SCHOOL OF ARCHITECTURE, BUILDING & DESIGN Centre for Modern Architecture Studies in Southeast Asia (MASSA) Bachelor of Science (Honours) in Architecture
PROJECT PROPOSAL REPORT INTEGRATED PROJECT [ARC 60904]
JOCELYN JILL JOSEPH
Ar. Lim Wey Shan June, 2021
0332751
CONTENTS
Project Proposal Report
1.0 PROJECT INTRODUCTION
1.1 Clients & Stakeholders 1.2 Roles & responsibilities of Project Team 1.3 Curriculum Vitae 1.4 Organization Structure
2.0 PROJECT ANALYSIS 2.1 Site Introduction, 2.2 SWOT Analysis 2.3 PESTEL 2.4 Project Viability
3.0 PROJECT PHASES
3.1 Basic Services in Architectural Practice 3.2 Processes of Planning and Building Submissions & Project Tender 3.2.1 Schematic Design Stage 3.2.2 Development Stage 3.2.3 Contract Documentation 3.2.4 Project tender
4.0 PROJECT PROCUREMENT
4.1 Cost Estimation 4.2 Resource Planning 4.3 Risk Analysis and Mitigation Strategy 4.4 Maintenance Strategy
5.0 PROJECT DELIVERABLES
5.1 Success Criteria 5.2 Work Breakdown Structure 5.3 Gantt Chart
1.0 PROJECT INTRODUCTION INTRODUCTION TO PROJECT BRIEF This project is to design an ‘Urban Room’ in the heart of Kuala Lumpur, where it should demonstrate architectural interventions, which are drawn from the needs of the people, place, and is timely and relevant. This project should be highly engaging to appeal to the target user from all socioeconomic backgrounds, age, and ethnicity. Thus complementing and heightening the quality of the urban fabric through its architecture. Where the essence of the community can be strengthened with architecture that may blend in or be a driver to enhance the image of the place and its community. PROJECT OBJECTIVES • Providing public space to promote community development • Establishing an urban respite and recreational facilities within a fastpaced city centre • To provide a platform for economic growth and advancement of local skillsets. • To change the perception of different groups towards each other. • To abolish the social stigma of the immediate context and its users. • To provide opportunities for growth and learning to establish a more self-sufficient community.
PROJECT GOALS • To ensure the project can be delivered according to the project timeline within the budget and scope of works. • To incorporate green and sustainable design strategies to optimise building efficiency and lower future running costs. • Utilise available resources efficiently to prevent any unintended wastage. • To create a cultural landmark capable of boosting the socioeconomic standard of its immediate context and community. • To gain approval from relevant authorities to encourage a smooth operation throughout the building phases.
PROJECT CLIENT Yayasan Chow Kit (YCK) is a NGO platform aiming to help and empower at-risk youth and children in Kuala Lumpur, by providing a diverse range of aid, facilities and education to enhance the livelihood of the marginalised. They offer programmes for education, arts and counselling to give opportunities for the children, ensuring equal development and welfare for the children. Universal Music Malaysia(UMM), a division of Universal Music Group (UMG), the world leader in music-based entertainment. Client Vision : Collaboration of YCK and UMM as main client could provide a better space for children to grow up in the community with a range of children friendly programmes for both migrants and locals.
The Kuala Lumpur City Hall is the city board that regulates the city of Kuala Lumpur. It guarantees the advancement of the city which covers viewpoints identifying with open transportation and city beautification. They are also responsible to ensure the design, planning and execution of the building are in compliance with the UBBL by laws set by the government.
1.0 PROJECT INTRODUCTION 1.1 Clients and Stakeholders Stakeholders is anyone that will, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a project. Stakeholders are either directly involved in the project or have interests that may be affected by the project’s outcome. Internal Stakeholders Organizations that are directly involved in the project inclusive of the owners, managers and employees.
External Stakeholders Organizations that do not have direct involvement in the project but will be affected by its presence. Client
Client DBKL
YCK & UMM Indah Water Konsortium (I.W.K)
Architect (Project Manager) Quantity Surveyor
Regulatory Bodies
Civil and Structural Engineer
Consultant Team
Bomba Department of Occupational Safety and Health Kuala Lumpur
Mechanical and Electrical Engineer Landscape Architect Interior Designer
Tenaga Nasional Berhad (electricity) Service Provider
Land Surveyor
Telekom Malaysia (Telecommunication) Indah Water Konsortium (sewerage)
Town Planner Local Malaysians Main Contractor Construction Team
Sub Contractor Supplier
End User
Migrants White, blue and brown collar workers Visiting Tourists
1.0 PROJECT INTRODUCTION 1.2 Roles and Responsibility of Project Team 1.2.1 Architect Architects are appointed by the client as the lead consultant for the project, being in charge of design and project planning. They advice the client on appointing other consultants and construction professionals relevant to the project. Before the project is built, the architect will also prepare documents and relevant procurement drawings for planning applications. During construction, the architect will coordinate with the contractor to ensure client’s budget, design and quality requirements are met on time, ensuring the contract is fairly administered. Hence, the architect is involved in a project from beginning to the end, a critical role to ensure the client’s project is to be realized. ROLES AND RESPONSIBILITY 1. Design plan and develop 2. Assisting the client to prepare a strategic brief. 3. Carrying out feasibility studies and options appraisals. 4. Advising on the need to appoint other professionals to the consultant team, independent client advisers, specialist designers and specialist contractors. 5. Advising on the procurement route. 6. Contributing to the preparation of a project brief. 7. Preparing the concept and detailed design. 8. Preparing planning applications. 9. Preparing applications for statutory approvals. 10. Preparing production information. 11. Preparing tender documentation. 12. Contributing to the assessment of tenders. 13. Reviewing designs prepared by others. 14. Acting as contract administrator. 15. Inspecting the works. 16. Advising on the rectification of defects.
1. Types of Architecture Consultancy Services: Basic Services • Schematic Design Phase; • Design Development Phase; • Contract Documentation Phase; • Contract Implementation and Management Phase; • Final Completion Phase. 2. Supplementary Services (services not included in basic services, but supple ment it: • Ascertaining the client’s objectives, brief and constraints • Inspecting and advising client on site selection and suitability • Preparing and Refining the Brief • Preparing an Outline Project Plan • Preparing a Master Plan • Preparing the Drawings for Sale and Purchase (S&P) Agreements • Certifying and Issuing Certificates of Stage Completion for S&P Agreements • Providing Interior Design Services 3. Additional Services (services that may be provided under a separate appointment): • advisory services; • survey and investigation services; • planning and development services; • financial advisory services; • exceptional negotiations and protracted involvement services; • project management consultancy services; • miscellaneous services. (landscaping, illumination design, decor commissions, etc.
1.0 PROJECT INTRODUCTION 1.2 Roles and Responsibilty of Project Team
1.2.2 Quantity Surveyor Quantity Surveyor ensures timely delivery of the project with minimal effect on expenses as they manage the costs relating to building and engineering projects. From early design costs to final figures, quantity surveyors sought to minimize project costs to enhance value for money whilst ensuring that the project meets all legal and quality assurance requirements and regulations. They also act as an estimator, negotiator, project coordinator and an expense manager for this project. ROLES AND RESPONSIBILITY 1. Advising on the potential of a site and feasibility of initial design cost estimation. 2. Assisting in the valuation of claims 3. Preparing and evaluating costs of tenderers and contracts. 4. Arranging staff payments and settling final accounts 5. Reviewing construction plans and preparing quantity requirements. 6. Scrutinizing maintenance and material costs, as well as contracts to ensure the best deals. 7. Liaising with site managers, clients, contractors, and subcontractors. 8. Preparing reports, analyses, contracts, budgets, risk assessment, and other documents. 9. Advising managers and clients on improvements and new strategies. 10. Keeping track of materials and ordering more when required. 11. Documenting any changes in design and updating budgets.
1.2.3 Civil and Structural Engineer For this project, the appointed C&S engineer would be required to co-ordinate and consult with the architect. They are to advice on preliminary investigation and survey of proposed building sites to determine the ground conditions to assess foundation options, advising the architect’s design planning regarding technical problems and provide expert technical knowledge for the infrastructure and structural works of the project. ROLES AND RESPONSIBILITY 1. Undertaking technical and feasibility studies including site investigations 2. Using a range of computer software for developing detailed designs 3. Liaising with clients and a variety of professionals including architects and subcontractors 4. Compiling job specs and supervising tendering procedures 5. Resolving design and development problems 6. Managing budgets and project resources 7. Scheduling material and equipment purchases and deliveries 8. Making sure the project complies with legal requirements, especially health and safety 9. Assessing the sustainability and environmental impact of projects 10. Ensuring projects run smoothly and structures are completed within budget and on time.
1.0 PROJECT INTRODUCTION 1.2 Roles and Responsibility of Project Team
1.2.4 Interior Designer The appointed interior designers are responsible to design according to spatial requirements and allocating the most ideal decorations and spatial planning for each space. They specialize in the coordination of colors, lighting and materials within a space. ROLES AND RESPONSIBILITY 1. Develop schematics and floor plans clearly defining furniture and display placement. 2. Preparing specifications of materials and furnishings related to the interior works. 3. Advice clients and coordinate with the consulting team on appropriate design choices for relevant spaces. 4. Creating timeline for the commencement of interior works and project cost estimations. 5. Coordinating materials and overseeing installation of materials and furnishings.
1.2.5 Mechanical and Electrical Engineer Mechanical and Electrical engineers are in charge of designing service systems for the building to make it more efficient, functional and safe. The job scope of Mechanical and Electrical engineers includes designing systems of ventilation, air conditioning (HVAC) lifts, lighting, electrical supply, telecommunication systems and more. ROLES AND RESPONSIBILITY 1. Preparing detailing for building services design of building. 2. Interpreting design and drawings to propose ideal building service systems to client. 3. Preparing tender documents regarding mechanical and electrical works of the building. 4. Investigate equipment failures and difficulties to diagnose faulty operation, and to make recommendations to client and contractors. 5. Ensuring installation of building services on site are as per contract agreement. 6. Certifying of Form G of CCC for approval for completed mechanical and electrical works.
1.0 PROJECT INTRODUCTION 1.2 Roles and Responsibility of Project Teams
1.2.6 Landscape Architect Landscape architect is appointed for this project as a designer for the open spaces complimenting the built architecture. The landscape architect coordinates the arrangement of existing and proposed land features, They are in charge of designing the compound lighting, street furniture, landscaping and vegetation of the building ROLES AND RESPONSIBILITY 1. Analyzing site condition to determine potential of site for proposal to client. 2. Preparing cost estimation of softscape works. 3. Preparing specifications of vegetations involved in landscape design. 4. Conducting environmental impact assessments of project. 5. Coordinating with local authorities for approval of landscape works. 6. Certifying of Form G of CCC for approval for completed landscape works.
1.2.7 Town Planner The main contractor appointed for this project is binded under a traditional contract to construct the design completed by the consulting team with approval from the client. The contractors are required to communicate with the consultants and client to update and ensure the project construction is running smoothly. As the main contractor is only in charge of common construction works, sub contractors are employed for more specified tasks. ROLES AND RESPONSIBILITY 1. Proposing ideal construction pricing to client for competitive tendering. 2. Prepare an appropriate overall project construction timeline 3. Coordinating inputs of other consultants correctly and translating them to real life construction. 4. Coordinating construction works of subcontractors. 5. Overseeing overall building construction works and ensure that contract is properly administered to avoid conflicts. 6. Liaise with the architect when issues on site arises.
1.0 PROJECT INTRODUCTION 1.2 Roles and Responsibility of Project Teams
1.2.8 Land Surveyor Landscape architect is appointed for this project as a designer for the open spaces complimenting the built architecture. The landscape architect coordinates the arrangement of existing and proposed land features, They are in charge of designing the compound lighting, street furniture, landscaping and vegetation of the building ROLES AND RESPONSIBILITY 1. Analyzing site condition to determine potential of site for proposal to client. 2. Preparing cost estimation of softscape works. 3. Preparing specifications of vegetations involved in landscape design. 4. Conducting environmental impact assessments of project. 5. Coordinating with local authorities for approval of landscape works. 6. Certifying of Form G of CCC for approval for completed landscape works.
1.2.9 Contractor The main contractor appointed for this project is binded under a traditional contract to construct the design completed by the consulting team with approval from the client. The contractors are required to communicate with the consultants and client to update and ensure the project construction is running smoothly. As the main contractor is only in charge of common construction works, sub contractors are employed for more specified tasks. ROLES AND RESPONSIBILITY 1. Proposing ideal construction pricing to client for competitive tendering. 2. Prepare an appropriate overall project construction timeline 3. Coordinating inputs of other consultants correctly and translating them to real life construction. 4. Coordinating construction works of subcontractors. 5. Overseeing overall building construction works and ensure that contract is properly administered to avoid conflicts. 6. Liaise with the architect when issues on site arises.
1.0 PROJECT INTRODUCTION 1.3 Curriculum Vitae
CV JOCELYN JILL JOSEPH
+0109863275 jocelynjill99@gmail.com Date of Birth 12.08.1999
Lakeville Residence , Jalan Sibu, 52100 Kepong Kuala Lumpur
EDUCATION AND CERTIFICATES • 2018 - 2021
WORKING EXPERIENCE
Bachelor of Science (Honours) in Architecture Taylor’s University, Kuala Lumpur - 3.26 cgpa
• 2017 - 2018
Foundation in Natural and Built Environments Taylor’s University, Kuala Lumpur - 2.60 cgpa
• 2011 - 2016
Science and Art Stream St. Francis Convent (M), Kota Kinabalu - SPM 4A 4B 2C 1D
TECHNICAL SKILLS Sketchup Revit Autocad Illustrator Photoshop InDesign Microsoft Office (word,ppt) Other key skills : Orthographic drawings /Axonometric Drawings / Physical Models /3d Modelling/Diagrams
LANGUAGES
2020 - Freelance Designer Experience Interior Design’s Personal Assistant
Contact and cooperate with different departments, organize construction schedule and reponsible for furniture design
Designer
Have experiences in home renovation project, outdoor and indoor landscaping, furniture design, condominium, office, cafe decoration and graphic design for event’s print media.
ADDITIONAL SKILLS Detail Orientated
Malay
English
Motivated Team Player
INTEREST Plantings Arts Sports
Critical Thinking and Problem Solving Ability To Take Initiative Optimistic and Motivated
1.0 PROJECT INTRODUCTION 1.4 Organization Structure Client YCK & UMM
Architect Project Manager S&G Architect Sdn Bhd TCF Project Consultancy
Main Contractor
Domestic Sub Contractor
Nominated Sub Contractor
Domestic Suppliers
Nominated Suppliers Construction Team
Quantity Surveyor [O’Brien Sdn Bhd]
C&S Engineer [NAL C&S Engineering Consultants Sdn Bhd]
M&E Engineer
Landscape Architect
[ACT Engineering Consultants Sdn Bhd]
[RKLA Studio Consultants]
Land Surveyor
Interior Designer
[LJT Consultants Sdn Bhd]
[Cobalt & Copper Design Sdn Bhd] Town Planner
[PEQ Consultants Sdn Bhd] Consultant Team
2.0 PROJECT ANALYSIS 2.1 Site Introduction As an active hotspot for migrants,tourists and night life shows a poor living environment for growing children either locals or migrants.
Surrounding context promotes an existing culture of segregated communities
The site needs a stimulant or a change in the existing system of community by cultivating a meaningful social culture and conversations.
Promote a rich Sociocultural community through musical programs for the children. To exchange culture in a productive way. Site B is located on a land used as a parking spot in the heart of Kuala Lumpur in the midst of famous tourists spot, such as Jalan Alor, Jalan Bukit Bintang and Jalan Pudu.
2.0 PROJECT ANALYSIS 2.2 SWOT Analysis STRENGTH •
High walkability and visual permeability due to strategic location
•
Famous landmark such as food hub in Jalan Alor makes a distint site and recognisable.
•
Public transportation within 5mins walking radius
WEAKNESS
OPPORTUNITIES
•
Parallel living of local and migrants
•
Existing small social community
•
Site close to residential area (project can be difficult to promote due to residents worried about noise)
•
Site close to residential building potential for family friendly programmes
•
Well known and easy to bring in potential users.
•
Lack of green public space and children spaces
THREAT •
Poor environmental security at night due to the high rate of homeless people and drug addicts around the site.
•
Programme may be rejected when it comes to infusing local and migrants together
•
Community has a level of xenophobia towards migrants
2.3 PESTEL POLITICS
The site is located adjacent to well known Jalan Pudu and Jalan Bukit Bintang, also nearby a cultural food hub street with is Jalan Alor. As it is located in the capital of Malaysia, Kuala Lumpur, it is surrounded by the governemt bodies such as Kuala Lumpur City Hall, DBKL.
The site is surrounded by varios vribrant and rich arts, cultural and heritage building. Therefore, the main site economical gain is generated by the local businesses, migrants businesses and target tourists.
SOCIAL
ECONOMICAL
Majority of users in the surrounding context are from the locals and migrants as the permanent user group. During the weekdays, the lacking of availability of amenities and unsafe environmental quality, the site are very usual with busttling traffic during traffic hours without high social quality. While the nightlife during the weekends tends to concentrate at a nearby street called Jalan Changkat.
DBKL developed an urban design strategy that street defined architecture where the building proposed must be adjacent to the surrounding neighbourhood.Green technology such as rainwater harvesting system to be abide as part of Green Building Index. New and modern TECHNOLOGY construction seem to be on a rise around that area, this development will contribute to that change and adapt to the modern technologies in construction. Green Building Index (GBI) isn’t quite applied around the site’s context. Therefore, there is an aim to reduce the amount of artificial lighting and ventilation system used, replacing with a passive system. Not only that, vibrants connection to the site promotes friendly walking experiENVIRONMENTAL ence and reduce transportation in the site. The new construction of the city lobby will abide to by-laws according to the regulations of the Uniform Building By-Laws 1984 (UBBL 1984). It’s design, safety, construction method and other criterias of the building will abide all the requirements as stated. The legal requirement also set by other relevant authorities such as Dewan Bandaraya Kuala Lumpur.
LEGAL
2.0 PROJECT ANALYSIS 2.4 Project Viability Floor Basement
Ground Floor
1st Floor
Space Security Room Parking Storage Services Kitchen Cafe Sepak Takraw Court Storage Stage Changing Room Offices Services Music Gallery Retail Store Offices Sound System Room Broadcasting Studio Writer’s Room Green Room Lounge Services
Area Floor Area (m2) Gross Floor (m2) 32 579 15 122 748 76 169 324 75 70 60 43 138 955 145 51 50 32 58 19 19 55 76 506
Floor
2nd Floor
3rd Floor
Space Floor Area (m2) 92 Studio Rehearsal Faculty Studio 108 Storage 34 Reading Space 51 Study Room 118 Living Quaters 160 Services 76 Meeting Room 126 Recital Hall 175 Orchestra Auditorium 700 Services 86 Total Gross Floor Area Landscape :
639
1087 3935
We start to develop a general plan and basic exterior design and how the building operates through sketches and consultions with clients. As sketch is refined, preliminary estimation for cost of construction based on current area, volume and shared with clients. We prepare and submit drawings and necessary documents to the relevant authorities as required under any relevant laws.
Documents like sketches, models and emails are compiled for the main contractor of the project. With the team of engineers,finalize on the technical aspects and engineering, after obtaining the necessary approvals from client. This includes the structural detailing and engineering. Client prepares to select the contractor for the project and we will invite tenders to work or collaborate with other consultants engaged by client. The results of the tenders are then evaluated by the design team and a report as well as recommendation will be submitted to client. Contract given to the chosen contractor and begin preparing the building contract documents, either alone or with other consultants appointed.
PHASE 4 - Contract Implementation & Management
The architect refers to the building programmes to develop schematic drawings
PHASE 2 - Design Development
3.0 PROJECT PHASES 3.1 Basic Services in Architectural Practice After satisfied that the building is fit and safe for occupancy, we will issue a certificate of completion and compliance to the main contractor, that satisfies built drawings and submitting maintenance manuals together with all warranties to client. After being satisfied that all defects to the building have been rectified, we will issue a certificate of making good defects. Finally, we will prepare the final accounts for the contract and issue a final certificate of payment to the contractor.
We consult client to select the appropriate materials, including the interior finishes, windows, doors and fixtures. We will revise the drawings with more details to allow other consultants to commence their respective detailed design work. For exp, the engineers will begin on the structure, plumbing, electrical, heating and ventilation systems if necessary. We together with client finalizes the interior and exterior design, the design development phase ends.
After the CD, we will then supervise the construction works to ensure the construction is done in compliance to the CD. The submittals and drawings from contractor and product manufacturers are reviewed, as well as the application for payment from the main contractor. Questions from the main contractor are also resolved by us as the architects, as there are always unforeseen circumstances that happens in the construction project.
PHASE 5 - Final Completion
We begin to develop the technical aspect of the design, especially those that will effect the architectural design of the project
PHASE 3 - Contract Documentation
PHASE 1 - Schematic Design
Technical aspects of the design asre developed, especially that will affect the architectural design of the project
3.0 PROJECT PHASES 3.2 Process of Planning and Building Submissions and Project Tender 3.2.1 Schematic Design Stage During this stage :-
1. Discuss with clients & stakeholders to determine the project’s development objectives and requirements. 2. Prepare a preliminary design proposal to interpret and/or formulate the project’s brief/terms of reference based on information from the Client. 3. Lead the coordination with consultant Mechanical & Electrical and Civil & Structural Engineers, Quantity Surveyors, and associated professionals such as Property Consultants, Land Surveyors and Town Planners, to ensure the preliminary design proposal meet the Client’s requirements. 4. Upon the Client’s approval of the preliminary design proposal and instruction, to prepare and submit schematic design drawings to the local authority for planning approval [Kebenaran Merancang or equivalent] based on the specific Local Authorities requirements. 5. If any kind of appeal is required for the planning approval, then to check with the Local Authorities on the possibilities of the appeal to be approved before submission. Pre-council or pre-submission checks with the Local Authorities will be done prior to the formal submission.
In Malaysia, any building / settlement that one intent to build must firstly obtain the approval of Development Order (Kebenaran Merancang). In order to get this Development Order sort out, developer or client must get their consultant team on board: 1. Architect – To furnish client with all necessary drawings and will act as the Superintendent Officer (S.O). 2. Town Planner –
3. C&S Consultant -
To advise regarding the local planning rules & regula tions and will submit the complete set of D.O. submission to OSC on behalf of client / developer. Advise client regarding the necessary civil & structural requirement and also to provide the necessary draings.
4. M&E Consultant - To advise client regarding the necessary mechanical & electrical requirement and also to provide the necessary drawings. 5. Quantity Surveyor - To advise regarding the preliminary cost / feasibility of the project and later stage for tender and claim verification. 6. Land Surveyor To sort out the land matters.
Development Order Development Order is the confirmed planning of the development. Whatever is approved during the D.O. stage must be followed later on. The developer / client must settle off the land matters / preliminary design and as well as firm on the type of development as well as the build up area, number of units and number of parking provided. All these must be coordinated by the consultant team and also from the developer side. Weekly / fortnightly Client- Consultant Meeting (CCM) may be required in order to coordinate on this submission and this process may takes up about 6 month to 2 years before D.O. is finally approved. D.O submission can be made to the local authority department which is called One Stop Centre, OSC. OSC will act as a coordinator for the local authority internal department and also toward the external approval agencies like SYABAS, TNB and IWK. Submission Requirements Subseksyen 22 (2) of Act 172* has explained the things that should be considered by the local planning authority before considering or making a decision on an application for planning permission. Among them include: 1. Provisions - provisions of the development plan which has been gazetted or in preparation. 2. Instructions - the instructions given by the State Planning Committee (if any). 3. Provisions - Sewerage Services Act 1993. 4. Proposed Development Report. 5. Objections made Neighbouring landowners under Section 21. 6. Applications should consult the National Physical Planning Council (NPPC) 7. Commentaries of the technical departments concerned.
3.0 PROJECT PHASES 3.2 Process of Planning and Building Submissions and Project Tender 3.2..2 Design Development Stage During this stage :-
1. Upon issuance of the planning approval [Kebenaran Merancang or equivalent] by the local authority, to review the requirements set in the planning approval, 2. Lead the coordination with consultant Mechanical & Electrical and Civil & Structural Engineers and associated professionals such as Land Surveyors and Town Planners, in order to coply with the requirements set in the planning approval 3. Review the current/coordinated and authorities’ compliant design against the Client’s project brief/terms of reference including cost and time implications 4. Upon instruction from the Client, to prepare and submit working drawings to various authorities for building plans approval [based on the specific Local Authorities requirements and, pre-council or pre-submission checks with the Local Authorities will be done prior to the formal submission] 5. Assist in the liaisons with the relevant authorities to pursue the approval of the various building plans submissions.
Building Plan Submission
Process Flow Chart of Building Plan Approval Council Endorsement Approval Approved Rejected
Objection/ Comments
Endorsement by Building Approval Committee
Local Authority reviews application and distributes to relevant departments for comments
Reapply
Submit Building and Infrastructure Plans to Local Authority
1. Dept of Irrigation and Drainage 2. Dept of Environment 3. Tenaga Nasional Berhad (TNB) 4. Public Works Dept 5. Telekom 6. Water Supply Dept 7. Fire Dept 8. Sewerage Service Dept 9. Alam Flora (if required)
Building Plan Submission will usually be made on new-build projects with full building details and structural calculations of proposed building work to be submitted for approval before construction works begin.
While applying for Building Plạn, Development Order (DO) is always required. All departments of respective local authorities and external departments are involved. Approval for concurrent application will take a maximum of 6 months for all the
processes to be completed.
The implementation of OSC (One Stop Centre) has accelerated the whole application process. The application for approval of Building Plan Submission is generally accompanied by fees calculated according to the First Schedule of the Uniform Building
By-Laws 1984 Section 3 (1)(a), 12 (1), 19 (2), 26 and 29*. The fees mainly depend on floor area and type of premises constructed.
Fees for consideration of plans No. submitted for approval in respect of 1. new buildings shall be computed as 2. followed:
Floor Ground Floor
7.00/9m2
minimum (RM) 70
First Floor
6.00/9m2
60
3.
Second Floor
5.00/9m2
50
4.
Third Floor
4.00/9m2
40
3.00/9m2
30
5. Fourth Floor and above or Baement Level
Unit Rate (RM)
3.0 PROJECT PHASES 3.2 Process of Planning and Building Submissions and Project Tender 3.2.2 Design Development Stage
Building Plan Approval Submission Requirements The submission requirements usually depend on the local departments. Different departments of the local authority in different district areas have different checklists for Building Plan Submission. Generally, the submission requires plan fee proof payment, fee calculation sheets with working calculations details as well as building plans endorsed by Architect/ Engineer including key plan, site plan, floor plan, roof plan and elevation plan (front, rear, and side). Submittal requirements for land subdivision shall be resubmitted for Building Plan Approval, plus additional details sufficient for construction to be carried out such as follows: 1. Layout plans must be accompanied with setting out details showing precise location of the complete stormwater management system proposed. 2. Drawings of conveyance facilities shall show the longitudinal sections and cross-sections with indication of peak discharge water levels for the designated return periods. 3. Detention/retention and water quality control facilities shall be detailed out in plans and cross-sections. Additional details shall be included to show inlet/ outlet systems and other pertinent components. 4. Detailed calculations shall be submitted to show peak discharge and pollution reduction are under control. For infiltration control, soil investigation borelogs (showing ground water tables) shall be submitted together with laboratory soil permeability test results. 5. Design calculations and drawings shall generally follow the format as established in the SWM Manual. 6. Erosion and sedimentation control plan shall also be submitted.
3.2.3 Contract Documentation During this stage :1. Upon instruction from the Client, to prepare working details and construction drawings for the architectural works 2. Finalise detailed coordination with consultant Mechanical & Electrical and Civil & Structural Engineers in order to comply with the requirements and conditions set by the authorities in the Building Plans approval against the Client’s project brief/terms of reference, 3. Review the Tender Document prepared by the Quantity Surveyor to ensure completeness and conformity with the Architectural design and the Client’s project brief/terms of reference, 4. Review Project Cost and Schedule prior to the Calling of Tender against the Clients’ requirements 5. Coordinate the preparation of documentation for constructional purposes by all consultants. 6. Finalizing detailed design to enable preparation of bill of quantities (B/Q).
3.0 PROJECT PHASES 3.2 Process of Planning and Building Submissions and Project Tender 3.2.3 Contract Documentation
Bill of Quantities BQ is a document prepared by the cost consultant (often a quantity surveyor) that provides project specific measured quantities of the items of work identified by the drawings and specifications in the tender documentation. The quantities may be measured in number, length, area, volume, weight or time. Preparing a bill of quantities requires that the design is complete and a specification has been prepared.
The bill of quantities is issued to tenderers for them to prepare a price for carrying out the works. The bill of quantities assists tenderers in the calculation of construction costs for their tender, and, as it means all tendering contractors will be pricing the same quantities (rather than taking off quantities from the drawings and specifications themselves), it also provides a fair and accurate system for tendering. The contractor tenders against the bill of quantities, stating their price for each item. This priced bill of quantities constitutes the tenderer’s offer. As the offer is built up of prescribed items, it is possible to compare both the overall price and individual items directly with other tenderers’ offers, allowing a detailed assessment of which aspects of a tender may offer good or poor value. This information can assist with tender negotiations.
B/Qs is not necessarily useful for every type of project or procurement system and this is the main issue contributing to the declining usage of B/Qs in the construction industry in Malaysia. This scenario is because of the processes of design, documentation and construction tend to run almost parallel to one another and the tendering process is much shortened. The adaptability of B/Qs depends on the types of procurement system in traditional procurement and non-traditional procurement system where both processes involved are different. For non-traditional procurement system, the contractors still have to prepare a document comprised of the concept design or schematic design and a proper cost document for bidding purposes and this document can be as detailed as to become a “concise B/Qs” but there is no specific term used for such document.In traditional procurement system, the design and the construction are carried out by separate organizations. Some basic characteristics of traditional procurement system are as follows: 1. Project delivery is a sequential process. 2. The design of the project is largely completed before work commences on site. 3. The responsibility for managing the project is divided between the client’s consultants and the contractors, and there is therefore little scope for involvement of either of the parties in the other’s activities. 4. Reimbursement of the client’s consultants is normally on a fee and expenses basis, whereas the contractor is paid for the work completed on admeasure or lump sum basis.
SIDE NOTE: B/Qs is not necessarily useful for every type of project or procurement system and this is the main issue contributing to the declining usage of B/Qs in the construction industry in Malaysia. This scenario is because of the processes of design, documentation and construction tend to run almost parallel to one another and the tendering process is much shortened. Therefore, the adaptability of B/Qs depends on the types of procurement system in traditional procurement and non-traditional procurement system where both processes involved are different. In traditional procurement system, the design and the construction are carried out by separate organizations.
3.0 PROJECT PHASES 3.2 Process of Planning and Building Submissions and Project Tender 3.2.4 Project Tender
There are many different types of tenders that can be used in different given situations. There are open tenders, selective tenders and negotiated tenders. Selective tendering is chosen for this project. Selective tendering will tend to be faster than open tendering, and can be seen as less wasteful, as there is no pre-qualification process as part of the tender procedure itself, and only suppliers that are known to be appropriate for the proposed contract are invited to prepare tenders. It can also give clients greater confidence that their requirements will be satisfied. Single Stage Tendering Tenderers are shortlisted by the client & the consul tant, and the bids will be obtained from the selected tenderers only. The adequate number of bidders maybe eight.
Selective Tendering
Selective (Competitive) Tendering Process Selective tendering only allows suppliers to submit tenders by invitation. A pre-selected list of possible suppliers is prepared that are known by their track record to be suitable for a contract of the size, nature and complexity required. They might then be asked if they would be interested in tendering for the contract, and then based on the responses received, a number of them invited to tender (generally no more than 6). From the tenders received, a preferred tenderer is selected based on criteria such as price and quality and negotiations entered into.
Consultants or experienced clients may maintain ‘approved’ lists of prospective suppliers appropriate for particular types of contract and then regularly review performance to assess whether they should remain on the list.
Two-Stage Tendering In the first stage, suitable contractors will be selected by evaluating their pre-qualification parameters (Past Experience, Strength of Resources, Financial Capabilities, etc..). In the second stage, negations will be carried out with the selected contractors and finalize the contractor, who is getting the award of the contract.
TENDER DOCUMENTS INCLUDE: 1. A letter of invitation to tender. 2. The form of tender. 3. Preliminaries: including pre-construction information and site waste management plan (if required). 4. The form of contract, contract conditions and amendments. This might include a model enabling amendment for building information modelling (BIM), making a BIM protocol a contractual document. 5. A tender pricing document (or contract sum analysis on design and build projects). 6. Employer’s information requirements for BIM. 7. Design drawings, and perhaps an existing building information model. 8. Specifications. 9. Tender return slip
4.0 PROJECT PROCUREMENT 4.1 Cost Estimation CONTRACT PROCUREMENT ( Traditional Procurement Method ) The method of procurement selected for this project is traditional procurement. The traditional procurement route involves separating the design process from the construction process. The main contractor will carry the works and prepare the tender documents. PAM Contract 2006 clearly states the project manager handles the most responsibility with the contractor following orders from the architect, therefore a separation between constyruction team and the design team and majority of the responsibility is transferred to the contractor. LUMP SUM CONTRACT
Usually, the bill of payments are in a lump sum and the contractor can submit an adjustment of the contract sun if there is fluctuations or other circumstances. A lump sum contract is a contract with a single lump sum price for all of the works and the contractor is responsible for completing the project within the agreed fixed cost set forth in the contract.
BUILDING COST (Excluding Carpark): Total construction cost = Total floor area x Estimated pricing, assuming : RM150 = 1sq.ft , 1 sqm = 10.764 sq.ft 3187 sqm x 10.764 = 34,304.87 sq.ft. 34,304.87 sq.ft. x RM150 = RM 5,145,730.50 Basement Parking Cost Basement area = Area of the building footing, assuming: RM200 = 1sq.ft. 1 sqm = 10.764 sq.ft Basement area = 748 sqm 748 sqm x 10.764 sq.ft = 8051.50 sq.ft 80151.50 sq.ft x RM200 = RM 1,603,030 Total building cost = RM 6,748,760.50 ADDITIONAL COST:
Client Design Consultant Team
Main Contractor
Architects (Project Lead)
Domestic SubContractor
Quantity Surveyor
Domestic Suppliers
Engineers
Nominated SubContractor
Landscape Architect
Nominated Suppliers
Engineers Landscape Architect Land Surveyor
Landscape area = Total Area of site - Total Building Footing area Assuming that RM200 = 1sq.ft. 1sq, = 10.764 qft Total area of site = 8092 sqm 8092 sqm- 748 sqm = 7344 sqm 7344 sqm x 10.764 sq.ft = 79,050.82 sq.ft 79,050.82 sq.ft x RM200 = RM 15,810,164 DIRECT EXPENSES COSTS: According to ARCHITECTS (SCALE OF MINIMUM FEES) RULES 2010 ARRANGEMENT OF RULES, this building is under the category of RM 8,000,001 - RM 16,000,000. Thus the minimum percentage of consultation fee is 4%. Consultation Fees (4% of building cost) = RM 358,800 Contingencies (10% Building Cost) = RM 897,000 Total Direct Expenses Cost = RM 1,255,800 GRAND TOTAL ESTIMATED COST
= RM 6,748,760.50 (Total Building Cost) + RM 15,810,164 (Landscape) + RM 1,255,800 (Total Direct Expenses Cost) = RM 23,814,724.50 (Not included construction and labour fees)
4.2 Resource Planning TASK
QUANTITY KEY PERSONNEL SCHEMATIC DESIGN PHASE
REQUIRED SKILLS
Site Visit & Survey
Client & Consultant Team
-
Tools & Equipment usage
Design Brief Formulation
Client & Consultant Team
-
-
Preliminary Design Proposal
Architect
1
AutoCAD
Feasibility Studies
Architect
1
Microsoft Excel
Initial Cost Estimation
Architect & Quantity Surveyor
1,1
Microsoft Excel
1,2
AutoCAD & Revit
DESIGN DEVELOPMENT PHASE Detailed Architectural Drawings
Architect & Draftsman
Detailed Structural Plan
Structural Engineer
2
AutoCAD & Revit
Detailed M&E Drawings
M&E Engineer
2
Solidworks
Final Cost Estimation
Architect & Quantity Surveyor
Submission to Local Authority
Architect
1,1
Microsoft Excel
1
AutoCAD & Revit
CONTRACT DOCUMENTATION PHASE Bill of Quantities Preparation
Quantity Surveyor
1
Microsoft Excel, WinQS
Open Tender Period
Architect
1
-
Tender Evaluation
Client & Consultant Team & Contractor
-
Minimum 5 years experience
Awarding of Contract
Architect & Contractor
1,1
Minimum 5 years experience
CONTRACT IMPLEMENTATION PHASE Site Planning & Management
Client & Consultant Team & Contractor
1
-
Project Administration
Architect
1,1
Microsoft Excel, Word
Monitor on-site Work & Construction
Architect & Engineer
1,1
-
Inspection & Testing
Client & Consultant Team & Contractor
1,1,1
-
Consultant Meeting
Consultant Team
3
-
PROJECT COMPLETION PHASE Final Site Inspection
Client & Consultant Team & Contractor
1,2
Microsoft Excel, WinQS
Building Handover
Client & Architect
2
-
Issuance of CPC & CCC
Client & Architect
2
Microsoft Word
Final Accounts
Client & Architect & QS
1,1
Microsoft Excel
4.3 Risk Analysis and Mitigation Strategy Risk
Likelihood
Severity
Effects
Mitigation Strategy
Contingency Plan
PRE- CONSTRUCTION STAGE [Schematic Design]
Design Proposal not meeting client’s satisfaction
1/5
3/5
Project to be delayed until complied Conduct frequent meetings with to client’s satisfaction client to understand their requirement and standards
Indecisive client who keeps changing design scheme
3/5
3/5
Slowing down the project workflow Set a specific time frame to finalise Project manager needs to make the design scheme sure client is aware and ontrack of the project schedule.
Misinterpretation of project goals and objectives among design team.
3/5
2/5
Over Budget after calculating cost according to updated working drawings from all consultants.
3/5
4/5
Deliverables by each member is not up to expectations and does not meet client’s requirement. This causes futher delay in the project
Modify and prepare a few scheme related to the client’s expectation.
A meeting including all member’s of Regular meeting should be conthe project [consultant & construc- ducted [weekly] to keep tabs on tion] to be held to bried and realign everyone’s progress and realign the project goals and objectives. the team’s expected outcomes.
The material and structural The client might reject or not be able Discuss and justify the updated costs concept of the design should be to financially support the project with the client. taken into account for cost.
PRE- CONSTRUCTION STAGE [Design Development]
Building Plan[BP] not approved by local authorities
3/5
3/5
The project will be delayed as delayed until amended BP drawings are approved by local authorities
Resend the amended BP for approval BP should be checked thorfrom local authority oughly through a few stages before submitting for approval
Consultants unabled to meet deadlines
3/5
5/5
Work flow is delayed and project is Plan schedule ahead and keep track Make sure consultants hired are based on proper experience to pushed forward until futher notice of procedures. avoid delays.
Material proposed are against budget
1/5
3/5
Project manager to always keep track Use prelimanary budget as a Recalculations has to be done, waste on budget usage with Architect and guide to not exceed amount. of time and resources. other consultants.
4.3 Risk Analysis and Mitigation Strategy Risk
Likelihood
Severity
Effects
Mitigation Strategy
Contingency Plan
PRE- CONSTRUCTION STAGE [Contract Documentation]
Delay of drawing approvals from local authorities
3/5
5/5
Installation of ground works and temporary works are delayed
Submit drawings earlier in case of any disapproval
Proceed with any approved process of simultaneous tasks according to Gantt Chart
CONSTRUCTION STAGE [Construction Management & Implementation]
Delay of drawing approvals from local authorities
3/5
5/5
Installation of ground works and temporary works are delayed Might exhaust resources and overwork labours. Heavy downpour and varying moisture levels wil affect curing of concrete.
Work delayed due to weather conditions
5/5
3/5
Major injury or accidents during construction
3/5
3/5
Budget reduced by client
3/5
3/5
Lawsuits and investigation would delay or stop project from continuing.
Submit drawings earlier in case of any disapproval A temporary storage should be built to protect materials from weather. The project manager should manage his labourers wisely. Conduct health and safety check guidelines with workers and certify beforehand
4/5
5/5
Failure to achieve the quality required and/ or functional requirements of the build
5/5
3/5
High maintenance cost
1/5
5/5
Temporary works should be carefully planned to prepare for unforeseen circumstances. Hire safety officers to ensure that all guideline are being followed on site.
Severity of changes vary on amount Consultants to procide variations of To have meeting with client to of budget cut specifications for client to choose. discuss implications of budget cuts POST- CONSTRUCTION STAGE [Final Completion]
Liquidated and ascertained damages are insufficient to cover costs if project delays.
Proceed with any approved process of simultaneous tasks according to Gantt Chart
Cost overrun will not be able to be covered by client, final accounts will be frozen, building may be abandoned. Client dissatisfied with quality of work, revenue of building compromised. High cost incurred on client in the long run
Ensure sufficient float in project timeline to avoid project delays. Use management techniques to properly coordinate the construction team to hit allocated goals and targets. Employ self-sustaining systems.
Transfer risks and liabilities to other parties or insurance to absorb liquidated damage Negotiate with client for specifications of lower cost or for longer project duration to accomplish design brief. Carry out meetings with consultants to look for solutions to minimising costs.
4.0 PROJECT PROCUREMENT 4.4 Maintenance Strategy PROGRAMME MAINTENANCE ELEMENT
FREQUENCY
Open Public Space
Daily
Cafe and Kitchen
Daily
Toilets and General Cleanliness
Daily
Storage Space
Monthly
STRATEGY
• • • • •
Ensure plants kept in good condition Trimming to prevent overgrowth and keeping cleanliness of water feature for user comfort Ensure the cleanliness of the eating area for hygiene purpose Ensuring food preparation are up to standard All spaces to be cleaned daily to ensure the cleanliness of the space and comdort of users
• Additional equipment should be cleaned and the quantities should be checked from time to time
SERVICE & MECHANICAL
Lifts
Annually
Sanitary & Piping (Water Supply)
Annually
Lighting Fixtures
Quaterly
Rainwater & Drainage System
Annually
Electrical Appliances
Annually
• Inspection to be carried out by specialist to ensure smooth and safe operating condition • Ensure the waste oil from the kitchen are disposed properly and drainage system is not clogged • Ensuring that the water supply has no leaks to avoid wastage • To endure all the light fixtures are working well and replace bulbs when necessary • To ensure theres no blockage in the drainage and downpipes so that the excess water from the rain can be fully dischard • Ensure electrical wirings are in good condition, inspections to be carried out by technicians yearly •
ARCHITECTURAL & BUILDING MAINTENANCE
• Gypsum partition which exposed to weather conditions should be inspected moisture damage
Interior Partition Walls
Annually
Glass Windows
Weekly
Facade
Monthly
• Movable facade should be serviced and lubricated
Floors & Ceiling
Monthly
• Regular inspection to ensure safe and good condition. To be repaired when necessary
• Cleaning job carry out regularly to ensure cleanliness and good indoor environment
5.0 PROJECT DELIVERABLES 5.1 Project Success Criteria Every project own by the government by Success Criteria. The 3 fundamental constraints of any project are Time, Cost and Scope. These parameters determine the outcome & degree of success of the project. This particular project places an emphasis on cost and scope (quality). The project is expected to achieve a high standard of deliverables within the span of time. Time The sequence from start to finish of a project is governed by the use of a structured gantt chart. The project will aim to achieve all construction stages and critical paths in order to ensure works progress effectively and consistently. This is to ensure no delays occur throughout the duration of the project.
Assessment Scope 1. Final cost does not exceed initial/ proposed budget. 2. Contingency fees used not to exceed allocated amount. 3. Project quality up to standard with minimal wastage on construction materials.
TIME / SCHEDULE Scope The requirements of the project should be adhered to. This entails that the materials, features and details of the building should be of a high standard to meet the demands of the client. The Work Breakdown Structure is utilized to keep track of the project structure.
Assessment Scope 1. Little to no compromisation of scope. 2. Project is completed to the client’s expected quality. 3. Limited scope creep 4. Meets the ISO criteria
Quality
SCOPE
BUDGET/ COST
Quality = Clieit is satisfied with the project delivered.
Cost For a building of this size and scope of requirements, an estimated RM 13,920,736 is needed to carry out all works. The total cost of this project comprises of the planning phase, construction phase and up to the completion phase. The cost is crucial in ensuring that the requirements are fulfilled whilst adhering to the given budget. The contingency fee has a big part in upholding this. Assessment Scope 1. Final cost does not exceed initial/ proposed budget. 2. Contingency fees used not to exceed allocated amount. 3. Project quality up to standard with minimal wastage on construction materials.
5.0 PROJECT DELIVERABLES 5.2 Work Breakdown Structure (WBS) URBAN ROOM 2.0 Construction Stage
1.0 Pre-Construction Stage 1.1 Preliminaries
1.1.1 Client Briefing 1.1.2 Design Requirements 1.1.3 Site Investigation 1.1.4 Soil Investigation 1.1.5 Feasibility Studies
1.2 Schematic Design
1.2.1 Conceptual Sketches 1.2.2 Spaces Planning 1.2.3 M&E & Landscape Planning 1.2.4 Material Submission 1.2.5 Cost Estimation 1.2.6 Visualisation
1.3 Design Development
1.3.1 Detailed Design Drawings 1.3.2 Detailed Landscape Design 1.3.3 Authority Submission 1.3.4 Revise Cost Estimation
1.4 Contract Documentation 1.4.1 Tender Documentation 1.4.2 Tender Review & Award 1.4.3 Project Planning & Schedule 1.4.4 Stakeholder Notification
2.1 Preliminary
2.1.1 Mobilisation & Site Enstablishment 2.1.2 Dilapiation Survey 2.1.3 Setting out 2.1.4 Hoarding & Signboard 2.1.5 Site Cleaning & Levelling
2.2 Foundation
2.2.1 Soil Excation 2.2.2 Piling Foundation 2.2.3 In-situ R.C Footing 2.2.4 Basement Slab& Wall
2.3 Superstructure
2.3.1 R.C Slab, Ramp & Landing 2.3.2 R.C Beam, Column & Flooring 2.3.3 Internal & External Wall 2.3.4 Roof System 2.3.5 Lift & Fire Staircase
2.4 Roofing
2.4.1 Steel Framework 2.4.2 Butterfly Roof System 2.4.3 Gutter & Drainage System
2.5 Facade
2.5.1 Glass Curtain Wall 2.5.2 Sliding Lourve System
2.6 Doors & Windows
2.6.1 Door Frame & Panel 2.6.2 Window Frame & Panel
2.7 M&E Services
2.7.1 Lift System 2.7.2 Air-Conditioning System 2.7.3 Earthing System 2.7.4 Conduit & Submain Wing 2.7.5 Fusebox Installation 2.7.6 Telephone & Data System 2.7.7 Light Fittings 2.7.8 Plumbing & Sanitary 2.7.9 Fire Protection System 2.7.10 ICT & Security System
2.8 External & Landscape 2.8.1 Surface Water Drainage 2.8.2 External M&E Work 2.8.3 Installation of Softscape & Hardscape 2.8.4 Turfing 2.8.5 Outdoor Lighting
2.9 Architectural Finishes 2.9.1 Tiling Works 2.9.2 Wall Finishes 2.9.3 Ceiling Finishes 2.9.4 Floor Finishes 2.9.5 Staircase & Handrail Finishing
3.0 Post Construction Stage 3.1 Handling Over
3.1.1 Final Clearing & Testing 3.1.2 Inspection 3.1.3 Issuance Certificate of Completion & Compliance (CCC) 3.1.4 Preparations of Final Accounts of Contract
5.0 PROJECT DELIVERABLES 5.3 Gantt Chart