Update on work on the Parish Hall roof

People may have noticed changes to the front of the Hall. SSE, the electricity supplier, have unclipped the main cable feeding the Hall, and then wrapped the cable in sheathing in preparation for work on the roof. The sheathing is to protect workers on the roof and scaffolding from contact with the 3-phase power into the Hall.
As we go to print, this is the planned schedule for work on the new roof.
Tuesday 18 March: Site set up - fencing, scaffolding, tree protection.
Thursday 20 March: roofing materials delivered to compound (still to be confirmed), and roof works to start
Week of 24 March: roof works continued with the main roof expected to be covered by Saturday 29 March.
There may be some tidy-up work needed in the following week. While work is being completed, the Hall will not be available during the day but will be open for evening bookings. The Hall should be available for daytime bookings from Monday 7 April. The builder’s compound will take up a few of the parking spaces at the back of the Hall.