2026 WEEKLY CONSTRUCTION UPDATES
AUGUST 21 After years of discussion, planning, communication, and preparation — and several weeks of mobilization — PN25 officially broke ground on Monday, August 17. Five days into construction, the progress is already noticeable. KCM hit the ground running on the front nine with a team of more than 25 staff, supervisors and project managers on site. We have been fortunate to have excellent weather throughout the first week, allowing the team to take full advantage of the long summer days and make significant early progress.
ON THE COURSE Architect Tom McBroom was on site Tuesday working directly with the construction team. Armed with his plans and a spray-paint gun, Tom began translating the designs for the first bunkers and the new #4 green complex into physical lines on the ground for KCM's shapers to follow. The transformation of #4 is already underway. The existing green has been removed and shaping has begun on the new, more visible green complex. Work has also progressed quickly on #1, where the first bunkers have been shaped and crews are now installing the soil bags that will help create the new rolled bunker edges, along with new subsurface drainage. Shaping is one of the most important components of the project. Beyond the functionality and drainage of the new bunkers, considerable attention is being paid to how they fit naturally into the existing landscape. The goal is simple: when the project is complete, the new features should look as though they have always belonged at GGC.
WHAT'S NEXT Next week, KCM will continue working its way through the front nine, with particular attention being paid to the greens complexes. One of the early construction priorities is to have all nine front-nine greens — including the newly constructed greens on #4 and #7 — prepared for seeding by Labour Day weekend. Getting these areas established as early as possible will provide the best opportunity for successful grow-in ahead of next season. For the foreseeable future, KCM's crews will be working six days per week, generally from 7:00 am to 7:00 pm. Weather conditions and available daylight will continue to be the primary factors affecting the pace of construction.
SAFETY AROUND THE PROJECT With a project of this scale comes a significant amount of activity around the property. Over the coming weeks, we expect to receive up to 20 truck and trailer loads of aggregate per day, in addition to the construction equipment and personnel already moving throughout the site. We ask everyone visiting the Club to continue respecting all construction boundaries and safety protocols and, particularly, the posted speed limits along the driveway. Please allow construction vehicles plenty of room and exercise a little extra patience when entering or leaving the property. A sincere thank you to everyone who came out this week to play the back nine. Your enthusiasm for the project has been great to see, and we especially appreciate how well members have respected the safety measures that have been put in place.
FOLLOW THE PROGRESS There will be a lot to see over the coming weeks, and we want to bring members along for the journey. In addition to these weekly updates, we'll be sharing regular behind-the-scenes photos and videos from the construction site on our Instagram page. Week One is officially in the books. There is a long way to go, but after years of planning, it is exciting to finally see PN25 taking shape on the golf course.
AUGUST 28 With the second week of Project Next 25 nearing completion, work continues to progress quickly across the front nine. Following the initial demolition, excavation and preparation work completed during the first week, several areas of the project are now moving into the shaping, fine grading, and finishing stages.
BUNKER CONSTRUCTION: HOLE 1 Last week, we shared some of the early stages involved in the bunker reconstruction process on the 1st hole, including sod removal, shaping, drainage preparation, and installation of the burlap bags used to establish the bunker edges. This week, those bunkers have progressed through several of the remaining construction stages and now provide our first look at the completed Better Billy Bunker system. The drainage gravel has been installed and treated with the Better Billy Bunker polymer, creating the durable, porous base that allows water to move rapidly through the bunker while helping prevent contamination of the sand from the underlying soil. ProAngle bunker sand has now been installed over the finished base. As work continues around the bunker surrounds, bluegrass sod will ultimately complete the transition between the bunkers and the surrounding turf.
GREENS RECONSTRUCTION: HOLE 4 Significant progress has also been made on the rebuild of the 4th green.
The green has now been raised to its new design elevation, drainage has been installed, and the putting surface and surrounding contours have been shaped. The next steps will include final grading, installation and adjustment of irrigation around the green and surrounds, followed by bluegrass sod throughout the surrounding areas. The putting surface itself will then be seeded with the new bentgrass. The redesigned green and approach will provide improved visibility and playability while creating more opportunity for shots landing short of the putting surface to feed onto the green.
GREENS AND GREENSIDE BUNKERS
Across the remainder of the front nine, work on the greens and greenside bunkers continues to advance quickly. With the exception of the complete rebuild of the 7th green, which is currently underway, the remaining green complexes and greenside bunkers are approaching the final stages of construction. Subject to weather and site conditions, we are hopeful that installation of bluegrass sod around the greens and greenside bunkers will begin later next week. The putting surfaces are expected to be seeded either before or shortly after the Labour Day weekend, comfortably within the desired establishment window for the new bentgrass. Rain is currently forecast for Sunday and Monday and, as with any construction project of this nature, weather can affect daily progress and sequencing. The project team will continue to adjust the work plan as required while maintaining focus on the overall construction schedule.
LOOKING AHEAD Over the first two weeks, members have been able to see the project move rapidly from demolition and preparation into reconstruction. Over the coming weeks, that transition will become even more visible as sod is installed around the completed green complexes, putting surfaces are seeded and additional bunkers move through the final stages of the Better Billy Bunker installation. We will continue to provide regular updates as the work progresses.
SEPTEMBER 2 Mother Nature delivered an unwelcome reminder this morning that even the bestlaid construction schedules remain subject to the weather. The property received more than two inches of rain in a very short period this morning, with additional rainfall expected. Unfortunately, the intensity and volume of the storm have had a significant impact on the PN25 construction site, particularly around several of the greens and bunkers where work was actively underway. The photos and video accompanying this update provide a good indication of the conditions currently facing the project team. What This Means for the Project At this stage, we expect the storm to result in a significant interruption to the construction schedule. For approximately the next two days, there will be very little productive work that can take place while the site drains and conditions dry sufficiently to allow heavy equipment and crews to safely return to the affected areas.
Once conditions permit, we anticipate approximately another two days will be required for cleanup and repairs to restore areas impacted by the storm and return the project to roughly where it stood prior to the rainfall. In practical terms, our best-case scenario is that we lose much of what was an extremely important week of September construction.
THE ROAD BACK The good news is that KCM has both the resources and experience to respond. One of the reasons KCM was selected for PN25 is its ability to mobilize significant labour, equipment and expertise when circumstances require it. Once site conditions allow productive construction to resume, the team has the capacity to increase resources and work aggressively to recover lost time. Getting to that point, however, will require patience. Before we can focus on catching up, the immediate priority is allowing the property to drain, assessing the full extent of the damage, completing the necessary cleanup and repairs, and getting the construction site back into workable condition. There is no shortcut through that process, and its timing will depend heavily on the weather over the coming days.
PERSPECTIVE Until this morning, the project had been progressing extremely well. KCM and the GGC team had taken advantage of favourable conditions and made substantial progress since construction began on August 17. Today's storm is a setback - and a meaningful one - but it is also one of the realities of undertaking a project of this scale outdoors. Our focus now is on protecting the work already completed, restoring the affected areas and giving KCM every opportunity to regain momentum as quickly as conditions allow. We will continue to assess the impact over the coming days and provide members with a further update once we have a clearer picture of the recovery timeline. Thank you for your patience and understanding.
SEPTEMBER 11 What a difference a week — and a few dry days — can make. Last week’s significant storm event ultimately cost the project approximately five full days of productive construction time. Before work could resume in earnest, the site needed time to dry, followed by considerable cleanup simply to return many areas to where they had been before the storm. Weather was always going to be one of the variables we could not control with a project of this scale. What we can control is how we respond. Our Golf Course Maintenance team worked diligently to address the storm damage and cleanup, while KCM responded by deploying its considerable workforce, equipment and expertise across the project. Combined with several days of favourable weather, the recovery has been impressive. As of Friday, September 11, the project is back on track and moving full steam ahead.
THE FRONT NINE IS STARTING TO TURN GREEN
Seven of the nine greens on the front nine have now been seeded. Members who have been at the Club this week may already have noticed the very early stages of bentgrass germination beginning to appear. Around here, we call it “peach fuzz.” It doesn't look like much just yet, but seeing that first hint of green emerging from what was bare soil only days ago is an exciting milestone. From here, those surfaces will continue to establish and mature over the coming weeks.
A NEW LOOK FOR NO. 4 The transformation of the fourth green complex continues to be one of the most dramatic elements of PN25. The entire green complex has been raised by more than 1.5 m, shifted slightly north and pushed approximately 10 yards back into the hillside. A new statement bunker has also been created behind the right side of the green, significantly changing both the strategy of the hole and the view from the tee. There is still considerable work ahead. Drainage, greens mix, irrigation, final grading, fine topsoil, seeding and surrounding sod remain, along with completion of the Better Billy Bunker system and installation of the new ProAngle bunker sand. With cooperative weather and a little help from Mother Nature, however, we expect the No. 4 green complex to be substantially completed well before the end of September.
REBUILDING NO. 7 If No. 4 is currently about transformation, No. 7 is still very much in the demolition and reconstruction stage. The former green has now been completely removed and work is underway to turn the resulting construction site into a new, more interesting and playable putting surface. The new design will also introduce a small bunker on the left side of the green. No. 7 presents a different construction challenge. It sits at one of the lowest points on the property, making drainage and the stability of the new green complex particularly important before final grading, seeding and sod can take place. This will be an important area of focus over the coming weeks and another race against the fall construction calendar.
NEXT UP: SOD With newly seeded greens beginning to germinate, the next visual transformation is about to begin. Starting Monday, fresh sod will begin arriving for installation around completed greens and bunker complexes. The sod team will move quickly across the completed areas, installing thousands of square feet of new bluegrass. This is one of those stages where the project can seemingly change overnight. Areas that have looked very much like a construction site for the past several weeks will suddenly begin looking like a golf course again. At the same time, the bunker crews will circle back to the remaining fairway bunkers on the front nine and continue preparing them for completion, while work progresses simultaneously on Nos. 4 and 7.
LOOKING AHEAD Losing nearly a full construction week to weather was certainly not part of the plan, but weather-related disruption was something we anticipated when establishing the project schedule and selecting our construction partner. KCM's ability to respond quickly — mobilizing people, equipment and expertise across multiple areas of the property — has allowed an enormous amount of work to be completed in a very short period following the storm. That capacity and experience were important considerations in selecting KCM for a project of this scale. There is plenty of work still ahead and Mother Nature will undoubtedly continue to have a say, but after a challenging week, it is great to report that PN25 is back on schedule and moving forward at full speed. We look forward to sharing another update with you next week.
SEPTEMBER 24 As Project Next 25 approaches the completion of its first major phase, progress across the front nine continues at a very strong pace. With KCM preparing to transition to the back nine beginning September 28, much of the work on the front nine is now approaching substantial completion. The transformation is becoming increasingly visible, and over the coming weeks the focus will begin shifting from construction toward establishment and grow-in. #4 Green – Taking Shape The rebuilt 4th green is now complete and seeded, with final grading of the surrounding areas also finished. The new bunker has been shaped, the Better Billy Bunker system installed, drainage completed and ProAngle bunker sand placed. Sodding of the entire new green complex is scheduled to take place early next week, which will complete one of the most significant transformations undertaken on the front nine.
#7 GREEN: RESPONDING TO WHAT WE FOUND BELOW THE SURFACE While progress across most of the front nine has been very smooth, #7 has provided a good example of the realities involved in a renovation of this scale. From the outset of demolition, the construction team encountered significantly wetter subsurface conditions than anticipated. Failed existing drainage, combined with #7's location at one of the lowest and wettest points on the golf course, had left the underlying soils heavily saturated. Before construction of the new green could proceed, KCM spent approximately two weeks methodically draining and stabilizing the site. Trenches approximately one metre deep were excavated at intervals across the green site and left open to allow the surrounding soils to dry before being collapsed and the process repeated. This cycle was completed five times before conditions were sufficiently stable to allow rough grading to proceed. The good news is that this work has been successful. The site is now stable, the subgrade has been completed and construction of the new green is moving forward. The conditions uncovered did, however, require two modifications to the original design. The finished grading of the green has been adjusted to direct water toward the front rather than maintaining a low drainage point at the back-left portion of the green.
The proposed bunker along the left side of #7 will also not be constructed. Once the area was excavated, it became clear that the saturated subsurface conditions at the required bunker depth would not support a Better Billy Bunker installation that could be expected to perform reliably over the long term.
Constructing the bunker under those conditions would have introduced unnecessary cost and additional delay while creating a significant risk of future liner movement and maintenance issues. Rather than force an element of the original design into unsuitable site conditions, KCM and Tom McBroom have adapted the design to the conditions actually encountered in the field. The priority is a stable, properly draining green complex that will perform successfully for many years. Situations like #7 are also an important reminder that even with extensive planning and design work, some conditions cannot be fully understood until the ground is opened and construction begins.
FRONT NINE GROW-IN
Elsewhere on the front nine, the focus is increasingly turning toward establishment and grow-in. Seven of the nine greens are now approaching the point where they will receive their first cut. The newly seeded approaches and bentgrass fall-off areas are progressing closely behind them, while bunker construction, drainage, grading and sodding continue throughout the front nine. The progress is particularly exciting to see from above, and we have included several recent photographs and drone flyovers showing the transformation taking place across the property.
NEXT UP: THE BACK NINE
Following the final day of back-nine golf on Sunday, September 27, KCM will transition to the back nine beginning Monday, September 28. The initial focus will be on the more remote green sites at #15, #16 and #13. This sequencing is intentional. By concentrating on these areas while fall weather and ground conditions remain favourable, KCM can complete as much work as possible in the portions of the property that are more difficult to access. KCM intends to continue advancing construction for as long as weather and ground conditions allow.
The window for successful seed establishment will begin to narrow shortly, but opportunities for sod installation and other construction activities can continue considerably longer, provided the ground remains workable and sod remains available from suppliers. Every productive construction day we gain this fall matters. The more work that can be completed before winter, the less construction remains for the spring and the more time renovated areas will have for establishment and grow-in ahead of reopening. As always, weather will ultimately determine how long that opportunity lasts. Our objective is therefore straightforward: make the most of every workable day we have this fall and put the project in the strongest possible position heading into winter. We look forward to sharing more progress as PN25 moves to the back nine.
OCTOBER 2 With the golf course now fully closed for the season, Project Next 25 has entered its next phase, with work underway on both the final areas of the front nine and the first group of holes on the back nine. Taking advantage of favourable weather and strong progress on the front nine, KCM was able to transition crews to the back nine three days earlier than originally planned. That additional construction time is valuable at this stage of the season, when every workable fall day matters.
FRONT NINE – NEARING SUBSTANTIAL COMPLETION With the exception of the 7th hole, the front nine has now reached substantial completion, with the focus increasingly shifting from construction to establishment and grow-in. Three truckloads of sod were delivered and installed this week around the newly completed work on holes #4, #5, #6 and #9. Additional sod is scheduled for next week around the remaining bunkers on #2 and throughout the newly reconstructed #7 green complex. The seeded greens and approaches continue to establish very well. An important milestone was reached earlier this week when the newly seeded greens received their first cut. While there is still a long way to go in the grow-in process, seeing turf established and mowed for the first time is another encouraging sign of the progress made over the past several weeks.
#7 GREEN – CONSTRUCTION COMPLETE AND SEEDED Following the challenging subsurface conditions encountered earlier in construction, significant progress has now been made on #7. The green has been shaped, drainage installed, greens mix placed and the new putting surface brought to final grade. The green has now been seeded, and our attention turns to establishment. At this point in the season, the germination window is beginning to narrow, so we will be relying on some cooperation from Mother Nature. Any establishment we can achieve this fall will provide a valuable head start heading into spring. Sod installation throughout the remainder of the #7 complex is scheduled for later next week.
BACK NINE – A DELIBERATE START Work on the back nine is initially concentrated in the far corner of the property around holes #12, #13, #15 and #16. This sequencing is intentional. These areas are the furthest from KCM’s staging area and among the more difficult locations to access, making it advantageous to tackle them while weather and ground conditions remain favourable. Just as importantly, KCM is being very deliberate about how much work is opened at one time. With colder and wetter weather inevitably approaching, the objective is to advance areas that can reasonably be brought to a stable point before winter rather than beginning work that may have to remain unfinished until spring.
Shaping, drainage, installation of the Better Billy Bunker system and sodding will continue for as long as weather and ground conditions permit. We are also planning to rebuild the Black and Gold tee complex on #2 this fall, should conditions allow. Rain brought construction to an early conclusion on Thursday, but we expect crews to be back in full swing on Monday.
TAKING ADVANTAGE OF THE CLOSURE
The full course closure has also provided Yanik and our Golf Course Maintenance team with a valuable opportunity to advance work beyond the PN25 construction itself. A significant amount of staff time is currently dedicated to watering and caring for newly seeded and sodded areas - an extremely important and time-consuming part of the grow-in process. When conditions and schedules permit, the team is also taking advantage of an empty golf course to complete cultural practices and other work that would be considerably more difficult during normal play. This has included dethatching and topdressing fairways and tees, tree and underbrush management, sightline improvements and a variety of other projects that would normally be reserved for the winter or worked around member play.
MAKING EVERY OCTOBER DAY COUNT
We are now entering the stage of the project where weather will increasingly dictate the pace and type of work that can be completed. The approach is therefore a measured one: continue moving aggressively while conditions are favourable, but avoid opening more work than can reasonably be completed and stabilized before winter arrives. The early transition to the back nine has given us several additional productive construction days, the front nine is approaching an important milestone, and growin is progressing well. There remains plenty of work ahead, but PN25 continues to move in a very positive direction as we make the most of the remaining fall construction window. Thank you and we look forward to sharing more exciting updates next week.
OCTOBER 9
FRONT NINE – SUBSTANTIAL COMPLETION We are pleased to report that construction on the front nine has reached substantial completion. All bunkers have been renovated and sodded, and the transformation is remarkable. The newly established bunker shapes and rolled edges have dramatically improved the appearance of the golf course, and we couldn't be more pleased with the results. The new bentgrass putting surface on #4 green, while slightly behind the others in its establishment, is progressing nicely. Meanwhile, #7 green was seeded just seven days ago, and with a little cooperation from Mother Nature, we hope to see the first signs of germination over the Thanksgiving long weekend. Our maintenance team has also begun the process of giving the new bunkers their first full rake. Yanik Mayer and Brad Miller have spent considerable time developing a consistent maintenance standard for the entire team. The new rolled bunker edges require a more detailed and deliberate approach to raking, and establishing these practices now will be essential to ensuring the bunkers look and perform as beautifully in the years ahead as they do today.
The only significant construction item remaining on the front nine is the new gold and black tee complex on #2. The timing of this work will be weather-dependent. KCM is understandably prioritizing progress on the back nine while favourable construction conditions continue. Should an appropriate window present itself later this month, the tees will be constructed and sodded this fall. Otherwise, this final component will be completed in spring 2027.
BEHIND THE SCENES – AN EXTRAORDINARY TEAM EFFORT While the construction progress is exciting, an equally important story is unfolding behind the scenes. Yanik and his small but dedicated maintenance team have been working from sunrise to sunset, seven days a week, to support the project. With acres of newly installed bluegrass sod and bentgrass seed requiring constant attention, irrigation has become an enormous undertaking. Much of this work has required painstaking hand-watering, particularly through the exceptionally dry conditions experienced throughout September and early October.
Their commitment to establishing these new playing surfaces is critical to the longterm success of PN25, and their dedication deserves special recognition and appreciation.
At the same time, the team has taken full advantage of the course closure to complete important maintenance work that would ordinarily be scheduled for November or carried out around member play. Fairways and tees have received aggressive thatch removal, topdressing and fertilizer applications, while additional property maintenance, tree work and sightline improvements are being completed throughout the golf course. This additional work will position the golf course exceptionally well heading into the 2027 season.
BACK NINE – CONSTRUCTION MOVING ALONG NICELY With the front nine substantially complete, construction activity has shifted to the back nine, where progress continues at an impressive pace. Greens #12, #13, #15 and #16 have been stripped, reshaped and seeded. Bunker construction on #13 and #15 is also well underway, with drainage and preparation for the Better Billy Bunker liner system progressing. These bunkers are expected to be ready for sand installation next week. Attention is now turning to greens #14 and #17, where stripping and preparation for reshaping and bunker renovation are underway. Members will be particularly interested in the improvements planned for #17. A new bunker is being introduced to the left side of the green, while the pronounced spine that has historically redirected otherwise excellent approach shots away from the putting surface is being softened.
Anyone who has played #17 knows that it is already one of the longest and most demanding holes on the property. Tom McBroom’s thoughtful adjustments are intended to make the green complex a little more receptive to well-executed shots while preserving the challenge and character of the hole.
MAKING THE MOST OF MOTHER NATURE We have been exceptionally fortunate with the weather this fall, and KCM and our maintenance team are making the most of every favourable day. However, as we move further into October, the construction window will inevitably begin to narrow. Shorter days mean fewer productive hours, and increasingly frequent frost delays can significantly affect construction activities. More importantly, colder temperatures slow or stop the germination and establishment of newly seeded putting surfaces. For now, the focus remains on maximizing progress while conditions permit, with the understanding that some work will ultimately need to carry over into spring 2027.
MEMBER TOURS Our PN25 construction tours are now underway and will continue through the end of October. These tours provide a unique opportunity to see the scale of the project, understand the construction techniques being employed and appreciate the extraordinary amount of work involved in rebuilding our golf course. If you haven't already registered, we encourage you to sign up and see firsthand how the transformation is taking shape.
LOOKING AHEAD Eight weeks into construction, we are extremely pleased with both the pace of progress and the quality of the work being delivered. The front nine has undergone a remarkable transformation, the back nine is advancing quickly, and the early results are providing an exciting glimpse of what awaits us in 2027. There is still plenty of work ahead, but with continued cooperation from Mother Nature, we intend to make every remaining day of the fall construction season count. Thank you for your continued enthusiasm, patience and support as Project Next 25 takes shape.
OCTOBER 16
With the front nine now complete, our attention has shifted to the continued establishment of newly seeded and sodded areas, while construction progresses on the back nine. On the front nine, our maintenance team is actively mowing, fertilizing and treating the new turf to encourage healthy establishment. The objective is to strengthen these young plants as much as possible before declining soil and air temperatures bring growth to a halt for the season. The work we do now will play an important role in helping the new turf withstand the winter months and emerge in good condition next spring.
PROGRESS ON THE BACK NINE The first four greens under renovation on the back nine — holes 12, 13, 15 and 16 — have now been stripped, shaped, prepared and seeded. We are beginning to see early germination on all four putting surfaces and, with some cooperation from Mother Nature, are hopeful that meaningful establishment will occur before winter arrives.
As previously communicated, some subtle adjustments have been made to the front third of the 16th green. These changes are intended to soften the severity of this portion of the putting surface and create additional hole locations while maintaining the character and challenge of the green. Bunker construction is also advancing. Eight bunkers in the back corner of the property have now been bagged, drained and lined with stone. The next steps involve application of the polymer liner, followed by installation of the new Pro/Angle bunker sand. With work progressing well on these initial holes, KCM has moved on to holes 14 and 17.
On the 14th, subtle adjustments to the right side of the putting surface will reduce some of its severity and create additional hole locations without compromising the strategic challenge. The greenside bunkering is also being redesigned. While the overall area of sand will be reduced, the existing two larger bunkers will be replaced by three smaller ones. It's a relatively modest change that should add visual interest and another layer of strategy to an already interesting short par four. On the 17th hole, the originally proposed greenside bunker will be replaced with a grassy hollow to improve sightlines and better accommodate the available space. Minor adjustments to the approach will also make the hole slightly more forgiving while preserving its overall challenge.
MAKING THE MOST OF THE REMAINING SEASON As we move further into October, our approach to construction becomes increasingly deliberate. With the uncertainty of late October and early November weather, we are being careful not to begin more work than we can reasonably expect to complete before winter conditions arrive. Opening up too many areas at once could leave unfinished work exposed over the winter and create unnecessary delays next spring, when every productive day will be particularly valuable.
This past week was shortened by the Thanksgiving holiday, today’s rain and the steadily decreasing daylight hours. Although we enjoyed a welcome stretch of summer-like weather earlier in the week, the reality is that our remaining productive construction days are numbered.
From this point forward, we consider each additional day of favourable weather a bonus. Every task completed before winter puts us in a stronger position when construction resumes in the spring and we begin the final push toward completion. One of the advantages of having an experienced contractor like KCM, working alongside our dedicated maintenance team, is their ability to adapt quickly to changing conditions. When the weather cooperates, we are well positioned to take full advantage of it.
NO GOOD WEATHER DAYS ARE BEING WASTED, AND EVERY DAY OF PROGRESS NOW IS ONE LESS DAY OF WORK NEXT SPRING. As always, we appreciate the continued support, patience and enthusiasm of our membership as we work toward delivering a golf course we can all look forward to enjoying for many years to come.
OCTOBER 23 Work continues to progress well on the back nine, with KCM advancing bunker construction, drainage and turf preparation throughout the week. Drainage, bunker bag installation, liner preparation and polymer application are underway on holes 12, 13, 14 and 17. Sand installation is also progressing in several bunkers, including those on holes 13, 15 and 16.
The greens on holes 12, 13, 15 and 16 have now been seeded and covered with protective tarps. These covers help retain warmth and create more favourable growing conditions as temperatures begin to cool and sunlight diminishes. Sod installation originally scheduled for this week has been pushed to Monday. Weather permitting, holes 12, 13, 15, and 16 are scheduled to receive sod next week, with holes 14 and 17 expected to follow the week after.
NEW TEES ON HOLE 2 KCM has also begun earthmoving and shaping the new black and gold tee decks on hole 2. This is one of the more exciting design improvements included in PN25. The elevated teeing areas will provide spectacular views across the wetlands and create what we expect will be two of the most impressive and intimidating tee shots on the property, particularly from the back tees.
LOOKING AHEAD Once construction on holes 12 through 17 is substantially complete, attention will shift toward finishing the new tees on hole 2 and beginning work on hole 18. Depending on weather conditions, there is an opportunity to complete hole 18 before winter. At this stage, we do not anticipate beginning significant construction work on holes 10 and 11 until early spring 2027, unless November delivers an unusually favourable stretch of weather.
CONSTRUCTION PROGRESS VS. REOPENING While construction has progressed exceptionally well, it is important to distinguish between the completion of construction activities and the golf course being ready for member play. Our anticipated reopening dates remain unchanged: June 1, 2027, for the front nine and July 1, 2027, for the back nine. These dates remain our targets, subject to favourable growing conditions and successful turf establishment. Newly seeded bentgrass greens require sufficient time to establish, develop healthy root systems and mature before they can withstand regular maintenance and member traffic. This process cannot be rushed, regardless of how quickly construction progresses. We currently anticipate that KCM will complete its remaining construction activities and demobilize from the property by mid-June 2027. This construction timeline is separate from our reopening schedule. The front nine is expected to be ready for play before KCM completes its work elsewhere on the property, while the back nine will require additional time for turf establishment following construction.
Ultimately, the readiness and condition of the putting surfaces will determine when each nine opens, not the date construction is completed. We will continue to monitor growing conditions and turf development throughout the spring and will not compromise the long-term success of the renovation simply to accelerate reopening. Thank you for your continued patience and support. We are very pleased with the progress to date and look forward to sharing further updates as the project continues.
OCTOBER 30
As we approach the end of October, Project Next 25 continues to make exceptional progress. An extended stretch of favourable weather, combined with the resources and capabilities of KCM Construction, has allowed us to advance considerably further than anticipated at this stage of the project. This week, there are two significant developments worth highlighting.
HOLE #2 – NEW BLACK AND GOLD TEE COMPLEX Construction of the new black and gold tee complex on hole #2 is progressing very well, with rough grading now complete. Tom McBroom was on site Tuesday to review the positioning and design of the new tee decks.
The improvements to the gold tees are significant. By elevating the tee decks approximately five feet and shifting them slightly to the south, we have dramatically improved the sightlines, opened up views of the fairway and created a more favourable angle of play. Perhaps the most exciting improvement, however, is the new black tee. By shifting the tee deck south into the natural hillside behind the first green and fifth black tee, we have gained approximately 15 feet of additional elevation without increasing the overall yardage of the hole. The result is a spectacular, elevated view of the fairway and what I believe will become one of the finest tee shots on the property.
An additional consideration in the design was ensuring that the elevation and alignment of the new black tee would preserve the option to lengthen hole #5 in the future, should the Club ever wish to explore that opportunity. Our goal is to complete the entire tee complex, including sodding, before November 15, when we anticipate sod harvesting will conclude for the season.
GREENS #10, #11 AND #18 – A CHANGE IN PLANS In last week's update, I indicated that the remaining three putting surfaces on holes #10, #11 and #18 would be left until spring 2027. Following further review and discussion with the project team, we have decided to take advantage of the exceptional fall conditions and proceed with stripping, grading and seeding these greens before the end of the 2026 construction season. This is an opportunistic decision intended to maximize our growing season in 2027.
By completing the preparation and dormant seeding this fall, we create the opportunity for what I refer to as passive germination next spring. Should we experience an early snowmelt in March and favourable temperatures in April, these greens will be positioned to begin germinating naturally, without waiting for KCM to remobilize and complete the work.
PROGRESS ACROSS THE BACK NINE Work continues throughout the remainder of the golf course, with Better Billy Bunker liner installation, bunker finishing and sodding progressing simultaneously. Holes #12, #13, #15 and #16 are all in various stages of completion, with the expectation that much of the remaining work will be wrapped up following the next sod delivery early next week. Greens #14 and #17 have been shaped and prepped for seed, with surrounding areas being prepared for sodding in the coming weeks. The volume of work being completed across multiple holes simultaneously continues to demonstrate the depth of KCM's resources and the efficiency of their operation.
LOOKING AHEAD When we developed the PN25 construction schedule, we considered virtually every scenario that could negatively affect progress: poor weather, material shortages, delivery challenges and unforeseen interruptions. What we did not anticipate was one of the most favourable stretches of fall construction weather imaginable. We have experienced virtually no rainfall since September 2, providing conditions that have allowed the project team to maintain an extraordinary pace.
We are now in the fortunate position of reassessing how much additional work can reasonably be completed before winter. Our approach remains measured. We are taking things one day at a time, balancing the opportunity to advance construction with the reality that the season will eventually come to an end. We do not want to become overly ambitious at the expense of quality, but neither do we want to waste an opportunity that may not come along again. As we approach November, the project is substantially further advanced than even my most optimistic expectations for the end of the 2026 construction season.
From the outset of PN25, our planned reopening dates have been June 1 and July 1, 2027. Those dates have not changed. While there remains considerable work ahead, particularly the establishment and maturation of the new putting surfaces, the progress achieved this fall has significantly improved our position heading into next spring.
We are not taking anything for granted. Weather and growing conditions will ultimately play an important role in determining our readiness. However, every additional day of construction completed this fall translates into more time for turf establishment and preparation next year. I am more encouraged today about our ability to meet those original reopening dates than at any previous point in the project. After years of planning and preparation, it is tremendously rewarding to see the project progressing so well.
NOVEMBER 6 PLANNING FOR THE UNEXPECTED When we first began discussing Project Next 25 with the membership back in 2023, there were understandably plenty of questions and concerns surrounding an undertaking of this magnitude. Was the budget realistic? Could the construction schedule be achieved? What challenges might emerge along the way? And perhaps most importantly, how could we prepare for the unexpected? These were all fair questions, and ones we took very seriously. Over the past three years, an extraordinary amount of time and effort has gone into planning, preparing and anticipating the challenges associated with a project of this scale. We considered everything from tariffs, rising fuel costs, and labour shortages to supply chain disruptions, extreme weather, early snowfall and broader economic and geopolitical uncertainty. Our approach was deliberate. We planned for the worst-case scenarios and worked backwards, building contingencies and flexibility into the project wherever possible. The objective was to avoid surprises, minimize unnecessary risk and position the Club to respond effectively when circumstances inevitably changed. As someone who appreciates a good plan, I find considerable comfort in knowing what comes next. I much prefer executing a carefully considered strategy over reacting to unexpected circumstances and scrambling to catch up. And yet, here we are, nearly twelve weeks into construction, dealing with the one scenario we apparently didn't spend nearly enough time preparing for.
WHAT HAPPENS WHEN EVERYTHING GOES BETTER THAN EXPECTED? Since the extraordinary rainstorm on September 2, we have experienced an almost uninterrupted stretch of exceptionally favourable construction weather. What began as a welcome opportunity to make up ground has evolved into something none of us could reasonably have anticipated. The weather has been remarkable. The construction progress has been equally remarkable. In fact, since the middle of October, our weekly project meetings have included a familiar exercise: reviewing completed work, assessing construction costs, and forecasting how much more we might reasonably accomplish before Mother Nature brings the season to an end. And every week, we underestimate just how much more can be achieved. Areas we had conservatively expected to leave until spring are now receiving attention. Work that once appeared unlikely to be completed before winter is suddenly within reach. Rather than managing delays, we find ourselves working to take advantage of opportunities we hadn't expected to have. It's a wonderful position to be in, although I must admit we're becoming a little greedy!
CONSTRUCTION PROGRESS AND THE WEEK AHEAD This week has been focused largely on preparation, positioning several important areas for what we hope will be another productive stretch of construction. Holes 10, 11, and 18 are now receiving attention, with greens being stripped and graded in preparation for dormant seeding early next week. Meanwhile, holes 12 through 17 are approaching a significant milestone. We have three major days of sod installation scheduled for next week, weather permitting. If conditions cooperate, we expect these six holes to be substantially completed by the end of the week, including greens, bunkers, ProAngle bunker sand and surrounding sod. On the front nine, the transformation of the second-hole tee complex continues to impress. The new tees have been shaped and graded and are ready for a substantial amount of sod. The question now is whether the weather will cooperate long enough to accommodate one more sod delivery and allow us to finish this remarkable improvement before winter. If it does, fantastic. If not, the remaining work can comfortably wait until spring. Completing the area this fall would be a bonus rather than a necessity. At this point, we're simply trying to make the most of every opportunity the weather provides.
A LITTLE SCIENCE: WHY WE CAN'T RUSH MOTHER NATURE One important distinction is worth reinforcing as we continue to enjoy this extraordinary construction progress. While favourable weather has allowed us to accomplish significantly more physical work than anticipated, there is one critical element of the growing environment that we cannot control: sunlight. As we move deeper into November, daylight hours continue to shorten, the sun sits lower in the sky and the amount of energy available to support turfgrass growth diminishes considerably.
Even with relatively warm temperatures, the putting surfaces seeded earlier this fall have now reached a point where meaningful additional establishment is extremely limited. The grass we have today is, for practical purposes, what we will carry into the spring of 2027. The greens scheduled for dormant seeding next week represent a slightly different approach. Dormant seeding involves placing seed into prepared soil when conditions are no longer favourable for germination. The objective is for that seed to remain in place through the winter and begin germinating naturally when soil temperatures and growing conditions become suitable in the spring. It is an established turfgrass management technique, but like all seeding practices, its success depends on weather, moisture, seedbed conditions and the arrival of favourable growing temperatures. In other words, we can prepare the growing environment, install the seed and position ourselves for success, but we cannot manufacture the growing season. And no amount of beautiful November weather can replace the longer days, stronger sunlight and sustained growing conditions that spring will provide.
WHAT THIS MEANS FOR 2027 This brings us to perhaps the most important message of this week's update. Our extraordinary construction progress does not mean we are changing our targeted opening dates of June 1 and July 1, 2027. I appreciate that this may seem counterintuitive. If we're accomplishing so much more than anticipated, why wouldn't we open earlier? The answer is straightforward.
Project Next 25 is not simply a construction project. It is a comprehensive reinvestment in the long-term quality, performance and sustainability of our golf course. Completing the physical construction is only one part of that undertaking. Establishing healthy, mature putting surfaces and preparing the entire property to deliver the experience our members expect is equally important. When we developed our original construction scenarios, we recognized the very real possibility that some work could extend well into the 2027 season, potentially continuing even after the full golf course reopened in July. Thanks to the remarkable progress achieved this fall, we are now in a position where much of that anticipated spring construction work may already be behind us. That is an enormous advantage. Rather than dividing our attention between ongoing construction, turf establishment and preparing the golf course for member play, we expect to be able to devote considerably more of our spring resources to growing grass, refining the finished surfaces, completing details and preparing the property for reopening. The benefit of finishing more work this fall is not necessarily opening sooner. It is opening better. That distinction is important. We are making an investment intended to serve Granite Golf Club for the next 25 years and beyond. Decisions surrounding turf establishment, course conditioning and opening dates must reflect that long-term responsibility. We have come too far, invested too much and worked too hard to compromise the finished product for the sake of gaining a few weeks on the calendar. There will undoubtedly be tremendous excitement surrounding the reopening of the golf course next year, and rightly so. But our responsibility is to ensure that when members return, they experience a property that reflects the full ambition of Project Next 25. We will not rush that process simply because the construction schedule has exceeded expectations.
LOOKING AHEAD As we enter what will inevitably be the final stretch of the 2026 construction season, I continue to be impressed by the coordination, commitment and professionalism demonstrated by everyone involved in this project. What began with years of planning, countless meetings, difficult decisions and a healthy appreciation for everything that could possibly go wrong has brought us to a point where we're now wondering just how much more might go right. It's a rather wonderful problem to have. We will continue to take advantage of favourable conditions for as long as they last, while remaining disciplined in our planning, oversight and decision-making. Mother Nature will eventually have the final word on when construction concludes for the season. Until then, we'll keep working. And perhaps, just perhaps, we'll squeeze one more remarkable week out of 2026.
NOVEMBER 13 As we approach the middle of November, construction activity on Project Next 25 has slowed considerably as seasonal weather conditions begin to dictate what can realistically be accomplished before winter. With shorter days, diminishing daylight, overnight frost and freezing temperatures becoming increasingly common, we have reached a point where further progress will depend almost entirely on a favourable break in the weather. Construction activities are temporarily paused, and while there remains a possibility of completing some additional work, we are also realistic about the challenges of continuing this late into the season.
One of our remaining objectives is to complete the sodding of the new tee complex on Hole #2. Should conditions improve and a suitable opportunity present itself, we may be able to bring the sod installation crew back for one final push. At this stage, however, we are not counting on that opportunity and are preparing for the possibility that meaningful construction activity may be finished for 2026.
Regardless of what the coming days bring, we could not be more pleased with the progress achieved to date.
In less than three months since construction began on August 17, an extraordinary amount of work has been completed. The pace of construction, quality of workmanship, and coordination between our project partners have exceeded expectations and placed us in an excellent position heading into the final stages of the project in 2027. Most importantly, Project Next 25 remains on track for completion on schedule and within budget. The work accomplished this fall provides a tremendous foundation for the remaining construction and grow-in activities next spring. As construction winds down, our communications will naturally reflect the level of activity taking place on the property. We will continue to provide updates through our regular member communications and Instagram, sharing meaningful developments as they occur and keeping everyone informed as we prepare for the next phase of the project. After nearly three months of remarkable activity and progress, a quieter period is certainly well deserved. Our project team will be ready to resume work as soon as conditions permit in the spring of 2027. Of course, we haven't completely given up hope that Mother Nature might have one last favourable window in store for us this fall. If she does, we'll certainly be ready to take advantage of it! Thank you for your continued patience, enthusiasm, and support as we work toward an exciting new chapter for Granite Golf Club.
NOVEMBER 23
With construction activities now concluded for 2026, we are pleased to share one final Project Next 25 update as we head into the winter months. What an extraordinary first construction season it has been! Since work began on August 17, favourable weather conditions, excellent coordination among our project partners, and the dedication of our staff have allowed us to accomplish considerably more than originally anticipated. As we close out the year, approximately 80% of the golf course construction work is complete, putting us significantly ahead of where we expected to be at this stage of the project. Much of the work originally anticipated for spring 2027 has already been completed, including substantial progress across the back nine. This has positioned us exceptionally well heading into the winter and provides greater flexibility as we prepare for the final stages of construction next spring.
We are equally encouraged by the project's financial position. While final quantities, costs, and outstanding work remain subject to reconciliation, we remain optimistic about completing the project within the approved budget.
LOOKING AHEAD TO SPRING 2027
Although we have accomplished a tremendous amount, important work remains before the golf course is ready to welcome members back. When construction resumes in the spring, our priorities will include: Completing the remaining sodding and landscape restoration on holes 12 through 17. Completing construction and restoration of the final three green sites. Constructing the remaining 11 bunkers. Completing the Short Game Academy (SGA), including the putting green located south of the clubhouse. Completing final grading, landscaping, and other finishing work throughout the golf course.
REOPENING OUTLOOK
Our anticipated reopening dates remain unchanged: June 1, 2027 – Target reopening of nine holes July 1, 2027 – Target reopening of the full 18-hole golf course
Based on our progress to date, we believe these remain achievable targets. That said, it is important to recognize that construction completion and golf course readiness are two different things. The successful establishment of newly seeded greens, recovery of existing turf, and completion of remaining landscape restoration will depend heavily on spring weather and growing conditions. Mother Nature will ultimately determine when the golf course is ready for play. While we are optimistic, we will continue to assess conditions carefully throughout the spring and will not compromise the long-term health and quality of the golf course simply to meet a calendar date.
WINTER ACCESS TO THE GOLF COURSE We recognize that many members enjoy walking the golf course with their dogs during the winter months and appreciate that this has become a valued seasonal activity. Unfortunately, the golf course will remain closed to all member access, including winter dog walking, throughout the upcoming winter. Although construction activities have concluded for the year, the property remains an unfinished construction site. Open trenches, incomplete work areas, newly installed sod, and recently seeded greens present both safety concerns and a significant risk of damage to the work completed this fall. In particular, newly established turf areas will be especially vulnerable throughout the winter and during the spring thaw.
We appreciate that this restriction will be disappointing to members who enjoy winter access. However, protecting the significant investment made in the golf course, while ensuring the safety of our members, must remain our priorities. We sincerely appreciate your understanding and cooperation.
Thank You As we conclude the 2026 construction season, I would like to acknowledge the outstanding efforts of KCM Construction, golf course architect Tom McBroom, our project consultants, and our own golf course maintenance team.
Their collaboration, professionalism, and commitment have been instrumental in achieving the remarkable progress made over the past fourteen weeks. I would also like to thank our members for their patience, encouragement, and support throughout what has been an unconventional but incredibly productive year at Granite Golf Club. There is still important work ahead, but we have every reason to be excited about what awaits us in 2027. We look forward to sharing further updates when construction resumes in the spring and, most importantly, to welcoming everyone back to a revitalized Granite Golf Club. Thank you again for your continued support.