DTMP 5.15.25 PC WS Presentation

Page 1


Commission Work Session | 05.15.2025

Hal Baillie | LRP - Manager Planning

1. PROJECT UPDATE

• 2045 Comprehensive Plan

* Placemaking policy #13: Update the Downtown Master Plan.

• Council allocated $500,000 towards developing a downtown master plan.

• MKSK was selected for the contract at a total cost of $495,075.00

• This master plan will be considered by the Planning Commission as an amendment to the 2045 Comprehensive Plan.

RECONNECTING TO OUR DOWNTOWN

2. PROJECT MILESTONES

02/13/2025

RECONNECTING TO OUR DOWNTOWN

3. PROJECT TIMELINE

TASK 0: STARTUP & COORDINATION

TASK 1: LAND USE ASSESSMENT (JUNE–SEPTEMBER)

TASK 2: HOUSING & MARKET ANALYSIS (AUGUST–DECEMBER)

TASK 3: PUBLIC ENGAGEMENT

TASK 4: PLAN DEVELOPMENT (OCTOBER–FEBRUARY)

TASK 5: DRAFT REPORT (FEBRUARY–MARCH)

TASK 6: FINAL DELIVERABLES (MARCH–MAY)

RECONNECTING TO OUR DOWNTOWN

4. NEXT STEPS

• Selection of a Project Advisory Committee and stakeholders. These groups will have opportunities to participate and provide input throughout the planning process.

• Council engagement will be key to ensure alignment with funding and policy priorities.

• Public input and collaboration are crucial—we encourage all stakeholders to stay engaged and help shape the future of downtown Lexington.

Questions?