Estaleiro Jurong Aracruz (EJA)’s Official Newsletter, No. 4, Year I, Aracruz (ES), August - October 2013
Meeting between Jurong and Petrobras in Singapore Petrobras Director José Antônio Figueiredo and the National Petroleum Agency (ANP) General Director Magda Chambriard met with the Group SembCorp Marine CEO, Mr. Wong, President of Estaleiro Jurong Aracruz (EJA) Martin Cheah, HR Manager Lucila Lopes and HSE Manager Lani Tardin this past July in Singapore. The aim was to present the progress of the work on the contracteds Drillships and FPSOs. The EJA was contracted by Sete Brasil to build seven rigs based on the Jurong Espadon design and contracted by TUPI BV for the integration of the modules in two FPSOs. The first drillship, Arpoador, will be delivered June 2014.
Martin Cheah, Mr. Wong and Magda Chambriard
Entourage Petrobras and Jurong in Singapore
Estaleiro Jurong Aracruz site visit
Drillship Arpoador
EJA construction progress The construction phase of the breakwater, south quay and pier are currently underway at Estaleiro Jurong Aracruz. The manufacturing warehouses for sheet metal and pipe are being erected. The equipment of these warehouses will be delivered by the end of 2013. Further surveys, bathymetry and seismic studies are being done for the preparation of the dredging project. The next steps will be the construction of administrative building, canteen, clinic, entrance way and north quay.
Petrobras Group and EJA at site
On August 3rd, Petrobras Director José Antônio Figueiredo, Manager Marina Fachetti and Manager Altamiro Ferreira da Motta Filho visited the construction at EJA's site. They were welcomed by EJA President Martin Cheah, Vice President, Tay Wee Lye, and Institutional Director Luciana Sandri. After the safety briefing, the group walked through the construction site of the breakwater and south quay.
South Quay construction
Martin Cheah, Rodrigo Amaral, José Figueiredo and Altamiro da Motta
Breakwater construction