RENOVATION OF PUBLICAND STAFF RESTROOMS
Contract No. 32200276/JUD-OC-2022-1 | HBRInternational, Inc.
For the month of October,contractor HBR continued to work on phase one of Room #203 - Men's Public Restroom Second Floor and Room #218 - Women's Public Restroom Second Floor. Renovation also started on October 17,2022 for the following areas:
Advertisement
- Room #121 - Associate Justice restroom;
- Room #126 - Chief Justice restroom;
- Room #129 - Associate Justice restroom;
- Room #168 - Supreme Chambers women's restroom; and
- Room #169 - Supreme Chambers men's restroom.
On October 25,HBR submitted an extension request for the Judiciary's consideration. Accompanying the request letter was an updated project schedule. The current contract expires on November 4,2022, but the updated project schedule shows project completion on December 31, 2022.
On the same day,HBRsubmitted Change Order No. 3 regarding an additional single toilet tissue with cellphone holder/urinal cellphone holder,wall mounted shelf/toilet portion coat hook. Additionally on October 26,2022,Change Order No. 4 was submitted regarding changes on microcement flooring to ceramic unglazed tiles 24"x25"x1/4" thk (2400 sq.ft. total area). The scope of work includes the furnishing of labor, tools,materials,equipment, and management and supervision to complete the work. See Exhibit H.1 for submittals,meeting sign-in sheet,and extension request.