Renfrewshire Roads Programme - Bishopton, Bridge of Weir & Langbank

Carriageway Resurfacing

Bishopton:

Advertisement

Porton Place 2100m2 - Start Date 16/8/21

Bridge of Weir:

Prieston Road 6460m2 - Start Date 30/8/21

Eldin Place 845m2 - Start Date 6/9/21

Donaldfield Road 2920m2 - Start date 6/9/21

Main Street 4178m2 - Start Date 13/9/21

Earl Place 861m2 - Start Date 20/9/21

Thriplee Road 1858m2 - Start Date 27/9/21

Kilgraston Road 1552m2 - Start date 4/10/21

Pre-Patching Work in Advance of Surface Dressing

Bishopton:

Reilly Road - Start Date 2/8/21

Bridge of Weir:

Warlock Road - Start Date 2/8/21

Langbank:

Finlaystone Road - Start date 2/8/21

Galahill Road - Start date 2/8/21

Netherton Road - Start Date 2/8/21

Old Greenock Road - Start Date 2/8/21

Station Road - Start Date 2/8/21

West Glen Road - Start Date 2/8/21

Footways and Pavements

Bishopton:

Old Greenock Road 680m2 - Start Date 1/11/21

Porton Place 1010m2 - Start Date 25/10/21

Bridge of Weir:

Kenbank Road & Crescent 590m2 - Start date 13/12/21

Ranfurly Road 1700m2 - Start Date 23/8/21

Shillingworth Place 560m2 - Start Date 13/12/21

Langbank:

Middlepenny Road 833m2 - Start Date 10/1/22

Please be aware that bad weather may delay some of these start dates.