3 minute read

SAVE CLIENT $10M

To learn more about the Centennial Pond/Perkett Ditch project, visit our website at www.ackerman-estvold.com/projects n Block 9 – A mixed-use tower building with offices, a hotel and condos with an estimated cost of $110 million. n Fargo City Hall – The new home to Fargo’s municipal operations in the downtown core will open in August, with an estimated cost of $27.7 million.

Building, a mix of commercial, parking and apartments, which is expected to start in 2019 and be completed in 2020.

Total cost of the development: More than $50 million.

Grand Forks

n Altru Health System – New hospital, to be built at Altru’s current campus in Grand Forks. Old building likely to be razed.

Cost: $250 million. Groundbreaking: 2019. Completion: 2022.

n State Mill and Elevator – New rail spur and grain storage expansion. Project includes addition of 18,000 feet of track near the state-owned mill, plus the construction of four 250,000-bushel grain bins. Cost: $24.7 million n Pure Development – New mixed apartment and commercial development, to be built at the corner of North 5th Street and DeMers Avenue. Project features a Hugo’s Family Marketplace and Alerus bank branch on ground level, 50 apartments on second, third and fourth levels. Construction expected to start in the fall and be completed in the fall of 2019. Cost: $10.5 million n St. John’s Block – Renovation of all six floors of St. John’s Block building, corner of North Third Street and DeMers Avenue, along with three-story Annex Building neighboring to the east. Project is expected to begin this summer and be completed by next summer or fall. Cost: $6-8 million n Arbor Lofts – New five-story, $7.5 million condo development on the site of the former Arbor Park in downtown Grand Forks. Construction is expected to begin by the end of the year.

Minot

n Trinity Health – New hospital complex, featuring a six-story hospital with about 200 beds, a 20-bed intensive care unit and an emergency trauma center with 27 treatment bays.

Location: Southwest Minot. Cost: Construction $275 million, furnishing $100 million. Groundbreaking is scheduled for June, and construction is expected to take three years.

n Mouse River Enhanced Flood Protection Project – Project to provide flood relief for Minot residents. Phase MI-1 Fourth Avenue: Six-block stretch (from west of Broadway to the east side of Third Street NE) of levees, floodwalls, a new sanitary lift station and a pump station.

Phase MI-2 Napa Valley: Levees, a road closure structure and two stormwater pump stations, running from the Highway 83 Bypass to 16th Street Southwest.

Phase MI-3 Forest Road: Earthen levees to protect the north side of river between 16th Street Southwest and the end of Third Avenue Southwest. Cost for all three phases: $99.4 million. Construction began in May and is scheduled to be completed in 2020.

n Roosevelt Park Zoo expansion and improvement – New lion, tiger and leopard habitats. Cost: $5 million. Construction expected to begin in the spring and be completed in time for the zoo’s 100th anniversary in 2021.

n Downtown Gathering Place – Project funded through Minot’s participation in the federal National Disaster Resilience Competition. Cost: $6 million. Construction of the multi-use, year-round facility awaits property acquisition and completion of an environmental assessment.

n Vallely Sport and Marine – Rebuilding after earlier structure was leveled in a July 2017 fire. Cost: $2.5 million. Construction began in March and will be completed in October.

Sioux Falls

n Avera on Louise Health Campus – Phase One of new healthcare campus for the Avera McKennan Hospital and University Health Center system. Location: Southwest Sioux Falls, 69th Street and Louise Avenue.

Campus will include a new five-story orthopedic hospital with spaces for 24 inpatient beds, six operating rooms, shells for 24 future inpatient beds and two more operating rooms and other facilities. The campus will also include a connected, three-story medical office building.

Cost: $134 million. Opening of the campus is slated for early 2020.

n Gage Brothers project – New concrete production facility for Gage Brothers, precast concrete company. Location: Industrial park in northeast Sioux Falls. Scale: 220,000-sq. ft. plant, 14,000-sq. ft. office. Completion: Office in the fall, plant in January. Cost: $40 million n Win Chill refrigerated food warehouse facility. Location: Foundation Park in northwest Sioux Falls. 205,000-sq.-ft. refrigerated warehouse, opening spring 2018. Cost: $32.9 million n Silverthorne Flats – Apartment community that will eventually include 230 units. Location: 2105 S. Silverthorne Ave. Cost: $8.9 million n Midcontinent Communications Tech Ops Building – Warehouse and technical operations office space. Location: 1305 N Terry Ave. in northwest Sioux Falls. Size: 30,500 sq. ft. Cost: $4.1 million. n MIxed-use parking ramp project – Structure will include hotel rooms, event center meeting space, restaurants, commercial space and 500-plus public parking spaces. Construction began in May and is expected to be complete by fall 2020. Cost: $50 million. PB

This article is from: