TA2025-Monthly Report for July 2025

Page 1


STATUS REPORT

TA 2026

JULY

2025

DAYS TO TA 2025*

*BASED ON NOVEMBER 2025

KEY HIGHLIGHTS:

TURNAROUND ROADMAP ALONG WITH THE PROGRESS CALCULATIONS ARE FOCUSING ON THE TARGET OF NOVEMBER 2025. CONDUCTED MEETING WITH TAT TEAM, TRT TEAM, PROCUREMENT AND WAREHOUSING TEAM AND SHE TEAM.

TA MODIFICATION & CAPEX DASHBOARD

TA PR DASHBOARD

TA MAINTENANCE WORK ORDER DASHBOARD

ACTIVITY STATUS

Completed Activities:

Issuance of Job list (Rev-08)

Completed Combined Meeting Presentations #7

Issuance of TA Readiness Assessment #04

Conducted Audit #09

Conducted Meeting with Procurement & WH#9

Started Job list discussion 2nd Round

Started Meeting: Mods & Capex 2nd Round

Conducted Meeting with SHE Department

Ongoing Activities:

Blocking of Stock Materials is in progress 92% completed

Detailed assessment for Critical/Major Jobs is in progress

Delivery of Capex Items are in progress.

Technical evaluation & issuance of final recommendation memos for manpower/ equipment/ packages and Vendors are in progress

Material reservation for PM orders and CM orders is in progress: 98% and 93% completed respectively

Turnaround CM order assessment is in progress: 96% completed

TA Job list Review Meetings are in progress

ACTIVITY STATUS

PlannedActivities-August2025:

OrganizationCharts(TechniciansLevel)

ListforAdditionalRadios

StartIssuanceofGPRs[LogesticsPart]

Pre-TARotaryEquipmentJobs

IssuanceofJoblist(Rev-09)

CombinedMeetingPresentations#8

MeetingwithP&WH#10

Concerns:

DelayinthedeliveryofnewUreaStripper

ROADMAP S-CURVE

CauseofSlippage:

Final recommendation for Package Contracts: 40/43 issued

Final recommendation for Vendor Services: 38/40 issued

Issuance of POs for Manpower and Equipment:

Issuance of Package Contracts Services

Issuance of POs for Vendor Services:

Meeting with ITDK

Finalize Seconded Manpower List

Issuance of Area Leader List (Final)

Issuance of Organization Charts (AL Level)

The commencement of the following milestones is deferred due to the rescheduling of the TA to summer 2026, situationwillbemuchclearerinSeptember2025

Confirmation to Contractors for Job Start date/Mobilization Date

Document Submission by Contractor for all type of services

Start Trade Testing of Overseas Manpower

Communicate with Contractors (Logistics)

Start Gate Passes Processing & Visas for Vendors & Contractors

Cut-off Date for MWOs & MODs Kick-off

CM MATERIAL STATUS

Major Rotary Reservation Status

98%

Minor Rotary Reservation Status

96%

PR STATUS

ActionPlan:

FinalizetheissuanceofremainingPOsforSparePartsInspection

ExpediteissuanceofPOsforDirectManpower&EquipmentHiring

ExpediteBudgetAllocationfor7PRs(1Manpower,6Packagecontracts)

TA AUDIT REPORT

2 0 2 4 2 0 2 5

CAPEX PROJECTS TIMELINE

HIMA ESD System* PO Incl FSE (Material Received)

42 Fans for Air Cooler ** PO Incl FSE (Material Received)

LV-08009** Routine (Material Received)

33kV SWBD 61MS5-1** PO Includes FSE (Material Received)

Methanol PG Cooler E-1201** PR#7236 (AC) (Material Received)

Electronic Governor MT0701 & MT-1401* PO Includes FSE (Material Received)

Trip Solenoid for Synth & Mug Turbines**** PR Includes FSE

HP Carbamate Seperator D-8201*** PR#7244(TE)

D-1501** Inhouse Installation, E-0001B**PR#7216 (AC) (Material Received)

Super Cup Trays R8201** PR#7244 (TE) E-0003** PR#7216 (AC)

LV-82011, HV-82005, HV-82008, HV-82009 ** Inhouse Installation

PSV-5253****, HSV-52236 & HSV-52336, PV-52201/351 & PV-52401/402* In-House Installation

Passivation Air Compressor** PO Includes FSE

Urea 2200 MTPD - MOV-82003**** In-House Installation

E-8601 E-8602A/B/C E8604*, E-0704*, Inhouse Installation

MD-6102 PLC* PR Includes FSE

Urea ESD**** ENG PR Includes FSE

Urea Stripper E-8201*** PR#7244 (AO)

Ammonia PG Cooler E-0301** PR#7241 (AC)

Honeywell DCS* PO Includes FSE

B-5203 ESD ****

Mode of Transport By Road* By Sea (Red Sea)***

Ammonia Plant

CONFIRMED MAJOR JOBS

Methanol Plant

CONFIRMED MAJOR JOBS

Urea Plant

Utilites Plant

Meeting With TRT Team

Meeting#9 With Procurement and Warehouse

TA Job list Review Meeting - Methanol Plant Civil and Electrical Equipment Jobs

Equipment Jobs