IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule with respect to Co

Page 1

International Research Journal of Engineering and Technology (IRJET)

e-ISSN: 2395-0056

Volume: 06 Issue: 02 | Feb 2019

p-ISSN: 2395-0072

www.irjet.net

Comparative Study of Top down & Bottom up Method Construction Schedule with Respect to Construction of a Residential Building Rafi Sakharkar1 1P.G

Student & Construction Engineer, Department of Civil Engineering Shivajirao S. Jondhle College of Engineering & Technology & Catapult Realty Consultants, Mumbai (India) ---------------------------------------------------------------------***---------------------------------------------------------------------

Abstract - The rapid increase in the construction sector

of project affected peoples etc. Though some of the associated problems faced in the developments cannot be resolved through the use of advanced technology there is a wide scope in technological advancements that can be adopted to counter the time over runs caused by the stated factors.

all around the globe has led to significant changes in the methodologies and techniques being adopted to cater to the modern requirements of the projects that are being executed. This has led to make the best use of land available and a substantial increment is seen with respect to utilization of underground structures for metros, high-speed railway corridors as well as residential and commercial structures. The general perspective regarding the construction activities are changed and a detailed planning, designing and monitoring approach has led to further advancements in methods that are being incorporated to complete the projects in effective, economic and efficient manner. “Top down Construction Method” is recent trend that is being adopted for infrastructural projects and its applicability for housing projects is being reviewed in this paper with reference to a building being constructed by traditional bottom up method in Mumbai.

When we talk about the construction industry the resources incorporated in completion of proposed works are time, capital, manpower and space. With the right and justified use of these resources a significant efficiency and economy can be achieved. The construction activities from ancient age have a typical stage of commencement during the execution phase i.e. the first activity starts from the foundation of the structure. The conventional method of construction of structures is based on Bottom-Up method in which the sub-structure and super-structure floors are constructed sequentially from the bottom of the sub-structure or lowest level of basement to the top of the super-structure. This method is suitable for small scale works, as there is rapid change in patterns of use of land available like use of underground basements for parking, underground metro stations the volume of works at the foundation level of the structures has increased to manifolds. In this context the construction industry experts has started to adopt a new Top Down method for better utilization of resources available.

Key Words: Top down Construction, Deep basement excavations, Residential building.

1. INTRODUCTION The current scenario of construction industry sector emphasizes on the timely delivery of the projects whether it be any infrastructural developments, residential/commercial building structures or any other civil works. There are various factors that affects the completion times of projects ranging from availability of funds to political issues, environmental laws, resettlement

2. Construction Schedule of a residential building with deep basement using conventional bottom up technique. A Construction schedule study was conducted with respect to the general output of work being observed and the number of man hours incorporated to complete the construction of various civil works of a residential building which consist of 9m deep basement and 20 upper habitable floors having a plot area of about 800 Sq.mt, basement area of 530 Sq.mt and superstructure built-up area of 7200 Sq.mt. The residential building project was located in Central Mumbai and major works were completed. The construction schedule is as shown in the Table 1. ID

WBS

Task Name

Duration

Start

Finish

Predecessors

1 2 3

1 1.1 1.2

PROJECT DURATION BORING, CASTING OF SHORE CASTING OF CAPPING

557 days 51 days 10 days

01/06/17 01/06/17 22/07/17

15/12/18 21/07/17 31/07/17

3

© 2019, IRJET

|

Impact Factor value: 7.211

|

ISO 9001:2008 Certified Journal

|

Total Slack 0 days 0 days 0 days

Page 2233