RAIL TRAIL QUICK FACTS

Next Article
THE SPOTS

THE SPOTS

This is the first of two trail phases funded by the Maryland Department of Transportation (MDOT), through the Recreational Trails Program

Advertisement

Phase 1 is .90 miles long Multi-Department project design and construction was overseen by the Engineering Department, constructed by Public Works, and once complete will be managed by the Parks and Recreation Department

Trail construction took a little over a year to complete

When Phase 2 is complete, the East-West trail will connect the existing Easton Village Trail to the existing North-South Trail (see map)

The State Highway Administration will need to install a traffic signal and pedestrian crossing at Glenwood Ave. and MD 322, before Phase 2 can be fully constructed. SHA work currently scheduled for fall/winter 2023