




Paul Walker Director of Housing and Property
Mark Butler Assistant Director of Regeneration & Place Shaping,
Michael Rourke Senior Regeneration Manager
Chantal Miller Project Manager
Vijay Patel Development Manager (Wates)
Lionel Stroh Development Manager (Wates)
• Block 9 and 10 progressing as Phase One.
• Community Design Engagement Sessions ongoing.
• Feedback from session been incorporated into updated design and presented / discussed with residents and planning officers.
• Public consultation of final design targeted July/August 2025
• Engagement session 05/06/25 providing design update.
• Wates SocialValue Team and Havering Council planned a garden clearing session earlier today.
• Hoarding repairs now carried out.
• Extra security still attending site.
• Proposed temporary car park (with 5 spaces) only for the use of church congregation to alleviate parking pressures.
• Revised Planning Application now consented.
• Parish Centre demolition being planned.
• In advance of works due to be carried out, condition surveys will be planned.
• Walker Construction Consultants will be contact with impacted residents.
• Temporary planning application has been consented.
• Development will be secured, with appropriate street lighting.
• It will provide more street activity and some natural surveillance.
• Modular demonstrator home from Romford Market has now been removed, and is temporarily stored at the WQS site.
• In the next couple of weeks, it will be moved to Harrow.
For any queries on the day to day activities on site (including anything urgent), please contact:
Keith Ward
Project Director
Wates Residential
Mobile: 07516 131341
Email: Keith.Ward@wates.co.uk
For all Waterloo related queries, please contact: Regeneration@havering.gov.uk