STATUS REPORT

TA 2026

JUNE 2025

DAYS TO TA 2025*

*BASED ON NOVEMBER 2025

KEY HIGHLIGHTS:

TURNAROUND ROADMAP ALONG WITH THE PROGRESS CALCULATIONS ARE FOCUSING ON THE TARGET OF NOVEMBER 2025. CONDUCTED MAINTENANCE BRAINSTORMING WORKSHOP FOR TURNAROUND DEFERMENT TO SUMMER 2026

TA MODIFICATION & CAPEX DASHBOARD

TA PR DASHBOARD

TA MAINTENANCE WORK ORDER DASHBOARD

ACTIVITY STATUS

Completed Activities:

Started Releasing Blocked Material [Fabrication jobs]

Issuance of Job list (Rev-07)

Completed Major machines spare parts checking by vendor/OEM

Ongoing Activities:

Blocking of Stock Materials is in progress 92% completed

Detailed assessment for Critical/Major Jobs is in progress.

Delivery of Capex Items are in progress

Technical evaluation & issuance of final recommendation memos for manpower/equipment services is in progress: 25 final recommendation memos issued to procurement; 70 POs issued by Procurement for 20 PRs.

Technical evaluation & issuance of final recommendation memos for package contracts services is in progress: 39 final recommendation memos issued to procurement; 22 POs issued by Procurement for 18 PRs

Technical evaluation & issuance of final recommendation memos for vendor services (FSEs) is in progress: 36 final recommendation memos issued to procurement 23 POs issued by Procurement for 23 PRs.

Material reservation for PM orders and CM orders is in progress: 96% and 91% completed respectively.

Turnaround CM order assessment is in progress: 94% completed

ACTIVITY STATUS

PlannedActivities-July2025:

ConfirmationtoContractorsforJobStartdate/MobilizationDate

IssuanceofAreaLeaderList(Final)

TAReadinessAssessment#04

Audit#09

CombinedMeetingPresentations#7

IssuanceofJoblist(Rev-08)

Concerns:

DelayinthedeliveryofnewUreaStripper

ROADMAP S-CURVE

CauseofSlippage:

Final recommendation for Hiring of Manpower and Equipment: 25/26 FRs issued

Final recommendation for Package Contracts: 39/43 issued

Final recommendation for Vendor Services: 36/40 issued

Issuance of POs for Manpower and Equipment: 70 POs issued for 20 PRs POs to be issued for another 7 PRs

Issuance of Package Contracts Services POs: 22 POs issued for 19 PRs POs to be issued for another 24 PRs

Issuance of POs for Vendor Services: 18 POs issued for 18 PRs POs to be issued for another 22 PRs

Finalize Seconded Manpower List

Meeting with SHE Department, Mods & Capex 2nd Round

Job list discussion 2nd Round for Methanol Utilities and Urea Plants

Combined Meeting Presentations #5 & #6 and meeting with Procurement & WH#9

The commencement of the following milestones are deferred due to the rescheduling of the TA to summer 2026, situationwillbemuchclearerinSeptember2025

Document Submission by Contractor for all type of services

Start Trade Testing of Overseas Manpower

Communicate with Contractors (Logistics)

Start Gate Passes Processing & Visas for Vendors & Contractors

Cut-off Date for MWOs & MODs

Kick-off Meeting with Vendors & Package Contractors (Technical & Logistics)

Start Major Jobs (new) Presentation by Area Leader & Finalize Plot Plan Approval Meeting with ITDK

CM MATERIAL STATUS

Major Rotary Reservation Status

95%

Minor Rotary Reservation Status

96%

PR STATUS

ActionPlan:

FinalizetheissuanceofremainingPOsforSparePartsInspection

ExpediteissuanceofPOsforDirectManpower&EquipmentHiring

ExpediteBudgetAllocationfor6PRs(1Manpower,3Packagecontracts,2vendorservicesPRs)

TA AUDIT REPORT

2 0 2 4 2 0 2 5

CAPEX PROJECTS TIMELINE

HIMA ESD System* PO Incl FSE (Material Received)

42 Fans for Air Cooler ** PO Incl FSE (Material Received)

LV-08009** Routine (Material Received)

33kV SWBD 61MS5-1** PO Includes FSE (Material Received)

Methanol PG Cooler E-1201** PR#7236 (AC) (Material Received)

Super Cup Trays R-8201** PR#7244 (TE)

Urea ESD**** ENG PR Includes FSE

Ammonia PG Cooler E-0301** PR#7241 (AC)

Honeywell DCS* PO Includes FSE

D-1501** Inhouse Installation, E-0001B**PR#7216 (AC) (Material Received)

PSV-5253****, HSV-52236 & HSV-52336, PV-52201/351 & PV52401/402* In-House Installation

Urea 2200 MTPD - MOV-82003**** In-House Installation

E-8601 E-8602A/B/C E8604*, E-0704*, Inhouse Installation

Electronic Governor MT-0701 & MR-1401* PO Includes FSE

LV-82011, HV-82005, HV-82008, HV-82009 ** Inhouse Installation

B-5203 ESD ****

Trip Solenoid for Synth & Mug Turbines**** PR Includes FSE MD-6102 PLC* PR Includes FSE

HP Carbamate Seperator D-8201*** PR#7244(TE) Mode of Transport

Passivation Air Compressor** PO Includes FSE

Urea Stripper E-8201*** PR#7244 (AO)

E-0003** PR#7216 (AC)

Ammonia Plant

CONFIRMED MAJOR JOBS

Methanol Plant

CONFIRMED MAJOR JOBS

Urea Plant

Utilites Plant

Meeting with Luigi Resta to discuss Piping Modification related to M-9386 - Increasing the Urea Plant's Production Capacity

Maintenance Brainstorming Session for Turnaround

Deferment to Summer 2026