How long will it take to set up a manioc flour processing plant in Nigeria?

Page 1

How long will it take to set up a manioc flour processing plant in Nigeria?

Henan Jinrui is professional manioc flour processing machine manufacturer who has installed many projects in Tanzania, DR Congo, Zambia, Ghana, Nigeria and Uganda, etc. Most clients are wondering how long it will take to set up a manioc flour processing plant, here we take Nigeria as an example to give out a project time line, hope that it can help you make your plan accordingly.

1.Machine manufacture cycle: about 2-3 months

manioc flour machine is making

Firstly, Henan Jinrui company usually make a project proposal based on clients requirement for production capacity. And final equipment list will be confirmed after detailed discussion with user. After all details are confirmed, customer will sign contract and arrange deposit. Once we received deposit, we will confirm voltage requirement with clients and start manufacturing works. It takes 2-3 months for drawing making and equipment manufacturing, and actual time will depends on our production schedule.

2.Machine delivery cycle and custom cleaance: totally about 3 months

Machine delivery cycle and custom clearance of manioc flour machines

After all the manioc flour processing machines are finished, clients arrange balance payment, and then next is transportation of machines. It takes one week for us to transport machines to port and waiting for shipping. If destination port is Apapa, the shipping period from China to Nigeria is normally 2 months.

And after the manioc flour processing machines arrive Nigeria, clients need to go and do custom clearance and then arrange transportation of machines from port to factory site, which takes about one month.

3.Machine installation cycle: about 3 months

After machines arrive factory site, our company will send engineers to guide installation works, train local workers and do commissioning of the manioc flour production line. How long it will take for installation depends on working efficiency of local workers. With all the personnel and installation tools available, it takes about 3 months for installation and commissioning.

To sum up, it takes about 8-9 months for one to set up a manioc flour processing plant in Nigeria. That means, you need to start making inquiry about machines at least one year before building up the factory.

Henan Jinrui company can customize you the most suitable manioc flour processing machine at a favorable price, and offer you professional solutions&technical support to guide your manioc flour processing plant installation. Please don’t hesitate to contact us now!

http://www.cassavaprocessing.com

WhatsApp/Phone:+86 135 2661 5783

Email:market@doinggroup.com

manioc flour plant is installing

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
How long will it take to set up a manioc flour processing plant in Nigeria? by Henan-Doing cassava processing machine - Issuu