continued from page 3 for graduation The Lecture Hall of the high school still has a leak and the insurance adjuster will test to locate the issue It will be fixed before school starts Wilson says

The library driveway will be completed in the next two weeks and Shane Cavender has begun moving dirt in preparation for the new project barns "He thinks he can get all the dirt work done and have the pad ready by July 1." said Wilson Roger Brown of Metal Masters will be finishing out the building

Bulldog Stadium will have a bleacher expansion to the north and south and should be completed by mid-August. A visitors press box will begin construction by Metal Masters in July

Wilson informed the board of a letter he received from Dan Patrick, Lieutenant Governor of Texas, encouraging the district to disregard any proclamations made from the federal government (concerning the bathroom policy)