CURRENT MARKET TRENDS SCHEDULE AND BUDGET IMPACTS ELECTRICAL ITEM
LEADTIME
BU D G E T I M PAC T
TA R I F F I M PAC T
ATS
24-52 Weeks
5% annual increases
*Potential higher increases due to more parts coming from overseas
Generators
24-65 Weeks
5% annual typical increases
No escalations for 2025 (CAT)
Iso Panels
20 Weeks
5% / April - May
*Potential 5% or higher in 60 days
Switchgear
35-52 Weeks
5% / April - May
*Potential 5% or higher in 60 days
Cabletray
Stock to 4 Weeks
5% / April - May
*Potential 5% or higher in 60 days
Typical hospital light fixtures
4-6 Weeks
5% annual increases
**Less of an impact, most are manufactured in USA
OR Lights/Specialty Light Fixtures
4-6 Weeks
5% annual increases
**Less of an impact, most are manufactured in USA
Lighting Controls
4-6 Weeks
5% annual increases
** Less of an impact, most are manufactured in USA
* This depends on which countries, companies, or products are subject to tariffs. ** This depends of foreign components and which countries, companies, or products are subject to tariffs.
P LU M B I N G ITEM
LEADTIME
BU D G E T I M PAC T
TA R I F F I M PAC T
Water Heaters
12 to 14 weeks
There’s a wide variance here, pending make, model & size, impact should be assessed at timew if design.
Increases due to tariffs or otherwise have been nominal to this point. ***Please see narrative for explanation.
Drinking Fountains
4 to 6 weeks
$5500.00 for standard models
Increases due to tariffs or otherwise have been nominal to this point. ***Please see narrative for explanation.
Circulation Pumps
4 to 6 weeks
$750.00 for standard models
Increases due to tariffs or otherwise have been nominal to this point. ***Please see narrative for explanation.
1
SCHEDULE AND BUDGET IMPACTS | Q2 2025