TA2025-Monthly Report for April 2025

Page 1


STATUS REPORT

TA 2026

APRIL 2025

DAYS TO TA 2025*

*BASED ON NOVEMBER 2025

KEY HIGHLIGHTS:

TURNAROUND ROADMAP ALONG WITH THE PROGRESS CALCULATIONS ARE FOCUSING ON THE TARGET OF NOVEMBER 2025.

COMBINED MEETING#5 FOR TA 2026 CONDUCTED ON 16.04.2025

TA MODIFICATION & CAPEX DASHBOARD

TA PR DASHBOARD

TA MAINTENANCE WORK ORDER DASHBOARD

ACTIVITY STATUS

Completed Activities:

Issuance of Job List (Rev 06)

Completed Audit #08

Started Pre-Fabrication Jobs

Combined Meeting Presentations #5 conducted on 16.04.2025.

Issuing detailed Bar Charts (Rev-01)

Conducted Meeting with Procurement & WH #8

Issued Area Leaders List (Rev-04)

Ongoing Activities:

Blocking of Stock Materials is in progress 92% completed

Major machines spare parts checking by vendor/OEM is in progress 90% completed

Detailed assessment for Critical/Major Jobs is in progress

Delivery of Capex Items are in progress.

Meeting with SHE Department

Technical evaluation & issuance of final recommendation memos for manpower/equipment services is in progress: 25 final recommendation memos issued to procurement; 60 POs issued by Procurement for 19 PRs.

Technical evaluation & issuance of final recommendation memos for package contracts services is in progress: 38 final recommendation memos issued to procurement; 18 POs issued by Procurement for 16 PRs

Technical evaluation & issuance of final recommendation memos for vendor services (FSEs) is in progress: 36 final recommendation memos issued to procurement 18 POs issued by Procurement for 18 PRs.

Material reservation for PM orders and CM orders is in progress: 90% and 82% completed respectively.

Turnaround CM order assessment is in progress: 89% completed

ACTIVITY STATUS

PlannedActivities-May2025:

Joblistdiscussion2ndRoundforMethanol,UtilitiesandUreaPlants

FinalizeSecondedManpowerList

StartMeeting:Mods&Capex2ndRound

StartTradeTestingofOverseasManpower

StartKick-offmeeting/CommunicatewithContractors(Logistics)

PlotPlanApproval

Concerns:

DelayinthedeliveryofnewUreaStripper

ROADMAP S-CURVE

Cause of Slippage:

Final recommendation for Hiring of Manpower and Equipment: 25/27 FRs issued

Final recommendation for Package Contracts: 38/43 issued.

Final recommendation for Vendor Services: 36/40 issued

Issuance of POs for Manpower and Equipment: 60 POs issued for 19 PRs, POs to be issued for another 8 PRs

Issuance of POs for Vendor Services: 18 POs issued for 18 PRs, POs to be issued for another 22 PRs

Issuance of Package Contracts Services POs: 19 POs issued for 16 PRs, POs to be issued for another 28 PRs

Kick-off Meeting with Package Contractors (Technical) Meeting with SHE Department

PR STATUS

ActionPlan:

FinalizetheissuanceofremainingPOsforSparePartsInspection

ExpediteissuanceofPOsforDirectManpower&EquipmentHiring

ExpediteBudgetAllocationfor12PRs(4Manpower5Packagecontracts3vendorservicesPRs)

TA AUDIT REPORT

2 0 2 4 2 0 2 5

CAPEX PROJECTS TIMELINE

HIMA ESD System* PO Incl FSE (Material Received)

42 Fans for Air Cooler ** PO Incl FSE (Material Received)

LV-08009** Routine (Material Received)

33kV SWBD 61MS5-1** PO Includes FSE (20/04/2025)

Passivation Air Compressor** PO Includes FSE

E-0003** PR#7216 (AC)

MD-6102 PLC* PR Includes FSE

LV-82011 HV-82005 HV-82008**** Inhouse Installation

HV-82009 ** Inhouse Installation

Methanol PG Cooler E-1201** PR#7236 (AC)

PV-52201/351 & PV52401/402**** In-House Installation

HSV-52236 & HSV52336*

Super Cup Trays R-8201** PR#7244 (TE)

Urea ESD**** ENG PR Includes FSE

Honeywell DCS* PO Includes FSE

PSV-5253****

D-1501** Inhouse Installation, E-0001B**PR#7216 (AC)

Electronic Governor MT0701 & MR-1401* PO Includes FSE

E-8601 E-8602A/B/C E-8604*, E-0704*, Inhouse Installation

Ammonia PG Cooler E-0301** PR#7241 (AC) HP Carbamate Seperator D-8201*** PR#7244(TE)

Trip Solenoid for Synth & Mug Turbines**** PR Includes FSE

B-5203 ESD ****

Urea 2200 MTPD - MOV-82003**** In-House Installation

Urea Stripper E-8201*** PR#7244 (AO)

Expected to be delivered on 19.11.2025

Ammonia Plant

CONFIRMED MAJOR JOBS

Urea Plant

Utilites Plant

Meeting with Alfa Laval Olmi Team

Meeting with Expertise Team for Hot Tapping