PN25 Update

Page 1


Prepared For : Committees

R

J E C T N E X T 2 5 N o t f o r c i r c u l a t i o n

U P D A T E

P R O J E C T

A S S U M P T I O N S

March 1, 2026 - final pricing expected (6-months prior to project commencement).

Stockpile of topsoil and clean fill at maintenance facility (fall 2025).

Staging of materials and supplies in staff parking lot (spring 2026)

Total number of KCM labourers 25-30.

*All dates are subject to change. Weather conditions will dictate progress.

*Tee times, rounds per day may be limited depending on strength of newly established turf

*Temporary greens may be necessary during phase one of opening

*Spikeless shoes may be mandatory during phase one of opening

August 2026

Week 1

Aug 3-7

Week 2

Aug 10-14

Week 3

Aug 17-21

Week 4

Aug 24-28

Week 1

Aug 31-Sept 4

Week 2

Sept 7-11

Week 3

Sept 14-18

Week 4

Sept 21-25

Week 5

Sept 28-Oct 2

Play as Usual KCM mobilizes

Play as Usual KCM mobilizes

Construction fence installed

Front 9 closed for member access. Work begins on front 9 greens resurfacing. Work begins on green rebuilds - #4, #7, #8

Work begins on front 9 bunker renovation.

September 2026

All Front 9 greens seeded.

Excavation and shaping of #4 green complete. Grading, seed and sod commence.

Bunker liner install begins followed by bunker sand/sod install on first bunkers.

Excavation and shaping of #4, #7 and #8 complete Grading, seeding sodding commence

Work begins on rebuild of #2 gold and black tees (sightline improvement)

Front 9 seeded greens are beginning to grow

Sand installation begins on front 9 bunkers and sodding continues

Front 9 substantial completion as early as September 25th, pending favorable weather.

Bunker sand and sod install nearing completion on front 9.

Week 1

Oct 5-9

Week 2

Oct 12-16

Week 3

Oct 19-23

Week 4

Oct 26-30

October 2026

Back 9 closed.

Back 9 greens resurface begins.

Shaping and grading of #2 tee complex compete, sodding begins.

First cut on front 9 greens.

Back 9 bunker renovation begins

Primarily stripping and removal of existing greens surfaces, coring of old bunker sand and liner

Stockpiling clean fill for later use

Grading of greens surfaces, seeding begins on first greens. Drainage inspection/bunker liner install begins.

Final grading of remaining greens on back 9

Seeding will be suspended at this stage due to temperature/sunlight

November 2026

Bunker, earth moving, and sodding will continue until freeze up

April 2027

Week 1

Apr 5-9

Week 2

Apr 12-16

Week 3

Apr 19-23

Week 4

Apr 26-30

KCM back on site to remobilize

Work continues on greens and bunkers on the back 9

Getting newly seeded front 9 greens established and ready for play

Work continues on greens and bunkers on the back 9

Repairing front 9 haul roads with soil and sod.

Week 1

May 3-7

Week 2

May 10-14

Week 3

May 17-21

Week 4

May 24-28

Week 1

May 31-Jun 4

Week 2

Jun 7-11

Week 3

Jun 14-18

Week 4

Jun 21-25

Week 5

Jun 28-Jul 2

May 2027

First cut on back 9 greens

Work continues on back 9 bunkers

Work continues on back 9 bunkers

Front 9 opens for play

Decision will be made on possible temporary greens, or other aforementioned restrictions

June 2027

Finishing back 9 bunker renovation.

SGA and Short Course closes for greens and bunker renovation. Repairing back 9 haul roads.

Work continues on SGA and Short Course.

Work continues on SGA and Short Course

Substantial completion

Full course open for member play

Primary

Bunkers-35%Shrinkage Sodremovals.

Oldbunkersandremoval

Topsoilstripandstorelocally

Bunkerreductions,splitting,new,add-ins,and shaping.

Overexcavate50mminexistingbunkersforBetter BillyBunkergravel

Olddrainageremovalandoff-sitedisposal.

Buildburlapbagperimeter.

Installnewdrainage-bunkerinterior

Finegradebunkerbasin

InstallBetterBillyBunkergravel-50mm.

InstallBetterBillyBunkerpolymerandquality controlcheck

Installbunkersand

Import,place,andfinegradescreenedtopsoilfor finishing

Haulroadrepair-grade,topsoil,andsod

SeedBentgrassapronexpansions

PlaceBluegrasssod.

PlaceFescuesod

GreensResurfacing

Surveyexistinggreenssurfaces

Excavategreensurfaces-50mm

Stripsurroundsandapproaches-Bluegrassand Bent

Supplyandplaceimportedgreenssandmix50mm

Re-surveysurfaces.

Finegradegreenssurface

Minormachinegradinggreensexterior

Finegradinggreenssurroundsincludingimported screenedtopsoil.

Seedgreensurfacesandapproaches-Bentgrass

SodBluegrasssurrounds #7Greenrebuilt.

Secondary

Greens Construction - #4 & 8

Sod strip, remove, and dispose - Bluegrass and Bentgrass

Remove existing greens mix and stockpile locally

Remove existing drainage and dispose offsite

Bulk earthworks

Shaping

Supply and install greens barrier

Drainage interior

Exterior outlet drainage

Install 80/20 greens sand mix

Irrigation installation

Import, place, and fine grade topsoil.

Fine grade green surfaces and surrounds.

Seed greens and approaches to Bentgrass.

Supply and install Bluegrass.

#2 Tee Complex

Strip and remove existing sod.

Strip existing topsoil.

Bulk earthworks

Shaping

Fine grade tee basins

Supply and install tees mix

Re-topsoil

Fine grade tee surfaces

Irrigation installation

Fine grading greens surrounds including imported screened topsoil

Bentgrass seed tees

Bluegrass sod surrounds

Total cost of Project - $4-million

Cost of Bunkers -~$2.5 million

Cost of Greens < $1 million

10% contingency

P N 2 5 : C O S T

B R E A K D O W N

Labour

Other

52%oftotalcostislabour

P N 2 5 : B U N K E R

C O M P O N E N T

Labour

Sand & Liner

Sod, Soil, Misc.

P N 2 5 : G R E E N S

C O M P O N E N T

Labour

Materials