,202
$30,051,255
$32,420,317
$13,750
$36,000,000 $32,400,000 $28,800,000 $25,200,000 $21,600,000 $18,000,000 $14,400,000 $10,800,000 $7,200,000 $3,600,000 $0
Project Update: - Schematic Design documents were received on August 23rd - Community Meeting postponed, will be rescheduled at a later date - Design Development documents are due on November 13th
Project Budget
Lawless HS - New
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
L.B. Landry Annex Building Demolition (RSD) 1100 Wagner Street, New Orleans, LA 70114 Scope of Work: Demolition of the Annex Building Funding Source - FEMA Architect - Perez Architects Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
LB Landry HS Annex - Demo
Plan Start
Plan Finish
Design
04/23/2012
06/23/2012
05/15/2012
06/13/2012
Procurement
06/24/2012
09/27/2012
06/14/2012
09/21/2012
Construction
09/28/2012
01/26/2013
09/22/2012
12/20/2012
Final Completion
01/27/2013
03/12/2013
12/21/2012
02/03/2013
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$0 $163,925 $17,651 $5,335 $0 $0 $0 $3,548 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $529 $0
$0 $163,925 $17,651 $5,335 $0 $0 $0 $3,548 $529 $0
$0 $0 $17,651 $5,335 $0 $0 $0 $3,548 $529 $0
$0 $0 $11,473 $5,335 $0 $0 $0 $3,548 $529 $0
$0 $163,925 $0 $0 $0 $0 $0 $0 $0 $0
$0 $163,925 $17,651 $5,335 $0 $0 $0 $3,548 $529 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$190,458
$529
$190,987
$27,062
$20,885
$163,925
$190,987
$0
$200,000 $180,000 $160,000 $140,000 $120,000 $100,000 $80,000 $60,000 $40,000 $20,000 $0
Comments - Bid Opening - August 14th - Contractor was non-responsive, and the Owner is going to award the contract to the lowest responsive bidder
Project Budget
LB Landry HS Annex - Demo
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Little Woods School (RSD) 10200 Curran Blvd., New Orleans, LA 70127 Scope of Work: New Pre-K - 8 School Funding Source - FEMA Architect - Group Novak, LLC Contractor - MAPP Construction
Schedule Phase
Forecast Start
Forecast Finish
Little Woods (New Construction)
Plan Start
Plan Finish
Design
05/12/2010
03/04/2011
04/05/2010
02/18/2011
Procurement
03/13/2011
07/11/2011
02/19/2011
05/09/2011
Construction
07/11/2011
04/05/2013
05/10/2011
09/10/2012
Final Completion
04/05/2013
07/04/2013
09/11/2012
12/09/2012
Cost Description
2010
2011
2012
2013
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$21,980,000 $0 $1,667,791 $20,900 $0 $0 $1,198,080 $70,170 $222,742 $0
$0 $0 $8,426 $0 $0 $0 ($12,116) $0 $3,690 $0
$21,980,000 $0 $1,676,217 $20,900 $0 $0 $1,185,964 $70,170 $226,432 $0
$21,980,000 $0 $1,645,504 $10,120 $0 $0 $0 $55,870 $226,432 $0
$14,170,822 $0 $1,431,727 $10,120 $0 $0 $0 $54,009 $121,441 $0
$90,496 $0 $30,713 $10,780 $0 $0 $1,185,964 $14,300 $0 $0
$22,070,496 $0 $1,676,217 $20,900 $0 $0 $1,185,964 $70,170 $226,432 $0
$90,496 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$25,159,683
$0
$25,159,683
$23,917,926
$15,788,119
$1,332,253
$25,250,179
$90,496
$27,000,000 $24,300,000 $21,600,000 $18,900,000 $16,200,000 $13,500,000 $10,800,000 $8,100,000 $5,400,000 $2,700,000 $0
Project Update: - CMU installation is complete in all areas - Installing brick veneer on interior of 1st floor and exterior of gymnasium is ongoing - Fireproofing is complete in all areas - Window and glass installation is 90% complete - Sprinkler piping is complete on 3rd floor and 80% complete on the 1st and 2nd floors - Interior metal stud framing is 95% complete - Installation of gypsum board has started - Pulling and terminating wire into panel boxes is ongoing throughout the building - Roof deck, insulation and roof membrane is complete
Project Budget
Little Woods (New Construction)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Edward Livingston High School (RSD) 7301 Dwyer Road, New Orleans, LA 70126 Scope of Work: New High School Funding Source - FEMA Architect - Rozas-Ward Architects Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
Livingston HS - New
Plan Start
Plan Finish
Design
02/13/2012
01/18/2013
01/01/2012
01/01/2013
Procurement
11/28/2012
03/15/2013
11/10/2012
02/17/2013
Construction
03/15/2013
07/15/2014
02/18/2013
06/20/2014
Final Completion
07/15/2014
10/12/2014
06/20/2014
09/17/2014
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$19,700,000 $0 $1,058,411 $20,900 $0 $0 $2,535,736 $28,270 $300,000 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$19,700,000 $0 $1,058,411 $20,900 $0 $0 $2,535,736 $28,270 $300,000 $0
$0 $0 $1,058,411 $5,390 $0 $0 $0 $0 $283,234 $0
$0 $0 $252,700 $5,390 $0 $0 $0 $0 $18,867 $0
$19,700,000 $0 $0 $15,510 $0 $0 $2,535,736 $28,270 $16,766 $0
$19,700,000 $0 $1,058,411 $20,900 $0 $0 $2,535,736 $28,270 $300,000 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$23,643,317
$0
$23,643,317
$1,347,035
$276,958
$22,296,282
$23,643,317
$0
$24,000,000 $21,600,000 $19,200,000 $16,800,000 $14,400,000 $12,000,000 $9,600,000 $7,200,000 $4,800,000 $2,400,000 $0
Project Update: - 50% Construction Documents were received on August 28th - 100% Construction Documents are due on November 9th pending approval of owner-requested changes
Project Budget
Livingston HS - New
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Dr. Martin Luther King Jr.School (RSD) 1617 Caffin Avenue, New Orleans, LA 70117 Scope of Work: Modular Building, Deck and Canopy Funding Source - Harrah's Architect - Perez, APC Contractor - T&D Contractors, LLC
Schedule Phase
Forecast Start
Forecast Finish
Martin L. King ES - Modular Buillding
Plan Start
Plan Finish
Design
08/15/2011
01/01/2012
08/15/2011
01/01/2012
Procurement
01/02/2012
05/14/2012
01/02/2012
04/16/2012
Construction
05/15/2012
08/02/2012
04/17/2012
08/14/2012
Final Completion
08/02/2012
08/02/2012
08/15/2012
09/28/2012
Cost Description
2011
2012
2013
2014
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$125,967 $0 $13,973 $0 $0 $0 $18,895 $0 $0 $0
$16,910 $0 $1,460 $0 $0 $0 ($18,895) $0 $526 $0
$142,877 $0 $15,433 $0 $0 $0 $0 $0 $526 $0
$144,857 $0 $17,042 $0 $0 $0 $0 $0 $526 $0
$144,857 $0 $14,315 $0 $0 $0 $0 $0 $526 $0
$706 $0 $0 $0 $0 $0 $0 $0 $0 $0
$145,563 $0 $17,042 $0 $0 $0 $0 $0 $526 $0
$2,687 $0 $1,609 $0 $0 $0 $0 $0 $0 $0
Totals:
$158,835
$0
$158,835
$162,424
$159,698
$706
$163,131
$4,296
$180,000 $162,000 $144,000 $126,000 $108,000 $90,000 $72,000 $54,000 $36,000 $18,000 $0
Project Update: - Project Completed in August, 2012
Project Budget
Martin L. King ES - Modular Buillding
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
McDonogh #15 Elementary School (RSD) 721 St. Phillip Street, New Orleans, LA 70117 Scope of Work: Masonry Repairs According to SOI Funding Source - FEMA Architect - VergesRome Architects, APAC Contractor - Hamp's Construction LLC
Schedule Phase
Forecast Start
Forecast Finish
McDonogh 15 ES - Masonry Repair
Plan Start
Plan Finish
Design
09/29/2010
06/29/2011
09/29/2010
06/29/2011
Procurement
06/30/2011
02/27/2012
06/30/2011
10/07/2011
Construction
02/28/2012
06/11/2012
10/08/2011
02/19/2012
Final Completion
06/12/2012
07/23/2012
02/20/2012
04/04/2012
Cost Description
2010
2011
2012
2013
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Owner Costs Misc
$216,319 $0 $23,245 $0 $0 $0 $0 $0 $0 $542
($39,419) $0 ($3,882) $0 $0 $0 $40,689 $2,613 $0 $0
$176,900 $0 $19,363 $0 $0 $0 $40,689 $2,613 $0 $542
$180,830 $0 $19,363 $0 $0 $0 $0 $2,613 $0 $542
$128,998 $0 $16,826 $0 $0 $0 $0 $2,613 $0 $542
$0 $0 $0 $0 $0 $0 $40,689 $0 $0 $0
$180,830 $0 $19,363 $0 $0 $0 $40,689 $2,613 $0 $542
$3,930 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$240,106
$0
$240,106
$203,348
$148,979
$40,688
$244,036
$3,930
$270,000 $243,000 $216,000 $189,000 $162,000 $135,000 $108,000 $81,000 $54,000 $27,000 $0
Project Update: - Project is substantially complete
Project Budget
McDonogh 15 ES - Masonry Repair
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
McDonogh 32 Roof Replacement (RSD) 800 De Armas Street, New Orleans, 70114 Scope of Work: Replace Roof Funding Source - FEMA Architect - Richard C. Lambert
Schedule Phase
Forecast Start
Forecast Finish
McDonogh 32 (Roof)
Plan Start
Plan Finish
Design
07/16/2010
05/09/2011
07/16/2010
05/09/2011
Procurement
05/10/2011
09/22/2011
05/10/2011
08/17/2011
Construction
09/23/2011
04/25/2012
08/18/2011
12/30/2011
Final Completion
02/18/2012
07/06/2012
12/31/2011
02/13/2012
Cost Description General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous Totals:
2010
2011
2012
2013
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
$82,553 $0 $39,031 $0 $0 $0 $0 $0 $0 $0
$335,047 $0 $2,524 $0 $0 $0 $0 $0 $526 $0
$417,600 $0 $41,555 $0 $0 $0 $0 $0 $526 $0
$417,600 $0 $41,555 $0 $0 $0 $0 $0 $526 $0
$407,517 $0 $38,854 $0 $0 $0 $0 $0 $526 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$417,600 $0 $41,555 $0 $0 $0 $0 $0 $526 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$121,584
$338,096
$459,680
$459,680
$446,896
$0
$459,680
$0
$500,000 $450,000 $400,000 $350,000 $300,000 $250,000 $200,000 $150,000 $100,000 $50,000 $0
Project Update: - Project is substantially complete. - Final Completion delayed to permit communication wiring switchover after LEAP testing.
Project Budget
McDonogh 32 (Roof)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
McDonogh 42 Elementary School (RSD) 1651 North Tonti Street, New Orleans, LA 70119 Scope of Work: Renovation & Addition to School Funding Source: FEMA Architect - Eskew+Dumez+Ripple Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
McDonogh 42 ES - Reno
Plan Start
Plan Finish
Design
06/04/2012
06/01/2013
06/04/2012
06/01/2013
Procurement
04/14/2013
07/29/2013
04/14/2013
07/29/2013
Construction
07/30/2013
01/29/2015
07/30/2013
01/29/2015
Final Completion
01/30/2015
04/29/2015
01/30/2015
04/29/2015
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$14,461,875 $0 $1,371,659 $20,900 $0 $0 $2,036,919 $29,770 $230,000 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$14,461,875 $0 $1,371,659 $20,900 $0 $0 $2,036,919 $29,770 $230,000 $0
$0 $0 $1,371,659 $0 $0 $0 $0 $0 $204,763 $0
$0 $0 $205,749 $0 $0 $0 $0 $0 $0 $0
$14,461,875 $0 $0 $20,900 $0 $0 $2,036,919 $37,250 $25,237 $0
$14,461,875 $0 $1,371,659 $20,900 $0 $0 $2,036,919 $37,250 $230,000 $0
$0 $0 $0 $0 $0 $0 $0 $7,480 $0 $0
Totals:
$18,151,123
$0
$18,151,123
$1,576,422
$205,749
$16,582,181
$18,158,603
$7,480
$20,000,000 $18,000,000 $16,000,000 $14,000,000 $12,000,000 $10,000,000 $8,000,000 $6,000,000 $4,000,000 $2,000,000 $0
Program Update: - Schematic Design Documents were received on September 14th - Design Development Documents are anticipated December 13th
Project Budget
McDonogh 42 ES - Reno
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
George Mondy Elementary School (RSD) 2327 St. Phillip Street, New Orleans, LA 70119 Scope of Work: Stabilize and Secure the Building Funding Source - FEMA Architect - VergesRome Architects, APAC Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
Mondy (Mothballing)
Plan Start
Plan Finish
Design
10/25/2011
07/10/2012
09/06/2011
09/19/2011
Procurement
08/15/2012
11/22/2012
09/20/2011
12/28/2011
Construction
11/23/2012
03/22/2013
12/29/2011
04/26/2012
Final Completion
03/23/2013
05/06/2013
04/27/2012
06/10/2012
Cost Description
2011
2012
2013
2014
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$250,000 $0 $26,023 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $11,220 $0 $0 $0 $0 $0 $0
$250,000 $0 $26,023 $11,220 $0 $0 $0 $0 $0 $0
$48,677 $0 $26,023 $11,220 $0 $0 $0 $0 $275 $0
$48,677 $0 $15,614 $11,220 $0 $0 $0 $0 $275 $0
$201,323 $0 $0 $0 $0 $0 $0 $0 $0 $0
$250,000 $0 $26,023 $11,220 $0 $0 $0 $0 $275 $0
$0 $0 $0 $0 $0 $0 $0 $0 $275 $0
Totals:
$276,023
$11,220
$287,243
$86,195
$75,786
$201,323
$287,518
$275
$300,000 $270,000 $240,000 $210,000 $180,000 $150,000 $120,000 $90,000 $60,000 $30,000 $0
Project Update: - Bid Opening - October 30th - Notice to Proceed is anticipated the end of November
Project Budget
Mondy (Mothballing)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
N.O. East at Abramson High School (RSD) 7301 Dwyer Road, New Orleans, LA 70126 Scope of Work: New High School Funding Source - FEMA Architect - Rozas-Ward Architects Contractor- TBD
Schedule Phase
Forecast Start
Forecast Finish
NO East HS @Abramson - New
Plan Start
Plan Finish
Design
06/25/2012
01/10/2013
06/25/2012
01/10/2013
Procurement
11/22/2012
03/01/2013
11/22/2012
03/01/2013
Construction
03/02/2013
07/02/2014
03/02/2013
07/02/2014
Final Completion
07/03/2014
09/30/2014
07/03/2014
09/30/2014
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Other Professional Services Other Costs Program Contingency Misc
$20,000,000 $0 $1,485,786 $20,900 $0 $0 $28,270 $230,000 $1,688,762 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$20,000,000 $0 $1,485,786 $20,900 $0 $0 $28,270 $230,000 $1,688,762 $0
$0 $0 $1,057,922 $1,980 $0 $0 $9,900 $236,206 $0 $22,550
$0 $0 $254,570 $1,980 $0 $0 $9,900 $0 $0 $22,550
$20,000,000 $0 $429,734 $18,920 $0 $0 $18,700 $0 $1,688,762 $0
$20,000,000 $0 $1,487,656 $20,900 $0 $0 $28,600 $236,206 $1,688,762 $22,550
$0 $0 $1,870 $0 $0 $0 $330 $6,206 $0 $22,550
Totals:
$23,453,718
$0
$23,453,718
$1,328,558
$289,000
$22,156,116
$23,484,674
$30,956
$24,000,000 $21,600,000 $19,200,000 $16,800,000 $14,400,000 $12,000,000 $9,600,000 $7,200,000 $4,800,000 $2,400,000 $0
Comments - Design will follow Edward Livingston High School.
Project Budget
NO East HS @Abramson - New
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Mildred Osborne School (RSD) 6701 Curran Blvd., New Orleans, LA 70126 Scope of Work: New Pre-K - 8 School Funding Source - FEMA Architect - Fauntleroy & Latham Contractor - F.H. Paschen, S.N. Nielsen
Schedule Phase
Forecast Start
Forecast Finish
Osborne (New Construction)
Plan Start
Plan Finish
Design
06/01/2009
04/27/2010
06/01/2009
01/24/2010
Procurement
04/22/2010
09/02/2010
01/23/2010
04/15/2010
Construction
09/03/2010
11/16/2012
09/03/2010
01/02/2012
Final Completion
11/17/2012
12/31/2012
01/03/2012
02/16/2012
Cost Description
2009
2010
2011
2012
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$21,375,000 $0 $1,623,972 $20,900 $0 $0 $1,164,162 $57,730 $205,639 $0
($391,733) $0 $184,315 $0 $0 $380 $204,492 $1,529 $1,018 $0
$20,983,267 $0 $1,808,287 $20,900 $0 $380 $1,368,654 $59,259 $206,657 $0
$21,447,118 $0 $1,808,286 $11,605 $0 $380 $0 $31,759 $206,657 $0
$18,532,812 $0 $1,471,361 $11,605 $0 $380 $0 $31,759 $156,349 $0
($463,851) $0 $0 $9,295 $0 $0 $1,368,653 $27,500 $0 $0
$20,983,267 $0 $1,808,286 $20,900 $0 $380 $1,368,653 $59,259 $206,657 $0
$0 $0 $0 $0 $0 $0 ($1) $0 $0 $0
Totals:
$24,447,403
$0
$24,447,403
$23,505,805
$20,204,266
$941,597
$24,447,402
($1)
$27,000,000 $24,300,000 $21,600,000 $18,900,000 $16,200,000 $13,500,000 $10,800,000 $8,100,000 $5,400,000 $2,700,000 $0
Project Update: - Finish trades are working in the gymnasium - Landscaping is nearly complete and the fencing is ongoing - Media Center and Music Room are 85% complete - Library is 90% complete - Gymnasium is 80% complete - School was Occupied August, 2012
Project Budget
Osborne (New Construction)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Parkview School (RSD) 4617 Mirabeau Avenue, New Orleans, LA 70126 Scope of Work: New Pre-K- 8 School Funding Source - FEMA Architect - Rozas-Ward Contractor - Citadel Builders, LLC
Schedule Phase
Forecast Start
Forecast Finish
Parkview (New Construction)
Plan Start
Plan Finish
Design
05/22/2009
04/26/2010
05/22/2009
01/19/2010
Procurement
04/27/2010
09/03/2011
01/20/2010
04/12/2010
Construction
11/10/2010
08/02/2012
08/06/2011
09/19/2011
Final Completion
08/03/2012
10/01/2012
09/19/2011
12/20/2011
Cost Description
2009
2010
2011
2012
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$17,852,348 $0 $1,336,822 $0 $0 $0 $492,030 $0 $118,800 $0
$3,933,762 $0 $283,679 $19,344 $0 $770 ($542,900) $83,145 $93,841 $0
$21,786,110 $0 $1,620,501 $19,344 $0 $770 ($50,870) $83,145 $212,641 $0
$21,524,490 $0 $1,620,501 $19,344 $0 $770 $0 $52,145 $212,640 $0
$21,508,010 $0 $1,516,262 $19,344 $0 $770 $0 $52,145 $164,798 $0
$261,620 $0 $0 $0 $0 $0 ($50,870) $31,000 $0 $0
$21,786,110 $0 $1,620,501 $19,344 $0 $770 ($50,870) $83,145 $212,640 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$19,800,000
$3,871,640
$23,671,640
$23,429,889
$23,261,328
$241,750
$23,671,639
$0
$24,000,000 $21,600,000 $19,200,000 $16,800,000 $14,400,000 $12,000,000 $9,600,000 $7,200,000 $4,800,000 $2,400,000 $0
Project Update: - Punch list is 90% complete - Owner requested addtional hardscape to the exterior of the building - Commissioning will begin in November - School was Occupied - 6 August 2012
Project Budget
Parkview (New Construction)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Dwight D. Eisenhower ES (RSD) Andrew Jackson ES (RSD) Paul B. Habans ES (RSD) Sylvanie F. Williams ES (RSD) Joseph S. Clark Senior High School (RSD) Scope of Work: Roof Repairs and Replacement
Schedule Phase
Forecast Start
Forecast Finish
Roof Repair-Various Sites (HMS)
Plan Start
Plan Finish
Design
11/10/2010
09/01/2011
10/10/2010
09/06/2011
Procurement
09/02/2011
03/18/2012
09/07/2011
12/07/2011
Construction
03/19/2012
07/06/2012
12/08/2011
03/06/2012
Final Completion
07/07/2012
11/15/2012
03/07/2012
04/20/2012
Cost Description
2010
2011
2012
2013
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$233,249 $0 $28,594 $0 $0 $0 $0 $0 $0 $0
($171,049) $0 ($11,594) $0 $0 $0 $182,049 $0 $594 $0
$62,200 $0 $17,000 $0 $0 $0 $182,049 $0 $594 $0
$62,200 $0 $17,000 $0 $0 $0 $0 $0 $594 $0
$6,000 $0 $0 $0 $0 $0 $0 $0 $594 $0
$0 $0 $0 $0 $0 $0 $182,049 $0 $0 $0
$62,200 $0 $17,000 $0 $0 $0 $182,049 $0 $594 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$261,843
$0
$261,843
$79,794
$6,594
$182,049
$261,843
$0
$270,000 $243,000 $216,000 $189,000 $162,000 $135,000 $108,000 $81,000 $54,000 $27,000 $0
Project Update: - Punch list will be complete November 2012
Project Budget
Roof Repair-Various Sites (HMS)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Dr. Martin Luther King School (RSD) Albert Wicker ES (RSD) A.P. Tureaud ES (RSD) Edgar P. Harney ES (RSD) Harriet R. Tubman ES (RSD) Scope of Work: Roof Repairs
Schedule Phase
Forecast Start
Roof Repair-Various Sites (RCL)
Forecast Finish
Plan Start
Plan Finish
Design
10/10/2010
08/23/2011
10/10/2010
10/10/2011
Procurement
08/24/2011
02/26/2012
10/11/2011
11/30/2011
Construction
02/27/2012
06/13/2012
12/01/2011
01/29/2012
Final Completion
06/14/2012
07/28/2012
01/30/2012
03/14/2012
Cost Description
2010
2011
2012
2013
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$251,390 $0 $30,859 $0 $0 $0 $0 $0 $0 $0
($145,690) $0 ($23,170) $0 $0 $0 $168,275 $0 $585 $0
$105,700 $0 $7,689 $0 $0 $0 $168,275 $0 $585 $0
$105,700 $0 $13,679 $0 $0 $0 $0 $0 $585 $0
$13,010 $0 $5,275 $0 $0 $0 $0 $0 $585 $0
$0 $0 $0 $0 $0 $0 $168,275 $0 $0 $0
$105,700 $0 $13,679 $0 $0 $0 $168,275 $0 $585 $0
$0 $0 $5,990 $0 $0 $0 $0 $0 $0 $0
Totals:
$282,249
$0
$282,249
$119,964
$18,870
$168,275
$288,239
$5,990
$300,000 $270,000 $240,000 $210,000 $180,000 $150,000 $120,000 $90,000 $60,000 $30,000 $0
Project Update: Funding Source - FEMA Architect - Richard C. Lambert Consultants, LLC Contractor - Hamp's Construction LLC - Project was substantially complete in July, 2012
Project Budget
Roof Repair-Various Sites (RCL)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
John A. Shaw Elementary School (RSD) 2518 Arts Street, New Orleans, LA 70117 Scope of Work: Stabilize and Secure the Building Funding Source - FEMA Architect - VergesRome Architects, APAC Contractor - Zimmer-Eschette Services
Schedule Phase
Forecast Start
Forecast Finish
Shaw (Mothballing)
Plan Start
Plan Finish
Design
08/08/2011
01/24/2012
08/08/2011
09/15/2011
Procurement
01/25/2012
05/03/2012
09/16/2011
12/24/2011
Construction
05/04/2012
09/30/2012
12/25/2011
04/22/2012
Final Completion
10/01/2012
11/14/2012
04/23/2012
06/06/2012
Cost Description
2011
2012
2013
2014
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$250,000 $0 $26,023 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $11,770 $0 $0 $0 $0 $0 $0
$250,000 $0 $26,023 $11,770 $0 $0 $0 $0 $0 $0
$631,204 $0 $48,090 $11,770 $0 $0 $0 $0 $527 $0
$493,254 $0 $39,049 $11,770 $0 $0 $0 $0 $527 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$631,204 $0 $48,090 $11,770 $0 $0 $0 $0 $527 $0
$381,204 $0 $22,067 $0 $0 $0 $0 $0 $527 $0
Totals:
$276,023
$11,770
$287,793
$691,591
$544,600
$0
$691,591
$403,798
$700,000 $630,000 $560,000 $490,000 $420,000 $350,000 $280,000 $210,000 $140,000 $70,000 $0
Project Update: - Metal panels over exterior windows is 65% complete
Project Budget
Shaw (Mothballing)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Sophie B Wright Middle School (RSD) 1426 Napoleon Avenue, New Orleans, LA 70115 Scope - Renovation of Existing School Funding Source - FEMA Architect - Waggonmer & Ball Architects Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
Sophie B Wright ES - Reno
Plan Start
Plan Finish
Design
06/18/2012
06/15/2013
06/18/2012
06/15/2013
Procurement
04/28/2013
08/06/2013
04/28/2013
08/12/2013
Construction
08/06/2013
04/06/2015
08/13/2013
02/12/2015
Final Completion
04/06/2015
07/04/2015
02/13/2015
05/13/2015
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$19,892,025 $0 $1,847,852 $20,900 $0 $0 $2,788,687 $35,970 $230,000 $0
$0 $0 $146,410 $6,831 $0 $0 ($153,241) $0 $0 $0
$19,892,025 $0 $1,994,262 $27,731 $0 $0 $2,635,446 $35,970 $230,000 $0
$0 $0 $1,847,676 $0 $0 $0 $0 $0 $212,572 $0
$0 $0 $277,151 $0 $0 $0 $0 $0 $0 $0
$19,892,025 $0 $146,586 $27,731 $0 $0 $2,635,446 $35,970 $17,428 $0
$19,892,025 $0 $1,994,262 $27,731 $0 $0 $2,635,446 $35,970 $230,000 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$24,815,434
$0
$24,815,434
$2,060,248
$277,151
$22,755,186
$24,815,434
$0
$27,000,000 $24,300,000 $21,600,000 $18,900,000 $16,200,000 $13,500,000 $10,800,000 $8,100,000 $5,400,000 $2,700,000 $0
Comments - Schematic Design Documents were delivered on September 24th - Community Meeting #1 is anticipated to be held on October 4th - Design Development Documents are anticipated December 7th
Project Budget
Sophie B Wright ES - Reno
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Sylvanie Williams Elementary School (RSD) 3127 Martin Luther King Jr., New Orleans, LA 70113 Scope of Work: AHU Replacement Funding Source - FEMA Architect - Integrated Management Servies Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
Sylvanie Williams AHU
Plan Start
Plan Finish
Design
02/20/2012
07/09/2012
06/07/2009
08/15/2009
Procurement
07/10/2012
10/24/2012
09/15/2009
11/16/2009
Construction
10/25/2012
04/02/2013
11/30/2009
03/01/2010
Final Completion
04/03/2013
05/17/2013
03/05/2010
03/08/2010
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$311,595 $0 $39,757 $0 $0 $0 $52,703 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$311,595 $0 $39,757 $0 $0 $0 $52,703 $0 $0 $0
$0 $0 $39,757 $0 $0 $0 $0 $0 $529 $0
$0 $0 $25,842 $0 $0 $0 $0 $0 $529 $0
$311,595 $0 $0 $0 $0 $0 $52,703 $0 $0 $0
$311,595 $0 $39,757 $0 $0 $0 $52,703 $0 $529 $0
$0 $0 $0 $0 $0 $0 $0 $0 $529 $0
Totals:
$404,055
$0
$404,055
$40,286
$26,371
$364,298
$404,584
$529
$450,000 $405,000 $360,000 $315,000 $270,000 $225,000 $180,000 $135,000 $90,000 $45,000 $0
Project Update: - Bid opening delayed 13 days due to Hurricane Isaac - Bid Opening - September 11th - Recommendation letter was sent out September 25th
Project Budget
Sylvanie Williams AHU
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Mary Church Terrell Elementary School (RSD) 3411 Broadway, New Orleans, LA 70125 Scope of Work: Demolition of School. Funding Source - FEMA Architect - SCNZ Architects Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
Terrell ES - Demo
Plan Start
Plan Finish
Design
04/09/2012
06/11/2012
04/09/2012
08/21/2012
Procurement
06/12/2012
09/13/2012
08/22/2012
11/29/2012
Construction
09/14/2012
12/08/2012
11/30/2012
02/27/2013
Final Completion
12/09/2012
01/22/2013
02/28/2013
04/13/2013
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Project Budget
Estimated Estimated Budget Adjustments
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$0 $270,000 $27,777 $0 $0 $0 $23,166 $0 $0 $0
$0 $0 $0 $15,796 $0 $0 ($23,166) $7,370 $0 $0
$0 $270,000 $27,777 $15,796 $0 $0 $0 $7,370 $0 $0
$0 $0 $27,777 $15,796 $0 $0 $0 $7,370 $527 $0
$0 $0 $18,055 $15,796 $0 $0 $0 $7,370 $527 $0
$0 $270,000 $0 $0 $0 $0 $0 $0 $0 $0
$0 $270,000 $27,777 $15,796 $0 $0 $0 $7,370 $527 $0
$0 $0 $0 $0 $0 $0 $0 $0 $527 $0
Totals:
$320,943
$0
$320,943
$51,470
$41,748
$270,000
$321,470
$527
$360,000 $324,000 $288,000 $252,000 $216,000 $180,000 $144,000 $108,000 $72,000 $36,000 $0
Project Update: - Bid Opening was July 31st - LDOE will issue a revised Notice of Intent to Award
Project Budget
Terrell ES - Demo
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Village de L'est Elementary School (RSD) 5100 Cannes St, New Orleans, LA 70129 Scope of Work: Replace Roof Funding Source - FEMA Architect - Richard C. Lambert Consultants, LLC Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
Village De L'est (Roof)
Plan Start
Plan Finish
Design
08/22/2011
10/25/2012
08/22/2011
09/29/2011
Procurement
10/26/2012
01/31/2013
09/30/2011
01/07/2012
Construction
02/01/2013
05/01/2013
01/08/2012
05/06/2012
Final Completion
05/02/2013
06/15/2013
05/07/2012
06/20/2012
Cost Description
2011
2012
2013
2014
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$79,925 $0 $9,269 $0 $0 $0 $0 $0 $522 $0
$0 $0 $528 $0 $0 $0 $0 $0 $0 $0
$79,925 $0 $9,797 $0 $0 $0 $0 $0 $522 $0
$0 $0 $79,039 $0 $0 $0 $0 $13,400 $255 $0
$0 $0 $5,878 $0 $0 $0 $0 $13,400 $255 $0
$79,925 $0 $0 $0 $0 $0 $0 $0 $267 $0
$79,925 $0 $79,039 $0 $0 $0 $0 $13,400 $522 $0
$0 $0 $69,242 $0 $0 $0 $0 $13,400 $0 $0
Totals:
$89,716
$528
$90,244
$92,694
$19,534
$80,192
$172,886
$82,642
$180,000 $162,000 $144,000 $126,000 $108,000 $90,000 $72,000 $54,000 $36,000 $18,000 $0
Project Update: - 95% Construction Documents are anticipated on October 4th - 100% Construction Documents are anticipated on October 26th
Project Budget
Village De L'est (Roof)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Village de L'est Elementary School (RSD) 5100 Cannes St, New Orleans, LA 70129 Scope of Work: Repair of Subsidence. Funding Source - FEMA Architect - Richard C. Lambert Consultants, LLC Contractor - Owen Construction Co.
Schedule Phase
Forecast Start
Forecast Finish
Village de Lest ES - Subsidence
Plan Start
Plan Finish
Design
10/18/2011
02/13/2012
10/10/2011
11/08/2011
Procurement
02/14/2012
05/28/2012
11/09/2011
02/16/2012
Construction
05/29/2012
07/27/2012
02/17/2012
06/15/2012
Final Completion
07/28/2012
08/17/2012
06/16/2012
07/15/2012
Cost Description
2011
2012
2013
2014
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$103,575 $0 $11,708 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$103,575 $0 $11,708 $0 $0 $0 $0 $0 $0 $0
$98,900 $0 $11,230 $0 $0 $0 $0 $6,490 $533 $0
$63,165 $0 $11,123 $0 $0 $0 $0 $6,490 $533 $0
$27,499 $0 $0 $0 $0 $0 $0 $0 $0 $0
$126,399 $0 $11,230 $0 $0 $0 $0 $6,490 $533 $0
$22,824 $0 ($478) $0 $0 $0 $0 $6,490 $533 $0
Totals:
$115,283
$0
$115,283
$117,153
$81,310
$27,499
$144,652
$29,369
$160,000 $144,000 $128,000 $112,000 $96,000 $80,000 $64,000 $48,000 $32,000 $16,000 $0
Project Update: - Project is Complete
Project Budget
Village de Lest ES - Subsidence
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Phillis Wheatley Elementary School (RSD) 2300 Dumaine Street, New Orleans, LA 70119 Scope of Work: New Elementary School Funding Source - FEMA Architect - Holly & Smith Architects Contractor - Gibbs Construction
Schedule Phase
Forecast Start
Forecast Finish
Wheatley (New Construction)
Plan Start
Plan Finish
Design
02/01/2010
06/20/2012
02/01/2010
12/11/2010
Procurement
06/21/2012
10/14/2012
12/12/2010
03/01/2011
Construction
10/15/2012
04/15/2014
03/02/2011
06/30/2012
Final Completion
04/16/2014
07/14/2014
07/01/2012
09/28/2012
Cost Description
2010
2011
2012
2013
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$18,663,700 $0 $1,428,518 $20,900 $0 $0 $2,063,869 $98,270 $222,742 $0
$0 $0 $399,930 $5,500 $0 $4,640 ($473,728) $62,534 $1,123 $0
$18,663,700 $0 $1,828,448 $26,400 $0 $4,640 $1,590,141 $160,804 $223,865 $0
$25,275,000 $0 $1,828,448 $26,400 $0 $5,390 $0 $143,024 $223,866 $0
$0 $0 $1,256,735 $22,000 $0 $4,640 $0 $143,024 $49,029 $0
$0 $0 $268,911 $0 $0 $0 $1,590,141 $17,780 $0 $0
$25,275,000 $0 $2,097,359 $26,400 $0 $5,390 $1,590,141 $160,804 $223,866 $0
$6,611,300 $0 $268,911 $0 $0 $750 $0 $0 $0 $0
Totals:
$22,497,999
$0
$22,497,999
$27,502,128
$1,475,428
$1,876,832
$29,378,960
$6,880,961
Committed Cost to Costs Date
Projected Costs
$30,000,000 $27,000,000 $24,000,000 $21,000,000 $18,000,000 $15,000,000 $12,000,000 $9,000,000 $6,000,000 $3,000,000 $0
Project Update: - Bid Date - August 9th - Contracts were returned by the contractor - Notice to proceeded is anticipated October 17th - Preconstruction meeting will be held October 16th
Project Budget
Wheatley (New Construction)
Status Date: 30-Sep-2012
Carter G. Woodson School (RSD) 2514 Third Street, New Orleans, LA 70113 Scope of Work: New Pre-K - 8 School Funding Source - FEMA Architect - Byron J. Stewart & Associates Contractor - Brice Building Company, LLC
Schedule Phase
Forecast Start
Forecast Finish
Woodson (New Construction)
Plan Start
Plan Finish
Design
06/08/2009
07/05/2010
06/08/2009
02/05/2010
Procurement
07/06/2010
10/26/2010
02/04/2010
04/27/2010
Construction
10/27/2010
09/14/2012
10/27/2010
02/25/2012
Final Completion
07/30/2012
10/27/2012
02/26/2012
03/28/2012
Cost Description
2009
2010
2011
2012
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$19,391,280 $0 $1,483,063 $20,900 $0 $0 $1,058,752 $63,270 $216,533 $0
$420,689 $0 $117,958 $0 $0 $1,524 ($541,527) $330 $1,026 $0
$19,811,969 $0 $1,601,021 $20,900 $0 $1,524 $517,225 $63,600 $217,559 $0
$20,065,520 $0 $1,601,021 $15,950 $0 $1,524 $0 $1,958 $217,559 $0
$19,818,011 $0 $1,524,264 $15,950 $0 $1,524 $0 $1,958 $167,126 $0
$9,511 $0 $0 $4,950 $0 $0 $517,225 $61,642 $0 $0
$20,075,031 $0 $1,601,021 $20,900 $0 $1,524 $517,225 $63,600 $217,559 $0
$263,062 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$22,233,798
$0
$22,233,798
$21,903,531
$21,528,833
$593,328
$22,496,860
$263,062
$24,000,000 $21,600,000 $19,200,000 $16,800,000 $14,400,000 $12,000,000 $9,600,000 $7,200,000 $4,800,000 $2,400,000 $0
Project Update: - Substantial Completion - September 14th - Punch list is 85% complete School occupied and classes began on September 17th - Commissioning will start in November
Project Budget
Woodson (New Construction)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Audubon School (OPSB) 428 Broadway Avenue, New Orleans, LA 70118 Scope of Work: Renovation & Addition to ES Funding Source - FEMA Architect - Blitch/Knevel Architects Contractor - FHP Tectonics Corporation
Schedule Phase
Forecast Start
Forecast Finish
Audubon School Renovation
Plan Start
Plan Finish
Design
09/08/2010
01/13/2012
02/01/2010
12/11/2010
Procurement
01/14/2012
05/22/2012
12/12/2010
03/01/2011
Construction
05/23/2012
09/21/2013
03/02/2011
06/30/2012
Final Completion
09/22/2013
12/20/2013
02/13/2012
05/13/2012
Cost Description Program Contingency A/E Fees & Reimbursables Demolition Environmental General Construction Modular Classrooms Other Costs Other Professional Services Permits & Fees Miscellaneous Totals:
2010
2011
2012
2013
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
$1,638,618 $964,939 $0 $20,900 $9,747,800 $0 $162,212 $28,270 $0 $0
($193,549) $190,915 $0 $1,709 $0 $0 $0 $175 $750 $0
$1,445,069 $1,155,854 $0 $22,609 $9,747,800 $0 $162,212 $28,445 $750 $0
$0 $1,168,994 $0 $21,842 $12,415,000 $0 $162,212 $7,298 $770 $0
$0 $807,975 $0 $18,209 $1,423,537 $0 $43,858 $7,298 $750 $0
$1,445,069 $0 $0 $4,400 $0 $0 $0 $21,147 $0 $0
$1,445,069 $1,168,994 $0 $26,242 $12,415,000 $0 $162,212 $28,445 $770 $0
$0 $13,140 $0 $3,633 $2,667,200 $0 $0 ($1) $20 $0
$12,562,739
$0
$12,562,739
$13,776,116
$2,301,626
$1,470,616
$15,246,732
$2,683,993
Committed Cost to Costs Date
Projected Costs
$16,000,000 $14,400,000 $12,800,000 $11,200,000 $9,600,000 $8,000,000 $6,400,000 $4,800,000 $3,200,000 $1,600,000 $0
Project Update: - Test Pile package is complete - Test Pile report was received September 24th - BZA and Safety / Permits are reviewing the Construction Documents - Pile driving is anticipate to start upon release of the permits - Wall layout in existing building is ongoing
Project Budget
Audubon School Renovation
Status Date: 30-Sep-2012
Benjamin Franklin Senior High School (OPSB) 2001 Leon C. Simon Drive, New Orleans, LA 70122 Scope of Work: Renovation and Repairs Funding Source - FEMA Architect - Perez, APC Contractor - Pete Vicari General Contractors, Inc
Schedule Phase
Forecast Start
Forecast Finish
Benjamin Franklin HS - Stabilization
Plan Start
Plan Finish
Design
03/23/2011
12/28/2011
03/23/2011
09/18/2011
Procurement
12/29/2011
06/18/2012
09/19/2011
12/07/2011
Construction
06/19/2012
01/14/2013
12/08/2011
06/04/2012
Final Completion
01/15/2013
02/28/2013
06/05/2012
07/19/2012
Cost Description
2011
2012
2013
2014
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$1,078,511 $0 $124,046 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$1,078,511 $0 $124,046 $0 $0 $0 $0 $0 $0 $0
$1,074,577 $0 $104,363 $5,720 $0 $0 $0 $8,580 $0 $0
$325,038 $0 $74,049 $5,720 $0 $0 $0 $8,580 $0 $0
$3,934 $0 $631 $0 $0 $0 $0 $0 $0 $0
$1,078,511 $0 $104,994 $5,720 $0 $0 $0 $8,580 $0 $0
$0 $0 ($19,052) $5,720 $0 $0 $0 $8,580 $0 $0
Totals:
$1,202,557
$0
$1,202,557
$1,193,240
$413,387
$4,565
$1,197,805
($4,752)
$1,400,000 $1,260,000 $1,120,000 $980,000 $840,000 $700,000 $560,000 $420,000 $280,000 $140,000 $0
Project Update: - Courtyard work will be complete in January - Exterior roof and lighting work is 90% complete
Project Budget
Benjamin Franklin HS - Stabilization
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Warren Eston High School (OPSB) 3019 Canal Street, New Orleans, LA 70119 Scope of Work: Interior Renovations Funding Source - FEMA Architect - Chenevert Architects LLC Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
Easton HS - Refurb
Plan Start
Plan Finish
Design
06/18/2012
10/06/2012
01/01/2012
01/01/2013
Procurement
10/07/2012
01/10/2013
11/10/2012
02/17/2013
Construction
01/11/2013
05/11/2013
02/18/2013
06/20/2014
Final Completion
05/11/2013
06/24/2013
06/20/2014
09/17/2014
Cost Description
2011
2012
2013
2014
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Project Budget
Estimated Estimated Budget Adjustments
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$1,615,900 $0 $198,267 $20,900 $0 $0 $966,777 $28,270 $0 $0
$0 $0 $32,372 $0 $0 $0 ($32,372) $0 $0 $0
$1,615,900 $0 $230,639 $20,900 $0 $0 $934,405 $28,270 $0 $0
$0 $0 $214,773 $0 $0 $0 $0 $0 $0 $0
$0 $0 $8,093 $0 $0 $0 $0 $0 $0 $0
$1,615,900 $0 $16,377 $20,900 $0 $0 $934,405 $28,270 $0 $0
$1,615,900 $0 $231,150 $20,900 $0 $0 $934,405 $28,270 $0 $0
$0 $0 $511 $0 $0 $0 $0 $0 $0 $0
Totals:
$2,830,114
$0
$2,830,114
$214,773
$8,093
$2,615,852
$2,830,625
$511
$3,000,000 $2,700,000 $2,400,000 $2,100,000 $1,800,000 $1,500,000 $1,200,000 $900,000 $600,000 $300,000 $0
Project Update: - 95% Construction Documents were received on September 15th - Owner requested increase in the scope of work will extend the Design Phase
Project Budget
Easton HS - Refurb
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Greater St. Stephens School (RSD) 11110 Lake Forest Blvd, New Orleans, LA 70128 Scope of Work: Demolition of School. Funding Source - FEMA Architect - Chenevert Architects LLC Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
GSt Stephens - Demo
Plan Start
Plan Finish
Design
06/13/2012
08/04/2012
05/21/2012
10/23/2012
Procurement
08/05/2012
10/23/2012
09/08/2012
12/11/2012
Construction
10/24/2012
02/20/2013
12/11/2012
03/28/2013
Final Completion
02/21/2013
04/06/2013
03/28/2013
05/11/2013
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$0 $280,000 $28,673 $5,412 $0 $0 $0 $10,943 $0 $0
$0 $0 $0 $0 $0 $0 $0 $11,502 $0 $0
$0 $280,000 $28,673 $5,412 $0 $0 $0 $22,444 $0 $0
$0 $0 $28,673 $5,412 $0 $0 $0 $22,444 $0 $0
$0 $0 $18,637 $5,412 $0 $0 $0 $10,943 $0 $0
$0 $280,000 $0 $0 $0 $0 $0 $0 $0 $0
$0 $280,000 $28,673 $5,412 $0 $0 $0 $22,444 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$325,028
$11,502
$336,529
$56,529
$34,992
$280,000
$336,529
$0
$360,000 $324,000 $288,000 $252,000 $216,000 $180,000 $144,000 $108,000 $72,000 $36,000 $0
Project Update: - Bid Date - September 13th - The Owner is reviewing the bids
Project Budget
GSt Stephens - Demo
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Alice Harte School (OPSB) 5300 Berkley Drive, New Orleans, La 70131 Scope of Work: New Pre-K - 8 School Funding Source - CDBG & FEMA Architect - WDG Architects Engineers Contractor - Woodrow Wilson Construction Co., Inc.
Schedule Phase
Forecast Start
Forecast Finish
Harte School (New Construction)
Plan Start
Plan Finish
Design
09/08/2010
06/05/2012
02/01/2010
12/11/2010
Procurement
06/05/2012
09/11/2012
12/12/2010
03/01/2011
Construction
09/12/2012
01/11/2014
10/16/2011
02/13/2013
Final Completion
01/12/2014
04/11/2014
02/14/2013
05/14/2013
Cost Description
2010
2011
2012
2013
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$22,990,000 $0 $1,736,350 $20,900 $0 $0 $2,599,178 $666,350 $225,000 $0
$0 $0 $7,471 $2,860 $0 $4,965 ($15,296) $0 $0 $0
$22,990,000 $0 $1,743,821 $23,760 $0 $4,965 $2,583,882 $666,350 $225,000 $0
$0 $0 $1,986,452 $23,210 $0 $4,965 $0 $79,150 $222,742 $0
$0 $0 $1,297,095 $23,210 $0 $4,965 $0 $78,820 $50,638 $0
$22,990,000 $0 $0 $550 $0 $0 $2,583,882 $587,200 $2,258 $0
$22,990,000 $0 $1,986,452 $23,760 $0 $4,965 $2,583,882 $666,350 $225,000 $0
$0 $0 $242,631 $0 $0 $0 $0 $0 $0 $0
Totals:
$28,237,778
$0
$28,237,778
$2,316,519
$1,454,728
$26,163,890
$28,480,409
$242,631
$30,000,000 $27,000,000 $24,000,000 $21,000,000 $18,000,000 $15,000,000 $12,000,000 $9,000,000 $6,000,000 $3,000,000 $0
Project Update: - Ground Breaking was September 11th - Notice to Proceed was issued September 12th - The contractor has mobilized and has begun site preparation
Project Budget
Harte School (New Construction)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
JoEllen Smith Modular Demolition (OPSB) 4400 General Meyer Ave., New Orleans, LA 70131 Scope of Work: Demolition of Medical Center Funding Source - FEMA Architect - VergesRome Architects Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
JoEllen Smith Med Ctr Demo
Plan Start
Plan Finish
Design
09/12/2012
03/12/2013
09/12/2012
03/12/2013
Procurement
01/07/2013
04/04/2013
01/07/2013
04/04/2013
Construction
04/05/2013
08/02/2013
04/05/2013
10/01/2013
Final Completion
08/03/2013
09/16/2013
10/02/2013
11/15/2013
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$0 $3,000,000 $253,481 $24,716 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $3,000,000 $253,481 $24,716 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $3,000,000 $253,481 $24,716 $0 $0 $0 $0 $0 $0
$0 $3,000,000 $253,481 $24,716 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$3,278,197
$0
$3,278,197
$0
$0
$3,278,197
$3,278,197
$0
$3,600,000 $3,240,000 $2,880,000 $2,520,000 $2,160,000 $1,800,000 $1,440,000 $1,080,000 $720,000 $360,000 $0
Project Update: - Notice to proceed was issued September 12th - 50% Construction Documents are anticipated October 31st - 100% Construction Documents are anticipated December 10th
Project Budget
JoEllen Smith Med Ctr Demo
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Edna Karr High School - Gymnasium Repair (OPSB) 3332 Huntlee Drive, New Orleans, LA 70131 Scopy of Work: Repair Structure in Gymnasium Funding Source: FEMA Architect: Chenevert Architects Contractor: Crescent Commercial Construction
Schedule Phase
Forecast Start
Forecast Finish
Karr HS - Gym Repair
Plan Start
Plan Finish
Design
04/20/2012
06/10/2012
01/01/2012
01/01/2013
Procurement
06/11/2012
10/08/2012
11/10/2012
02/17/2013
Construction
10/09/2012
02/06/2013
02/18/2013
06/20/2014
Final Completion
02/07/2013
03/23/2013
06/20/2014
09/17/2014
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Owner Costs Miscellaneous
$250,000 $0 $32,372 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$250,000 $0 $32,372 $0 $0 $0 $0 $0 $0 $0
$0 $0 $22,943 $0 $0 $0 $0 $0 $0 $0
$0 $0 $8,093 $0 $0 $0 $0 $0 $0 $0
$250,000 $0 $0 $0 $0 $0 $0 $0 $0 $0
$250,000 $0 $22,943 $0 $0 $0 $0 $0 $0 $0
$0 $0 ($9,429) $0 $0 $0 $0 $0 $0 $0
Totals:
$282,372
$0
$282,372
$22,943
$8,093
$250,000
$272,943
($9,429)
$300,000 $270,000 $240,000 $210,000 $180,000 $150,000 $120,000 $90,000 $60,000 $30,000 $0
Project Update: - Bid Opening date - July 24th - Owner returned signed contract September 26th - Notice to proceeded is anticipated October 8th
Project Budget
Karr HS - Gym Repair
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Lake Forest PK-8 at Greater St. Stephens (OPSB) 11110 Lake Forest Blvd, New Orleans, LA 70127 Scope of Work: New PK-8 School Funding Source - FEMA Architect - Imre hegedus & Associates Architectes Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
Lake Forest School @ Greater St. Stephens
Plan Start
Plan Finish
Design
06/14/2012
05/12/2013
05/21/2012
03/26/2013
Procurement
03/28/2013
07/01/2013
02/26/2013
05/22/2013
Construction
07/02/2013
10/31/2014
05/23/2013
09/22/2014
Final Completion
11/01/2014
01/29/2015
09/22/2014
12/20/2014
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$22,080,000 $0 $1,634,734 $20,900 $0 $0 $930,001 $98,270 $230,000 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$22,080,000 $0 $1,634,734 $20,900 $0 $0 $930,001 $98,270 $230,000 $0
$0 $0 $1,382,303 $0 $0 $0 $0 $0 $0 $0
$0 $0 $207,345 $0 $0 $0 $0 $0 $0 $0
$22,080,000 $0 $252,431 $20,900 $0 $0 $930,001 $98,270 $230,000 $0
$22,080,000 $0 $1,634,734 $20,900 $0 $0 $930,001 $98,270 $230,000 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$24,993,905
$0
$24,993,905
$1,382,303
$207,345
$23,611,602
$24,993,905
$0
$27,000,000 $24,300,000 $21,600,000 $18,900,000 $16,200,000 $13,500,000 $10,800,000 $8,100,000 $5,400,000 $2,700,000 $0
Project Update: - Community Meeting #3 - September 24th - Schematic Design documents were received September 29th - Design Development documents are anticipated October 18th
Project Budget
Lake Forest School @ Greater St. Stephens Site
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Lusher Fortier Elementary School (OPSB) 5624 Freret Street, New Orleans, LA 70115 Scope of Work: Renovation of Existing School Funding Source - FEMA Architect - Meyer Engineers, LTD Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
Lusher Fortier HS – Refurb
Plan Start
Plan Finish
Design
09/26/2012
05/09/2013
01/01/2012
01/01/2013
Procurement
03/25/2013
06/27/2013
11/10/2012
02/17/2013
Construction
06/27/2013
10/12/2013
02/18/2013
06/20/2014
Final Completion
10/12/2013
01/09/2014
06/20/2014
09/17/2014
Cost Description
2011
2012
2013
2014
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Owner Costs Miscellaneous
$12,585,430 $0 $1,090,236 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$12,585,430 $0 $1,090,236 $0 $0 $0 $0 $0 $0 $0
$0 $0 $1,128,827 $0 $0 $0 $0 $0 $0 $0
$0 $0 $60,986 $0 $0 $0 $0 $0 $0 $0
$12,585,430 $0 $0 $0 $0 $0 $0 $0 $0 $0
$12,585,430 $0 $1,128,827 $0 $0 $0 $0 $0 $0 $0
$0 $0 $38,591 $0 $0 $0 $0 $0 $0 $0
Totals:
$13,675,666
$0
$13,675,666
$1,128,827
$60,986
$12,585,430
$13,714,257
$38,591
$14,000,000 $12,600,000 $11,200,000 $9,800,000 $8,400,000 $7,000,000 $5,600,000 $4,200,000 $2,800,000 $1,400,000 $0
Project Update: - Program Documents are anticipated on October 10th - Program Documents are anticipated on October 15th - Community Meeting postponed and will be rescheduled at a later date
Project Budget
Lusher Fortier HS – Refurb
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Mahalia Jackson ES Office Renovation (OPSB) Scope of Work: Convert Office Space into Cassrooms Funding Source - OPSB General Fund Architect - VergesRome Architects, APAC Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
Mahalia Jackson - Off Reno
Plan Start
Plan Finish
Design
04/17/2012
09/10/2012
04/17/2012
09/10/2012
Procurement
07/10/2012
10/09/2012
07/10/2012
10/09/2012
Construction
10/10/2012
12/23/2012
10/10/2012
12/23/2012
Final Completion
12/24/2012
01/07/2013
12/24/2012
01/07/2013
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$174,500 $0 $18,658 $0 $0 $0 $6,842 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$174,500 $0 $18,658 $0 $0 $0 $6,842 $0 $0 $0
$0 $0 $18,658 $0 $0 $0 $0 $0 $0 $0
$0 $0 $11,195 $0 $0 $0 $0 $0 $0 $0
$174,500 $0 $0 $0 $0 $0 $6,842 $0 $0 $0
$174,500 $0 $18,658 $0 $0 $0 $6,842 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$200,000
$0
$200,000
$18,658
$11,195
$181,342
$200,000
$0
$210,000 $189,000 $168,000 $147,000 $126,000 $105,000 $84,000 $63,000 $42,000 $21,000 $0
Project Update: - Bid Opening - August 21st - Contract was re-awarded after protest - Notice to proceeded is anticipated October 18th - Permits are in place
Project Budget
Mahalia Jackson - Off Reno
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
McDonogh #35 School (Phillip/Waters Site) (OPSB) 1200 Senate Street, New Orleans, LA 70122 Scope of Work: New 3 Story High School Funding Source - FEMA Architect - Sizeler, Thompson, Brown Architects Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
McDonogh 35 (Phillips/Waters)
Plan Start
Plan Finish
Design
05/24/2010
10/02/2012
02/01/2010
12/11/2010
Procurement
09/27/2012
12/24/2012
12/12/2010
03/01/2011
Construction
12/25/2012
08/24/2014
03/02/2011
10/29/2012
Final Completion
08/25/2014
11/22/2014
10/30/2012
01/27/2013
Cost Description
2010
2011
2012
2013
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$48,132,700 $0 $3,472,312 $20,900 $0 $0 $5,188,418 $28,270 $230,000 $0
$0 $0 $384,714 $94,744 $0 $4,865 ($673,903) $97,700 $91,880 $0
$48,132,700 $0 $3,857,026 $115,644 $0 $4,865 $4,514,515 $125,970 $321,880 $0
$4,478,381 $0 $3,974,517 $115,644 $0 $4,865 $0 $113,529 $321,880 $0
$2,815,769 $0 $2,730,437 $114,698 $0 $4,865 $0 $113,529 $73,167 $0
$43,705,475 $0 $223,898 $0 $0 $0 $4,514,515 $17,809 $0 $0
$48,183,856 $0 $4,198,415 $115,644 $0 $4,865 $4,514,515 $131,338 $321,880 $0
$51,156 $0 $341,389 $0 $0 $0 $0 $5,368 $0 $0
Totals:
$57,072,600
$0
$57,072,600
$9,008,816
$5,852,465
$48,461,697
$57,470,513
$397,913
$60,000,000 $54,000,000 $48,000,000 $42,000,000 $36,000,000 $30,000,000 $24,000,000 $18,000,000 $12,000,000 $6,000,000 $0
Project Update: Site Remediation: - A Phase II environmental assessment revealed heavy metals and PAHs exist in the fill - Scope of work is to remediate fly-ash materials found in the soil - Remediation work is anticipated to be completed end of November New Construction: - The resubdivision request was submitted to the City Of New Orleans - 100% Construction Documents will be received on October 2nd - 1st Advertisement scheduled for October 10th - Bid Opening - November 15th
Project Budget
McDonogh 35 (Phillips/Waters)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
McDonogh 35 High School Stabilization (OPSB) 1331 Kerlerec Street, New Orleans, LA 70116 Scope of Work: Stabilize Bldg and New Elevator Funding Source - FEMA Architect - Chenevert Architects LLC Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
McDonogh 35 HS - Stabilization (Elevator)
Plan Start
Plan Finish
Design
04/20/2012
08/08/2012
01/01/2012
01/01/2013
Procurement
08/09/2012
11/06/2012
11/10/2012
02/17/2013
Construction
11/07/2012
04/05/2013
02/18/2013
06/20/2014
Final Completion
04/06/2013
05/20/2013
06/20/2014
09/17/2014
Cost Description
2011
2012
2013
2014
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Owner Costs Other Costs Miscellaneous
$250,000 $0 $32,372 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$250,000 $0 $32,372 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $23,815 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $15,658 $0 $0 $0 $0 $0 $0 $0 $0
$250,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$250,000 $0 $23,815 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 ($8,557) $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$282,372
$0
$282,372
$23,815
$15,658
$250,000
$273,815
($8,557)
$300,000 $270,000 $240,000 $210,000 $180,000 $150,000 $120,000 $90,000 $60,000 $30,000 $0
Project Update: - Bid Opening - September 20th - Bids were higher than expected - Project is being reviewed by the Owner
Project Budget
McDonogh 35 HS - Stabilization (Elevator)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Eleanor L. McMain School (OPSB) 5721 S. Claiborne Avenue, New Orleans, LA 70125 Scope of Work: Stabilize Bldg and New Gymnasium Funding Source - FEMA Architect - Jahncke & Burns Architect Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
McMain School - Gymnasium
Plan Start
Plan Finish
Design
08/06/2012
11/17/2012
08/06/2012
11/17/2012
Procurement
09/25/2012
12/12/2012
09/25/2012
12/12/2012
Construction
12/13/2012
12/12/2013
12/13/2012
12/12/2013
Final Completion
12/13/2013
03/12/2014
12/13/2013
03/12/2014
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$10,253,605 $0 $980,393 $20,900 $0 $0 $1,692,475 $28,270 $0 $0
$0 $0 $0 $4,829 $0 $0 ($156,619) $42,568 $109,222 $0
$10,253,605 $0 $980,393 $25,729 $0 $0 $1,535,856 $70,838 $109,222 $0
$0 $0 $1,025,554 $19,239 $0 $0 $0 $206,023 $109,222 $0
$0 $0 $621,789 $16,055 $0 $0 $0 $193,602 $23,725 $0
$10,253,605 $0 $14,967 $10,670 $0 $0 $1,535,856 $12,547 $6,620 $0
$10,253,605 $0 $1,040,521 $29,909 $0 $0 $1,535,856 $218,570 $115,842 $0
$0 $0 $60,128 $4,180 $0 $0 $0 $147,732 $6,620 $0
Totals:
$12,975,643
$0
$12,975,643
$1,360,038
$855,171
$11,834,265
$13,194,303
$218,660
$14,000,000 $12,600,000 $11,200,000 $9,800,000 $8,400,000 $7,000,000 $5,600,000 $4,200,000 $2,800,000 $1,400,000 $0
Project Update: - 100% Construction Documents were received on September 21st - First Advertisement October 3rd - Bid Opening - November 7th
Project Budget
McMain School - Gymnasium
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
New Karr HS at the JoEllen Smith Site (RSD) 4400 General Meyer Avenue, New Orleans, LA 70131 Scope of Work: New High School Funding Source - FEMA Architect - Lee Ledbetter / Gould Evans Contractor- TBD
Schedule Phase
Forecast Start
Forecast Finish
New Karr HS (JE Smith)
Plan Start
Plan Finish
Design
05/14/2012
05/09/2013
01/01/2012
01/01/2013
Procurement
04/05/2013
06/24/2013
11/10/2012
02/17/2013
Construction
06/24/2013
02/22/2015
02/18/2013
06/20/2014
Final Completion
02/23/2015
04/08/2015
06/20/2014
09/17/2014
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$25,400,000 $655,945 $1,921,893 $20,900 $0 $0 $1,625,855 $98,270 $230,000 $0
$0 $0 $47,414 $0 $0 $0 ($47,414) $0 $0 $0
$25,400,000 $655,945 $1,969,307 $20,900 $0 $0 $1,578,441 $98,270 $230,000 $0
$0 $0 $2,583,078 $30,470 $0 $0 $0 $19,624 $0 $0
$0 $0 $98,465 $30,470 $0 $0 $0 $19,624 $0 $0
$25,400,000 $655,945 $0 $4,400 $0 $0 $1,578,441 $78,646 $230,000 $0
$25,400,000 $655,945 $2,583,078 $34,870 $0 $0 $1,578,441 $98,270 $230,000 $0
$0 $0 $613,771 $13,970 $0 $0 $0 $0 $0 $0
Totals:
$29,952,863
$0
$29,952,863
$2,633,172
$148,559
$27,947,432
$30,580,604
$627,741
$32,000,000 $28,800,000 $25,600,000 $22,400,000 $19,200,000 $16,000,000 $12,800,000 $9,600,000 $6,400,000 $3,200,000 $0
Project Update: - Community Meeting #3 is anticipated to be held in November - Schematic Design Documents were completed on August 17th - Due to design issues and additional scope of work, Schematic Design Documents will be resubmitted
Project Budget
New Karr HS (JE Smith)
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
New PK-8 at North Kenilworth Park (Curran) (OPSB) 8500 Curran Boulevard, New Orleans, LA 70127 Scope of Work: New Pre-K - 8 School Funding Source - FEMA Architect - Mathes Brierre Architects Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
New PK-8 at North Kenilworth Park
Plan Start
Plan Finish
Design
04/28/2011
10/02/2012
04/28/2011
04/28/2012
Procurement
09/18/2012
01/02/2013
03/21/2012
06/18/2012
Construction
01/02/2013
07/04/2014
06/19/2012
10/11/2013
Final Completion
07/04/2014
08/17/2014
10/11/2013
01/09/2014
Cost Description
2011
2012
2013
2014
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Estimated Estimated Budget Adjustments
Project Budget
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$21,108,000 $0 $1,562,660 $20,193 $0 $0 $0 $4,818 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$21,108,000 $0 $1,562,660 $20,193 $0 $0 $0 $4,818 $0 $0
$86,118 $0 $1,607,360 $20,193 $0 $0 $0 $78,694 $254,730 $0
$0 $0 $747,897 $20,193 $0 $0 $0 $71,318 $42,429 $0
$21,021,882 $0 $0 $0 $0 $0 $0 $0 $254,730 $0
$21,108,000 $0 $1,607,360 $20,193 $0 $0 $0 $78,694 $509,460 $0
$0 $0 $44,700 $0 $0 $0 $0 $73,876 $509,460 $0
Totals:
$22,695,671
$0
$22,695,671
$2,047,095
$881,837
$21,276,612
$23,323,707
$628,036
$24,000,000 $21,600,000 $19,200,000 $16,800,000 $14,400,000 $12,000,000 $9,600,000 $7,200,000 $4,800,000 $2,400,000 $0
Project Update: - 100% CD Documents were received on September 11th with comments incorporated - 1st Advertisement - September 25th - Pre-Bid Conference - 9:00 a.m. on October 10th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA - Bid Date - November 8th
Project Budget
New PK-8 at North Kenilworth Park
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
Timbers HVAC (OPSB) 3520 General DeGaulle, New Orleans, LA 70114 Scope of Work: Replacement of HVAC Funding Source - General Fund Architect - Moses Engineers Contractor - TBD
Schedule Phase
Forecast Start
Forecast Finish
Timbers - HVAC
Plan Start
Plan Finish
Design
06/08/2012
01/11/2013
06/08/2012
01/11/2013
Procurement
11/01/2012
01/27/2013
11/01/2012
01/27/2013
Construction
01/28/2013
05/27/2013
01/28/2013
05/27/2013
Final Completion
05/28/2013
08/25/2013
05/28/2013
08/25/2013
Cost Description
2012
2013
2014
2015
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Project Budget
Estimated Estimated Budget Adjustments
Uncommitted Committed Costs Costs Cost to Date
Projected Costs
Projected Ovr/(Undr)
General Construction Demolition A/E Fees & Reimbursables Environmental Modular Classrooms Permits & Fees Program Contingency Other Professional Services Other Costs Miscellaneous
$1,000,000 $0 $114,928 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$1,000,000 $0 $114,928 $0 $0 $0 $0 $0 $0 $0
$0 $0 $114,928 $0 $0 $0 $0 $0 $0 $0
$0 $0 $57,464 $0 $0 $0 $0 $0 $0 $0
$1,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $0
$1,000,000 $0 $114,928 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Totals:
$1,114,928
$0
$1,114,928
$114,928
$57,464
$1,000,000
$1,114,928
$0
$1,200,000 $1,080,000 $960,000 $840,000 $720,000 $600,000 $480,000 $360,000 $240,000 $120,000 $0
Project Update: - 100% Construction Documents were received on September 28th - Anticipated 1st Advertisement - November 2012
Project Budget
Timbers - HVAC
Committed Cost to Costs Date
Projected Costs
Status Date: 30-Sep-2012
APPENDIX A
Appendix A Funding Analysis Reports
APPENDIX A
Status Date: 30-September-2012
TABLE OF CONTENTS
Part I............................................................................................................................................................................................. 1 Item 1. Executive Summary............................................................................................................................................1 Item 2. Alternate Project Amendments, PW Versions, and Policy ..................................................................................3 Item 3. Grants Management ...........................................................................................................................................8 Item 4. Environmental & Historic Preservation (EHP) ....................................................................................................9 Part II.......................................................................................................................................................................................... 11 Item 5. Summary of FEMA Funding .............................................................................................................................11 Item 6. Summary of Reimbursements Against Facilities Master Plan Alternate Project ...............................................12 Item 7. Closeout Status Log .........................................................................................................................................16
Quarterly Report ending September 30, 2012
Part I Item 1. Executive Summary This quarter has witnessed the progressive expansion in the Funding Department to include a Funding Team Leader, Closeout and Audit Support as well as IT and database analysis staff. The inclusion of these staff members increases the Jacobs/CSRS knowledge base with more than 50 years of disaster recovery experience. Along with the influx of new personnel, a new Project Execution Plan (PEP) was developed and is now being utilized to provide structure and accountability to the department. Enhanced monthly reporting has been added to ensure that RSD is kept apprised of the Funding Teams’ progress towards closeout of the various project worksheets (PWs) as well as grants management and compliance matters. This quarter, FEMA obligated PW 19166 Version 1 to reflect RSD’s planned Capital Projects for Phase II of the Master Plan. PW 19166 Version 1 provides approval for the addition of four (4) new campuses and funding approval for A/E services and other professional services. The Funding Group submitted Version 2 for PW 19166 resulting in pending obligation of funding totaling $69.4 MM. PW 19166 Version 2 focuses on RSD’s Historic Preservation efforts and approves specific campus sites that may be built to the Advisory Base Flood Elevation (ABFE). Historic Preservation compliance reviews and communication have been streamlined between Jacobs/CSRS, FEMA and the SHPO in order to secure project approval earlier in the Construction Design Phase. In addition, design documentation requirements have been clarified and expanded to facilitate approval of Historic Tax Credits to take advantage of Federal and State Historic Tax Credits. In preparation for Closeout, the Funding Group has reviewed recent FEMA and GOHSEP guidance regarding Direct Administrative Costs and Indirect Administrative Costs related to the FEMA August 2013 deadline. The Funding Group has committed to the closeout of some 570 non-SSR Project Worksheets prior to the August 2013 deadline. This quarter, the Funding Group submitted 141 Project Worksheets to GOHSEP for closeout. With a full complement of staff in place, the look forward in the next Quarter will involve a concentrated focus on closeout of some 539 non-SSR Project Worksheets prior to the 8/31/2013 deadline; increased focus on grants management, financial reporting and risk assessment to ensure that the RSD is properly positioned for the project ahead.
1
Quarterly Report ending September 30, 2012
SUMMARY OF RSD OBLIGATED AND PENDING PROJECTS* CURRENT OBLIGATION
FEDERAL FUNDS PAID
FEDERAL FUNDS BALANCE
$ 1,504,347,076.72
$ 685,767,277.53
$ 820,963,556.56
* Current Obligation reflects the total amount approved by FEMA. Federal Funds Paid denotes the total amount paid to the Applicant from current obligated funds. Federal Funds Balance reflects the total available amount remaining to be paid by FEMA to the Applicant from current obligated funds. Please refer to page 11 for details of funding obligations and payments
2
Quarterly Report ending September 30, 2012
Item 2. Alternate Project Amendments, PW Versions, and Policy Project Deliverables/Updates Master Plan Alternate Project Amendments Amendments are written to add eligible scopes of work to Alternate Project PW 19166 for approval of FEMA funds for Master Plan projects. This approval allows projects to be pursued on a timeline that accords with the Master Plan. The following alternate project amendments are currently identified and tracked by status: Approved by FEMA: Landry High School Lawless (Lower Ninth Ward) High School Pending FEMA Approval: Bradley Elementary School Colton Elementary School (Expedited Post-Katrina Work) Douglass High School (Expedited Post-Katrina Work) Fisk-Howard Elementary School M L King Jr. Charter School (Expedited Post-Katrina Work) Marshall Middle School (Expedited Post-Katrina Work) Reed Senior High School (Expedited Post-Katrina Work) Washington Senior High School (Expedited Post-Katrina Work) New Algiers Elementary School NOHSSC – Derham New Orleans East High School at Abramson Master Plan Alternate Project Amendments in Development New Buildings and Full Renovations Amendments prepared for submission to GOHSEP are still pending final site selection on: Behrman Elementary School (new) Habans Elementary School Refurbishments Assessments of the exterior skin, structure, civil, MEP, fire protection and special systems scheduled for the second quarter of 2012 will inform the scope of work alignment revisions including estimated costs and schedules in order to align with the October 2011 Master Plan Alternate Project Revised Amendments. Transmittal to GOHSEP is targeted for November for the following: Allen Elementary School Bauduit Elementary School Crossman Elementary School Eisenhower Elementary School Gentilly Terrace Elementary School Green Middle School Harney Elementary School
3
Quarterly Report ending September 30, 2012
Jackson Elementary School Laurel Elementary School Marshall Elementary School King Jr. Charter School McDonogh 7 Elementary School McDonogh 28 Elementary School Reed High School Rosenwald High School Schaumburg Elementary School Schwarz High School Village de L’est Walker High School Wicker Elementary School Sylvanie Williams Elementary School
Project Worksheet Versions Master Plan Alternate Project PW 19166, Version 2 Version 2 for PW 19166 is still awaiting final obligation by FEMA. This version addressed EHP holdouts and Elevation requirements for building locations. FEMA obligation is anticipated in the very near future. Additional Alternate Projects Category G Alternate Project RSD has submitted an alternate project request to roll-up remaining eligible FEMA Category G (outdoor facility) PWs. The $762,186.51 PW will be available to support currently planned Master Plan project activities such as soil remediation, outdoor play equipment and/or fencing. Category E Alternate Project RSD has submitted a small alternate project request to roll up $58,500 in eligibility that was made available by FEMA for outdoor sheds and weather stations. RSD will have the discretion to use the funding to support a piece of a small capital project in order to utilize the available funding. Temporary Modular Facilities Versions are being written by FEMA to capture eligibility on relocation and refurbishment on modular facilities. These include:
Hughes: PW 15708 v5 (Kennedy to Schwarz and Coghill). This Project Worksheet version for Category B work provides actual costs for A/E, contract costs and four change orders associated with moving and refurbishing modular units from Kennedy to Coghill. This will allow RSD to draw upon the base contract value and the four change orders. It is envisioned that FEMA questions regarding duplication of scope of work between PWs 15708 and PW 15696 will be resolved by November 2012, with additional Amendment requests completed by December 2012. Hughes PW 15708 v6 (Kennedy to Schwarz and Coghill). This Project Worksheet version for Category B work addresses the zero dollar salvage value of the modular classroom units located at this temporary facility. Fannie C. Williams PW 15706 v6 (At Livingston Middle School). This Project Worksheet version for Category B work addresses the zero dollar salvage value of the modular
4
Quarterly Report ending September 30, 2012
classroom units located at this temporary facility was submitted to GOHSEP in October 2012 for approval. The Notice to proceed on the work will be issued next week with the demolition work completed by the end of January. Close out may be completed by May. Site Work has been delayed while RSD obtains the Modular Building Titles. Abramson Senior High School PW 15696 v6 (Kennedy to Abramson). This Project Worksheet version for Category B work captures eleven (11) additional change orders associated with the temporary facility installation at Holy Cross. This version has been signed by RSD and has been submitted to FEMA for processing. Carver PW 16082 v5 (At Sarah Reed High School). This Project Worksheet version for Category B work addresses the zero dollar salvage value of the modular classroom units located at this temporary facility. Hardin Elementary School PW 15700 v6. This Project Worksheet version for Category B work addresses the zero dollar salvage value of the modular classroom units located at this temporary facility. Carver High School PW 15708 v6. This Project Worksheet version for Category B work addresses the zero dollar salvage value of the modular classroom units located at this temporary facility. Carver High School PW 15701 v6. This Project Worksheet version for Category B work addresses the zero dollar salvage value of the modular classroom units located at this temporary facility. Edwards Elementary School 15701 v5. This Project Worksheet version for Category B work addresses the zero dollar salvage value of the modular classroom units located at this temporary facility.
Temporary Transportation PW version to add eligibility in the amount of $690,940 to the RSD for addition bus transportation has been submitted to GOHSEP for processing. Contents The funding group has completed the exercise to validate eligible school contents in response to FEMA’s material error in PW 19300. As a result of that analysis, FEMA has versioned PW 19300 with a de-obligation of $29M. Lafon Interpretive Display & Sculpture Stabilization The RSD is continuing to satisfy the interpretive display requirements pursuant to the MOA and remain within the allocated budget. Bids received were in excess of the original estimates and the A/E is currently redesigning the displays to lower costs. The RSD will submit proposed changes and FEMA will submit the scope of work for the PW concurrently with circulation of the design to consulting parties by FEMA EHP. Document Remediation The document stabilization PW to clean historic architectural drawings of mold and dirt is moving towards obligation by FEMA. Policy Master Plan Alternate Project PW 19166, Version 2 RSD met with senior management at FEMA’s LRO and GOHSEP on May 2nd to clarify and
5
Quarterly Report ending September 30, 2012 resolve outstanding technical matters at a case study charrette. Tentative agreements have been reached, and GOHSEP concurrence has been received in writing. FEMA’s prospective agreements are being reviewed by its internal counsel. A determination is expected in the next Quarter, and any determinations will be requested for memorialization in PW 19166.
CDBG White Paper The Funding Group developed a white paper on the streamlined allocation of CDBG costs as a result of RSD’s settlement with FEMA and the completion of the October 2011 Amendments to the Master Plan. The white paper was presented to Office of Community Development (OCD), the Grantee of the CDBG Disaster Recovery Program on last spring and was receptive to the proposal. OCD is awaiting RSD’s progress with FEMA to reallocate prior expenditures to upcoming new construction in Phase 2 of the Master Plan prior to taking formal action on the White Paper. FEMA is currently reviewing documentation for 6 CDBG funded schools to determine their eligibility for funding. It is envisioned that the final FEMA eligibility determination will not be made until March 2013. HABS RFQ for Large-Format Photography of Historic Buildings CARMA contract registration issues with the State of Louisiana are resolved and complete through action of the LA Board of Architectural Examiners. HABS recordation has been received, and the Director of the Historic American Buildings Survey (HABS) with the National Park Service has verbally approved HABS large format photography. No additional photographs are required, and demolition and selective demolition may proceed. Liquidated Damages: Allowable Collection Methods &Utilization The Funding Group is continuing the review of the current process for the reimbursement to Charter Schools for expenses incurred due to delays by construction contractors. The Funding Group is developing a brief which is consistent with FEMA policy and GOHSEP pay policies. NEPA Environmental Justice (EJ) Compliance on RSD’s October 2011 Master Plan Amendments FEMA has no comments on the update to RSD’s Public Involvement Plan (PIP) concerning NEPA EJ compliance. Comments will be included in the next version of PW 19166 to memorialize compliance Preservation Resource Center CEA The Cooperative Endeavor Agreement (CEA) with the Preservation Resource Center is still under review by the RSD and the PRC agreement is consistent with FEMA Alternate Project policies and Louisiana State laws. Tax Credits New Market Tax Credit Structure The Funding Group is working in collaboration with RSD and its New Market Tax Credit consultants to develop a policy overlay to determine the feasibility of mingling New Market Tax Credit and FEMA or CDBG Disaster funding. There appears to be precedent in post-Katrina New Orleans for the latter, but business process and policy discussions are ongoing relative to FEMA-New Market projects.
6
Quarterly Report ending September 30, 2012
State Historic Tax Credits The Funding Group is working with RSD and the Jacobs/CSRS the Project Management and Design Management Groups to realign project documentation standards and requirements in order to capture State Historic Tax Credits. As Cultural Products District eligible schools are identified, Jacobs/CSRS will prepare the tax credit applications.
Federal Historic Tax Credits The Funding Group is also working with RSD to determine eligibility for Federal Historic Tax Credits in combination with FEMA and/or CDBG funds. If the Federal Historic Tax Credit bill aimed at school eligibility is passed (timely) by Congress, RSD’s positioning will be materially improved.
7
Quarterly Report ending September 30, 2012
Item 3. Grants Management Project Deliverables/Updates 1. Louisiana Department of Education Appropriations Control & GOHSEP Grants Management Project Deliverables/Updates Bi-weekly meetings with GOHSEP Grants Management continue to be an outstanding grants management tool to promote effective and clear communications, consider options when working with complete documentation packages and eligibility matters, and preventing and resolving small problems before they grow roots. This quarter, the emphasis was placed on a the following: Development of a common standard for use by GOHSEP Disaster Recovery Specialist use in the review of Project Management and Direct Administrative Costs for GOHSEP reimbursement to the RSD Review of RSD outstanding debt to determine the need for applied payments to resolve that debt. The LDOE Division of Appropriation Controls and the RSD Finance Department continue to be meaningfully engaged in resolving long-term reimbursements issues. LDOE continues to support the RSD Finance Department by submitting Requests for Reimbursements on contents and non-capital expenditures in the interest of system efficiency and consistency. The Funding Group continues to support the communications related to these matters and is also vetting some documentation to keep RRF submissions moving. The Funding Group developed the Project Execution Plan setting forth the goals, standards, projects and measures of success that will govern all future closeout and compliance related project activities. The outcome of that process is as follows: Some 570 non-SSR FEMA projects requiring closeout were identified and prioritized. Roles and responsibilities for each aspect of closeout phase were identified and agreements were reached with RSD Capital Projects Executive. Standardized reporting tools were implemented to measure progress against goals. This quarter the Funding Group completed an analysis some 231+ PWs to determine the readiness of these PWs for closeout. Results of that analysis indicated that applied payments would be required by RSD to clear the debt remaining on these PWs before any closeout activity could proceed. 2. Closeout Project Deliverables/Updates The Funding Team continues to monitor the closeout process. To date, 614 PWs have been transmitted to GOHSEP for closeout. GOHSEP has officially closed 241 of the 614 PWs submitted and forwarded those 241 PWs to FEMA for final close-out. FEMA has issued final close out for 145 of the 241 PWs. The status of each of the 614 PWs is detailed in Item 7 – Closeout Status Log.
8
Quarterly Report ending September 30, 2012
Item 4. Environmental & Historic Preservation (EHP) – updated by Dodie Scope: Continued support on multiple Environmental and Historic Preservation issues including design reviews on SOI compliant building rehabilitation as well as memoranda of agreements and streamlined Section 106 consultations between RSD, GOHSEP, FEMA, SHPO, & The Advisory Council on Historic Preservation in accordance with the Secondary programmatic Agreement (2PA). Project Deliverables/Updates Armstrong: The contract for construction was awarded to CDW Services, LLC. Notice to proceed was awarded in September 2012 and the substantial completion for the mothballing of the school is anticipated March 2013. Augustine: The construction contract for mothballing of the school was awarded to CDW Services, LLC and notice to proceed was issued in July 2012. Anticipated substantial completion for the mothballing of the school was moved forward to February 2013. Bell: Continuing damage to the main facility required additional removal of interior finishes for structural inspection to assist in completion of the documents for the mothballing scope of work. Additional damages to the chapel, part of the main building, may require more finish removal which will be need review by FEMA as well. Construction documents for the revised roof repair scope of work were bid July 2012. Notice to proceed for the roof repair construction contract was issued September 2012 with an expected date of completion, June 2013. Conditions assessments for the main buildings have been started and are on hold pending selective finish removal on going concurrent with other stabilization activities. Carver: The value engineered project is waiting on notice to proceed into construction pending Owner’s direction. The interpretive plan is in process working with the community to develop a display representative of the 1950’s Orleans Public Schools Master Plan. Colton: An “End of Fieldwork Letter” has been received from Goodwin and Associates regarding the additional ten square meters of excavation required as mitigation to the unauthorized trench digging. Conclusion of this work should satisfy the mitigation required by FEMA on the site. Minor subsurface work relating to SWB tie-in is being monitored by FEMA currently. The revised date for substantial completion is March 2013. Drew: Design development drawings are due shortly. The AE has coordinated design decisions affecting historic properties through EHP and SHPO with preliminary acceptance of the additions being sympathetic and in accordance to SOI standards. The parts I&II State Commercial Tax Credit application has been prepared and is ready to submit to SHPO. Douglass: Schematic design has just been received from the AE. The template of treatments for the character defining features is outstanding and submission to EHP is pending receipt of the information. Frantz: The interpretive display working group will be re convened consisting of Kevin Ferguson, Mercy Hodge, Larry Jordan, Lynn Wiltz and Nathan Schwam. They anticipate coordination with the Ruby Bridges Foundation to finalize the interpretive display, a period classroom, with pictures and inspirational quote. The project manager has requested information on potentially sealing the previously painted brick due to evidence of brick saturation following hurricane Isaac. FEMA historian suggested the AE review the application of a silane based transparent sealer as a potential material to correct this issue.
9
Quarterly Report ending September 30, 2012
Haley: Construction activities are proceeding for mothballing the historic building and are anticipated to be complete early November 2012. Review of onsite activities during construction indicated the work is proceeding according to the plans in conformance to the standards as reviewed by FEMA. Hansberry: Construction activities are proceeding for mothballing the historic building and are anticipated to be complete November 2012. Review of onsite activities during construction indicated the work is proceeding according to the plans in conformance to the standards as reviewed by FEMA. Jeff: Construction documents for mothballing were finalized and bid opening was July 2012. Notice to proceed was issued September 2012 and construction activities should be complete by March 2013. Jones: Plans for mothballing are complete and have been bid. Notice to proceed was issued September 2012 with projected completion March 2013. Lafon: Bids were received and were greatly in excess to the available funding. Value engineering appears infeasible due to the skewed pricing of over 300% of AFC. EHP recommended a greatly simplified interpretive display taking into account the skew that will be present. The A/E firm is revising their work for re-bidding. McDonough 42: Schematic design has been submitted for review with the character defining treatment matrix. Revisions to the matrix have been requested before submission to the EHP for review. It is anticipated that the design with the addition will be in conformance to the SOI standards due to the location and scale of the addition. Mondy: The sheds were partially destroyed in a fire in October 2012. Demolition of the cottage scope of work is approved by FEMA but on hold pending Owner direction. The two burned trailers (sheds) were demolished after obtaining properly procured quotes from various vendors. Shaw: Review of onsite activities during construction indicated the work is proceeding according to the plans in conformance to the standards as reviewed by FEMA. Completion of construction is anticipated to be October 2012. Booker T Washington: Final submissions of the HABS level II documentation by CARMA are being compiled; a HABS project number has been assigned for the submission to the National Park Service for recordation. The cooperative endeavor agreement with the Preservation Resource Center is still actively being pursued. Legal issues relative to procurement are being researched to allow the recoupment to proceed. Interior demolition is 65% complete. Currently, the items for recoupment are being stored on site pending resolution of the CEA. Wheatley: EHP review is complete for Wheatley although some value engineering required delay of the bid. New bid documents are received August 2012. Content of the educational materials for the interpretive display are under review for the development of panels within the school, a power point presentation and a brochure. Sophie Wright: Early options for the renovations were presented for SHPO discussions relative to interior space planning and treatment of windows. Schematic design submission is expected this week. State Historic Tax Credit Design Reviews: Tax credit applications, parts 1 and 2, for Audubon, and Drew are complete and will be send to SHPO this week. These submissions are “test” cases pending a rulings letter regarding the applicability of SCTC for these projects.
.
10
Quarterly Report ending September 30, 2012
Part II Item 5. Summary of FEMA Funding
Contents Debris Removal/Demolition Costs Emergency Protective Measures Emergency Transportation Immediate Re‐Occupation Costs Management Costs Permanent Facility Repair Permanent Facility Replacement Stabilization/Temporary Roof Repair Temporary Facility and related costs
Federal Obligated
Federal Paid
$ 165,343,863.17 $ 2,500.00 $ 1,554,247.34 $ 27,244,062.66 $ 4,183.28 $ 17,816,076.92 $ 33,043,320.45 $ 1,117,565,719.89 $ 475,407.24 $ 141,297,695.77
$ 79,420,906.28 $ 2,500.00 $ 1,382,130.66 $ 23,916,354.40 $ 4,183.28 $ 12,075,820.51 $ 4,398,220.27 $ 451,120,411.99 $ 329,066.64 $ 109,394,636.85
$ 85,922,956.89 $ ‐ $ 172,116.68 $ 3,327,708.26 $ ‐ $ 5,740,256.41 $ 28,645,100.18 $ 666,445,307.90 $ 146,340.60 $ 31,903,058.92
$ 682,044,230.88
$ 822,302,845.84
Total $ 1,504,347,076.72
Balance
The total $1,504,347,076.72 obligated FEMA dollars reflects a $1,202,584.89 decrease from last quarter’s total obligation. This reduction is largely attributed to FEMA de-obligation of funds associated with the Contents rollup PW 19300. The status of the federal obligated dollars will continue to be in a state of flux until FEMA completes all de-obligations associated with the Single Settlement Request.
11
Quarterly Report ending September 30, 2012
Item 6. Summary of Reimbursements Against Facilities Master Plan Alternate Project. To date, documentation has been submitted in the amount of $418,719,488 to GOHSEP in the form of RRF’s. A total of $194,059,471 has been received; $2,392,761 has been allocated for the replenishment of Harrah’s and other sources used to fund prior project work. This reflects an increase of $52,285,995 of documented expenses; $29,002,213 in receipts, and an additional $25,683,620 applied to advances over the second quarter’s results.
Total Original Amount
Project Name
Total Review Amount Currently on LAPA
Total Amount Received
Total Amount Received (Replenishing Alt. Source)
Total Amount Applied to Advances
Total Receipts
Armstrong - Mothballing
$
116,919.60
$
116,919.60
$
116,919.60
$
-
$
Assessments (710253)
$
156,392.80
$
156,392.80
$
156,392.80
$
-
$
Assessments (710258)
$
128,946.00
$
128,946.00
$
128,946.00
$
-
Assessments (710585)
$
145,162.00
$
145,162.00
$
145,162.00
$
Augustine - Mothballing
$
419,901.51
$
419,901.51
$
419,644.31
BAS
$
238,962.58
$
238,962.58
$
238,962.58
Behrman - Roof
$
778,319.34
$
778,319.04
$
Bell - Demo
$
6,275.70
$
6,275.70
$
6,088.20
$
Bell - Mothballing
$
256,788.40
$
256,788.40
$
67,275.40
$
189,513.00
$
Bell - Roof
$
50,067.97
$
50,067.97
$
49,795.93
$
272.04
$
Bell - Shoring
$
1,263,545.70
$
1,230,295.70
$
1,168,512.45
$
-
$
Bienville - New
$
19,126,930.75
$
19,126,980.74
$ 17,991,361.26
$
-
$
1,116,987.14
Bienville - Test Pile
$
38,694.74
$
38,694.74
$
3,400.00
$
-
$
35,294.74
Bradley - New
$
237,431.70
$
237,431.70
$
237,431.70
$
-
$
BTW - Demo
$
516,685.34
$
516,685.34
$
505,870.99
$
-
$
BTW - New & Auditorium
$
1,883,379.18
$
1,883,379.18
$
1,883,379.18
BTW - Renovations
$
687,597.73
$
687,597.73
$
BTW - Soil Testing
$
19,880.55
$
19,880.55
$
Carver - Demo
$
22,308.57
$
22,308.57
Carver - New
$
2,665,242.67
$
Carver - Test Pile
$
83,422.13
Cohen - HVAC
$
Colton - Renovations
$
-
$
101,429.60
-
$
156,392.80
$
-
$
128,946.00
-
$
-
$
145,162.00
$
-
$
$
404,654.31
$
-
$
$
238,962.58
$
778,319.04
$
771,560.44 -
$ $
$
-
$
$
-
$
19,880.55
$
-
$
$
22,308.57
$
-
$
2,665,242.67
$
2,145,248.02
$
-
$
$
83,422.13
$
16,231.00
$
-
$
18,242.85
$
18,242.85
$
18,242.85
$
-
$
19,885,450.50
$
19,885,450.50
$ 17,220,372.18
$
-
$
-
(15,490.00)
(14,990.00) 6,758.60 -
$
6,088.20
$
222,804.40
-
$
50,067.97
-
$
1,168,512.45
(33,984.00)
$ 19,108,348.40 $
38,694.74
-
$
237,431.70
-
$
505,870.99
-
$
1,883,379.18
$
687,597.73
-
$
19,880.55
-
$
22,308.57
519,994.65
$
2,665,242.67
67,191.13
$
83,422.13
$
18,242.85
687,597.73
2,664,067.64
$ 19,884,439.82
Colton - Test Pile
$
36,453.84
$
36,453.84
$
8,132.00
$
-
$
28,321.84
$
36,453.84
Commissioning (665699)
$
918,264.48
$
918,264.48
$
189,981.01
$
-
$
659,465.97
$
849,446.98
Commissioning (689385)
$
1,036,726.72
$
1,036,726.72
$
456,830.72
$
-
$
262,745.00
$
719,575.72
Commissioning (694714)
$
278,634.69
$
278,634.69
$
223,819.19
$
-
$
54,815.50
$
278,634.69
Craig - Canopies
$
6,838.05
$
6,838.05
$
6,838.05
$
-
$
-
$
6,838.05
Craig - Elevator
$
9,369.67
$
9,369.67
$
8,468.30
$
-
$
-
$
8,468.30
Craig - Reno
$
1,712,608.28
$
1,712,607.98
$
$
-
$
$
1,712,607.98
12
-
1,712,607.98
Quarterly Report ending September 30, 2012
Total Original Amount
Project Name
Total Review Amount Currently on LAPA
Crocker - New
$
16,070,609.87
$
16,065,513.87
Crocker - Test Pile
$
46,497.39
$
DAC - JCSRS
$
2,089,363.73
$
Total Amount Received
Total Amount Received (Replenishing Alt. Source)
Total Amount Applied to Advances
Total Receipts
$ 15,150,838.21
$
-
$
914,675.66
46,497.39
$
45,975.32
$
-
$
522.07
$
46,497.39
2,089,363.73
$
1,183,738.07
$
-
$
806,980.92
$
1,990,718.99
361,347.15
DAC - Modulars
$
361,347.15
$
361,347.15
$
Derham(NOHSSC) - Modulars
$
103,092.78
$
103,092.78
$
-
Dibert - Roof
$
25,188.87
$
25,188.87
$
Douglas - Roof
$
2,354.26
$
2,354.26
$
2,354.26
$
Douglass - HVAC
$
28,619.90
$
28,619.90
$
28,619.90
Douglass - Reno
$
130,932.65
$
130,932.65
$
Drew - Reno
$
218,481.90
$
218,481.90
Drew - Roof
$
385,931.73
$
Dunbar - New
$
468,985.94
Edison - Demolition
$
5,000.00
FC Williams - New
$
FC Williams - Reno and Repair
103,092.78
-
$
-
$
$
7,451.47
-
$
361,347.15
$
103,092.78
$
17,737.40
$
25,188.87
-
$
0.00
$
2,354.26
$
-
$
-
$
28,619.90
130,932.65
$
-
$
-
$
130,932.65
$
218,481.90
$
-
$
-
$
218,481.90
385,931.73
$
362,904.93
$
$
-
$
385,931.73
$
464,345.94
$
464,071.40
$
-
$
-
$
464,071.40
$
5,000.00
$
5,000.00
$
-
$
-
$
5,000.00
22,011,151.81
$
21,988,893.57
$ 19,981,358.72
$
-
$
933,238.43
$ 20,914,597.15
$
382,025.40
$
382,025.40
$
-
$
-
$
382,025.40
$
382,025.40
FC Williams - Test Pile
$
41,722.27
$
41,722.27
$
-
$
-
$
41,722.27
$
41,722.27
Fencing - Various Sites
$
8,692.45
$
(8,692.45)
$
Fisk-Howard - Demolition
$
447,367.43
$
Fisk-Howard - New
$
740,510.10
Frantz - Reno & Addition
$
Frantz - Roof
$
Frantz - Test Pile
-
-
$ $
$ 16,065,513.87
23,026.80
$
8,692.45
$
-
$
447,367.43
$
447,367.43
$
-
$
-
$
447,367.43
$
503,078.40
$
474,863.40
$
-
$
-
$
474,863.40
17,666,719.69
$
17,650,338.63
$ 16,305,935.35
$
-
$
1,344,403.28
204,109.00
$
204,109.00
$
173,324.36
$
-
$
30,784.64
$
204,109.00
$
39,863.99
$
39,863.99
$
36,095.99
$
-
$
3,768.00
$
39,863.99
Gaudet/Lake Forest - Roof Gaudet/Lake Forest - Soil Testing
$
276,541.40
$
276,541.40
$
253,761.20
$
$
5,149.05
$
5,149.05
$
5,149.05
$
Gentilly Terrace - Roof
$
62,784.55
$
62,784.55
$
19,224.21
$
GOHSEP Migrations
$
25,778,958.51
$
25,684,668.40
$
Gregory - Demolition
$
126,457.81
$
126,457.82
$
Guste - Renovations
$
911,665.40
$
911,665.40
$
Guste - Roof & Elevator
$
1,016,617.77
$
1,015,640.53
$
Guste - Science Lab
$
34,089.00
$
34,089.00
$
Haley - Demo
$
187.49
$
187.49
$
Haley - Mothballing
$
428,816.87
$
428,816.87
$
426,593.88
Hansberry - Mothballing
$
332,692.21
$
332,692.21
$
Henderson - Roof
$
79,272.31
$
79,272.31
Henry Allen - Roof
$
388,907.99
$
Hughes - New
$
29,642,647.87
Jeff - Mothballing
$
72,287.67
17,672.95
$ 17,650,338.63
$
-
$
276,541.40
$
-
$
5,149.05
$
62,784.55
$
25,887.39
$
-
$
25,684,668.40
$
-
$
0.01
$
126,457.82
$
-
$
911,665.40
$
911,665.40
$
-
$
$
1,015,640.53
-
$
-
$
$
34,089.00
-
$
-
$
$
-
$
(11,990.00)
$
414,603.88
163,201.67
$
-
$
57,197.54
$
220,399.21
$
76,670.01
$
2,602.30
$
$
79,272.31
374,576.67
$
235.00
$
367,439.00
$
6,902.67
$
374,576.67
$
29,603,348.59
$
2,148,107.71
$
-
$
27,454,984.61
$
72,287.67
$
72,287.67
$
-
$
(10,992.00)
13
-
22,780.20
-
126,457.81 1,015,640.53
34,089.00 -
-
$ 25,684,668.40
$
-
$ 29,603,092.32 $
61,295.67
Quarterly Report ending September 30, 2012
Total Original Amount
Project Name
Total Review Amount Currently on LAPA
Total Amount Received
Total Amount Received (Replenishing Alt. Source) 433,079.95
Total Amount Applied to Advances
Johnson - Roof
$
500,781.04
$
500,781.04
$
67,701.09
$
Jones - Mothballing
$
179,854.67
$
179,854.67
$
179,854.67
$
-
$
Kennedy - Demo
$
94,615.47
$
94,615.47
$
90,528.77
$
-
$
Lafayette - Roof
$
868,335.19
$
868,335.19
$
868,335.19
$
-
Lafon - Demo
$
73,204.69
$
73,204.69
$
73,204.69
$
-
Lake Area - New
$
39,431,961.90
$
39,305,722.95
$
367,738.65
$
-
$
Lawless - Fence
$
57,932.03
$
57,932.03
$
57,400.00
$
Lawless - New
$
99,067.25
$
99,067.25
$
99,067.25
$
Lawless - Soil Testing
$
4,313.05
$
4,313.05
$
4,313.05
LB Landry - Demo
$
1,082,580.09
$
1,081,697.54
$
LB Landry - New
$
59,543,243.56
$
59,543,086.75
$
Little Woods - New
$
11,768,270.99
$
11,768,270.99
$ 11,261,693.30
$
Little Woods - Test Pile
$
47,625.83
$
47,625.83
$
47,625.83
$
Live Oak - Doors
$
37,421.92
$
37,421.92
$
14,904.52
$
-
$
Live Oak - Roof & Floor
$
75,956.18
$
75,956.18
$
32,588.26
$
Livingston - New
$
2,330,120.80
$
2,330,120.80
$
1,805,369.25
$
Livingston - Test Pile
$
57,254.13
$
57,254.13
$
57,254.13
Master Plan
$
1,272,634.51
$
1,272,634.51
$
McDonogh - Roof
$
463,515.34
$
463,515.34
McDonogh 15 Waterproofing/Masonry
$
323,411.12
$
McDonogh 28 - Roof
$
48,103.54
McDonogh 32 - Roof
$
McDonogh 42 - HVAC
532.03
$
Total Receipts -
$
500,781.04
$
161,868.67
-
$
90,528.77
$
-
$
868,335.19
$
-
$
73,204.69
(17,986.00)
38,937,984.30
$ 39,305,722.95
$
-
$
57,932.03
-
$
-
$
99,067.25
$
-
$
-
$
4,313.05
1,081,422.16
$
-
$
-
$
1,081,422.16
4,209,241.07
$
-
$
55,333,845.68
-
$
467,362.50
-
$
$ 11,729,055.80 $
47,625.83
22,517.40
$
37,421.92
$
639.52
$
75,956.18
-
$
524,751.55
$
2,330,120.80
$
-
$
-
$
57,254.13
1,272,634.51
$
-
$
-
$
1,272,634.51
$
2,629.00
$
460,886.34
$
-
$
463,515.34
323,411.12
$
274,870.81
$
13,507.15
$
$
321,087.56
$
48,103.54
$
48,103.54
$
406,144.72
$
406,144.72
$
399,194.92
$
$
106,917.32
$
106,917.32
$
10,994.81
$
-
$
McDonogh 42 - Renovation
$
205,748.85
$
68,582.95
$
68,582.95
$
-
$
McDonogh 42 - Roof
$
379,731.51
$
379,731.51
$
379,731.51
$
-
Mondy - Demolition
$
1,767.30
$
1,767.30
$
1,579.80
$
-
Mondy - Mothballing
$
75,510.80
$
75,510.80
$
75,510.80
$
-
$
$
64,518.80
Morial - Fencing
$
37,750.09
$
37,750.09
$
37,750.09
$
-
$
-
$
37,750.09
NO HS Signature Center
$
881,053.94
$
881,053.94
$
881,053.94
$
-
$
-
$
881,053.94
OIG
$
136,006.00
$
136,006.00
$
136,006.00
$
-
$
-
$
136,006.00
Osborne - New
$
19,064,676.50
$
19,048,431.50
$ 16,656,303.65
$
-
$
1,126,857.23
Osborne - Test Pile
$
29,978.89
$
29,978.89
$
6,060.00
$
-
$
23,918.89
Parkview - New
$
21,821,731.22
$
21,821,146.87
$ 20,372,236.48
$
-
$
1,020,572.26
Parkview - Test Pile
$
44,485.91
$
44,485.91
$
$
-
$
35,622.91
Priestley - Refurbishment
$
29,032.00
$
29,032.00
$
$
-
$
-
$
Priestley - Soil Testing
$
3,606.00
$
3,606.00
$
3,606.00
$
-
$
-
$
Project Management
$
31,864,163.90
$
31,370,939.01
$
8,603,883.82
$
-
$
14
8,863.00 -
42,728.40
6,949.80
-
$ 59,543,086.75
32,709.60
$
-
$
48,103.54
$
-
$
406,144.72
$
106,917.32
-
$
68,582.95
$
-
$
379,731.51
$
-
$
1,579.80
95,922.51
(10,992.00)
22,767,055.19
$ 17,783,160.88 $
29,978.89
$ 21,392,808.74 $
44,485.91 3,606.00
$ 31,370,939.01
Quarterly Report ending September 30, 2012
Total Original Amount
Project Name
Total Review Amount Currently on LAPA
Total Amount Received
Total Amount Received (Replenishing Alt. Source)
Total Amount Applied to Advances
Reed - Bleacher Installation
$
69,565.14
$
69,565.14
$
68,770.14
$
795.00
$
Reed - Wall
$
12,287.48
$
12,287.48
$
231.20
$
11,535.80
$
Total Receipts -
520.48
$
69,565.14
$
12,287.48
RFQs
$
2,498.42
$
2,498.42
$
494.96
$
-
$
-
$
494.96
S Williams - HVAC
$
422,267.55
$
422,267.55
$
421,995.53
$
-
$
-
$
421,995.53
S Williams - Play Yard
$
218,483.40
$
214,983.40
$
29,172.10
$
-
$
185,811.30
$
214,983.40
Schaumburg - Chillers
$
201,300.85
$
201,300.85
$
$
-
$
201,098.52
$
201,098.52
Schaumburg - Windows
$
1,019,714.36
$
1,019,714.36
$
980,328.20
$
-
$
39,386.16
$
1,019,714.36
Shaw - Mothballing
$
417,619.85
$
417,619.85
$
290,201.85
$
-
$
127,418.00
$
417,619.85
Terrell - Demo Various Roofs (HMS CFMS 694721) Various Roofs (RCL CFMS 694717)
$
36,193.01
$
36,193.01
$
35,937.67
$
-
$
-
$
35,937.67
$
5,994.38
$
5,994.38
$
5,994.38
$
-
$
-
$
5,994.38
$
51,734.35
$
51,734.35
$
44,181.86
$
$
-
$
51,734.35
Village de Lest - Subsidence
$
89,285.38
$
89,285.38
$
89,285.38
$
$
-
$
89,285.38
Walker - Auditorium
$
189,199.20
$
189,199.20
$
176,323.60
$
$
-
$
189,199.20
Wheatley - Construction
$
1,289,340.42
$
1,207,413.64
$
1,201,968.64
$
-
$
$
1,207,413.64
Wheatley - Demolition
$
176,988.60
$
176,988.60
$
176,988.60
$
-
$
-
$
176,988.60
Wheatley - Soil Testing
$
4,626.55
$
4,626.55
$
4,626.55
$
-
$
-
$
4,626.55
Wheatley - Test Pile
$
48,294.26
$
48,294.26
$
48,294.26
$
-
$
-
$
48,294.26
Wilson - Cottage
$
47,352.76
$
47,352.76
$
18,303.02
$
-
$
29,049.74
$
47,352.76
Wilson - Renovations
$
27,809,811.63
$
27,720,003.94
$
279,734.07
$
-
$
27,440,269.87
$ 27,720,003.94
Woodson - New
$
19,777,334.02
$
19,777,334.02
$ 17,742,330.69
$
-
$
1,001,180.28
$ 18,743,510.97
$
418,719,488.11
$
417,293,157.19
$ 194,059,470.91
$ 2,392,760.76
$ 216,123,270.60
$ 412,575,502.27
Grand Total
15
-
7,552.49 12,875.60
5,445.00
Quarterly Report ending September 30, 2012
Item 7. Closeout Status Log The Funding Team continues to monitor the closeout process. To date, 614 PWs have been transmitted to GOHSEP for closeout. GOHSEP has officially closed 241 of the 614 PWs submitted and forwarded those 241 PWs to FEMA for final close-out. FEMA has issued final close out for 145 of the 241 PWs. The facilities and PWs are listed below:
PW Number 8779 10006 10903 11352
Facility/ Campus Laurel Elementary School Walter L. Cohen Sr. High School Mahalia Jackson Elementary School Little Woods Elementary School
Building Name
Category E
Total Obligated
Date of GOHSEP Request
-
2/20/2012
$
Date of FEMA Request
FEMA Complete Date
Bldg. B - Main Walter L. Cohen Sr. HS
E
$
-
4/14/2011
6/8/2011
6/8/2011
6/30/2011
Main Building
E
$
-
5/23/2011
7/22/2011
7/22/2011
7/27/2011
Portable Building
E
$
-
5/3/2011
Kitchen
E
Main Building
E
5/3/2011
5/3/2011
11363
New Orleans Center for Health Careers Sarah T. Reed Senior High School
11372
Bell, Andrew J. Junior High School
Bldg. D
E
11373
Gentilly Terrace Elementary School
Lounge/Auditorium
E
$
-
5/3/2011
Main Building
E
$
-
2/9/2011
Main Building
E
$
-
5/23/2011
11355
Date of GOHSEP Complete
$
$
$
2/18/2012 -
-
5/23/2011 2/20/2012
11382
McDonogh Elementary School #42 Walter L. Cohen Sr. High School
11385
Gentilly Terrace Elementary School
Main Bldg
E
$
-
5/3/2011
9/2/2011
9/2/2011
11386
Gentilly Terrace Elementary School
Main Building
E
$
-
2/9/2011
5/6/2011
5/6/2011
Portable Building
E
$
-
2/9/2011
Building C
E
$
0.01
2/9/2011
4/29/2011
4/29/2011
Building B
E
$
-
4/9/2012
Portable #4
E
$
-
2/20/2012
Kitchen
E
$
-
2/20/2012
Main Bldg.
E
$
-
2/20/2012
Portable #3
E
$
-
2/20/2012
Main Bldg.
E
$
-
2/20/2012
Main Bldg.
E
$
-
2/20/2012
11377
11388 11400
Gentilly Terrace Elementary School Andrew J. Bell Junior High School
11418
Williams, Sylvanie F., Elementary School Little Woods Elementary School
11419
New Orleans Center for Health Careers
11407
11422 11428 11449 11453
Lawless High School Little Woods Elementary School Cohen, Walter L., Senior High School Abramson, Marion Senior High
16
9/8/2011
5/3/2011
Quarterly Report ending September 30, 2012 PW Number 11463 11471 11476 11477 11481 11485 11500 11524 11525 11535 11612 11651 11736 11794
Facility/ Campus Fisk-Howard Elementary School Bell, Andrew J. Junior High School Andrew J. Bell Junior High School Andrew J. Bell Junior High School Dunbar Elementary School MCDonogh #28 Middle School Village De Lest Elementary School Dunbar Elementary School Mary Church Terrell Elementary School Little Woods Elementary School New Orleans Center for Health Careers Walter L. Cohen Sr. High School Gregory, F. W. Junior High Waters Elementary School - Modular Classroom 7
Building Name
Total Obligated
Category
$
Date of GOHSEP Complete
Date of FEMA Request
FEMA Complete Date
2/9/2011
4/29/2011
4/29/2011
5/3/2011
Building B
E
Kitchen
E
Building B
E
$
-
2/9/2011
5/4/2011
5/4/2011
Building A
E
$
-
2/9/2011
5/4/2011
5/4/2011
Classroom Bldgs 108109
E
$
-
5/3/2011
5/31/2011
5/31/2011
Main Bldg.
E
$
0.01
9/5/2012
Building 1
E
$
-
4/9/2012
Main Building
E
2/9/2011
5/4/2011
5/4/2011
Terrel ES
E
2/9/2011
5/31/2011
5/31/2011
Main Building
E
2/9/2011
5/4/2011
5/4/2011
Main Bldg.
B
$
-
2/20/2012
Main Building
E
$
0.01
2/9/2011
7/11/2011
7/11/2011
Bldg. B.
E
$
-
2/20/2012
Portables #1-7
E
$
-
4/21/2011
Main Building
E
$
-
2/9/2011
8/12/2011
8/12/2011
Building A
E
$
-
2/9/2011 7/11/2011
7/11/2011
2/9/2011
6/25/2011
6/25/2011
$
-
Date of GOHSEP Request
-
$ $
2/20/2012
0.01
$
-
11809
Charles R. Drew Elementary School Fisk-Howard Elementary School
11814
James Weldon Johnson Elementary School
Building 1
E
$
-
2/9/2011
11826
Valena C. Jones Elementary School
Modular Buildings
E
$
-
2/9/2011
11856
Oretha C. Haley Elementary School
Main Building
E
Main Building Portable Classroom #2 Portable Classroom #1
E
$
-
2/9/2011
7/11/2011
7/11/2011
E
$
-
2/9/2011
8/12/2011
8/12/2011
11955
Edgar P. Harney Elementary School Wheatley Elementary School Wheatley Elementary School
E
$
-
2/9/2011
8/12/2011
8/12/2011
11956
Charles R. Drew Elementary School
Main Building
E
$
-
5/23/2011
11957
Valena C. Jones Elementary School
Portable Classroom 4
E
$
-
2/9/2011
4/18/2011
4/18/2011
11805
11864 11950
$
17
0.01
6/7/2011
6/7/2011
7/1/2011
Quarterly Report ending September 30, 2012 PW Number 11961
Facility/ Campus Wheatley Elementary School
Building Name
Category
Building #1
E
Date of GOHSEP Request
Total Obligated $
-
Date of GOHSEP Complete
Date of FEMA Request
2/9/2011
Main Bldg.
E
$
-
2/20/2012
11986
Craig, Joseph A., Elementary School Wheatley Elementary School
Bldg. # 2
E
$
-
2/20/2012
12147
Bell, Andrew J., Junior High School
Bldg. A
E
$
-
4/9/2012
12279
Charles J. Colton Junior High School
Main Building
E
$
-
2/9/2011
4/18/2011
4/18/2011
Main Building
E
$
-
2/9/2011
5/6/2011
5/6/2011
Library
E
$
-
2/9/2011
$
-
5/23/2011
5/11/2011
5/11/2011
6/25/2011
6/25/2011
5/4/2011
5/4/2011
4/18/2011
4/18/2011
11963
12280 12285
Oretha C. Haley Elementary School Thomy Lafon Elementary School
Portable #7
E
12288
Vorice Jackson Waters Elementary School Lake Area Middle School
Bldg. 3 Large Gym
E
$
-
2/20/2012
12290
Jordan, Barbara Elementary School
Modular #7
E
$
-
2/20/2012
Bldg. D-Lawn Equipment
E
$
0.01
9/5/2012
Building 11
E
-
2/9/2011
Kitchen
E
Building 10
E
$
-
2/9/2011
Building 12
E
$
-
2/9/2011
Main Bldg.
E
Building 2
E
$
-
5/23/2011
Building 9
E
$
-
2/9/2011
Bld. 3 - Large Gym
E
0.01
2/18/2012
Modular 2
E
-
2/9/2011
Modular #4
E
Building 2
E
12287
12291 12296 12297 12298 12302 12304 12305 12306 12310 12313
Village de'Lest Elementary School Barbara Jordan Elementary School Lake Area Middle School Barbara Jordan Elementary School Barbara Jordan Elementary School New Orleans Center for Creative Arts - Live Oak Middle School Hughes Elementary School Barbara Jordan Elementary School Lafon, Thomy, Elementary School Barbara Jordan Elementary School
12331
Jordan, Barbara Elementary School Ray Abrams Elementary School
12333
Jordan, Barbara Elementary School
Modular #6
E
12334
Vorice Jackson Waters Elementary School
Building 3 (Large Gym)
E
12319
$ $
-
$
$ $
2/20/2012
$
$ $
18
2/20/2012
-
$
FEMA Complete Date
2/20/2012 -
-
2/9/2011 2/20/2012
-
2/9/2011
7/1/2011
Quarterly Report ending September 30, 2012 PW Number 12336 12339 12340 12342 12343 12344
Facility/ Campus McDonogh #15 Creative Arts Magnet Clark, Joseph S., High School Jordan, Barbara Elementary School Barbara Jordan Elementary School Vorice Jackson Waters Elementary Bauduit Elementary School
Building Name
Date of GOHSEP Request
Total Obligated
Category
Mc 15 Lodge Bldg. B - Gym Cafeteria
E
$
0.01
9/10/2012
E
$
-
2/20/2012
Bldg. #8
E
$
-
2/20/2012
Modular #3
E
$
-
5/3/2011
Portable #6
E
$
-
2/9/2011
Main Building
E
$
-
5/3/2011
Date of GOHSEP Complete
Date of FEMA Request
5/18/2011
5/18/2011
Portable #4
E
$
-
5/3/2011
12348
Vorice Jackson Waters Elementary School Lake Area Middle School
Building 1
E
$
-
5/3/2011
12349
Ernest N. Dutch Morial Elementary School
Annex Building
E
$
-
2/9/2011
12355
Valena C. Jones Elementary School
Modular Buildings
E
$
-
2/9/2011
12365
Vorice Jackson Waters Elementary School
Building 1
E
$
-
2/9/2011
5/6/2011
5/6/2011
12407
Johnson C. Lockett Elementary School
Building B
E
$
-
2/9/2011
4/15/2011
4/15/2011
12492
Martin Luther King Jr. Elementary School
Main Bldg
E
$
-
5/3/2011
10/27/2011
10/27/2011
12493
John W. Hoffman Elementary School
Building F
E
$
-
2/9/2011
4/15/2011
4/15/2011
12494
Sherwood Forest Elementary School
Building 4
E
$
-
2/9/2011
5/4/2011
5/4/2011
12495
Eisenhower, Dwight D., Elementary School
Portable Buildings
E
$
-
4/9/2012
12496
Sherwood Forest Elementary School
Bldg. #3
E
$
-
2/20/2012
A.J. Bell
E
$
-
4/14/2011
6/3/2011
6/3/2011
Building 5
E
$
-
2/9/2011
4/15/2011
4/15/2011
4/15/2011
4/15/2011
12346
12500
Andrew J. Bell Junior High/Alternative HS Lake Area Middle School
12501
John W. Hoffman Elementary School
Building B
E
$
-
5/3/2011
12506
Sherwood Forest Elementary School
Portable 2
E
$
-
2/9/2011
Building 2
E
$
-
5/23/2011
Building 2
E
$
-
2/9/2011
12498
12508 12511
Sherwood Forest Elementary School Lake Area Middle School
19
FEMA Complete Date
10/28/2011
7/1/2011
Quarterly Report ending September 30, 2012 PW Number 12512
Facility/ Campus Shaw, John A. Elementary School
12514
Sherwood Forest Elementary School John A. Shaw Elementary School
12516
Fischer, William J., Elementary School
12513
Building Name
Date of GOHSEP Request
Total Obligated
Category
Shaw ES
E
$ (0.29)
Portable 1
E
$
-
2/9/2011
Portable 3
E
$
-
2/9/2011
Kitchen/Cafeteria
E
Building 4
E
$
Date of GOHSEP Complete
Date of FEMA Request
FEMA Complete Date
4/29/2011
4/29/2011
5/10/2011
9/10/2012
-
4/9/2012
Building 4-Gym
E
12522
Sherwood Forest Elementary School Lake Area Middle School John A. Shaw Elementary School
Main Building
E
$
-
2/9/2011
4/29/2011
4/29/2011
5/10/2011
12523
John W. Hoffman Elementary School
Building A
E
$
-
2/9/2011
4/29/2011
4/29/2011
5/4/2011
Portable 1
E
$
-
5/23/2011
Building A
E
$
-
4/14/2011
9/9/2011
9/9/2011
9/16/2011
6/25/2011
6/25/2011
7/1/2011
12519 12520
12525
$ $
-
5/23/2011 9/5/2012
12534
Lawless High School Fisk-Howard Elementary School
12536
Sherwood Forest Elementary School
Portable 3
E
$
-
5/23/2011
12538
Sherwood Forest Elementary School
Building 1
E
$
-
5/3/2011
12540
John F. Kennedy Senior High School
Main Building
E
$
-
4/29/2011
12552
Eisenhower, Dwight D., Elementary School
Eisenhower ES
E
$
0.01
9/10/2012
12571
Eisenhower, Dwight D., Elementary School
Portable Buildings
E
$
-
4/9/2012
12574
Lawless High School
Portable 2
E
$
-
5/23/2011
12588
John W. Hoffman Elementary School
Building C
E
$
-
2/9/2011
5/6/2011
5/6/2011
12598
William J. Guste Elementary School
Main Building
E
$
-
2/9/2011
5/6/2011
5/6/2011
12601
John W. Hoffman Elementary School
Building E
E
$
-
5/3/2011
12607
John W. Hoffman Elementary School
Building D
E
$
-
2/9/2011
5/16/2011
5/16/2011
12610
Valena C. Jones Elementary School
Main Building
E
$
-
2/9/2011
5/3/2011
5/3/2011
12675
Thomas Alva Edison Elementary School
Main Building
E
$
-
2/9/2011
5/6/2011
5/6/2011
12677
Martin Behrman Elementary School
Main Building
E
$
-
2/9/2011
5/4/2011
5/4/2011
12679
Waters, Vorice Jackson Elementary
Portable #3
E
$
20
-
9/10/2012
Quarterly Report ending September 30, 2012 PW Number
Facility/ Campus
Building Name
Total Obligated
Category
Date of GOHSEP Request
Date of GOHSEP Complete
Date of FEMA Request
12680
Sherwood Forest Elementary School
Building 1
E
$
-
2/9/2011
5/3/2011
5/3/2011
12682
Johnson C. Lockett Elementary School
Building A
E
$
-
2/9/2011
5/6/2011
5/6/2011
5/4/2011
5/4/2011
5/3/2011
5/3/2011
FEMA Complete Date
Building 2
E
$
-
2/9/2011
12697
Vorice Jackson Waters Elementary School Waters Elementary School - Portable #1 Contents
Portable #1
E
$
-
5/23/2011
12704
Vorice Jackson Waters Elementary
Portable #2
#
$
-
2/9/2011
Waters ES
E
Annex Buildiing 2
E
$
-
2/9/2011
4/29/2011
4/29/2011
5/4/2011
6/30/2011
6/30/2011
7/5/2011
6/30/2011
6/30/2011
7/5/2011
12/5/2011
12/5/2011
12692
12713
Waters, Vorice Jackson Elementary John A. Shaw Elementary School
12714
Mary Church Terrell Elementary School
Mary Church Terrell Elementary School
E
$
-
4/14/2011
12718
Waters Elementary School - Bldg. #4
Building #4
E
$
-
5/3/2011
12722
Langston Hughes Elementary School
Building 1
E
$
-
2/9/2011
Avery Alexander School
E
$
-
5/13/2011
Campus Wide
G
$
-
2/20/2012
Sheds
E
$
-
9/5/2012
Sheds
E
$
-
9/5/2012
$
-
2/20/2012
12712
12747 12772 12773 12777
Avery Alexander Elementary School Phillips, Edward H. Junior High Habans, Paul B., Elementary School Lake Area Middle School
$
-
9/10/2012
Campus Wide
G
12794
Lake Forest Montessori Magnet School Little Woods Elementary School
Modular Classroom
E
$
-
5/13/2011
12795
Gentilly Terrace Elementary School
Portable Building
E
$
-
5/13/2011
Storage Complex Bldg E
E
$
-
4/14/2011
Building 1
E
$
-
2/9/2011
6/25/2011
6/25/2011
7/8/2011
Building E
E
$
-
2/9/2011
7/11/2011
7/11/2011
7/21/2011
Building 1
E
$
-
2/9/2011
7/11/2011
7/11/2011
7/21/2011
Modular #1
E
$
-
5/13/2011
Main Building
E
$
-
2/9/2011
6/30/2011
6/30/2011
7/5/2011
12784
12797 12801 12804
Mahalia Jackson Dr. Martin Luther King Elementary School for Science an F.W. Gregory Junior High School
12817
Edward H. Phillips Junior High School Little Woods Elementary School
12823
William J. Guste Elementary School
12811
21
Quarterly Report ending September 30, 2012
PW Number
Total Obligated
Date of GOHSEP Request
$
-
2/20/2012
$
0.01
9/10/2012
$
-
2/9/2011
$
-
5/23/2011
$
-
5/23/2011
$
-
4/14/2011
$
0.01
9/10/2012
$
-
2/20/2012
Date of GOHSEP Complete
Date of FEMA Request
6/29/2011
6/29/2011
6/30/2011
6/30/2011
7/5/2011
6/30/2011
6/30/2011
7/5/2011
2/9/2011
6/30/2011
6/30/2011
7/5/2011
2/9/2011
7/12/2011
7/12/2011
6/30/2011
6/30/2011
12829
Facility/ Campus Shaw, John A. Elementary School
Portable #4
E
12841
Rabouin Career Magnet High School
Rabouin HS
E
12846
Morris F.X. Jeff Elementary School
Building 1
E
12847
Mahalia Jackson Elementary School
Building C
E
12853
Mahalia Jackson Elementary School
Building B
E
12854
Mahalia Jackson
Administrative/Storage
E
12864
Jeff, Morris F.X., Elementary School
Building #1AAA
E
Sheds
E
Building A
E
$
-
4/14/2011
Main Building
E
$
-
2/9/2011
Building D
E
$
-
5/23/2011
Sheds
E
$
-
2/20/2012
Sheds
E
$
-
2/20/2012
Portable 1
E
Storage Container
E
Building A
E
$
-
Main Building
E
$
-
Auditorium
E
$
-
2/20/2012
12867
12880
Lawless High School Fannie C. Williams Middle School New Orleans High School Signature Centers
12884
Mahalia Jackson Elementary School
12870
12885 12892 12895
Sherwood Forest Elementary School Little Woods Elementary School F.W. Gregory Junior High School
Building Name
Category
$
-
2/9/2011
12910
Reed, Sarah T., Senior High School F.W. Gregory Junior High School Alcee Fortier High School New Orleans High School Signature Centers
12913
Jackson, Mahalia, Elementary School
Admin. Bldg.
E
$
-
2/20/2012
12914
Kennedy, John F., Senior High School
Sheds
E
$
-
2/20/2012
12922
Mondy, George O., Elementary School
Main Bldg.
E
$
Storage Building D
E
$
-
4/14/2011
Portable 2
E
$
-
2/9/2011
Building B
E
$
-
5/3/2011
12898 12903 12908
12924 12926 12929
Mahalia Jackson F.W. Gregory Junior High School Schaumburg Elementary School
$
22
-
FEMA Complete Date
2/20/2012
-
4/9/2012 7/5/2011
Quarterly Report ending September 30, 2012
PW Number 12934
Facility/ Campus New Orleans High School Signature Centers
Building Name
Category
Total Obligated
Date of GOHSEP Request
Main Bldg.
E
$
-
2/20/2012
Lodge
E
$
-
4/9/2012
Main Building
E
$
-
2/9/2011
Modular #5
E
$
-
4/29/2011
12952
Mondy, George O., Elementary School Fannie C. Williams Middle School Little Woods Elementary School
12963
Jordan, Barbara Elementary School
Sheds
E
12981
Andrew H. Wilson Elementary School
Building A
E
$
-
2/9/2011
Main Building
E
$
-
5/3/2011
Sheds
E
$
-
5/23/2011
Building C
E
$
-
2/9/2011
Building A
E
$
-
5/3/2011
Modular #7
E
$
-
5/13/2011
Modular #6
E
$
-
4/29/2011
Sheds
E
0.01
2/18/2012
Building G
E
-
5/3/2011
Sheds
E
$
-
2/20/2012
Sheds
E
$
-
2/20/2012
Sheds
E
$
-
2/20/2012
Sheds
E
$
-
2/20/2012
12935 12945
13053
William J. Guste Elementary School Armstrong (MLK) School F.W. Gregory Junior High School Schaumburg Elementary School Barbara Jordan Elementary School Barbara Jordan Elementary School
13060
Cohen, Walter L., Senior High School
12991 13002 13003 13045 13047
13062 13066 13067
Carver Middle/High School Complex Shaw, John A. Elementary School Shaw, John A. Elementary School
$
-
$ $
13075 13076
McDonogh #42 Elementary School
Sheds
E
$
-
2/20/2012
13077
Drew , Charles R., Elementary School
Sheds
E
$
-
2/20/2012
Modular #5
E
$
-
2/20/2012
Storage Container
E
$
-
9/10/2012
Portable P5
E
Sheds
E
13078 13079 13080 13083
Jordan, Barbara Elementary School Howard, Fisk Elementary Storage Container Parkview Elementary School McNair Elementary School
$ $
23
Date of FEMA Request
FEMA Complete Date
6/30/2011
6/30/2011
7/5/2011
10/11/2011
10/11/2011
10/17/2011
10/27/2011
10/27/2011
10/27/2011
6/27/2011
6/27/2011
7/1/2011
6/30/2011
6/30/2011
7/5/2011
2/20/2012
Drew , Charles R., Elementary School Lockett, Johnson C. Elementary
13071
Date of GOHSEP Complete
-
4/21/2011
0.01
9/5/2012
Quarterly Report ending September 30, 2012
Total Obligated
Date of GOHSEP Request
-
4/9/2012
Date of GOHSEP Complete
Date of FEMA Request
8/12/2011
8/12/2011
4/14/2011
6/25/2011
6/25/2011
7/1/2011
PW Number
Facility/ Campus
13084
Walker, O. Perry, Senior High School
Main Building
E
13092
Carver Middle/High School Complex
Building G
E
13093
Walker, O. Perry, Senior High School
Campus Wide
B
Sheds
E
$
-
5/23/2011
Library Building
E
$
-
Building Name
Category $
$ $
-
5/3/2011
FEMA Complete Date
4/9/2012
13114
McDonough #42 Elementary School Fannie C. Williams Middle School
13116
John F. Kennedy Senior High School
Modular #1
E
$
-
4/21/2011
6/25/2011
6/25/2011
7/8/2011
13119
John F. Kennedy Senior High School
Modular #2
E
$
-
5/13/2011
9/14/2011
9/14/2011
9/15/2011
13121
Langston Hughes Elementary School
Building D
E
$
-
4/14/2011
5/18/2011
5/18/2011
Modular #4
E
$
-
4/29/2011
6/25/2011
6/25/2011
7/8/2011
Main Building
B
Main Building
E
2/9/2011
6/28/2011
6/28/2011
6/30/2011
Classroom Building
E
2/9/2011
7/19/2011
7/19/2011
7/25/2011
Building B
E
$
-
2/9/2011
Modular #5
E
$
-
4/29/2011
6/27/2011
6/27/2011
7/1/2011
Langston Hughes
E
$
-
9/10/2012
Sheds
E
$
-
9/5/2012
13102
13149
John F. Kennedy Senior High School McDonogh Elementary School #7 Albert Wicker Elementary School Samuel J. Green Middle School
13162
Andrew H. Wilson Elementary School
13122 13127 13139
$
-
$ $
4/9/2012 -
0.01
13179
John F. Kennedy Senior High School Hughes, Langston Elementary Jones, Valencia C. Elementary
13193
Mildred C. Osborne Elementary School
Main Building
E
$
-
2/9/2011
4/18/2011
4/18/2011
13226
John F. Kennedy Senior High School
Modular #3
E
$
-
4/29/2011
6/27/2011
6/27/2011
13248
Langston Hughes Elementary School
Building A
E
$
-
4/14/2011
6/29/2011
6/29/2011
13258
Edward H. Phillips Junior High School
Building A
E
$
-
4/14/2011
6/30/2011
6/30/2011
7/5/2011
13272
Fannie C. Williams Middle School
Cafeteria, Kitchen & Court Yard
E
$
-
4/14/2011
6/30/2011
6/30/2011
7/5/2011
13280
Fannie C. Williams Middle School
Fannie C. Williams Middle School
E
$
-
4/14/2011
7/11/2011
7/11/2011
7/21/2011
13170 13173
24
7/1/2011
Quarterly Report ending September 30, 2012
PW Number
Facility/ Campus
13317
Fannie C. Williams Middle School Sophie B. Wright Middle School Alcee Fortier High School New Orleans High School Signature Centers
13342 13348
13289 13300 13310
Building Name
Total Obligated
Category
Date of GOHSEP Request
Date of GOHSEP Complete
Date of FEMA Request
FEMA Complete Date
6/25/2011
6/25/2011
7/8/2011
Administration & Classroom Bldg
E
$
-
4/14/2011
Classroom Building
E
$
-
2/9/2011
Main Building
E
$
-
2/9/2011
6/28/2011
6/28/2011
6/30/2011
Building A
E
$
-
4/21/2011
6/25/2011
6/25/2011
7/8/2011
Mary Church Terrell Elementary School
Main Bldg., Bldg A
E
$
-
4/29/2011
6/3/2011
6/3/2011
7/1/2011
Bienville, Jean Batiste de, Elementary School
Campus Wide
G
$
-
2/20/2012
$
-
9/10/2012 10/27/2011
10/27/2011
10/28/2011
6/28/2011
6/28/2011
6/30/2011
11/30/2011
11/30/2011
Parkview
E
13377
Parkview Fundamental Magnet School B.T. Washington High School
Building B
E
13379
Waters, Vorice Jackson Elementary
Sheds
E
$
-
2/18/2012
Sheds
E
$
-
2/20/2012
Sheds
E
$
-
2/20/2012
Bradley ES
E
$
-
9/10/2012
Campus Wide
G
$
-
2/20/2012
Hoffman ES
E
$
-
9/10/2012
Sheds
E
$
-
9/10/2012
13357
13382
Frantz, William, Elementary School Village de'Lest Elementary School
13385
Bradley, Stuart R. Elementary School
13380
13390 13392 13396 13397 13400 13401
Lawless High School Hoffman, John W. Elementary Jeff, Morris F.X., Elementary School Dibert, John, Elementary School Hansberry Elementary Wheatley Elementary School
$
-
5/3/2011
Dibert ES
E
$
-
9/10/2012
Sheds
E
$
-
9/10/2012
Bldg. C Restroom
E
$
-
9/10/2012
Sheds
E
$
-
9/10/2012
Alexander ES
E
$
-
9/10/2012
13407
Tureaud, A.P., Elementary School Alexander, Avery Elementary
13412
Langston Hughes Elementary School
Building B
E
13444
Gentilly Terrace Elementary School
Sheds
E
$
-
9/5/2012
13466
Coghill, Mary D. Elementary School
Sheds
E
$
-
9/5/2012
13482
Pierre A. Capdau Junior High School
Main Building
E
13405
$
$
25
-
-
4/14/2011
5/23/2011
Quarterly Report ending September 30, 2012
PW Number
Facility/ Campus
Building Name
Date of GOHSEP Request
Total Obligated
Category
Date of GOHSEP Complete
Date of FEMA Request
FEMA Complete Date
13494
Osborne, Mildred C. Elementary School
Campus Wide
G
13504
Lawless High School
Modular Classrooms
E
$
-
5/13/2011
13574
Edward H. Phillips Junior High School
Building B
E
$
-
4/14/2011
9/14/2011
9/14/2011
9/16/2011
13575
Thurgood Marshall Middle School
Auxiliary PE Lecture Bldg
E
$
-
5/3/2011
9/2/2011
9/2/2011
9/8/2011
13610
Moton Elementary
Moton Elementary
E
$
-
4/14/2011
8/12/2011
8/12/2011
13717
Langston Hughes Elementary School
Building C
E
$
-
4/14/2011
6/25/2011
6/25/2011
7/1/2011
Sheds
E
$
-
2/20/2012
Gymnasium
E
$
-
2/20/2012
Building B
E
6/25/2011
6/25/2011
7/1/2011
6/25/2011
6/25/2011
7/1/2011
13831 13970 13979 13990
Craig, Joseph A., Elementary School Phillips, Edward H. Junior High New Orleans High School Signature Centers
$
-
$ $
2/20/2012
-
4/21/2011
Not Applicabe
E
13992
Multi - Campus New Orleans High School Signature Centers
Main Bldg., Bldg A
E
14162
Harte, Alice M., Elementary School
Campus Wide
E
$
-
4/5/2012
14332
Gaudet, Frances, Elementary School
Buildings B and E (contents)
E
$
-
4/9/2012
14341
Jackson, Andrew, Elementary School
Campus Wide
E
$
-
4/9/2012
14344
McDonough #42 Elementary School
Main Building
E
14346
Habans, Paul B., Elementary School
Campus Wide
E
$
-
4/9/2012
14348
Walker, O. Perry, Senior High School
Campus Wide
E
$
-
4/9/2012
14353
Kennedy, John F., Senior High School
Bldg. E- Caretaker Residence
E
$
-
2/20/2012
Campus Wide
E
$
-
4/9/2012
Dibert ES
E
$
-
9/10/2012
Edwards ES
E
$
-
9/10/2012
$
4/5/2012 -
$
-
4/21/2011
5/23/2011
14366
Frantz, William, Elementary School Dibert, John, Elementary School Edwards, Helen S. Elementary
14379
Schaumburg, H.C., Elementary School
Campus Wide
E
$
-
4/9/2012
14411
New Orleans Center for Health Careers
Campus Wide
E
$
-
4/5/2012
14355 14358
26
Quarterly Report ending September 30, 2012
PW Number
Facility/ Campus
Building Name
Category
Total Obligated
Date of GOHSEP Request
Date of GOHSEP Complete
Date of FEMA Request
7/11/2011
7/11/2011
FEMA Complete Date
14416
Jackson, Mahalia, Elementary School
Campus Wide
E
$
-
4/9/2012
14422
Guste, William J., Elementary School
Campus Wide
E
$
-
4/9/2012
14430
Jackson, Mahalia, Elementary School
Campus Wide
E
$
-
4/9/2012
Campus Wide
E
$
-
4/9/2012
Campus Wide
E
$
-
4/9/2012
Campus Wide
E
$
-
4/9/2012
Campus Wide
E
$
-
4/9/2012
Campus Wide
E
Campus Wide
E
$
-
4/9/2012
Campus Wide
E
$
-
4/9/2012
Campus Wide
E
$
-
4/9/2012
Building 2
E
$
-
2/9/2011
7/12/2011
7/12/2011
Building 1
E
$
-
2/9/2011
6/25/2011
6/25/2011
Modular Buildings
E
$
-
4/29/2011
5/18/2011
5/18/2011
Main Building
E
$
-
2/9/2011
7/20/2011
7/20/2011
7/21/2011
Unit 1
E
$
-
2/9/2011
6/25/2011
6/25/2011
7/1/2011
Abrams ES
E
$
0.01
9/10/2012
$
-
2/20/2012
6/27/2011
6/27/2011
7/1/2011
14501
Terrell, Mary Church, Elementary School Marshall, Thurgood, Middle School Wicker, Albert, Elementary School
14505
Fischer, William J., Elementary School
14457 14486
14622 14629 14647 14691 14735 14736 14738 14741
New Orleans Center for Education of Adults Green, Samuel J., Middle School Harney, Edgar P., Elementary School Clark, Joseph S., High School Joseph A. Hardin Elementary School Ray Abrams Elementary School Osborne Elementary School Joseph S. Clark High School
$
-
2/9/2011
14745
Parkview Fundamental Magnet School Abrams, Ray, Elementary School
14746
Augustine, Israel Meyer, Middle School
Sheds
E
14749
John F. Kennedy Senior High School
Kitchen
E
$
-
2/9/2011
14750
A.D. Crossman Elementary School
Modular 2
E
$
-
5/23/2011
14755
Valena C. Jones Elementary School
Kitchen
E
$
-
2/9/2011
Building 2
E
$
-
2/9/2011
Campus Wide
G
14744
14756 14757
Florence J. Chester Elementary School Abrams, Ray, Elementary School
$
27
-
2/20/2012
7/1/2011
Quarterly Report ending September 30, 2012
PW Number 14758
Facility/ Campus Mary D. Coghill Elementary School
Building Name
Total Obligated
Category
Date of GOHSEP Request
Date of GOHSEP Complete
Date of FEMA Request
FEMA Complete Date
Main Building
E
$
-
2/9/2011
6/28/2011
6/28/2011
6/30/2011
Portable 1
E
$
-
2/9/2011
6/28/2011
6/28/2011
6/30/2011
Main Bldg.
E
$
-
2/20/2012
Sheds
E
$
-
2/20/2012
14763
Florence J. Chester Elementary School Marshall, Thurgood, Middle School Wicker, Albert, Elementary School
14765
Florence J. Chester Elementary School
Portable 2
E
$
-
2/9/2011
6/28/2011
6/29/2011
6/30/2011
14766
Mildred C. Osborne Elementary School
Portable 2
E
$
-
2/9/2011
6/28/2011
6/28/2011
6/30/2011
14769
Coghill, Mary D. Elementary School
Modular Bldg.
E
$
-
2/20/2012
Annex Building
E
$
0.01
2/9/2011
6/25/2011
6/25/2011
7/1/2011
Kitchen
E
$
-
2/9/2011
Main Classroom Building
E
$
-
2/9/2011
Building 1
E
$
-
5/3/2011
Kitchen
E
$
-
2/9/2011
Kitchen
E
$
-
2/9/2011
9/14/2011
9/14/2011
9/15/2011
Kitchen
E
$
-
2/9/2011
6/27/2011
6/27/2011
7/1/2011
Main Building
E
$
-
4/9/2012
Sheds
E
$
-
2/20/2012
14760 14762
14771 14774 14781 14784 14789 14790
A.D. Crossman Elementary School Carter G. Woodson Middle School Henry W. Allen Elementary School Chester Elementary School Charles R. Drew Elementary School Fisk-Howard Elementary School
14799
Lawrence D. Crocker Elementary School Marshall, Thurgood, Middle School Lafon, Thomy, Elementary School
14801
A.D. Crossman Elementary School
Modular 1
E
$
-
2/9/2011
9/14/2011
9/14/2011
9/16/2011
14802
Gentilly Terrace Elementary School
Kitchen
E
$
-
2/9/2011
6/27/2011
6/27/2011
7/1/2011
14803
A.D. Crossman Elementary School
Kitchen
E
$
-
2/9/2011
9/14/2011
9/14/2011
9/16/2011
14805
A.D. Crossman Elementary School
Boiler Building
E
$
-
5/23/2011
Main Building
E
$
-
2/9/2011
5/16/2011
5/16/2011
Kitchen
E
$
-
2/20/2012
Sheds
E
$
-
2/20/2012
14791 14794
14817
A.D. Crossman Elementary School Dibert, John, Elementary School
14818
Allen, Henry W., Elementary School
14811
28
Quarterly Report ending September 30, 2012
PW Number 14824
Facility/ Campus Dilbert Elementary School
Building Name
Total Obligated
Category
Date of GOHSEP Request
Date of GOHSEP Complete
Date of FEMA Request
FEMA Complete Date
9/2/2011
9/2/2011
9/8/2011
Main Bldg
E
$
-
5/3/2011
Kitchen
E
$
-
2/9/2011
Kitchen
E
$
-
2/9/2011
5/16/2011
5/16/2011
14831
Edgar P. Harney Elementary School Barbara Jordan Elementary School Ray Abrams Elementary School
Modular 3
E
$
-
2/9/2011
5/16/2011
5/16/2011
14835
Israel Meyer Augustine Middle School
Building 2
E
2/9/2011
5/9/2011
5/9/2011
5/17/2011
14838
Lorraine Hansberry Elementary School
Kitchen
E
$
-
2/9/2011
5/10/2011
5/10/2011
5/16/2011
14827 14829
$
0.01
Modular Buildings
E
$
-
4/29/2011
6/3/2011
6/3/2011
7/1/2011
14841
Avery Alexander Elementary School F.W. Gregory Junior High School
Kitchen
E
$
-
2/9/2011
5/10/2011
5/10/2011
5/16/2011
14842
Carver Middle/High School Complex
Building H
E
$
-
5/3/2011
12/2/2011
12/2/2011
Kitchen
E
$
-
2/9/2011
5/18/2011
5/18/2011
Kitchen
E
$
-
2/9/2011
Kitchen
E
$
-
2/9/2011
Kitchen
E
$
-
2/9/2011
Kitchen
E
$
-
2/9/2011
5/18/2011
5/18/2011
Portable 1
E
$
-
4/21/2011
5/19/2011
5/19/2011
14839
14844
Sylvanie F. Williams Elementary School John A. Shaw Elementary School
14845
Florence J. Chester Elementary School
14843
14848
Avery Alexander Elementary School Lake Area Middle School Bradley Elementary School
14850
Avery Alexander Elementary School
Portable 2
E
$
-
2/9/2011
9/7/2011
9/7/2011
14852
Joseph A. Hardin Elementary School
Building 5
E
$
-
2/9/2011
5/10/2011
5/10/2011
Kitchen
E
$
-
2/9/2011
5/16/2011
5/16/2011
Portables #1 &2
E
Modular Classroom #1
E
$
-
4/21/2011
Main Building
E
$
-
5/3/2011
Modular #4
E
$
-
5/13/2011
Kitchen
E
$
-
2/9/2011
8/17/2011
8/17/2011
Gym
E
14846 14847
14853 14857 14858 14859 14861 14863 14864
Joseph A. Hardin Elementary School Wheatley Elementary School Bradley Elementary School John McDonough Senior High School Abrams Elementary School Walter L. Cohen Sr. High School Carver, George Washington
$
$
29
-
-
2/20/2012
9/5/2012
Quarterly Report ending September 30, 2012
PW Number 14866 14869 14873 14874 14875 14876 14878 14880 14881 14882 14888 14890 14892
Facility/ Campus Joseph S. Clark High School Carver, George W., Middle/High School Complex Temporary Facility at Drew Elementary School Fredrick A. Douglass High School Langston Hughes Elementary School Abrams Elementary School William Frantz Elementary School Louis Armstrong Elementary School Dunbar Elementary School Andrew J. Bell Junior High School Wheatley Elementary School Stuart R. Bradley Elementary School Ray Abrams Elementary School
Building Name
Total Obligated
Category
$
Date of GOHSEP Complete
Date of FEMA Request
FEMA Complete Date
5/3/2011
10/11/2011
10/11/2011
10/17/2011
10/13/2011
Building A
E
Sheds
E
Main Bldg
E
$
-
5/3/2011
10/11/2011
10/11/2011
Kitchen
E
$
-
2/9/2011
5/10/2011
5/10/2011
Kitchen
E
$
-
2/9/2011
6/25/2011
6/25/2011
Portable 1,2 & 3
E
$
-
4/21/2011
6/25/2011
6/25/2011
Main Building
E
$
-
2/9/2011
6/25/2011
6/25/2011
Kitchen
E
$
-
2/9/2011
6/1/2011
6/1/2011
Kitchen
E
$
-
2/9/2011
Kitchen
E
$
-
2/9/2011
8/12/2011
8/12/2011
Kitchen
E
$
-
2/9/2011
5/16/2011
5/16/2011
Building A
E
$
-
2/9/2011
Kitchen
E
$
-
2/9/2011
$
-
2/9/2011
6/25/2011
6/25/2011
$
-
Date of GOHSEP Request
2/20/2012
-
Unit 2
E
14895
Parkview Fundamental Magnet School Alexander, Avery Elementary
Portable #5
E
14896
Joseph A. Hardin Elementary School
Building 3
E
14901
Augustine, Israel Meyer, Middle School
Bldg. B
E
14902
Fischer Elementary School
Main Building & Cafetorium
E
$
-
4/21/2011
14906
Parkview Fundamental Magnet School
Portable 2
E
$
-
2/9/2011
Kitchen
E
$
-
2/9/2011
Building 4
E
$
-
5/23/2011
Portable 1
E
$
-
2/9/2011
6/1/2011
6/1/2011
Kitchen
E
2/9/2011
6/1/2011
6/1/2011
14894
14915 14922 14931 14934
Israel Meyer Augustine Middle School Hardin Elementary School Avery Alexander Elementary School Fannie C. Williams Middle School
$
$
-
$
30
2/20/2012
$
7/1/2011
2/9/2011 2/20/2012
0.01
7/1/2011
Quarterly Report ending September 30, 2012
PW Number 14935 14940 14941 14943 14944 14945
Facility/ Campus Marion Abramson Senior High School Dunbar Elementary School Lorraine Hansberry Elementary School Abramson, Marion Senior High Woodson , Carter G., Middle School Abramson, Marion Senior High
Building Name
Date of GOHSEP Request
Total Obligated
Category
$
Date of FEMA Request
5/10/2011
5/10/2011
Modular 1
E
Sheds
E
Main Building
E
Sheds
E
$
-
2/20/2012
Building 5
E
$
-
4/9/2012
Campus Wide
G
$
-
2/20/2012
$
0.01
2/9/2011
6/25/2011
6/25/2011
$
-
Date of GOHSEP Complete
$
2/9/2011 2/20/2012
-
2/9/2011
Kitchen
E
14949
Mildred C. Osborne Elementary School Carter G. Woodson Middle School
Building 3
E
$
-
2/9/2011
6/1/2011
6/1/2011
14950
Lawless High School
Kitchen
E
$
-
2/9/2011
6/1/2011
6/1/2011
Building C
E
$
-
2/9/2011
6/1/2011
6/1/2011
Building 2
E
$
-
2/9/2011
6/1/2011
6/1/2011
Building E
E
$
-
2/9/2011
6/25/2011
6/25/2011
Portable 1
E
$
-
2/9/2011
8/12/2011
8/12/2011
Sheds
E
$
-
2/20/2012
Library
E
$
-
4/9/2012
Unit 5
E
5/18/2011
5/18/2011
Sheds
E
$
-
2/20/2012
Sheds
E
$
-
2/20/2012
Portable D
E
5/10/2011
5/10/2011
14946
14952 14953 14955 14956 14957 14958 14959 14960
Frances Gaudet Elementary School Carter G. Woodson Middle School Jean Gordon Elementary School Stuart R. Bradley Elementary School Gordon, Jean Elementary Clark, Joseph S., High School Parkview Fundamental Magnet School McDonodh #32 Elementary
14963
Rosenwald, Julius Accelerated School Jean Gordon Elementary School
14967
Douglass, Fredrick A., High School
Portable Bldg.
E
14969
Medard H. Nelson Elementary School
Main Building
E
14970
Tubman, Harriet, Elementary School
Sheds
E
14974
Joseph A. Hardin Elementary School
Building 6
E
14975
Henderson, Murray, Middle School
Sheds
E
14961
$
-
$ $
-
$ $
$
-
31
2/9/2011
2/9/2011 2/20/2012
-
2/9/2011
2/20/2012 -
$
FEMA Complete Date
2/9/2011 2/20/2012
7/1/2011
Quarterly Report ending September 30, 2012
PW Number
Facility/ Campus
14977
Dunbar, Paul L., Elementary School McDonogh #7 Elementary
14978
Avery Alexander Elementary School
14976
14980 14981
Lawless High School Gordon, Jean Elementary
Building Name
Category
Total Obligated
Date of GOHSEP Request
Date of GOHSEP Complete
Date of FEMA Request
5/11/2011
5/11/2011
5/14/2011
5/14/2011
5/11/2011
5/11/2011
5/26/2011
5/26/2011
6/1/2011
2/9/2011
5/9/2011
5/9/2011
5/12/2011
2/9/2011
5/26/2011
5/26/2011
6/1/2011
Portable 2
E
$
-
4/9/2012
Sheds
E
$
-
2/20/2012
Portable Bldg 4
E
$
-
5/23/2011
Main Building
E
$
-
2/9/2011
Portable F
E
Campus Wide
E
$
-
2/9/2011
Portable Bldg 4
E
$
-
5/23/2011
Administration Bldg
E
$
-
5/3/2011
$
-
2/9/2011
$
-
2/20/2012
14991
Carver Middle/High School Complex Village De Lest Elementary School Dunbar Elementary School
14993
Joseph A. Hardin Elementary School
Portable 1
E
14997
Gaudet, Frances, Elementary School
Sheds
E
$
0.01
2/18/2012
14998
Morial, Ernest N. Dutch, Elementary School
Portable 2
E
$
-
4/9/2012
Kitchen
E
$
-
2/9/2011
$
-
5/3/2011
14985 14990
Pre K Bldg
E
15006
Parkview Fundamental Magnet School Ray Abrams Elementary School Carver, George W., Middle/High School Complex
Parent/Child Development Center
E
15007
Medard H. Nelson Elementary School
Kitchen
E
15008
Sylvanie F. Williams Elementary School
Building A
E
Main Building
E
$
-
2/9/2011
4/29/2011
4/29/2011
Kitchen
E
$
-
2/9/2011
4/25/2011
4/25/2011
$
-
2/9/2011
4/15/2011
4/15/2011
2/9/2011
5/26/2011
5/26/2011
15002 15003
$
4/9/2012
$
$
0.01
15011
Lawrence D. Crocker Elementary School Jean Gordon Elementary School
15012
John W. Hoffman Elementary School
Kitchen
E
15015
Bienville Elementary School
Building with Rooms 104-110
E
15016
Carver Middle/High School Complex
Campus Wide
E
$
-
2/9/2011
5/3/2011
5/3/2011
15017
Rabouin Career Magnet High School
Main Bldg
E
$
-
5/3/2011
10/7/2011
10/7/2011
15019
John F. Kennedy Senior High School
Modular #3
E
$
-
5/3/2011
15010
$
32
FEMA Complete Date
0.01
6/1/2011
10/12/2011
Quarterly Report ending September 30, 2012
PW Number
Total Obligated
Date of GOHSEP Request
$
-
4/9/2012
$
-
2/20/2012
Date of GOHSEP Complete
Date of FEMA Request
5/4/2011
5/4/2011
6/25/2011
6/25/2011
5/14/2011
5/14/2011
2/9/2011
5/14/2011
5/14/2011
2/9/2011
5/11/2011
5/11/2011
2/9/2011
5/16/2011
5/16/2011
15022
Facility/ Campus Little Woods Elementary School
Portable 2
E
15024
Little Woods Elementary
Main Bldg.
E
15025
Bienville Elementary School
Portable with Rooms 116-117
E
15026
Bienville, Jean Batiste de, Elementary School
Office Building
E
15027
Sherwood Forest Elementary School
Modular Classrooms 1 &2
E
15028
Kennedy, John F., Senior High School
Modular 2
E
15029
Ernest N. Dutch Morial Elementary School
Kitchen
E
$
-
2/9/2011
15031
John F. Kennedy Senior High School
Modular #1
E
$
-
5/3/2011
Portable 2
E
$
-
Kitchen
E
$
-
Pre-K Bldg.
E
Kitchen
E
$
-
15032 15033
Joseph A. Hardin Elementary School Thurgood Marshall Middle School
Building Name
Category
$ $
-
$ $
2/9/2011 4/9/2012
-
4/21/2011
Kitchen
E
$
-
2/9/2011
5/16/2011
5/16/2011
15040
Kitchen
E
$
-
2/9/2011
6/25/2011
6/25/2011
15041
Bienville Elementary School
Kindergarten Classroom 120-121
E
$
-
2/9/2011
4/21/2011
4/21/2011
15042
Rabouin Career Magnet High School
Rabouin HS
E
$ (0.06)
Main Bldg
E
$
-
5/3/2011
9/2/2011
9/2/2011
Building 1
E
$
-
2/9/2011
4/21/2011
4/21/2011
Portables 1&2
E
$
-
4/21/2011
6/25/2011
6/25/2011
Kitchen
E
$
-
2/9/2011
$
-
2/9/2011
15036 15039
15049
McDonogh #42 Elementary School Carter G. Woodson Middle School Shaw Elementary School Livingston Middle School
15052
Sherwood Forest Elementary School
Kitchen
E
15053
Bienville, Jean Batiste de, Elementary School
Library Building
E
15054
Edward H. Phillips Junior High School
Kitchen
E
15043 15046 15048
$
-
$ $
33
7/1/2011
4/9/2012
Bienville, Jean Batiste de, Elementary Little Woods Elementary School Sarah T. Reed Senior High School Dr. Martin Luther King Elementary School for Science an
15034
FEMA Complete Date
2/20/2012
9/10/2012
-
4/9/2012 -
2/9/2011
9/8/2011
7/1/2011
Quarterly Report ending September 30, 2012
PW Number
Date of GOHSEP Request
Date of FEMA Request
FEMA Complete Date
5/31/2011
5/31/2011
6/2/2011
4/21/2011
4/21/2011
5/26/2011
5/26/2011
4/21/2011
4/21/2011
2/9/2011
9/30/2011
9/30/2011
10/4/2011
2/9/2011
5/23/2011
5/23/2011
5/25/2011
15056
Library Building
E
15062
Vorice Jackson Waters Elementary
Kitchen
E
$
0.01
2/9/2011
15068
Gaudet, Frances, Elementary School
Bldg. D
E
$
0.01
2/18/2012
15069
John F. Kennedy Senior High School
Building ABD
E
$
-
2/9/2011
Building C
E
$
-
2/9/2011
Kitchen
E
$
-
4/9/2012
Modular Building
E
$
0.01
2/9/2011
Campus Wide
E
Pre K Building
E
Campus Wide
E
Bldgs. A,B,C,D, Pre-K.
E
15073
John F. Kennedy Senior High School Wicker, Albert, Elementary School
15075
Carver Middle/High School Complex
15070
15082
A.D. Crossman Elementary School Abrams, Ray, Elementary School
15083
Helen S. Edwards Elementary School
15076
Building Name
Total Obligated
Date of GOHSEP Complete
Facility/ Campus Bienville Elementary School
Category
$
-
$ $
-
6/1/2011
5/3/2011 4/9/2012
$
2/9/2011
-
2/9/2011
Campus Wide
E
15087
Gaudet, Frances, Elementary School Lafayette Elementary School Fredrick A. Douglass High School
Main Building
E
15088
Ernest N. Dutch Morial Elementary School
Main Building
E
$
-
2/9/2011
4/21/2011
4/21/2011
15097
John McDonough Senior High School
Main Bldg
E
$
-
5/3/2011
10/27/2011
10/27/2011
Main Building
E
$
-
2/9/2011
6/25/2011
6/25/2011
Modular Buildings
E
$
-
4/29/2011
6/3/2011
6/3/2011
7/1/2011
Bldg. C
E
9/14/2011
9/14/2011
9/15/2011
15084 15086
15114
Medard H. Nelson Elementary School Carver Middle/High School Complex - 1 Bldg. Gordon, Jean Elementary
15117
Johnson C. Lockett Elementary School
Building A
B
15119
Dunbar, Paul L., Elementary School
Cafeteria
E
15120
Thomas Alva Edison Elementary School
Building 2
E
Main Classroom Building
E
Sheds
E
15100 15106
15121 15124
Clark, Joseph S., High School Wilson, Andrew H. Elementary
$
$
$
$
2/20/2012 -
0.01
$
2/20/2012 -
2/9/2011
0.01
9/5/2012
-
5/23/2011
$
0.01
9/5/2012
$
-
2/20/2012
$ $
34
10/28/2011
Quarterly Report ending September 30, 2012
PW Number
Facility/ Campus
15125
Walker, O. Perry, Senior High School
Sheds
E
15126
Parkview Fundamental Magnet School
Portables 2 & 3
E
15127
McDonogh #15 Elementary School
15128
Building Name
Total Obligated
Date of GOHSEP Request
$
-
2/20/2012
$
-
2/20/2012
Category
Date of GOHSEP Complete
Date of FEMA Request
FEMA Complete Date
Main Bldg
E
$
-
5/3/2011
10/7/2011
10/7/2011
10/12/2011
Modular Classrooms
E
$
-
4/14/2011
6/3/2011
6/3/2011
7/1/2011
Building 3
E
$
-
5/23/2011
Sheds
E
5/23/2011
5/23/2011
5/24/2011
15131
Green Charter School Chester Elementary School Marshall, Thurgood, Middle School
15133
James Weldon Johnson Elementary School
Building 2
E
15134
Morial, Ernest N. Dutch, Elementary School
Portables # 1,2, 3
E
Portable Bldg P1
E
$
-
5/13/2011
6/25/2011
6/25/2011
7/1/2011
Building 2
E
$
-
2/9/2011
5/9/2011
5/9/2011
5/12/2011
Sheds
E
Kitchen
E
7/20/2011
7/20/2011
7/21/2011
Kitchen
E
Building B
E
$
-
4/21/2011
6/25/2011
6/25/2011
7/1/2011
Portable 118-119
E
$
-
2/9/2011
5/23/2011
5/23/2011
5/24/2011
15129
15135 15136 15137 15138 15140
Parkview Fundamental Magnet School Thomy Lafon Elementary School Wheatley Elementary School Thomy Lafon Elementary School Wicker, Albert, Elementary School
$
$
$
2/20/2012 -
-
$
2/20/2012
$
$
2/9/2011
2/20/2012 -
-
2/9/2011 2/20/2012
15142
James Weldon Johnson Elementary School Bienville Elementary School
15143
Marion Abramson Senior High School
6 Classroom Portable Building
E
$
-
2/9/2011
5/23/2011
5/23/2011
5/24/2011
15144
McDonogh #42 Elementary School
Library
E
$
-
5/3/2011
10/27/2011
10/27/2011
10/28/2011
15145
Rabouin Carerre Magnet High School
Sheds
E
15147
James Weldon Johnson Elementary School
Building C (CafĂŠ'/Kitchen)
E
6/3/2011
6/3/2011
7/1/2011
Sheds
E
Portable Classrooms
E
$
-
5/13/2011
6/3/2011
6/3/2011
7/1/2011
15141
$
-
$
2/20/2012 -
4/21/2011
15153
Terrell, Mary Church, Elementary School Gordon Elementary School
15157
Jones Elementary School - 3 Bldgs.
Modular Buildings
E
$
-
4/29/2011
6/3/2011
6/3/2011
7/1/2011
15159
Hansberry Elementary
Main Building
E
$
-
4/21/2011
6/3/2011
6/3/2011
7/1/2011
15160
Crocker, Lawrence D., Elementary School
Sheds
E
15148
$
$
35
-
-
2/20/2012
2/20/2012
Quarterly Report ending September 30, 2012
PW Number
Facility/ Campus
Building Name
Total Obligated
Category
Date of GOHSEP Request
Date of GOHSEP Complete
Date of FEMA Request
FEMA Complete Date
2/9/2011
5/9/2011
5/9/2011
5/12/2011
5/12/2011
15161
McDonogh Elementary School #42
Kitchen
E
15163
Osborne, Mildred C. Elementary School
Sheds
E
15164
Dunbar Elementary School
Classroom Building 103-107
E
$
-
2/9/2011
5/9/2011
5/9/2011
15165
Marion Abramson Senior High School
Kitchen
E
$
-
2/9/2011
5/16/2011
5/16/2011
15166
Frances Gaudet Elementary School
Building A
E
$
-
2/9/2011
5/16/2011
5/16/2011
Sheds
E
Main Bldg
E
11/30/2011
11/30/2011
Sheds
E
Building B
E E
$ $
9/9/2011
9/9/2011
5/16/2011
5/16/2011
4/13/2011
4/13/2011
4/14/2011
9/15/2011
15168 15172
Bell, Andrew J. Junior High School McNair Elementary School
15176
Douglass, Fredrick A., High School Bradley Elementary School
15177
Bienville, Jean Batiste de Elementary
Sheds
15178
Little Woods Elementary
Little Woods
E
15179
Green Charter School
E
Campus Wide
B
15183
Green Charter School Lafon, Thomy, Elementary School Dunbar Elementary School
Portable #1
E
15184
Edison, Thomas Alva, Elementary School
PK Prototype Bldg.
E
15173
15181
$ $
-
$
2/20/2012
$
$
2/20/2012 -
$
2/20/2012 -
-
$
9/10/2012 -
$
$
5/23/2011 2/20/2012
$
5/3/2011
4/14/2011
9/16/2011
4/5/2012 -
-
5/3/2011 9/10/2012
Building 1
E
15188
Florence J. Chester Elementary School Abrams, Ray, Elementary School
Main Building
E
15189
Parkview Fundamental Magnet School
Portable 3
E
Storage Container
E
Building A
E
$
-
2/9/2011
9/14/2011
9/14/2011
Campus Wide
E
$
-
5/3/2011
11/30/2011
11/30/2011
Main Building
E
$
-
2/9/2011
4/13/2011
4/13/2011
4/14/2011
Adjacent Structures
E
$
-
2/9/2011
4/9/2011
4/9/2011
4/14/2011
15186
15190 15191 15193 15194 15195
McDonogh, John, Senior High School Ray Abrams Elementary School New Orleans Center for the Creative Arts Livingston Middle School Little Woods Elementary School
$ $
-
$
36
4/9/2012
$
2/9/2011
-
2/9/2011 9/10/2012
Quarterly Report ending September 30, 2012
PW Number
15196 15198 15199 15200 15201 15202 15205 15208
Facility/ Campus New Orleans High School Signature Centers (Derham Middle School) Kennedy, John F., Senior High School Barbara Jordan Elementary School McDonogh Elementary School #42 Lafayette Elementary School Joseph A. Hardin Elementary School Gordon, Jean Elementary New Orleans High School Signature Centers
15210
Marion Abramson Senior High School Village De Lest Elementary School
15211
H.C. Schaumburg Elementary School
15209
Building Name
Category
Total Obligated
Date of GOHSEP Request
$
-
9/10/2012
Modular 4
E
$
-
4/9/2012
Portables 1,2&3
E
$
-
4/29/2011
6/3/111
6/3/2011
7/1/2011
Library
E
$
-
2/9/2011
4/9/2011
4/9/2011
4/14/2011
Main Bldg
E
$
-
5/3/2011
9/2/2011
9/2/2011
9/8/2011
Modular Bldgs 1&2
E
$
-
5/13/2011
9/14/2011
9/14/2011
9/15/2011
Portable classroom
E
Kitchen
E
$
-
2/9/2011
6/27/2011
6/27/2011
7/1/2011
Office Building
E
$
-
2/9/2011
Kitchen
E
$
-
2/9/2011
Annex Building
E
5/23/2011
5/23/2011
5/24/2011
Kitchen
E
$
-
2/9/2011
Building 1
E
$
-
2/9/2011
Main Bldg.
E
Main Building
E
6/28/2011
6/28/2011
6/30/2011
Main Bldg.
E
2/9/2011
5/23/2011
5/23/2011
5/24/2011
10/11/2011
10/11/2011
10/13/2011
7/21/2011
$
-
$
9/10/2012
0.01
2/9/2011
15221
Valena C. Jones Elementary School
Kitchen
E
$
-
2/9/2011
15223
Parkview Fundamental Magnet School
Unit #3
E
$
-
5/23/2011
Building 7
E
Building A
E
$
-
5/3/2011
15216 15217
15226 15227
Joseph A. Hardin Elementary School Village De Lest Elementary School
FEMA Complete Date
E
15219
15213
Date of FEMA Request
N.O. High (Derham)
Mary Church Terrell Elementary School Thomy Lafon Elementary School Dibert, John, Elementary School Andrew J. Bell Junior High School MaNair, Ronald G. Elementary
15212
Date of GOHSEP Complete
$
$
$
2/20/2012 -
-
$
4/21/2011 2/20/2012
0.01
Main Classroom Building
E
$
-
2/9/2011
15235
Jean Gordon Elementary School Sarah T. Reed Senior High School
Main Building
E
$
-
4/21/2011
7/20/2011
7/20/2011
15236
Parkview Fundamental Magnet School
Unit #4
E
$
-
5/23/2011
11/30/2011
11/30/2011
15230
37
Quarterly Report ending September 30, 2012
PW Number
Date of GOHSEP Request
Date of GOHSEP Complete
Date of FEMA Request
FEMA Complete Date
-
2/9/2011
5/23/2011
5/23/2011
5/25/2011
$
-
5/13/2011
6/28/2011
6/28/2011
6/30/2011
$
-
5/3/2011
10/11/2011
10/11/2011
10/12/2011
15239
Facility/ Campus Carter G. Woodson Middle School
Building 4
E
$
15241
Gordon Elementary School
Wood-sided Portable Bldg
E
Building A
E
Bldg. C (Kdgn)
E
Building Name
Total Obligated
Category
15246
Sylvanie F. Williams Elementary School Village de'Lest Elementary School
15248
John F. Kennedy Senior High School
Building C (Voc. Ed, Indust Art)
E
$
-
4/21/2011
9/9/2011
9/9/2011
9/16/2011
15250
Ernest N. Dutch Morial Elementary School
Portable 1
E
$
-
2/9/2011
5/23/2011
5/23/2011
5/25/2011
15251
McDonogh, John, Senior High School
Main Bldg.
E
15256
Carver Middle/High School Complex
Modular Day Care Bldg
E
$
-
5/13/2011
15258
Julius Rosenwald Accelerated School
Classroom Building
E
$
-
2/9/2011
5/23/2011
5/23/2011
5/25/2011
15262
Morial, Ernest N. Dutch, Elementary School
Campus Wide
B
15265
F.W. Gregory Junior High School
Building A (Admin Office & Classrooms)
E
$
-
4/21/2011
6/25/2011
6/25/2011
7/1/2011
15271
James Weldon Johnson Elementary School
Building A
E
$
-
4/21/2011
9/2/2011
9/2/2011
9/8/2011
15283
Sherwood Forest Elementary School
Modular Buildings
E
$
-
5/13/2011
7/11/2011
7/11/2011
7/21/2011
Main Building
E
$
-
2/9/2011
4/9/2011
4/9/2011
4/14/2011
Portable 2
E
Main Building
E
$
-
2/9/2011
9/12/2011
9/12/2011
9/15/2011
15243
$
-
$
2/20/2012
-
$
2/20/2012
-
4/5/2012
15305
Lorraine Hansberry Elementary School Village De Lest Elementary School John Dibert Elementary School
15314
H.C. Schaumburg Elementary School
Main Building
E
$
-
2/9/2011
4/9/2011
4/9/2011
4/14/2011
15320
Julius Rosenwald Accelerated School
Main Building
E
$
-
2/9/2011
4/9/2011
4/9/2011
4/14/2011
Campus Wide
E
$
-
2/9/2011
4/9/2011
4/9/2011
4/14/2011
Main Building
E
$
-
5/3/2011
10/11/2011
10/11/2011
10/13/2011
Campus Wide
E
$
-
5/3/2011
10/11/2011
10/11/2011
10/12/2011
Main Building
E
$
-
2/9/2011
9/14/2011
9/14/2011
9/15/2011
15299 15301
15326
Carver Middle/High School Complex Walter L. Cohen Sr. High School Fredrick A. Douglass High School
15327
Avery Alexander Elementary School
15324 15325
$
38
-
4/9/2012
Quarterly Report ending September 30, 2012
PW Number 15343 15344 15345 15370 15373 15375 15377
Facility/ Campus Marion Abramson Senior High School Edgar P. Harney Elementary School MCDonogh #28 Middle School Louis Armstrong Elementary School Hardin Elementary School Alcee Fortier High School Ray Abrams Elementary School
Building Name
Total Obligated
Category
Date of GOHSEP Request
Date of GOHSEP Complete
Date of FEMA Request
FEMA Complete Date
4/13/2011
4/13/2011
4/18/2011
Main Building
E
$
-
2/9/2011
Main Bldg
E
$
-
5/3/2011
Main Building
E
$
-
4/21/2011
Main Building
E
$
-
2/9/2011
5/9/2011
5/9/2011
5/11/2011
Building 8
E
$
-
4/21/2011
6/25/2011
6/25/2011
7/8/2011
Alcee Fortier High School
E
$
-
4/14/2011
6/25/2011
6/25/2011
7/8/2011
Modular 2
E
$
-
2/9/2011
5/9/2011
5/9/2011
5/11/2011
5/9/2011
5/9/2011
5/12/2011
5/12/2011
Portable 3
E
$
-
2/9/2011
15386
Avery Alexander Elementary School Banneker Elementary School
Main Bldg
E
$
-
5/3/2011
15388
Parkview Fundamental Magnet School
Portable 1
E
$
-
2/9/2011
5/9/2011
5/9/2011
15435
Parkview Fundamental Magnet School
Unit #6
E
$
-
5/23/2011
8/2/2011
8/2/2011
4/13/2011
4/13/2011
5/11/2011
5/11/2011
6/3/2011
6/3/2011
7/1/2011
9/2/2011
9/2/2011
9/8/2011
5/27/2011
5/27/2011
15379
Portable 3
E
$
-
2/9/2011
15477
Joseph A. Hardin Elementary School Dunbar Elementary School
Library Building
E
$
-
2/9/2011
15478
L.B. Landry High School
Kitchen
E
$
-
2/9/2011
Kitchen
E
Care Keeper's College
E
$
-
5/23/2011
Modular Buildings
E
$
-
4/29/2011
15451
15481
Sherwood Forest Elementary School Armstrong (MLK) School
15483
Chester Elementary School - 2 Bldgs
15479
$
-
2/20/2012
Campus Wide
G
15488
Morial, Ernest N. Dutch, Elementary School A.P. Tureaud Elementary
Main Building
E
15489
Bienville, Jean Batiste de Elementary
Portables #1,2,3
E
$
-
2/20/2012
Kitchen
E
$
-
2/20/2012
Bldg. A
E
$
0.01
9/5/2012
Main Building
E
-
2/9/2011
15484
$
$
2/20/2012 -
4/21/2011
15516
Parkview Fundamental Magnet School Laurel Elementary School Livingston Middle School
15720
Multi- Campus
N/A
B
$
-
2/20/2012
15807
Multi - Campus
Not Applicable
B
$
-
4/5/2012
15490 15492
$
39
4/14/2011
Quarterly Report ending September 30, 2012
PW Number
Facility/ Campus
Building Name
Category
Total Obligated
Date of GOHSEP Request
15813
Multi- Campus
N/A
B
$
-
2/20/2012
15830
Multi-Campus
N/A
B
$
-
2/20/2012
15868
Multi-Campus
N/A
B
$
-
2/20/2012
15888
Joseph A. Hardin Elementary School
Portable 3
E
15970
Multi - Campus
Not Applicable
B
$
16087
Douglass, Fredrick A., High School
$
16089
Campus Wide
E
Portables 1&2
E
Campus Wide
E
$
-
Date of FEMA Request
FEMA Complete Date
6/3/2011
6/3/2011
7/1/2011
5/13/2011 4/5/2012
$
Date of GOHSEP Complete
4/9/2012
16092
Gregory Middle School McDonogh Elementary School #7
16129
Temporary Facility Colton Middle School
Campus Wide
E
$
-
5/3/2011
10/27/2011
10/27/2011
10/27/2011
16138
Mildred C. Osborne Elementary School
Modular Buildings
E
$
-
2/9/2011
5/12/2011
5/12/2011
5/16/2011
16209
Multi - Campus
Not Applicable
B
$
-
4/5/2012
Portable 1
E
$
-
4/9/2012
Campus Wide
E
$
-
4/9/2012
Abrams ES
B
$
-
9/10/2012
Coustodial Lodge
E
$
-
4/9/2012
5/12/2011
5/12/2011
5/16/2011
$
-
4/29/2011 4/9/2012
16403
Douglass, Fredrick A., High School Wicker, Albert, Elementary School Abrams, Ray, Elementary School
16510
New Orleans Free Elementary School
16511
Jackson, Andrew, Elementary School
Coustodial Lodge
E
$
-
4/9/2012
16512
Ashe, Arthur, School
Lodge
E
$
-
4/9/2012
16515
McDonogh Elementary School #42
Coustodial Lodge
E
$
-
4/9/2012
16517
Tubman, Harriet, Elementary School
Lodge
E
$
-
4/9/2012
16524
Allen, Henry W., Elementary School
Caretaker's lodge
E
$
-
4/9/2012
16525
Jeff, Morris F.X., Elementary School
Portable 1
E
$
-
4/9/2012
16527
Jeff, Morris F.X., Elementary School
Portable 2
E
$
-
4/9/2012
16547
Frances Gaudet Elementary School
Kitchen
E
16813
Edison, Thomas Alva, Elementary School
Portable 1
E
$
-
4/9/2012
16816
Edison, Thomas Alva, Elementary School
Portable 2
E
$
-
4/9/2012
16211 16214
$
40
-
2/9/2011
Quarterly Report ending September 30, 2012
PW Number 17058 17060 17061
Facility/ Campus Johnson, James Weldon, Elementary School Drew , Charles R., Elementary School Wicker, Albert, Elementary School
Building Name
Category
Total Obligated
Date of GOHSEP Request
Campus Wide
E
$
-
4/9/2012
Campus Wide
E
$
-
4/9/2012
Campus Wide
E
$
-
4/9/2012
Campus Wide
E
$
-
4/9/2012
Campus Wide
E
$
-
4/9/2012
17064
Bauduit, Agnes L., Elementary School Laurel Elementary School
17065
Rosenwald, Julius Accelerated School
Campus Wide
E
$
-
4/9/2012
17066
Alternative High School (Schwartz)
Campus Wide
E
$
-
4/9/2012
17067
McDonogh, John, Senior High School
Campus Wide
E
$
-
4/9/2012
17068
Tureaud, A.P., Elementary School
Campus Wide
E
$
-
4/9/2012
17069
Cohen, Walter L., Senior High School
Campus Wide
E
$
-
4/9/2012
17070
Habans, Paul B., Elementary School
Campus Wide
E
$
-
4/9/2012
17071
Reed, Sarah T., Senior High School
Campus Wide
E
$
-
4/9/2012
17072
Douglass, Fredrick A., High School
Campus Wide
E
$
-
4/9/2012
Campus Wide
E
$
-
4/9/2012
Campus Wide
E
$
-
4/9/2012
Campus Wide
E
$
-
4/9/2012
17063
17075
Craig, Joseph A., Elementary School Dibert, John, Elementary School Clark, Joseph S., High School
17076
Rabouin Career Magnet High School
Campus Wide
E
$
-
4/9/2012
17077
Williams, Sylvanie F., Elementary School
Campus Wide
E
$
-
4/9/2012
Campus Wide
E
$
-
4/9/2012
Campus Wide
E
$
-
4/9/2012
17073 17074
17079
Henderson, Murray, Middle School New Orleans Center for Creative Arts - Live Oak Middle School
17081
Banneker, Benjamin, Elementary School
Campus Wide
E
$
-
4/9/2012
18333
Multi - Campus
N/A
E
$
-
4/9/2012
17078
41
Date of GOHSEP Complete
Date of FEMA Request
FEMA Complete Date
Quarterly Report ending September 30, 2012
PW Number
Facility/ Campus
Building Name
Category
Total Obligated
Date of GOHSEP Request
-
4/9/2012
Main Bldg
B
$
18601
Crocker, Lawrence D., Elementary School Multiple School Contents or Equipment(other than Parish
Emergency Preparedness
B
$ 691,350.00
2/9/2011
18964
Multi - Campus
Multi-campus
E
$
-
4/5/2012
19030
Gregory, F.W., Junior High School
F.W. Gregory Junior High School
E
$
-
4/9/2012
19189
Parkview Fundamental Magnet School
Portable 4/5
E
$
-
2/9/2011
Building D
E
$
-
4/21/2011
Campus-wide
E
$
-
4/9/2012
Multi campus contents
E
$
-
4/9/2012
18345
19194 19197 19722
L.B. Landry High School Landry, L.B., High School Bell Middle School Building A
42
Date of GOHSEP Complete
Date of FEMA Request
FEMA Complete Date
5/9/2011
5/9/2011
5/17/2011
Quarterly Report dated September 30, 2012 TABLE OF CONTENTS
Part I .............................................................................................................................................................. 2 Item 1. Executive Summary ....................................................................................................... 2 Item 2. SSR Amendments .......................................................................................................... 3 Item 3. Alternate & Improved Project Formulation ...................................................................... 4 Item 4. RRF and Grant Processing ............................................................................................ 6 Item 5. Environmental and Historic Preservation........................................................................ 7 Item 6. Special Initiatives............................................................................................................ 8 Item 7. Close Out Information & Submissions .......................................................................... 11 Part II ........................................................................................................................................................... 13 Item 8. Project Worksheets Reviewed...................................................................................... 13 Item 9. Summary of FEMA Funding ......................................................................................... 16
1
Quarterly Report dated September 30, 2012
Part I Item 1. Executive Summary General The third quarter of 2012 has been a period of consistent follow up, analysis, and progress for the OPSB Funding Team. Our activities included: 1) completing one (1) Amendment Request in order to amend the scope of work in PW #19290, 2) consolidating (analysis & official request submitted) the remaining OPSB Category G Project Worksheets into a Single Alternate Project, 3) reviewing the Mahalia Jackson Elementary School Improved Project, 4) creating a database to track past project worksheet close out requests, which enabled the funding team to follow up GOHSEP & FEMA on outstanding close out submittals, 5) submitting 186 Zero Dollar Close Out Request Letters to GOHSEP, 6) continuing to be well-information on all FEMA Environmental Historic Preservation matters, and 7) reviewing 38 draft OPSB PW’s presented by FEMA. These activities have cultivated an on-going positive relationship between GOHSEP, FEMA, the Disaster Recovery Section (DRS), OPSB accounting personnel, and the Jacobs/CSRS Funding Team. In the first quarter, the funding team created and implemented a Tracker Log; to monitor, track, and allow the ability to follow-up on all amendments, versions, time extensions, and clarifying memorandums for the OPSB. The Tracker Log continues to be an outstanding tool to constantly follow the path of critical communication. During the second quarter the funding team had focused on assisting the OPSB obtain reimbursement for past work completed; specifically work completed at Laurel Elementary School ($564k) and Bethune Elementary School ($783k). After contacting the contractor of the Laurel ES work and working with the GOHSEP Cost Estimating Team regarding the Bethune ES work; the funding team secured all necessary documentation that allows the OPSB to submit for reimbursement(s) to GOHSEP. Throughout the third quarter, the funding team made momentous progress on OPSB close out documentation and submitted 186 Zero Dollar Project Worksheets for close out. Our team filed and categorized all past OPSB close out documentation currently on hand (both paper and electronic copy). Furthermore, the funding team created a database to track OPSB close out requests through all stages of the close out process. This enables our team to not only track requests, but effectively communicate and follow up on information with GOHSEP, DRS Close Out Team and FEMA. Our team sent GOHSEP and FEMA clarifying memorandums and version requests on OPSB’s behalf. These requests were related to OPSB amendment project names, EHP matters, lease projects worksheets, and alternate/improved projects.
SUMMARY OF OBLIGATED PROJECTS* CURRENT OBLIGATION $394,798,264.52
FEDERAL FUNDS PAID $ 66,072,667.55
2
FEDERAL FUNDS BALANCE $ 328,725,468.62
Quarterly Report dated September 30, 2012 * Current Obligation reflects the total amount approved by FEMA. Federal Funds Paid denotes the total amount paid to the Applicant from current obligated funds. Federal Funds Balance reflects the total available amount remaining to be paid.
Item 2. SSR Amendments PROJECT OVERVIEW ____________________________________________________________________________________________ The $307M SSR PW, along with an additional $47M for items such as contents and temporary student transportation, was obligated by FEMA in 2010 to fund work outlined in the Master Plan for rebuilding of the Orleans Parish Public Schools. With the SSR complete, Jacobs/CSRS has begun to amend the scope of work to include many active projects from the Master Plan. Scopes of work for the following projects have been submitted for inclusion into the SSR, PW 19290 in this quarter: Facility / AIDB # Capdau Junior High School: AIDB #1918
Work Type New Work
Work Description Safe & Secure
Amount $ 65,000.00
NOTE: AIDB #1918 supersedes (i.e. replaces) AIDB #1400
Of the amendments submitted in FY2011 the following have cleared the Governor’s Office of Homeland Security (GOHSEP) and FEMA this quarter: Facility Audubon K – 8 Audubon K – 8
Work Type New Work New Work
Work Description Renovation & Addition Demolition of Custodial Cottage
Amount $14,000,000.00 $0.00
AIDB # & Approval Date AIDB #1395: Sept 21, 2012 AIDB #1629: Sept 21, 2012
Amendments will be ongoing as projects move into design and construction. This will maintain grant alignment with the Master Plan for Orleans Parish Schools.
3
Quarterly Report dated September 30, 2012
Item 3. Alternate & Improved Project Formulation PROJECT UPDATES ____________________________________________________________________________________________ Category G Project Worksheet: Single Alternate Project Jacobs/CSRS funding team analyzed all OPSB Category G Project Worksheets that had remaining eligible federal dollars to be utilized. The below were the identified Category G PW’s (facility’s, PW #, associated eligible funding): Facility
Robert R. Moton Elementary School Fleur De Lis Park – Playground Equipment Benjamin Franklin Senior High School Warren Easton High School McDonogh #35 Senior High School McMain Magnet School
Address
3000 Abundance Street, New Orleans, LA 70126 6751 Fleur De Lis Drive, New Orleans, LA 70124 2001 Leon C. Simon Drive, New Orleans, LA 70122 3019 Canal Street, New Orleans, LA 70119 1331 Kerlerac Street, New Orleans, LA 70119 5712 Claiborne Avenue, New Orleans, LA 70125
NEMIS PW #
PW Amount
12537
$33,728.00
12941
$19,804.79
17577
$236,821.00
18947
$19,339.90
19063
$138,010.00
20208
$24,539.25
Total PW's
Grand Total $$ Amount
6
$472,242.94
The OPSB agreed to consolidate the above six (6) Category G PW’s into a Single Alternate Project. This would allow for the flexibility in utilizing the Category G funding on other FEMA eligible OPSB facilities. Upon agreement, the funding team coordinated/performed the following: 1. Coordinated with a Jacobs/CSRS Senior Project Manager to identify possible sites that could benefit from Category G funding (i.e. fences) 2. Three (3) sites were identified A) New Lake Forest School at Greater St. Stephens Site B) New McDonogh #35 High School C) Audubon Montessori Elementary School 3. Performed a cost analysis on four (4) different types of fences (Vinyl Coated Chain Link, Montage Plus, Montage II, and Echelon/Aluminum) 4. Montage Plus Style Fence was presented to the OPSB 4
Quarterly Report dated September 30, 2012 The Montage Plus was determined to be a suitable option; due to its reasonable cost, minimal maintenance and appearance. The funding team composed a “Request for consolidation of Category G Project Worksheets into a Single Project Worksheet” (dated September 25, 2012) to the OPSB, and will be transmitted to GOHSEP/FEMA shortly. As other OPSB projects enter into the design process, the OPSB will evaluate additional eligible Category G projects, and at that time provide/submit scope of work requests (i.e. Amendment Requests) to GOHSEP FEMA. Mahalia Jackson Elementary School: Improved Project In formulation In a letter dated, June 8, 2012, FEMA approved the consolidation of five (5) PW’s into an Improved Project (15171, 15206, 15234, 15245 and 15224). In addition, the nineteen (19) Hazard Mitigation (HMP) proposals for the five (5) facilities were also approved. On July 17, 2012, FEMA transmitted PW Reference #IP1638 to the OPSB, which was five (5) PW’s consolidated into a single improved project. Jacobs/CSRS reviewed and analyzed the PW on the behalf of the OPSB. All information and documentation was captured accordingly and the final consolidation yielded the following: Donor Project Worksheets Building A B C D E Total
PW # 15206 15234 15171 15224 15245
Eligible Costs $738,202.00 $933,855.00 $947,560.00 $1,098,098.00 $939,969.00 $ 4,657,684.00
Insurance Reductions ($473,445.04) ($44,760.28) ($93,179.26) $0.00 ($80,426.25) $ (691,810.83)
Eligible Costs After Insurance Reductions $264,756.96 $889,094.72 $854,380.74 $1,098,098.00 $859,542.75 $ 3,965,873.17
Eligible Hazard Mitigation Proposals Captured Building PW # A 15206 B 15234 C 15171 D 15224 E 15245 Totals Grand Total of HMP's
$ $
Flooring $17,964.00 $32,881.00 $30,116.00 $18,807.00 $30,116.00 129,884.00 252,837.00
Overall Improved Project Eligible Costs
$
Ceilings $1,626.00 $2,651.00 $3,658.00 $5,966.00 $2,030.00 15,931.00
Exterior Doors $3,548.00 $12,418.00 $12,418.00 $19,514.00 $12,418.00 $ 60,316.00
HVAC Equipment $8,307.00 $12,967.00 $12,851.00 $0.00 $12,581.00 $ 46,706.00
$ 4,218,710.17
McMain Clinic HRSA Grant This quarter Jacobs/CSRS continued grant administration on the McMain Health Based Clinic. Activities this quarter included submission of the Environmental Assessment and updating the project schedule. Currently the project is in the procurement phase. The submission of the construction contract and insurance is anticipated in the next 60 days. 5
Quarterly Report dated September 30, 2012
Item 4. RRF and Grant Processing PROJECT STATUS ____________________________________________________________________________________________ The Funding Team supports ongoing capital improvement projects by working in conjunction with the Jacobs/CSRS Project Managers and FEMA to assure project activities and estimates align with Project Worksheet scope through the amendment process. This activity assures funding is secured and is in place prior to expenses being incurred. In the third quarter of FY2012 OPSB did not submit any new RRF requests. However, the funding team performed risk analysis on past projects. This process was instrumental in identifying missing project documents which would have impeded resolution of outstanding debt and current project reimbursement. Our analysis this quarter aided our team in engaging GOHSEP finance to clarifying outstanding debt and using past project/expense documentation to support this debt, which facilitates current project reimbursement. The review of past debt and collaboration with GOHSEP will be dealt with in more detail in Section 6. Jacobs/CSRS is working diligently with OPSB and GOHSEP to submit multiple RRF’s within the 4th Quarter of FY2012.
6
Quarterly Report dated September 30, 2012
Item 5. Environmental and Historic Preservation PROJECT UPDATES __________________________________________________________________________________________ We continue our support of multiple EHP issues including Section 106 consultations, compliance with Secretary of Interior building remediation and memorandum of understandings between OPSB, GOHSEP, SHPO, FEMA and The Advisory Council on Historic Preservation. Project deliverables and updates Almonaster: The original historic construction drawings salvaged from Central Services are stored in a conditioned space. The remediation is expected to move forward this quarter. Audubon: The demolition and abatement work on the school is proceeding. Periodic review of the work will take place to ensure the work conforms to the Secretary of Interior standards for final close out of the consultation at the end of the construction phase. Parts I&II of the State Commercial Tax Credit Application have been completed and are ready for submission to SHPO pending the Owner’s signature. Bethune: A list of character defining features for the school has been developed and forwarded
by FEMA EHP. AE procurement is pending Owner direction.
Capdau: An alternatives letter has been developed for the Owners signature for submission to FEMA. The change will be to secure the building and begin the marketing of the property to others for redevelopment. Based on this change, it is anticipated that FEMA will require additional photographic documentation standards and a historic narrative, outline form compliant to the Secretary of the Interior Standards for documentation Level II. Easton: Design development drawings for the scope of work have been submitted. No EHP review is anticipated for this scope. Lusher Bridge: AE has been selected; a review of the SOW indicates it may be increased. Depending on the final agreement of the scope of repairs, EHP review may be limited. Lusher Fortier: AE kick off meeting occurred 9/26/2012. The AE is advised to prepare a template for the character defining features within the scope of work which are exterior items only. McMain: Ongoing activities in the selection of replacement windows by the AE, PM, and third party consultants are happing concurrently with the AE revisions; alongside the scope of work to the exterior stucco and new window recommendations for this historic building. The new gym was separated for bidding from the historic refurbishments and is scheduled for a bid opening 11/2/2012.
7
Quarterly Report dated September 30, 2012
Item 6. Special Initiatives PROJECT UPDATES ____________________________________________________________________________________________
Reimbursement of Past Work Cost Reasonableness Analysis $783,240 – Construction Masters, Inc. The OPSB’s Facilities Department determined that the portable classrooms at the Bethune Elementary School needed to be replaced (due to significant damage Hurricane Katrina). In order to accomplish this in time for the opening of school for the 2007-2008 year, the OPSB approved an emergency purchase of the portable classrooms. In August, the funding team provided a background/history and a cost reasonableness analysis, which illustrated the Bethune Portable Classrooms were reasonable in price. Our team worked in collaboration with GOHSEP and a Disaster Recovery Specialist to gain data regarding similar modular facilities constructed at the Thomas Jefferson Senior High School. This documentation allowed our team to compare the Bethune Portable Classroom costs and determine the cost to be reasonable. The funding team prepared a Memorandum (dated August 2, 2012), with an analysis, on the OPSB’s behalf; to be submitted with an RRF package (within the 4th Quarter). Our team is certain this will allow the OPSB to be reimbursed for the $783,240 expended immediately Hurricane Katrina. Change Order Documentation $564,873.38 – Satterfield & Pontikes Construction, Inc. The OPSB determined that repairs were required at the Laurel Elementary School (LES) immediately after Hurricane Katrina. In order to accomplish this, the OPSB solicited bids for general construction services to repair and reconstruct the LES. A mandatory pre-bid was held at the LES on April 20, 2006 to address any questions or concerns relative to the invitation for bid. All bidders were required to attend the pre-bid meeting. The bid opening occurred on May 4, 2006 and a total of six (6) bids were received. Satterfield and Pontikes Construction, Inc. (S&P) was the apparent low bidder and was awarded the project. Shortly after the Notice to Proceed was issued, OPSB and S&P discovered additional items that needed immediate attention and repair. These repairs were not either visible and or accessible during the initial walk-through of the facility on April 20, 2006. There were a total of fourteen (14) change orders for the LES, consisting of approximately $465,093; the OPSB approved all fourteen (14) change orders. The fourteen (14) change order had insufficient backup documentation to be eligible for reimbursement. During third (3rd) quarter, the funding team contacted S&P (via mail and telephone), requesting additional documentation in order to substantiate the fourteen (14) change orders. S&P provided the appropriate documentation to Jacobs/CSRS. The funding team prepared a Memorandum (dated August 21, 2012), outlining the background/history, on the OPSB’s behalf; to be submitted with an RRF package (within the 4th Quarter).
8
Quarterly Report dated September 30, 2012
Orleans Parish School Board’s Leased Temporary Facilities: Category B PW #19289 The funding team revisited the OPSB’s Category B Lease PW #19289 during this quarter. After the review of the back-up documentation contained in PW #19289, it was identified that FEMA had captured incorrect lease timeframes and amounts. The funding team performed an analysis of all the temporary facilities being utilized (i.e. executed lease agreements). The analysis was presented to FEMA, who acknowledged that Jacobs/CSRS was, in fact correct, and a version to PW #19289 was needed to capture the corrections. The results yielded an additional $532,372.43 in eligible Category B Funding and the version is anticipated within the next few weeks. Past Zero Dollar PW Close Out Requests This quarter the funding team started an analysis of prior submitted Zero Dollar PW closeout requests for content and continuity. During the analysis, several open requests were discovered and our team endeavored to follow up on these requests with GOHSEP. The review process entailed an analysis of server stored data as well as hard copy archived copies of past closeout request for missing documents as well as review of actual obligated project worksheets to assure the project worksheets were in fact zero dollar PW’s. After our analysis, the funding team was able to identify and obtain missing documentation from the GOHSEP Close Out Team and submit new PW’s for close out this quarter. Further close out activities are discussed in “Item #7: Close Out Information & Submissions”.
9
Quarterly Report dated September 30, 2012
PROJECT UPDATES OPSB Zero Dollar Project Worksheets: Close-Outs Jacobs/CSRS is revisiting and re-assessing OPSB’s current zero dollar Project Worksheets; in order to compose and submit additional close-out letters to GOHSEP. This task will be ongoing over the next few months DELIVERABLES COMPLETED Category G Alternate Project Worksheet Request Completed and transmitted a “Request for Consolidation of Category G Project Worksheets into a Single Project Worksheet” ($472k in eligible funding) Mahalia Jackson Elementary School: Consolidation of Improved Projects Review of PW Reference #1638 – consolidation of five (5) Improved Projects into a Single Improved Project. Ensured Hazard Mitigation Proposals were captured correctly. Cost Reasonableness Analysis: Past Work Jacobs/CSRS collaborated with OPSB/GOHSEP/DRS to complete a cost reasonableness analysis for the Bethune Elementary School Portable Classrooms. The funding team composed and transmitted a Memorandum to the OPSB. Change Order Documentation: Past Work Laurel Elementary School: contacted Satterfield & Pontikes for additional change order documentation Contractor provided documentation and the funding team composed/transmitted a Memorandum to the OPSB Close Out Requests The funding team submitted 186 Zero Dollar Close Out Letter requests this quarter Clarification Memorandums Composed three (3) Clarifying Memorandums in order to change the Project Names on Amendment Requests submitted New Lake Forest School at the Greater St. Stephens Site (AIDB #1818) New Karr High School at the Jo Ellen Smith Site (AIDB #1815) Edna Karr High School – Gymnasium Repair (AIDB #1822) UPCOMING SCHEDULE
No immediate items scheduled
10
Quarterly Report dated September 30, 2012
Item 7. Close Out Information & Submissions PROJECT UPDATES ____________________________________________________________________________________________ The funding team made significant progress this quarter in regards to OPSB close out information. The results were the following: 1) Developed a database to track OPSB close out requests – through all stages of the close out process Incorporated past close out requests and associated dates: approximately 352 prior submissions to FY2012 Cross-referenced information with Louisiana Public Assistance website Ensured both hard copy and electronic copy were on file of all close out requests: this is an ongoing process as the funding team obtains missing official GOHSEP/FEMA close out letters Capturing all applied payments Created an overall summary tab to share with GOHSEP Finance / DRS / GOHSEP Close Out Team 2) Submission of Close Out Requests A total 186 Zero Dollar Project Worksheet close out requests were submitted this quarter 59 close out requests submitted on August 15, 2012 65 close out requests submitted on August 23, 2012 62 close out requests submitted on September 4, 2012 3) Extensive analysis of Zero Dollar Project Worksheet Close Out Requests During the review and submission process it was discovered that the majority of the Zero Dollar PW’s requested for close out had electronic payments on them (i.e. small projects that were initially paid without documentation) The electronic payments made on the Zero Dollar PW’s are considered OPSB “Debt”: monies that need be repaid in order to clear/close the grant This fostered the need to coordinate/collaborate with GOHSEP Finance / DRS / GOHSEP Close Out Team 4) Categorization of OPSB “Debt”: part of the OPSB Close Out Requests Database Through the funding teams analysis of the OPSB’s Zero Dollar Project Worksheets a need to categorize the perceived “debt” became evident The “debt” analysis consisted of 1) identifying the amount paid on the PW, 2) reading the latest version of the PW (300+ PW’s) and 3) classifying the “debt” into the below categorizes - Type 1 Debt: De-obligations from OPSB and Re-obligations to RSD - Type 2 Debt: PW’s were monies should transfer to PW #19290 (OPSB SSR PW) - Type 3 Debt: Monies paid on Inactive/Ineligible facilities - Type 4 Debt: PW’s were monies should transfer to PW #18773 (Contents Improved PW) - Type 5 Debt: PW’s were monies should transfer to PW #12933 (Demolition PW) The categorization of the “debt” gives the OPSB the visibility and a way-ahead to tackle the issue 11
Quarterly Report dated September 30, 2012
5) Meeting scheduled with GOHSEP Finance / DRS / GOHSEP Close Out Team / OPSB / Jacobs/CSRS: October 9, 2012 The funding team coordinated a meeting with the parties identified above for October 9, 2012: to discuss the “debt” issue Main items to be discussed: - Applying valid RRF’s against OPSB “debt”: designation of certain RRF’s when submitted - Identification of applied payments in the “Notes” section of Louisiana PA: so the DRS Team / Close Out Team can quickly distinguish PW’s that can be closed - Categorization of OPSB’s “debt”: four types noted above - Systematic approach to applying RRF payments to “debt” PW’s – in sequential order - As applied payments occur, can the GOHSEP Close Out Team close Zero Dollar PW’s (in sequential order)
12
Quarterly Report dated September 30, 2012
Part II Item 8. Project Worksheets Reviewed Listed below (in order or reviewed) are the PWs that Jacobs/CSRS reviewed on OPSB’s behalf during the 3nd Quarter of 2012:
Project Worksheet # 15234
15224
15206
15171
15245
Version 7
7
7
7
Facility Mahalia Jackson: Building B
Mahalia Jackson: Building E
Mahalia Jackson: Building A
Mahalia Jackson: Building C
Category
SOW
E
De-obligate SOW & Eligible Finding: roll into one Improved PW Ref #1638
E
De-obligate SOW & Eligible Finding: roll into one Improved PW Ref #1638
E
De-obligate SOW & Eligible Finding: roll into one Improved PW Ref #1638
E
De-obligate SOW & Eligible Finding: roll into one Improved PW Ref #1638
E
De-obligate SOW & Eligible Finding: roll into one Improved PW Ref #1638
7
Mahalia Jackson: Building D
IP1638
0
Mahalia Jackson: Roll-Up Improved PW
E
8190
2
Easton High School
E
Contents Roll-Up: De-obligation to transfer to PW #18773
8753
2
Benjamin Franklin Senior High School
E
Contents Roll-Up: De-obligation to transfer to PW #18773
8758
3
Benjamin Franklin Senior High School
E
9281
4
Bienville Elementary School
E
Contents Roll-Up: De-obligation to transfer to PW #18773 De-obligation: Contents - cost share error and the correct applicant is RSD
9650
3
Lake Forest Magnet Elementary School
E
Contents Roll-Up: De-obligation to transfer to PW #18773
9693
4
Edward Hynes Elementary School
E
Contents Roll-Up: De-obligation to transfer to PW #18773
9770
2
Bethune Elementary School
E
Contents Roll-Up: De-obligation to transfer to PW #18773
9786
3
Lake Forest Magnet Elementary School
E
Contents Roll-Up: De-obligation to transfer to PW #18773
13
Group 5 IP's into 1 Improved Project PW
Quarterly Report dated September 30, 2012 Contents Roll-Up: De-obligation to transfer to PW #18773
10526
2
Robert R. Moton Elementary School
E
10954
3
Robert R. Moton Elementary School
E
11364
2
JROTC Headquarters
E
Contents Roll-Up: De-obligation to transfer to PW #18773 De-obligation: Contents OPSB is not the eligible applicant RSD is: will be transferred to PW #19300
11378
2
Timbers Central Office JROTC
E
Contents Roll-Up: De-obligation to transfer to PW #18773
11384
3
Almonaster Central Services
E
Contents Roll-Up: De-obligation to transfer to PW #18773
11887
3
Almonaster Central Services
E
Contents Roll-Up: De-obligation to transfer to PW #18773
12362
3
Almonaster Central Services
E
Contents Roll-Up: De-obligation to transfer to PW #18773
13171
3
Lusher Elementary School
E
Contents Roll-Up: De-obligation to transfer to PW #18773
13337
2
Almonaster Central Services
E
Contents Roll-Up: De-obligation to transfer to PW #18773
14375
2
District Wide: Food & Supply
E
Contents Roll-Up: De-obligation to transfer to PW #18773
15229
3
Mahalia Jackson Elementary School
E
Contents Roll-Up: De-obligation to transfer to PW #18773
16061
3
New Orleans Center for Health Careers
E
16124
2
Sophie B. Wright
E
Contents Roll-Up: De-obligation to transfer to PW #18773 De-obligation: Contents OPSB is not the eligible applicant RSD is: will be transferred to PW #19299
16135
2
Edward Phillips Junior High School
E
Contents Roll-Up: De-obligation to transfer to PW #18773
16136
2
New Orleans Center for Health Careers
E
Contents Roll-Up: De-obligation to transfer to PW #18773
16230
1
New Orleans Center for Health Careers
E
16288
1
Capdau Charter School
E
14
Contents Roll-Up: De-obligation to transfer to PW #18773 De-obligation: Contents OPSB is not the eligible applicant RSD is: will be transferred to PW #19299
Quarterly Report dated September 30, 2012
16303
11896
16311
1
1
1
Samuel Green Charter School
Lusher Extension School
Nelson Elementary School
E
De-obligation: Contents OPSB is not the eligible applicant RSD is: will be transferred to PW #19299
E
De-obligation: funds were previously added to PW #18773, but not de-obligated
E
De-obligation: Contents OPSB is not the eligible applicant RSD is: will be transferred to PW #19299 Re-obligation of erroneous deobligation during the SSR Process$10,758,824.71
19297
1
OPSB Contents
E
9932
3
Gregory Junior High School
E
18773
2
OPSB Contents
E
De-obligation as this facility is an RSD facility and not OPSB Contents Roll-Up Obligation PW - adding 22 donor and realigning BCG's to correct amounts
Jacobs/CSRS Action Items after Reviewing above Project Worksheets
OPSB Contents Improved Project: PW #18773: Multiple changes required prior to submission – the version prepared/delivered to OPSB had incorrect verbiage and reference PW numbers (RSD PW’s instead of OPSB). FEMA acknowledged and made adjustments accordingly to the version.
15
Quarterly Report dated September 30, 2012
Item 9. Summary of FEMA Funding Work Type
* Eligible Obligated
Federal Paid
Balance
$44,948,342.67
$7,969,748.10
$36,978,594.57
$1,845.76
$1,854.99
($9.23)
$12,916.64
$13,271.77
($355.13)
Labor and Equipment Costs
$1,136,232.28
$258,779.26
$877,453.02
Management Costs
$7,912,152.04
$1,607,284.67
$6,304,867.37
Permanent Facility Repair
$8,252,194.06
$5,306,827.87
$2,945,366.19
$313,038,186.51
$41,140,380.40
$271,897,806.11
Stabilization/Temporary Roof Repair
$1,844,003.35
$1,839,193.82
$4,809.53
Temporary Facility and related costs
$15,652,399.85
$7,935,326.67
$7,717,073.18
$392,798,273.16
$66,072,667.55
$326,725,605.61
Contents Debris Removal/Demolition Costs Interim Housing
Permanent Facility Replacement
Grand Total
NOTE: *“Eligible Obligated� dollars do not include Sub-Grantee Administration Funding the amount of $1,999,991.58
16
APPENDIX B
Appendix B School Map
SCHOOL MAP
Status Date: 30-September-2012
New Orleans Parents’ Guide To Public Schools
Spring 2012 Edition
3
4
7
38
I-10
Loui sa S t
St d
Caff in A ve Tup elo St
Br oa
rS t
tu
De ca
Nunez St
N
Mag azin e St
Ge ne
ral M
eye
e 22 Macarthu r Blvd Ge ne ral 80 De 24 ga ulle Dr
TIP: The letter and number on the sides
70
of each school map (see sample right) tell you in which grid you can find the school on the city map above.
A-6
Almonaster Ave
r Av
16
TIP: Use the map above to find schools near your home. Use the maps on each school page to pinpoint the school’s location
e
Paris Rd
Wisner Blvd St Bernard Ave
Marconi Dr
Canal Blv d
West End Blvd
Jeffe rson Ave
Hw y
fM Che
Village de L’Est
y r Hw nteu
Louisiana Hwy 406
Lo
Tchoupitoulas St
an
56
15
Elementary Schools Middle Schools/Junior High Combination High Schools High Schools
Ward
Algiers rm
e Av
7
50
d lar
89
64
Newton St 90 54 42 18 25 83
Be h
l Bu
69
51
d tR
21
Lower 9th
8
87
88 49
89 28
NOTE: Map key numbers are also school page numbers.
TIP: The bullet shape for each school tells you which type of school it is. For example: square bullets are high schools.
Ave
Woodland Dr
45
13
e Av na sia
65 86 19 19
5
Florid a
h rig W
67 40
i Lou
39
Bywater NG
St
Uptown
58
Warehouse District 23 61 52 Garden 29 59 District 76 75
67
vd Bl
37 79
60
71 72
ne er
d
ve Napoleon A
6
Mid-City
Blv
ad Re
36 31
Ca na 53 l ne Ave St 30 57 33
lvd Crowder B
art
Tul a
11
a41 lvez S t N Claiborne Ave 55 74 63St Claude A 66 35 3ve 11 36 62 81 85 34
84
1
lvd st B e r o eF
n Rd
Ea rh
77
43
46
ak 68 L
Rd
d France R
9 Airline H wy 17
44
20
e
City Park Ave 14 10
ie Rd Metair
en G
47 Desaix Blvd 26
y till
vd Bl
Elysian Fields Av
I-610
32 2
48
nm a Dow
27
Gentilly Paris Ave
C
Lakeview
4
Blvd
Mo
on rris
New Orleans East
82 Franklin Ave
Jefferson Parish
Filmore Ave
78 Robert E Lee Blvd Dr Press
B
E
6
New Orleans Public Schools ne Hay
D
5
c Lu
A
2
Michoud Blvd
1
Key to Map of New Orleans Public Schools 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46
Abramson Elementary School Akili Academy of New Orleans ARISE Academy Arthur Ashe Charter School Audubon Charter School Benjamin Banneker Elementary School Batiste Cultural Arts Academy @ Live Oak School Martin Behrman Charter School Mary McLeod Bethune Elementary School Pierre A. Capdau Charter School Mary Coghill Elementary School Joseph Craig Elementary Lawrence D. Crocker Arts and Technology School John Dibert Community School Einstein Charter School Dwight Eisenhower Elementary School Esperanza Charter School William J. Fischer Accelerated Academy Benjamin Franklin Elementary Math and Science School (2 locations) Gentilly Terrace Elementary School Samuel J. Green Charter School Paul B. Habans Elementary School Edgar P. Harney Elementary School Alice Harte Elementary School Murray Henderson Elementary School Langston Hughes Academy Charter School Edward Hynes Charter School Intercultural Charter School International School of Louisiana Morris Jeff Community School James Weldon Johnson Elementary School KIPP Believe Primary KIPP Central City Primary KIPP McDonogh 15 Primary School KIPP New Orleans Leadership Primary Lafayette Academy Charter School of New Orleans Lagniappe Academies of New Orleans Lake Forest Elementary Charter School Lusher Charter School Lycée Français de la Nouvelle Orléans Benjamin E. Mays Preparatory School McDonogh 32 Literacy Academy McDonogh 42 Elementary Charter School McDonogh City Park Academy Milestone SABIS Academy of New Orleans Robert Russa Moton Charter School
A-7
47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90
Medard H. Nelson Charter School Pride College Prep (at Mildred Osborne) Sarah T. Reed Elementary School Henry Schaumburg Elementary School SciTech Academy @ Laurel School James M. Singleton Charter School Success Preparatory Academy Harriet Tubman Elementary School A.P. Tureaud Elementary School Fannie C. Williams School Sylvanie Williams College Prep Elementary School Andrew H. Wilson Charter School Cohen College Prep Middle School KIPP Believe College Prep KIPP Central City Academy KIPP McDonogh 15 Middle School KIPP New Orleans Leadership Academy Dr. Martin Luther King Charter School for Science and Technology Lusher Charter School McDonogh 35 College Preparatory High School Eleanor McMain Secondary School Miller-McCoy Academy for Mathematics and Business Sophie B. Wright Charter School Algiers Technology Academy Architecture Design Engineering Prep George W. Carver High School Collegiate Academies (not shown) Joseph S. Clark Preparatory High School Cohen College Prep High School Walter L. Cohen Senior High School Warren Easton High School Benjamin Franklin High School International High School of New Orleans Edna Karr High School KIPP Renaissance High School Lake Area New Tech Early College High School!!!! L.B. Landry High School John McDonogh High School New Orleans Center for Creative Arts (NOCCA) New Orleans Charter Science & Mathematics High School New Orleans Military/Maritime Academy Sci Academy Sarah T. Reed High School O. Perry Walker College and Career Preparatory High School
APPENDIX C
Appendix C Understanding the Quarterly Report
UNDERSTANDING THE QUARTERLY REPORT
Status Date: 30-September-2012
UNDERSTANDING THE QUARTERLY REPORT
Schedule Phases Design Procurement Construction Final Completion
Schedule Data Plan Start and Finish-Plan schedule is the baseline start and finish dates. These dates are held static throughout the project, and future schedule updates are measured against this baseline. Schedule phases shown as gray bars. Forecast Start and Finish-Anticipated start and finish dates. The forecast dates are updated as schedule changes occur. Schedule phases shown as blue bar for completed activities and yellow bar as future activities.
UNDERSTANDING THE QUARTERLY REPORT
Status Date: 30-September-2012
UNDERSTANDING THE QUARTERLY REPORT Project Budget-Current project budget. Committed Costs-Sum of all contracts, contract change orders, amendments and purchase orders to date. Cost to Date-Sum of all contract invoices and general expenditures to date. Uncommitted Costs-Anticipated cost to complete the project. Projected Costs-Committed Costs plus Uncommitted Costs. Projected Ovr/(Undr)-Difference between the Project Budget and Projected Costs.
Graphical representation of the cost status of each project.
UNDERSTANDING THE QUARTERLY REPORT
Status Date: 30-September-2012
UNDERSTANDING THE QUARTERLY REPORT General Construction-Facility construction in general and other associated allowance expenditures. Category also includes Construction Contingency and Builder’s Risk Insurance. Demolition-Costs associated with demolishing an existing facility. A/E Fees & Reimbursables-Cost of the Architect/ Engineer Fee and reimbursable expenditures. Environmental-Cost for hazardous materials abatement, testing and State fees. Modular Classrooms-Costs for procurement, installation and permits for pre-fabricated units. Permits & Fees-Costs for project permit and fees. Program Contingency-Budget to be used as necessary for unanticipated project costs. Other Professional Services-Costs for Surveys, Geotechnical, Material Testing, TAB, etc. Other Costs-Other expenses. Miscellaneous-Any expenses not recorded in above descriptions. “Catch All” category.
Status Date-Document is current through date shown.
UNDERSTANDING THE QUARTERLY REPORT
Status Date: 30-September-2012