STATUS REPORT
TA 2026
AUGUST 2025
DAYS TO TA 2025* 61
*BASED ON NOVEMBER 2025

ACTIVITY STATUS
Completed Activities:
Issuance of Job list (Rev-09)
Conducted Meeting with Procurement & WH#10
Job list discussion is in progress for Metahnol, Urea & Utilities Plants
Prepared Schedule Bar Chart for Boiler-D and Boiler-C Shutdown
Completed Combined Meeting Presentation #8.
Ongoing Activities:
Blocking of Stock Materials is in progress 92% completed
Detailed assessment for Critical/Major Jobs is in progress
Delivery of Capex Items are in progress.
Technical evaluation & issuance of final recommendation memos for packages and Vendors are in progress.
Material reservation for PM orders and CM orders is in progress: 98% and 94% completed respectively.
Turnaround CM order assessment is in progress: 97% completed
TA Job list Review Meetings are in progress.
Issuance of Area Leader List (rev 05)
Issuance of Organization chart (Area leader level).
Issuance of seconded manpower list
Organization Charts (Technicians Level).

ACTIVITY STATUS

ROADMAP S-CURVE
Planned
Completed
Slippage
CM MATERIAL STATUS
Pending CM Material Reservation (No. of WOs)
PM MATERIAL STATUS
Pending PM Material Reservations (No. of WOs)
PR STATUS
REFURBISHMENT STATUS
Issued PO Status:
1. MG-6401 Exciter - DM+
TA AUDIT REPORT
Total of 9 Audits Conducted till August 2025 on turnaround planning department by TAT (Turnaround Audit team)
CAPEX PROJECTS TIMELINE
HIMA ESD System* PO Incl FSE (Material Received)
42 Fans for Air Cooler ** PO Incl FSE (Material Received)
LV-08009** Routine (Material Received)
33kV SWBD 61MS5-1** PO Includes FSE (Material Received)
Methanol PG Cooler E-1201** PR#7236 (AC) (Material Received)
Electronic Governor MT0701 & MT-1401* PO Includes FSE (Material Received)
PSV-5253****, In-House Installation
Trip Solenoid for Synth & Mug Turbines**** PR Includes FSE
Urea 2200 MTPD - MOV82003****
In-House Installation
E-8601 E-8602A/B/C
E-8604*, E-0704*, Inhouse Installation
D-1501** Inhouse Installation, E-0001B**PR#7216 (AC) (Material Received)
Ammonia PG Cooler
E-0301** PR#7241 (AC)
MD-6102 PLC* PR Includes FSE
Passivation Air Compressor** PO Includes FSE
HSV-52236 & HSV52336, Inhouse Installation
Super Cup Trays R8201** PR#7244 (TE)
PV-52201/351 & PV52401/402*
In-House Installation
LV-82011, HV-82005, HV-82008 ** Inhouse Installation
Urea Stripper E-8201*** PR#7244 (AO)
E-0003** PR#7216 (AC)
HP Carbamate Seperator D-8201*** PR#7244(TE)
Honeywell DCS* PO Includes FSE
HV-82009 ** Inhouse Installation
Urea ESD**** ENG PR Includes FSE
B-5203 ESD ****
CONFIRMED MAJOR JOBS
Ammonia Plant
CONFIRMED MAJOR JOBS
Methanol Plant
Replacement of Process Gas Cooler (E-1201) at Methanol Plant
B-1201 Replacement of MTH reformer walls : 2 side walls (B-1201) [Recommended Option]
CONFIRMED MAJOR JOBS
Urea Plant
Utilites Plant