2 minute read
Mardie salt project awards $16 million pump contract
BCI Minerals Limited (BCI) has awarded a $16 million contract for a main seawater pump structure at the Mardie Salt and Potash Project, also announcing that the project’s northern embankment trial is nearly completed and construction of its southern trial pond is beginning.
The contract for the main seawater pump structure is fully funded from BCI’s existing cash balance of $110 million as of July 2021, and has been awarded to Western Australian company, Ertech’s Geomarine business.
Advertisement
Ertech’s Geomarine specialises in designing and constructing nearshore marine infrastructure for the resources, infrastructure and defence sectors.
When the project is fully operational, the primary seawater pump station will pump 160GL of water into the evaporation ponds each year, equivalent to approximately 70,000 Olympic swimming pools.
The Mardie Salt and Potash Project’s investigative works are an essential precursor to main construction, to provide confidence about key assumptions, including materials availability, construction methodology, pond wall settlement, pumping rates, pond floor water retention, and cost and schedule assumptions.
Construction of the northern embankment trial was nearing completion in September and the southern trial pond will incorporate construction methodology, materials and equipment learnings from the northern embankment trial.
Construction of the civil works will form part of a broader contract awarded to WBHO Infrastructure in March 2021, which includes the northern embankment trial, southern trial pond, and after full regulatory and access approvals, Pond 1 and Pond 2.
The work involves the design, procurement, construction and commissioning of all the detailed earthworks, piling, structural steel, concrete, mechanical and electrical installations required to accommodate and operate six 3,000L per second pumps within the pump structure.
Main construction of the project can only commence when BCI has received approval from the Western Australian Minister for Environment, as well as associated secondary approvals, including when final tenure and funding have been secured.
BCI anticipated all these to be in place by late 2021.
VERTICAL TURBINE PUMPS Layne Bowler vertical turbine pumps have a proven record under the most demanding and toughest of conditions. • Flows to 7,500 L/Sec • Heads to 500 m • Power to 1000+ kW • Temperatures to 150°C • Bowls Diameter up to 45 inch WELCOME TO THE BIG END OF TOWN.

When high head and high flows are required look no further than this quality Italian made range. • Flows to 5000m³/h • Head to 220m • Pumps that exceed EN733 (DIN 24255 standard)
SKD Series NCBK Series
NCA Series