Update on the Waterloo estate regeneration

Page 1


H A V E R I N G

ESTATE REGENERATION

REPRESENTATIVES

Paul Walker Director of Housing and Property

Mark Butler Assistant Director of Regeneration & Place Shaping,

Michael Rourke Senior Regeneration Manager

Chantal Miller Project Manager

Vijay Patel Development Manager (Wates)

Lionel Stroh Development Manager (Wates)

PROJECT UPDATE

H A V E R I N G

ESTATE REGENERATION

DEVELOPMENT PLANS

• Block 9 and 10 progressing as Phase One.

• Community Design Engagement Sessions ongoing.

• Feedback from session been incorporated into updated design and presented / discussed with residents and planning officers.

• Public consultation of final design targeted July/August 2025

• Engagement session 05/06/25 providing design update.

H A V E R I N G

ESTATE REGENERATION

COMMUNITY GARDEN

H A V E R I N G

ESTATE REGENERATION

COMMUNITY GARDEN

• Wates SocialValue Team and Havering Council planned a garden clearing session earlier today.

H A V E R I N G

ESTATE REGENERATION

NEIGHBOURHOOD ISSUES

ESTATE REGENERATION

LATEST UPDATES

• Hoarding repairs now carried out.

• Extra security still attending site.

H A V E R I N G

ESTATE REGENERATION

TEMPORARY CAR PARK

• Proposed temporary car park (with 5 spaces) only for the use of church congregation to alleviate parking pressures.

• Revised Planning Application now consented.

H A V E R I N G

ESTATE REGENERATION

CONDITION SURVEYS

• Parish Centre demolition being planned.

• In advance of works due to be carried out, condition surveys will be planned.

• Walker Construction Consultants will be contact with impacted residents.

H A V E R I N G

ESTATE REGENERATION

TEMPORARY HOUSING

H A V E R I N G

ESTATE REGENERATION

TEMPORARY HOUSING

• Temporary planning application has been consented.

• Development will be secured, with appropriate street lighting.

• It will provide more street activity and some natural surveillance.

H A V E R I N G

ESTATE REGENERATION

MODULAR DEMONSTRATOR HOME

• Modular demonstrator home from Romford Market has now been removed, and is temporarily stored at the WQS site.

• In the next couple of weeks, it will be moved to Harrow.

H A V E R I N G ESTATE REGENERATION

KEY CONTACTS

KEY CONTACTS:

For any queries on the day to day activities on site (including anything urgent), please contact:

Keith Ward

Project Director

Wates Residential

Mobile: 07516 131341

Email: Keith.Ward@wates.co.uk

For all Waterloo related queries, please contact: Regeneration@havering.gov.uk

ESTATE REGENERATION QUESTIONS?

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.