Dhiraj Awade1 , Vinayak Bachal2, Seema Jagtap3
1Dhiraj Awade, Dept of Civil Engineering, Thakur College of Engineering Kandivali, Maharashtra, India
2Vinayak Bachal, Dept of Civil Engineering, Thakur College of Engineering Kandivali, Maharashtra, India
3Seema Jagtap, Dept of Civil Engineering, Thakur College of Engineering Kandivali, Maharashtra, India
Abstract The problem of leakage through the expansion joints of bridges carrying elevated metro lines is of great importance in urban engineering, as water leakage from such joints falls directly on the roads and footpaths, posing dangers of injury to pedestrians and vehicles, and deterioration of bridge structures such as the caps of piers. This research suggests a unique drainage scheme where there is provision of a 150 mm height wall that will collect all the water leaking out of the joints into a 50 mm drainpipe and transfer them to the ground level. Such a system will help in avoiding unnecessary water flow, prevent the structure from deterioration due to continued seepage and ensure safety of both pedestrians and vehicles. Additionally, this drainage arrangement will help in reducing maintenance needs of the system and increase its longevity. This paper presents an approach to the design and implementation of the suggested scheme.
Keywords Expansion joints, Metro bridge drainage, Water leakage control, Pier cap deterioration, Pedestrian safety.
Elevated metro bridges are an essential part of modern urban transportation systems, providing efficient and uninterrupted connectivity in densely populated cities. These structures are continuously exposed to environmental conditions such as rainfall, temperature variation, and moisture infiltration. One of the major maintenance issues observed in metro bridge structures is waterleakagethroughexpansionjoints.Expansionjointsare provided in bridges to accommodate thermal movement, vibration, and structural displacement; however, improper drainage and deterioration of these joints often result in leakage of rainwater onto roads, footpaths, and bridge substructures.
Continuouswaterseepagefromexpansionjointscancreate several problems, including slippery road conditions, inconvenience to pedestrians, traffic disturbances, and deteriorationofstructuralcomponentssuchaspiercaps.In many metro corridors, leakage water directly falls from elevatedbridgesontopublicroads,leadingtosafetyhazards and increased maintenance requirements. Prolonged exposure to moisture may also result in corrosion of
reinforcement,concretedamage,andreducedservicelifeof bridgecomponents.
Thisstudyproposesapracticaldrainagecontrolsystemfor metro bridge expansion joints using a 150 mm protective wall combined with a 50 mm drainage pipe arrangement. The proposed system is intended to collect leakage water and safely divert it to ground level without affecting pedestrians or vehicles. The study focuses on improving public safety, minimizing structural deterioration, and enhancing the durability and maintenance efficiency of elevatedmetrobridgeinfrastructure.
Expansionjointsformsomeofthekeystructuralelements thatareinstalledonbridgesinordertoallowformovement resulting from various factors such as changes in temperatures,vibrationsfromtrafficloading,vibrationfrom trafficvibration,shrinkage,andseismologyamongothers.In elevated metro bridges, expansion joints play a significant role in ensuring that movements occur in a controlled manner in order to prevent the formation of stress and cracksonstructuralcomponents.
However, despite being critical to the stability and durability of structures, expansion joints are subject to difficult environmental conditions such as water, dust, and traffic vibration. Damaged joints form the main sources of water leakage in elevated metro bridges, especially since rainwater that gets into joints drips directly onto roads, pedestrian walkways, as well as bridge substructure elements. This can pose safety hazards as well as cause deterioration of the structure, including corrosion of reinforcedconcreteandsteel.
Managementofleakingexpansionjointshasbecomeone ofthecriticalissuesinmetrostructures,especiallyinurban settings. Therefore, there arises the need for an effective drainagesystem.

Volume: 13 Issue: 05 | May 2026 www.irjet.net p-ISSN: 2395-0072

1.2.M
Water collects in the top parts of metro bridges during rainfall due to insufficient drainage flow and constant exposure to the environment. Although there is drainage providedinthebridges,waterusuallycollectsinthevicinity oftheexpansionjointbecausethegapinthestructureserves asadrainagepoint.Sincethejointareabecomesexposedto environmentalelements,dirtaccumulationandpoorsealing performanceresultinwaterloggingintheregion.
Thecollectionoflargeamountsofwateratthe region of expansion joints causes water leakage into the road and walkwaybeneaththe bridge.Leakageofwaterfromsucha great height causes problems for both pedestrians and motorists. The risk of accidents on the slippery road increaseswhenrainfallsheavily.
Apartfromexternalleakage,someoftheleakingwateris collectedinpartsofthestructures,suchaspiers'caps,and support structure below the deck surface. Stagnation of water in such places can cause damage to the concrete as wellasthereinforcementbars,staininganddecreaseinthe life of bridge components. For this reason, it is imperative that leakage water should be collected and diverted appropriatelythroughtheexpansionjoints.
1.3.A
Aim- To develop an effective drainage control system for elevated metro bridge expansion joints to prevent uncontrolledwaterleakageontoroadsandpedestrians.The proposed system focuses on collecting and safely diverting
seepage water to reduce structural deterioration and improvepublicsafety.
Objectives:
1.Tostudythecausesofwaterleakagethroughexpansion jointsinmetrobridges.
2. To design a 150 mm protective wall with a 50 mm drainagepipesystemforcontrolledwaterdiversion.
3.Toreducewateraccumulationonpiercapsandimprove pedestrianandvehicularsafetybelowmetrobridges.
The leakage of water from the expansion joints on elevatedmetrorailwaybridgesallowswatertofallstraight on to the road surfaces and walking spaces, leading to various dangers and disruptions to the flow of traffic. Constantleakageofwaterresultsinwateraccumulationon the surface of pier caps, thus affecting the structure of bridgesandrequiringregularmaintenance.
Theexperimentonbridgeexpansionjointdamagecarried out by Li et al., (2023), was based on natural frequency analysis. The study analyzed how the bridge modal expansion joints behaved differently depending on varying damagestatesandcuringperiods.Deteriorationinelements suchascenterbeams,supportbars,andanchorageconcrete loweredthenaturalfrequencyofexpansionjoints.Thisisan indicationofbridgedamage.Thestudyemphasizedtheneed to keep track of expansion joint states in order to avoid leakageandsubstructuredeterioration.
Transport Infrastructure Ireland, (2023), developed a standard guideline on the design, construction, inspection, andmaintenanceofroadbridgeexpansionjoints.Thestudy focused on how bridge expansion joints could be designed andinstalled.Inaddition,thestudyanalyzedtheeffectsthat improper drainage and defects have on expansion joints. Improper drainage and joint defects cause leakage, deterioration,andmaintenancechallenges.
The role of the joints in bridge structures and its significance in handling thermal effects, shrinkage, creep, and traffic load effects was discussed by Mohamed and Noothangal, (2022). Poor management of joints has been associatedwithconcretespalling,leakage,anddeterioration ofpiercapsamongotherpartsofthebridge.Theresearchers emphasized the necessity of proper management of expansionjointsforbetterfunctioningofbridges.
Avudaiappan et al., (2021) studied the effect of thermal andearthquakeloadsonconnectionsbetweenpierandpier capinintegralbridges.Deteriorationoftheexpansionjoints may be associated with water leakage, concrete cracking,

International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 13 Issue: 05 | May 2026 www.irjet.net p-ISSN: 2395-0072
andfailureofthebridgesubstructureunderneath.Thestudy aimed at minimizing maintenance problems related to conventionalexpansionjointsinbridgesystems.
Phares and Ruble, (2020) conducted research on rapid repair and replacement of bridge deck expansion joints. Specifically,theuseofultra-high-performanceconcreteand hydrodemolitionprocesswasconsideredinthestudy.The results revealed that expansion joints are some of the earliest bridge structures to undergo failure and that their repair would extend their useful lives and minimize maintenancetime.
Jahren et al., (2017) conducted research about rapid replacement techniques for bridge deck expansion joints and various maintenance and rehabilitation practices. According to the findings, faulty expansion joints facilitate penetrationofcorrosivematerialthroughwatertopiersand abutments, leading to corrosion and deterioration. Therefore, the authors suggested improved maintenance practicesforthepurposeofincreaseddurabilityofbridges.
LimaanddeBrito,(2010),amanagementsystemforroad bridge expansion joints should incorporate maintenance, rehabilitation, and defect classification. The authors found thatexpansion joints were among the main componentsof bridge maintenance costs. In addition, preventive maintenance could be used as a method of reducing deterioration and leakage problems in order to increase servicelife.
Chang and Lee's, (2001) research was assessment of various bridge expansion joint types through surveys, inspection, and data analysis. The most typical problems foundincludedwaterleakage,corrosion,anddeterioration. Consequently, the researchers concluded that appropriate material, installation, and maintenance of expansion joints were necessary conditions for improvement of their performanceandextendedlifetime.
Dahir and Mellott (1987), evaluated expansion joints systemsthathavebeeninstalledinPennsylvaniabridges.It was stated that a huge percentage of the expansion joints were allowing water to enter the bridges, thus causing deterioration due to contamination with chlorides and corrosion. Guidelines were given in terms of appropriate expansionjointsystems.
Purvis and Berger (1983), there are maintenance problemsrelatedto bridge deck expansion joints and their effects on the bridges. Poorly performing expansion joints allowthewaterandcontaminantstoenterintobridgeseats, bearings,andsupports.Thiscausesdamagetothestructure ofthebridge,thusincreasingmaintenancecosts.
III. METHODOLOGY

The issue that influenced the choice of the topic under investigation is the occurrence of the leakage of water at expansionjointsoftheelevatedmetrobridges.Waterdrops fallingontoroadsandotherareasusedbypedestrianscause numerous problems in urban territories. This project is aimedatdesigningaviablesolutiontocontroltheleakageof water. Structural safety and sustainability of the infrastructurewillbetakenintoconsiderationaswell.
A thorough literature review was conducted relying upon articles published in journals, research papers, and other sources. The results of the previous studies contributed greatlytoananalysisofthereasonsfortheleakageofwater, deteriorationofpiercaps,andnumerousissuesthatshould

International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 13 Issue: 05 | May 2026 www.irjet.net p-ISSN: 2395-0072
be addressed. Various expansion joints and drainage systemswillbeconsideredduringtheprocess.
Water leakage at expansion joints of the elevated metro bridges caused by the rainfall is the main problem under discussion.Waterdropsfallingontoroadsandpathwaysof pedestrians create numerous troubles. Moreover, continuousseepageofwaterleadstoitsaccumulationonthe surface of pier caps. The issue may cause structural deteriorationofsuchelementsandevencorrosion.
Site inspections were made in order to examine the real conditionsofmetrobridgeexpansionjointsaswellastheir water drainage systems. Locations of leakage, water pathways,andconditionsofwaterloggingwereobserved.In addition,conditionsofthepiercapandtheareasurrounding this area which have been affected by the leakage were observedaswell.
5.DataCollection
Datarelevanttotheconditionoftheexpansionjoints,degree ofleakage,waterpathways,andstructuralobservationwere gathered through field inspections. Measurements concerning the zone of the leakage and water drainage systems were taken. Data from photographic records and visual observation were recorded as well. Collected data servedasinputinformationregardingtherealwaterleakage problems.
Analysisofthe collecteddataprovidedthe researcherwith aninsightintothecausesandconsequencesofwaterleakage through expansion joints. Areas where water accumulates, as well as its behaviour in relation to the pier cap, were observedindetail.Dataanalysisalsoidentifiedsiteswhere drainage systems were needed. This stage also served as a guidefortheproposeddesignconcept.
Theideaofinstallinga150 mmprotectivewallsystemhas beenrecommendedneartheareaoftheexpansionjointsin ordertocollectthe leakedwatereffectivelyandcontainits flow. It will serve the purpose of preventing leakage water fromenteringandfallingonroadsorpedestrianwalkways. Thus,properplanningofthesystemisrequiredintermsof sizeandlocation.
A 50 mm drainage pipe system has been suggested for transferringleakagewaterthroughpipesfromtheproposed wallsystemtodischargeatgroundlevel.Aproperdrainage pipesystemwillnotonlyfacilitatecontrolledflowofwater without disturbing the surrounding area but will also help avoid water stagnation around pier cap areas. Proper connectivityneedstobeensured.
Amodel ofthe proposeddrainage control systemhasbeen createdsothattheconceptcouldbeunderstoodeasilyalong withitsworkingprinciplesandimplementationprocedures. In addition to layout planning, the system should have proper design of the proposed wall system and piping connectionstoensuresmoothdrainageprocess.
10.ExecutionandImplementationMethodology
An execution method for implementation of the drainage systemwasalsoinvestigatedindetail.Constructionprocess, material needs, man-power requirements, and the method of installation was investigated. The implementation methodology was mainly directed towards reducing any disruption to ongoing metro bridge operations. Practical conditions at construction site and ease of maintenance werealsoconsidered.
11.PerformanceEvaluation
Theperformanceevaluationoftheproposedsystemisbased ontheefficacyoftheproposedsystemincontrollingtheflow of leakage water. The performance evaluation takes into consideration the performance of the walls and pipes in ensuring proper flow of water. Issues regarding safety and efficiency of drainage were considered when evaluating performance.
12.ResultsandDiscussion
The analysis of the results obtained was undertaken in context of the performance in terms of improving the drainage efficiency and increasing public safety. The drainage system proposed in this case proved capable of controllingleakagewaterfromexpansionjoints.Controlling of uncontrolled water flow and protecting the piers' caps werefoundtobethekeybenefits.
13.ConclusionandRecommendation
Thestudyconcludedthatthesuggesteddrainagesystemwill be effective in addressing issues relating to water leakages through the expansion joint of the metro bridge. The application of the protective wall and the pipe drainage

International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 13 Issue: 05 | May 2026 www.irjet.net p-ISSN: 2395-0072
system enhance safety and prevents any damages to the structure.Recommendationshavebeenmadeonhowsucha drainagesystemmaybeimprovedinthefuture.
4.1.PROBLEMDUETOWATERLOGGING
Waterloggingcausedbyleakageattheexpansionjointin an elevated metro bridge is a critical concern. During the rainy season, water collects around expansion joints that havebeendamagedorsealedinadequatelyandstartstoleak out of them. Leakage water drips to the ground, causing watertologontheroads,pathways,andevenpublicplaces located under the bridges. Continuous leaking of water on road surfaces results in slippery road surfaces and traffic hazards such as lack of visibility, which increases the probabilityofaccidents.

In addition to posing dangers to public transport users, water leakage also creates problems regarding the structural elements of the bridge. Leakage of water causes moistureaccumulationonstructuralelementsandresultsin corrosion of concrete and reinforcement, deterioration of concrete, stains on the concrete surface, and a shortened lifespanofthestructuralelements.Inmostcases,leakageof wateraroundstructuralelementsofthebridgesnecessitates frequent maintenance work. Thus, efficient water management and drainage from expansion joints are vital forbetterperformanceofbridges.
4.2.PROBLEMSFACEDDUETOWATERLOGGING
There are several challenges caused by water leakage fromexpansionjointsofmetrobridgestructures.Rainwater collectedwithinthecracksofthejointflowsdownontothe roadwaysandpathwayslocatedbeneaththeelevatedmetro
bridgestructure.Waterdischargefromtheexpansionjoints createschallengesforbothpedestriansandmotorists.There isalsoariskofreducedvisibilityformotoristsdrivingbelow the bridge. The continuous flow of water can also cause disruptionduringtherushhourperiod.
Apart from posing potential risks of accidents, water accumulation near the pier caps and roadway poses problems such as bad drainage system and unhealthy environment.Itispossiblefortheroadstobecomeslippery becauseofwateraccumulation,increasingthelikelihoodof accidents. Prolonged exposure to water may also lead to damagetothenearbystructures.
1.Slipperyroadsandfootpaths
2.Possibilityofanaccidenttopedestriansand vehicles
3.Trafficjamsduringrain
4.Splashesfromwaterontopedestriansand vehicles
5.Difficultiesinseeingformotorists
6.Difficultymovingaroundundermetrobridges
7.Puddlesofwaterclosetoroadsideareas
8.Damagedroadsurfacesandpublicareas adjacenttotheroads
9.Badsmellresultingfromwateraccumulation
10.Inconvenienceforpeopleduringmonsoons
4.3.PROPOSEDMEASURESFORTHEPROBLEM
Theproposed150mmprotectivewallanddrainagepipe system offers an effective solution for controlling water leakagefromexpansionjointsinelevatedmetrobridges.The protective wall helps in collecting and restricting uncontrolled water flow near the expansion joint area, thereby preventing water from directly falling onto roads and pedestrian pathways. This improves public safety by reducingslipperyroadconditions,trafficdisturbances,and inconvenience to pedestrians during rainfall. The wall also helps in minimizing water accumulation on pier caps, reducing the chances of concrete deterioration and reinforcementcorrosion.

International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 13 Issue: 05 | May 2026 www.irjet.net p-ISSN: 2395-0072

Figure4:DrainageSystemforwater
The 50 mm drainage pipe network safely diverts the collected leakage water to ground-level discharge points through a controlled flow path. This system improves drainage efficiencyandpreventswaterloggingnearbridge components and roadside areas. In addition, the arrangementreducesmaintenancerequirements,improves structuraldurability,andenhancestheoverallservicelifeof metrobridgeinfrastructure.Theproposedsystemissimple, practical, economical, and can be easily implemented in existing elevated metro bridge structures for better water managementandpublicsafety.
1.Itwasobservedthatthewaterleakageduetoexpansion joints in metro bridges posed several risks of injury to pedestrians and automobiles, along with water accumulationonthesurfaceofthepiercapsandstructures.
2.Thedesignoftheprotectivewalluptoaheightof150 mmprovedtobea solutioninthecollectionandlimitation ofwaterdischargedfromtheexpansionjoints.
3.Theinstallationofthedrainagepipeshavingadiameter of50mmisefficientindivertingthewaterleakagetoground level.
4.Thewholeproposedsystemisnotonlysafebutensures properdrainageandlongevityofstructure.
REFERENCES
[1] J.Li,F.Wen,J.Chen,C.Yang,W.Du,L.Xu,andP. Li,“ExperimentalStudyofBridgeExpansionJoint
Damage Based on Natural Frequency,” Sensors, vol.23,no.14,pp.6437,2023.
[2] Transport Infrastructure Ireland, “Expansion Joints for Use in Road Bridge Decks,” TII PublicationsDN-STR-03006,Feb.2023.
[3] M.SheikMohamedandS.Noothangal,“Reviewof the Role of Joints Usage in Bridge Structures,” International Research Journal of Engineering and Technology (IRJET),vol.9,no.4,pp.2979–2984, 2022.
[4] S.Avudaiappan,K.Prabu,D.Selvaraj,K.Raja,P.O. Awoyera,andE.I.SaavedraFlores,“Performance of Pier-to-Pier Cap Connections of Integral Bridges under Thermal and Seismic Loads,” Advances in Civil Engineering,vol.2021,ArticleID 5580841,2021.
[5] B. M. Phares and K. Ruble, “Accelerated Repair and Replacement of Expansion Joints,” Bridge Engineering Center, Iowa State University, Final Report,Apr.2020.
[6] C. Jahren, “Rapid Replacement of Bridge Deck Expansion Joints – Phase II,” Iowa State University,TechTransferSummary,May2017.
[7] J. M. Lima and J. de Brito, “Management System for Expansion Joints of Road Bridges,” Structure and Infrastructure Engineering, vol. 6, no. 6, pp. 717–729,2010.
[8] L. M. Chang and Y. J. Lee, “Evaluation and Policy for Bridge Deck Expansion Joints,” Joint Transportation Research Program, Purdue University,FHWA/IN/JTRP-2000/1,Feb.2001.
[9] S. H. Dahir and D. B. Mellott, “Bridge Deck Expansion Joints,” Transportation Research Record,no.1118,pp.16–25,1987.
[10] R. L. Purvis and R. H. Berger, “Bridge Joint Maintenance,” Transportation Research Record, no.899,pp.1–10,1983.