Solar PV Installation Project, AGMC Showroom, Dubai

Project Highlights

Rooftop PV Solar On-Grid Installation of 1.1 MW.

Complete Project with Supply, Installation, Testing,

Commissioning & Energizing including handover to DEWA and Building Owner, AGMC

Villa Project, ETIHAD ESCO, Dubai

Retrofit Project as per DEWA/Etihad ESCO standard. GECO were first awarded 1500 Villas but then additional 1200 Villas added. Still, we completed project within project timeline.

h

The Cost Savings amounted to 13.7 Millions per year and the payback of 6 months.

Project Result

Al Batha Labour Accommodations Project, Sharjah

Project Highlights

GECO completed HVAC Control retrofit and Lighting retrofit in 2 facilities of Al Batha Real Estate

Energy Audit for Retrofits

Why

Why Energy Audit for Retrofit? Supply Demand Correlation

We Know That…..

• No Equipment is ever as efficient as the day it was installed, therefore how do we judge if the equipment is worn enough to warrant replacement?

• Equipment in the UAE market is often oversized and therefore runs at low load conditions during most of its life. Perhaps resizing would serve to reduce energy usage

• Function or load requirements of the Facility often change with time. Equipment may not be well sized for the new function/load.

When gauging the retrofit/replacement of equipment in a facility, Energy audit can act as a great instrument to measure and guide the retrofit process.

Through the use of Energy audit, measurement and data analysis we can appropriately gauge the effectiveness, efficiency and aptness of equipment to serve its intended purpose.

Gulf Tower Building, Lighting Project, Dubai

Project Highlights

GECO completed Lighting retrofit in 2 facilities of Bu-Haliba Real Estate

Energy Highlights

The annual Energy Highlights is only for light consumption since this is the focus area of this retrofit project. 272,874

Energy Audit for Hyatt Hotels, Dubai

Project Highlights

EPC project for 5 facilities of Hyatt Hotels for Etihad ESCO. The Annual Savings per year after implementation of ECMs amount to 7.2 Million AED

Energy Audit for GEMS Education, UAE

Project Highlights

Shared Saving Project for GEMS Education. Project is Energy Retrofit for 5 diversified school facilities in Sharjah.

Project Result

Energy Audit for NEDAA, Dubai

Project Highlights

EPC project for building energy retrofit for NEEDA Professional Communication Building in Dubai.

Turn static files into dynamic content formats.