MTM Fact Sheet 2024

Page 1

A special construction update for the Omaha metro area.

NEBRASKA DEPARTMENT OF TRANSPORTATION

2024 CONSTRUCTION SEASON

The 2024 construction season is underway as we work to build and maintain an efficient, long-lasting transportation system within the Omaha metropolitan area. We recognize the frustration that construction can cause. Thank you for your patience as we work to make these important changes. Please drive slowly, use detours and always remember: Buckle Up, Phone Down!

The site also offers other project information, such as:

Anticipated traffic impacts

Anticipated project start and completion timeframes

Project contacts

1 MISSOURI RIVER ELKHORN R I VER PLATTE RIVER LA VISTA PAPILLION MILLARD OMAHA ELKHORN WATERLOO YUTAN BENNINGTON BELLEVUE SPRINGFIELD RICHFIELD GRETNA VALLEY 680 80 80 80 80 80 80 29 680 680 480 6 6 6 6 6 75 75 75 75 275 275 275 275 275 275 34 66 50 50 92 28B 31 36 36 64 64 133 64 370 370 66 66
Visit ndot.info/mtm to view an interactive map of construction projects for NDOT,
DOT, City of Omaha, Douglas County, Sarpy County and other municipal projects.
Iowa

PARKER ST – FORT ST, OMAHA

CONSTRUCTION START: Summer 2023

ANTICIPATED

CONSTRUCTION

COMPLETION: Fall 2024

IMPROVEMENTS:

Improvements consist of repairing and painting bridges, as well as milling and resurfacing US-75.

TRAFFIC IMPACTS: Traffic impacts include lane and ramp closures on US-75. The Bristol Street bridge over US75 is currently closed to traffic through approximately midJune 2024. Pedestrian access would be maintained during the Bristol Street bridge detours. The Hamilton Street bridge is anticipated to close April through fall 2024. During this, a detour will be in place, and an ADA accessible shuttle will offer service from 6:00 a.m. to 9:00 p.m. to accommodate area businesses and programs

CUMING ST HAMILTON ST PARKER ST LAKE ST BINNEY ST BRISTOL ST PRATT ST MANDERSON ST SPRAGUE ST AMES ST N 30TH ST N 24TH ST FLORNCE BLVD N 30TH ST N 34TH AVE N 24TH ST FLORNCE BLVD STORZEXPY 75 75 75 75 Project Location - Remaining Work Legend Project Location - Completed Work

BANCROFT ST – DEWEY ST, OMAHA

ANTICIPATED CONSTRUCTION

START: Spring 2024

ANTICIPATED CONSTRUCTION

COMPLETION: Spring 2024

IMPROVEMENTS:

Improvements consist of asphalt crack sealing and new pavement markings.

TRAFFIC IMPACTS:

Construction will be completed overnight with intermittent temporary lane and ramp closures.

F ST VINTON ST ARBOR ST PARK AVE 24TH AVE CENTER ST WOOLWORTH AVE LEAVENWORTH ST HARNEY ST 75 6 480 480 80 80 Project Location Legend

CONSTRUCTION START: March 2024

ANTICIPATED CONSTRUCTION

COMPLETION: Summer 2025

IMPROVEMENTS: Improvements consist of concrete pavement and bridge repairs on N-50.

TRAFFIC IMPACTS: During construction, N-50 will be limited to one lane in each direction for major bridge repair work. For concrete pavement and minor bridge repairs, temporary daytime and overnight lane closures can be expected.

12TH STREET – MISSOURI RIVER BRIDGE

PAINTING, OMAHA

ANTICIPATED CONSTRUCTION

START: Spring 2024

IMPROVEMENTS:

Improvements consist of painting specific locations within the bridge.

TRAFFIC IMPACTS: Work will require multiple extended closures of Exit 4 (westbound ramp to Dodge Street). A designated detour will utilize Exit 3 to 14th Street. Local traffic under I-480 may be detoured onto local roads or experience lane closures to accommodate work. Pedestrian traffic may be detoured to adjacent sidewalks or maintained with temporary protective covers.

ANTICIPATED CONSTRUCTION

COMPLETION: Winter 2024

GILES RD CORNHUSKER RD HARRISON ST S 168TH ST S 144TH ST 275 80 80 370 50 Project Location Legend
M I SSOUR I R I VER N 19TH ST N 13TH ST N 14TH ST N 24TH ST N 10TH ST N 30TH ST HARNEY ST JACKSON ST FARNAM ST DODGE ST CUMING ST NEBRASKA IOWA 6 6 75 480 Legend Project Location Ramp Closure I-480 Westbound Ramp to Dodge Street Detour

I-480 – MISSOURI RIVER BRIDGE, OMAHA

ANTICIPATED CONSTRUCTION START: Spring 2024

IMPROVEMENTS:

Improvements consist of bridge repairs, superstructure painting, adding a bridge drainage system, minor electrical repairs, and updating lighting.

TRAFFIC IMPACTS: Work will require multiple extended closures of Exit 4 (westbound ramp to Dodge Street). A designated detour will utilize Exit 3 to 14th Street. Additionally, the Iowa Riverfront Trail would be closed under I-480 for approximately 21 days to accommodate work. A designated detour would be provided utilizing the River Edge Services Road Trail.

MAHONEY – N-370

ANTICIPATED CONSTRUCTION START: Spring 2024

ANTICIPATED CONSTRUCTION

COMPLETION: Fall 2024

IMPROVEMENTS:

Improvements consist of installing 11.2 miles of cable barrier in the grassy median on I-80 from Mahoney State Park area to N-370.

TRAFFIC IMPACTS: Traffic impacts are anticipated to be shoulder closures.

ANTICIPATED CONSTRUCTION COMPLETION: Fall 2026

5
M I SSOUR I R I VER LEAVENWORTH ST S 24TH ST N 19TH ST N 13TH ST N 14TH ST N 24TH ST N 10TH ST N 30TH ST HARNEY ST JACKSON ST LEAVENWORTH ST FARNAM ST DODGE ST CUMING ST NEBRASKA IOWA 6 6 75 480 480 Legend Project Location Ramp Closure I-480 Westbound Ramp to Dodge Street Detour
PLATTERIVER Springfield Ashland Gretna ASHLAND RD 6 6 80 80 50 66 66 66 63 31 66 370 370 Project Location Legend

US-6/192ND STREET INTERCHANGE, OMAHA

CONSTRUCTION START: March 2024

ANTICIPATED CONSTRUCTION

COMPLETION: Winter 2024

IMPROVEMENTS: Improvements consists of reconfiguring the existing interchange of US-6/West Dodge Road and 192nd Street to a Diverging Diamond Interchange (DDI). Additionally, the project includes removing and replacing pavement, bridge repairs, ramp work, reconstruction of curb inlets and storm sewer, new ADA curb ramps and sidewalk, new traffic signals, and updated street lighting.

TRAFFIC IMPACTS: TRAFFIC IMPACTS: Traffic impacts include temporary daytime and overnight lane closures as well as overnight ramp closures.

6
SHWS CLEVELAND BLVD W DODGE RD
W DODGE RD
192ND ST
NHWS CLEVELAND BLVD BURKE ST
6 6
LAWRENCE YOUNGMAN LAKE
Project
Location Legend

SKYLINE DR, 168TH ST, OMAHA

ANTICIPATED CONSTRUCTION START: Spring 2024

ANTICIPATED CONSTRUCTION COMPLETION: Winter 2024

IMPROVEMENTS: Improvements consist of bridge repairs, shoulder replacement, approach replacements, curb and flume installation, culvert work, removing and replacing impacted guardrail and lighting, grading, and erosion control. Additional work includes overhead sign structure replacement.

TRAFFIC IMPACTS: Traffic impacts include multi-day closure of 180th Street and 168th Street overpass bridges and interchange ramps as well as lane restrictions on US-6, ramps, and 180th and 168th streets.

7
ELKHORNRIVER BLONDO ST BLONDO ST PACIFIC ST PACIFIC ST PACIFIC ST W DODGE RD N 192ND ST N 180TH ST N 168TH ST N 240TH ST RIVER RD DR N SKYL I N E D R W DODGE RD OLD LINCOLN HWY SKYLIN E D R 6 6 6 275 275 31 28B Project Location Legend

60TH ST – 24TH ST, OMAHA

ANTICIPATED CONSTRUCTION

START: Spring 2024

ANTICIPATED CONSTRUCTION

COMPLETION: Winter 2024

IMPROVEMENTS: Improvements consist of milling and resurfacing the roadway, culvert work, and preventative maintenance and repairs to bridge structures.

TRAFFIC IMPACTS: Traffic impacts include overnight lane and ramp closures.

13TH ST WEST, OMAHA

ANTICIPATED CONSTRUCTION START: Spring 2024

ANTICIPATED CONSTRUCTION

COMPLETION: Summer 2024

IMPROVEMENTS:

Improvements consist of crack sealing the asphalt pavement and adding new pavement markings along Interstate 80 (I-80).

TRAFFIC IMPACTS: Traffic impacts include overnight lane and ramp closures.

8
20TH ST S 13TH ST F ST VINTON ST 75 480 80
Project Location Legend
F ST F ST GROVER ST S 42ND ST S 50TH ST S 36TH ST S 24TH ST VINTON ST 75 480 80 80 80 Project Location Legend
20TH ST

US-34 TO I-80, OMAHA

ANTICIPATED CONSTRUCTION

START:

Fall 2024

ANTICIPATED CONSTRUCTION

COMPLETION: Spring 2025

IMPROVEMENTS:

Improvements consist of concrete diamond grinding, crack and joint sealing, and concrete pavement repair.

TRAFFIC IMPACTS:

Traffic impacts include overnight lane and ramp closures.

9
S 25TH ST S 10TH ST Q ST MADISON ST HARRISON ST CHANDLER RD S 30TH ST S 36TH ST S 42ND ST S 48TH ST M S S O U R I R I VER CORNHUSKER RD HARLAN DR CAPEHART RD FORT CROOK RD S S 25TH ST S 36TH ST HIDDEN VALLEY DR 75 75 34 75 75 370 BELLEVUE OFFUTT AIR FORCE BASE
Location Legend
Project

HARRISON ST - DODGE ST, OMAHA

I-80/I-680 INTERCHANGE – Q ST (WB), OMAHA

ANTICIPATED

CONSTRUCTION START: Fall 2024

ANTICIPATED

CONSTRUCTION

COMPLETION: Spring 2025

IMPROVEMENTS:

Improvements consist of asphalt crack sealing and pavement marking.

TRAFFIC IMPACTS: Traffic impacts include overnight lane and ramp closures.

I ST L ST Q ST S 108TH ST S 120TH ST 275 80 680
Location Legend
Project

DOUGLAS COUNTY LINE – N-64

ANTICIPATED CONSTRUCTION START: Spring 2024

ANTICIPATED CONSTRUCTION COMPLETION: Winter 2024

IMPROVEMENTS: Improvements consist of concrete pavement repair, milling and resurfacing asphalt shoulders, and joint and crack sealing.

TRAFFIC IMPACTS: Traffic impacts include temporary overnight lane and ramp closures during which alternate routes would need to be utilized.

11
P l att e R i v er WREICHMUTHRD N 312TH ST N 300TH ST N 288TH ST N 276TH ST IDA ST STATE ST RAINWOOD RD 275 275 64 36 36 VALLEY
Project Location Legend

District 2 Headquarters

PO Box 45461

Omaha, NE 68145-0461

dot.nebraska.gov

12
St
4425 S 108th
Timothy W. Weander, P.E. District Engr. Barbara Gerbino-Bevins, P.E. Dist. Construction Engr. Maurice P. Hinchey, P.E. Asst. Dist. Construction Engr.
ELKHORN RIVER S 252ND ST S 240TH ST PACIFIC ST 275 275 92 Project Location Legend