Gaston County FY 2024 Adopted Budget at a Glance - Capital Improvement Plan

Page 1

GASTON COUNTY

FY 2024 Adopted Budget at a Glance

FY 24-28 CAPITAL IMPROVEMENT PLAN

$13,623,209

Funds Needed to Fully Implement FY24 Projects

12 projects were recommended for funding in FY24, totaling $27,223,209

Total project cost of $122,132,985 over the next five years

Project costs are offset by $13.6 million in non-County funding:

$ 27,223,209

$ 6,600,000

Total FY24 Cost - All Projects

Funding via Medicaid Max

$ 7,000,000 Funding via ARPA Salary Savings

$ 13,623,209

FY24 FUNDING BY CATEGORY

$23.9M

Facilities, maintenance, repairs, and new construction

Public Safety Campus (Approved in Concept - FY23 CIP)

Public Health Renovations (Approved in ConceptFY23 CIP)

City of Gastonia FUSE Parking Contribution

Catawba Cove - Multiphase Project

Dallas Park Master Plan Buildout

Courthouse 5th Floor Upfit Gap Funding

Fleet Maintenance Facility Gap Funding

Poston Park Sidewalk Construction

Expanded Maintenance Facility Poston Park

$450K

Purchase of new or replacement equipment and vehicles

Playground Updates

$2.9M

Economic development land acquisition and infrastructure improvements

US74 Catawba River Bridge (NCDOT)

I-85 Betterments (NCDOT)

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
Gaston County FY 2024 Adopted Budget at a Glance - Capital Improvement Plan by gcbudget - Issuu