3 minute read
State Route 57 (SR-57) Projects [G
FREEWAYS
STATE ROUTE 57 (SR-57) PROJECTS
PROJECT G
Status: Environmental Phase Complete; Design Proposals Under Review Contact: Rose Casey, Capital Projects • (714) 560-5729 Summary: This project studied the addition of a new northbound general purpose lane (approximately one mile) on SR-57 from Orangewood Avenue to Katella Avenue in the cities of Anaheim and Orange. The northbound general purpose lane would join the northbound general purpose lane between Katella Avenue and Lambert Road, which was opened to traffic in 2014. The final ED and PR were approved on March 29, 2019. On March 8, 2021, the Board approved the final design cooperative agreement with Caltrans and released the RFP for the preparation of PS&E. During the quarter, staff reviewed the proposals received by the April 5, 2021 due date. Consultant selection recommendation is anticipated to be presented to the Board in July 2021 to initiate final design in early 2022.
Segment: SR-57 Northbound, Katella Avenue to Lincoln Avenue Status: PROJECT COMPLETE
Contact: Rose Casey, Capital Projects • (714) 560-5729 Summary: This project increased capacity by adding a new general purpose lane (approximately 2.8 miles), and improved on- and off-ramps and soundwall improvements on northbound SR-57 between Katella Avenue and Lincoln Avenue in the City of Anaheim. Bridges at Katella Avenue and Douglas Road were also widened in the northbound direction. The final ED was approved on September 30, 2009, and the final PR was approved on November 25, 2009. Construction began on November 17, 2011, and opened to traffic on November 19, 2014. The project was officially completed on April 21, 2015.
Segment: SR-57 Northbound, Orangethorpe Avenue to Yorba Linda Boulevard Status: PROJECT COMPLETE
Contact: Rose Casey, Capital Projects • (714) 560-5729 Summary: This project increased capacity by adding a northbound general purpose lane (approximately 2.5 miles) between Orangethorpe Avenue in the City of Placentia to Yorba Linda Boulevard in the City of Fullerton and improved operations with the reconstruction of northbound on- and off-ramps, widening of seven bridges, and the addition of soundwalls. The final ED and PR were approved on November 30, 2007. Construction began on October 26, 2010, and opened to traffic on April 28, 2014. The project was officially completed on November 6, 2014.
FREEWAYS

Segment: SR-57 Northbound, Yorba Linda Boulevard to Lambert Road Status: PROJECT COMPLETE
Contact: Rose Casey, Capital Projects • (714) 560-5729
Summary: This project improved capacity, operations, and traffic flow on SR-57 with the addition of a new northbound general purpose lane (approximately 2.5 miles) between Yorba Linda Boulevard in the City of Fullerton and Lambert Road in the City of Brea. Additional project benefits included on- and off-ramp improvements, the widening and seismic retrofit (as required) of six bridges in the northbound direction, and the addition of soundwalls. Existing lanes and shoulders were also widened to standard widths, enhancing safety for motorists. The final ED and PR were approved on November 30, 2007. Construction began on November 2, 2010, and opened to traffic on September 23, 2013. The project was officially completed on May 2, 2014.
Status: Schedule TBD Contact: Rose Casey, Capital Projects • (714) 560-5729 Summary: Caltrans previously completed a Project Study Report/Project Development Support document to add a northbound truck-climbing lane (approximately 2.5 miles) from Lambert Road to Tonner Canyon Road in the City of Brea. The project will require coordination with Los Angeles County Metropolitan Transportation Authority (LA Metro) on planned improvements or related work across the Orange County/Los Angeles County line. The mainline project includes interchange and ramp improvements at Lambert Road. Through the SB 1 Trade Corridor Enhancement Program, funds were allocated to initiate the construction phase for interchange improvements at Lambert Road which will complement and serve as a first phase to the freeway improvement project. Construction began in mid-2019 and is anticipated to be completed at the end of 2021. Phase two, which is the mainline improvement, was initially approved for State Transportation Investment Program (STIP) funding in March 2018 to initiate the environmental phase. However, due to the 2019 STIP reduction, funding was shifted to cover projects already underway. To ensure coordination with other projects planned for construction and to avoid unreasonable impacts to the public, this project is currently scheduled to be constructed beyond the Next 10 Plan timeframe.