STATUS REPORT
TA 2026
OCTOBER
2025
164
DAYS TO TA 2026


ACTIVITY STATUS
Completed Activities:
Turnaround Notification Cut-off date announced as 14th October 2025
Trade Test of local Manpower has been started
Started conducting Kick-off Meeting with Manpower and Equipment Suppliers
Started conducting Kick-off Meeting with Package Contractors
TA 2026 Temporary Site Facilities/Plot Plan is currently under review
Ongoing Activities:
Major Jobs Presentations Round#1 by Area Leaders.
TA Job list Review Meetings are in progress
Issuance of seconded manpower list
Issuance of Organization Charts (Technicians Level)
Delivery of Capex Items are in progress
Started Unblocking of Stock Materials.
Turnaround CM order assessment is in progress: 98% completed
Material reservation for PM orders and CM orders is in progress: 99% and 94% completed respectively

ACTIVITY STATUS

ROADMAP S-CURVE
Planned
Completed
Slippage
CM MATERIAL STATUS
Pending CM Material Reservation (No. of WOs)
PM MATERIAL STATUS
Pending PM Material Reservations (No. of WOs)
PR STATUS
REFURBISHMENT STATUS
Issued PO Status:
TA AUDIT REPORT
Total of 9 Audits Conducted till October 2025 on turnaround planning department by TAT (Turnaround Audit team)
CAPEX PROJECTS TIMELINE
HIMA ESD System* PO Incl FSE (Material Received)
42 Fans for Air Cooler ** PO Incl FSE (Material Received)
LV-08009** Routine (Material Received)
33kV SWBD 61MS5-1** PO Includes FSE (Material Received)
Methanol PG Cooler E-1201** PR#7236 (AC) (Material Received)
December
January
February
April
Electronic Governor MT-0701 & MT-1401* PO Includes FSE (Material Received)
PSV-5253****, In-House Installation
HV-82009 ** Inhouse Installation
E-0003** PR#7216 (AC)
E-8601 E-8602A/B/C
E-8604*, E-0704*, Inhouse Installation
Honeywell DCS* PO Includes FSE
Orion Auxiliary Console *
MCR UPS**
D-1501** Inhouse Installation, E-0001B**PR#7216 (AC) (Material Received)
Ammonia PG Cooler E-0301** PR#7241 (AC)
Super Cup Trays R8201** PR#7244 (TE)
PV-52201/351 & PV-52401/402* In-House Installation
HSV-52236 & HSV52336 * , Inhouse Installation
Urea ESD**** ENG PR Includes FSE
MD-6102 PLC* PR Includes FSE
Trip Solenoid for Synth & Mug Turbines*** PR Includes FSE
B-5203 ESD ****
LV-82011, HV-82005, HV-82008 ** Inhouse Installation
Urea 2200 MTPD - MOV82003**** In-House Installation
Urea Stripper E-8201** PR#7244 (AO)
HP Carbamate Seperator D-8201** PR#7244(TE)
Passivation Air Compressor** PO Includes FSE
CONFIRMED MAJOR JOBS
Ammonia Plant
CONFIRMED MAJOR JOBS
Methanol Plant
CONFIRMED MAJOR JOBS
Urea Plant
Utilites Plant
Major Jobs Presentation by Maintenance Area leaders


Kick-off Meeting With Ramsis Team for the Replacement of Methanol PG
Cooler (E-1201)


Kick-off Meeting With JACR Team for the Catalyst Replacement/Skimming Project


Meeting with Baker Hughes for Gas Turbine Shutdown

Trade Testing of Electrical Local Manpower for TA2026