TA2025-Monthly Report for August 2025

Page 1


STATUS REPORT

TA 2026

AUGUST 2025

DAYS TO TA 2025* 61

*BASED ON NOVEMBER 2025

ACTIVITY STATUS

Completed Activities:

Issuance of Job list (Rev-09)

Conducted Meeting with Procurement & WH#10

Job list discussion is in progress for Metahnol, Urea & Utilities Plants

Prepared Schedule Bar Chart for Boiler-D and Boiler-C Shutdown

Completed Combined Meeting Presentation #8.

Ongoing Activities:

Blocking of Stock Materials is in progress 92% completed

Detailed assessment for Critical/Major Jobs is in progress

Delivery of Capex Items are in progress.

Technical evaluation & issuance of final recommendation memos for packages and Vendors are in progress.

Material reservation for PM orders and CM orders is in progress: 98% and 94% completed respectively.

Turnaround CM order assessment is in progress: 97% completed

TA Job list Review Meetings are in progress.

Issuance of Area Leader List (rev 05)

Issuance of Organization chart (Area leader level).

Issuance of seconded manpower list

Organization Charts (Technicians Level).

ACTIVITY STATUS

ROADMAP S-CURVE

Planned

Completed

Slippage

CM MATERIAL STATUS

Pending CM Material Reservation (No. of WOs)

PM MATERIAL STATUS

Pending PM Material Reservations (No. of WOs)

PR STATUS

REFURBISHMENT STATUS

Issued PO Status:

1. MG-6401 Exciter - DM+

TA AUDIT REPORT

Total of 9 Audits Conducted till August 2025 on turnaround planning department by TAT (Turnaround Audit team)

CAPEX PROJECTS TIMELINE

HIMA ESD System* PO Incl FSE (Material Received)

42 Fans for Air Cooler ** PO Incl FSE (Material Received)

LV-08009** Routine (Material Received)

33kV SWBD 61MS5-1** PO Includes FSE (Material Received)

Methanol PG Cooler E-1201** PR#7236 (AC) (Material Received)

Electronic Governor MT0701 & MT-1401* PO Includes FSE (Material Received)

PSV-5253****, In-House Installation

Trip Solenoid for Synth & Mug Turbines**** PR Includes FSE

Urea 2200 MTPD - MOV82003****

In-House Installation

E-8601 E-8602A/B/C

E-8604*, E-0704*, Inhouse Installation

D-1501** Inhouse Installation, E-0001B**PR#7216 (AC) (Material Received)

Ammonia PG Cooler

E-0301** PR#7241 (AC)

MD-6102 PLC* PR Includes FSE

Passivation Air Compressor** PO Includes FSE

HSV-52236 & HSV52336, Inhouse Installation

Super Cup Trays R8201** PR#7244 (TE)

PV-52201/351 & PV52401/402*

In-House Installation

LV-82011, HV-82005, HV-82008 ** Inhouse Installation

Urea Stripper E-8201*** PR#7244 (AO)

E-0003** PR#7216 (AC)

HP Carbamate Seperator D-8201*** PR#7244(TE)

Honeywell DCS* PO Includes FSE

HV-82009 ** Inhouse Installation

Urea ESD**** ENG PR Includes FSE

B-5203 ESD ****

CONFIRMED MAJOR JOBS

Ammonia Plant

CONFIRMED MAJOR JOBS

Methanol Plant

Replacement of Process Gas Cooler (E-1201) at Methanol Plant

B-1201 Replacement of MTH reformer walls : 2 side walls (B-1201) [Recommended Option]

CONFIRMED MAJOR JOBS

Urea Plant

Utilites Plant