STATUS REPORT

TA 2026

OCTOBER

2025

164

DAYS TO TA 2026

ACTIVITY STATUS

Completed Activities:

Turnaround Notification Cut-off date announced as 14th October 2025

Trade Test of local Manpower has been started

Started conducting Kick-off Meeting with Manpower and Equipment Suppliers

Started conducting Kick-off Meeting with Package Contractors

TA 2026 Temporary Site Facilities/Plot Plan is currently under review

Ongoing Activities:

Major Jobs Presentations Round#1 by Area Leaders.

TA Job list Review Meetings are in progress

Issuance of seconded manpower list

Issuance of Organization Charts (Technicians Level)

Delivery of Capex Items are in progress

Started Unblocking of Stock Materials.

Turnaround CM order assessment is in progress: 98% completed

Material reservation for PM orders and CM orders is in progress: 99% and 94% completed respectively

ACTIVITY STATUS

ROADMAP S-CURVE

Planned

Completed

Slippage

CM MATERIAL STATUS

Pending CM Material Reservation (No. of WOs)

PM MATERIAL STATUS

Pending PM Material Reservations (No. of WOs)

PR STATUS

REFURBISHMENT STATUS

Issued PO Status:

TA AUDIT REPORT

Total of 9 Audits Conducted till October 2025 on turnaround planning department by TAT (Turnaround Audit team)

CAPEX PROJECTS TIMELINE

HIMA ESD System* PO Incl FSE (Material Received)

42 Fans for Air Cooler ** PO Incl FSE (Material Received)

LV-08009** Routine (Material Received)

33kV SWBD 61MS5-1** PO Includes FSE (Material Received)

Methanol PG Cooler E-1201** PR#7236 (AC) (Material Received)

December

January

February

April

Electronic Governor MT-0701 & MT-1401* PO Includes FSE (Material Received)

PSV-5253****, In-House Installation

HV-82009 ** Inhouse Installation

E-0003** PR#7216 (AC)

E-8601 E-8602A/B/C

E-8604*, E-0704*, Inhouse Installation

Honeywell DCS* PO Includes FSE

Orion Auxiliary Console *

MCR UPS**

D-1501** Inhouse Installation, E-0001B**PR#7216 (AC) (Material Received)

Ammonia PG Cooler E-0301** PR#7241 (AC)

Super Cup Trays R8201** PR#7244 (TE)

PV-52201/351 & PV-52401/402* In-House Installation

HSV-52236 & HSV52336 * , Inhouse Installation

Urea ESD**** ENG PR Includes FSE

MD-6102 PLC* PR Includes FSE

Trip Solenoid for Synth & Mug Turbines*** PR Includes FSE

B-5203 ESD ****

LV-82011, HV-82005, HV-82008 ** Inhouse Installation

Urea 2200 MTPD - MOV82003**** In-House Installation

Urea Stripper E-8201** PR#7244 (AO)

HP Carbamate Seperator D-8201** PR#7244(TE)

Passivation Air Compressor** PO Includes FSE

CONFIRMED MAJOR JOBS

Ammonia Plant

CONFIRMED MAJOR JOBS

Methanol Plant

CONFIRMED MAJOR JOBS

Urea Plant

Utilites Plant

Major Jobs Presentation by Maintenance Area leaders

Kick-off Meeting With Ramsis Team for the Replacement of Methanol PG

Cooler (E-1201)

Kick-off Meeting With JACR Team for the Catalyst Replacement/Skimming Project

Meeting with Baker Hughes for Gas Turbine Shutdown

Trade Testing of Electrical Local Manpower for TA2026