2 minute read

Redevelopment Update - February 2025

Our highly anticipated redevelopment project is progressing well, with Rubicon Design and Construct retuning to site after the Christmas break and ensuring the project stays on schedule and within budget.

Civil works are progressing well, with footing installation complete and the retaining wall foundation poured. Key milestones have been set, with major works such as the erection of the tensile steel structure commencing in the coming months.

The next key milestone is 14 February 2025, when all below-ground works and backfilling will be completed, the perimeter retaining wall constructed, and the steel framework between the columns erected. From there, BioScapes will begin preparing the foundation for the synthetic greens, with MakMax arriving in March.

Major Milestones & Completion Dates

Site Cut and Level - 13 November 2024

In Ground Civil Drainage - 12 December 2024

Erect Tensile Structure Steel - 28 April 2025

Concrete Slab for Greens - 17 July 2025

Synthetic Bowls Green Surface - 11 August 2025

Final Clean - 29 August 2025

Date for Practical Completion - 29 August 2025

Exciting Technology Partnership

We are thrilled to announce our partnership with Bellarine AV and LED Media to deliver cutting-edge Audio and Visual technology. This will include:

▪ Livestreaming capabilities

▪ Enhanced digital software

▪ Two 4.5-metre video screens on each green for an enhanced experience

With practical completion set for August 2025, our undercover bowling structure will be a game-changer for our club and community. Stay tuned for more updates as we move closer to this exciting milestone!

Nathan O'Neill (CEO) with Chair John Gibcus (Chair)