FLASH SUMMER 2015

A F O C U S O N F LY N N G R O U P O F C O M PA N I E S ’ C R E W S A N D P R O J E C T S

Ryerson Student Learning Centre

Read more on pages 18 & 19

Also in this issue: An introduction to Flynn Mid-Atlantic…page 6 Introducing Flynncrew.com.…page 27 Mentorship Matters – Joseph Raposo…page 34 Flynn wins CRCA Roofing Canada Award Two Years in a Row…page 42


PRESIDENT’S MESSAGE I am deeply saddened to share that on May 21st, there was an accident on one of our jobsites that ended in the worst possible result. You should hear from me – not anyone from outside the company – what happened. One of our veteran Architectural Panel crews in Toronto suffered catastrophic misfortune. The elevated work platform that two crew members from our Toronto branch were working on toppled. One of our own, Nelson Ferreira – was pronounced deceased at the scene. In the man lift with Nelson was Joaquim Moreira, who colleagues and friends know as “Peta.” Peta has undergone many hours of surgery, and although he recently has shown positive progress, he has a lengthy recovery ahead of him. This was a devastating day for our Flynn family, and only further reinforces why safety is, and will continue to remain, our top priority. We will do everything we can to learn from this and share the lessons learned with those in the company and the industry. There has been an outpouring of love and support from all corners of the company for the families of Nelson and Peta as they deal with this tragedy. Many people have inquired as to how they can assist the families. In response to that outpouring, a note from our Human Resources Department explaining how you can assist the families if you choose to do so, can be found on page 9. Please join me in extending our heartfelt thoughts to the families of Nelson and Peta during this time of healing. Until next time, take care.

Doug Flynn

2

FLYNNFLASH | SUMMER 2015

Doug Flynn President & CEO


KC IS NOW HERE TO SERVE Flynn Midwest recently established their new Roofing Service Department, following the Flynn Group of Companies model. Managed by Will Pierce with the aid of Nick Markley, the team is made up of 11 Roofers, Glaziers, and Sheet Metal Workers who have years of experience with the company. Pierce has been a Project Manager for the company for 13 years prior to taking on this new position. According to him, the servicemen are embracing their new roles, “They love the structure, the trucks, the uniforms, and are just happy with the change.”

FIRST FUSE IN THE US Congratulations to members of our Baltimore, Kansas City, Springfield, Flagstaff and Phoenix branches who recently completed the very 1st U.S. Flynn University for Service Excellence held at Great Wolf Lodge in Kansas City. Thanks to all participants (and their families, of course) for sharing this milestone with us, and a special thanks to Jerry Schaefer, Senior Vice President, Flynn Midwest.

KANSAS CITY

FUFL 16 From left to Right Back: Will Pierce (Manager), Mike Kelly, P.J. Benson, Doug Hepting and Chris Petrovich. Front: Yogi Wright, Billy Smith and Cory Hall. Not pictured: Jesse Faulkner.

Congratulations to all participants of FUFL 16 (Flynn University for Front-line Leaders) held in Minneapolis. This two‑day leadership program is designed specifically for the leaders (and future leaders) of our field operations. Representatives of our Kansas City, Phoenix, Flagstaff and Baltimore branches were all on board and made the first FUFL held in the US a success. Great job, guys! Special thanks to Joe Neva, Mark Roy and Rob Dowrick.

From left to right: Kris Baer, Jim Engelman, Jason Rodriguez and Nick Markley.

FLYNNFLASH | SUMMER 2015

3


PROMISING A BUSY YEAR AHEAD Flynn Midwest in Kansas City has been awarded two major new construction projects: Cerner Three Trails and The University of Kansas Hospital – North Cambridge Tower.

KANSAS CITY

entire skin of the new seven-story North Cambridge Tower. This hospital extension will add another 120 beds and 12 operating rooms to the hospital, as well as expand the neuroscience and surgical oncology departments, creating over 600 new healthcare jobs. “I am extremely proud of our project teams. They took these immense potential projects and turned them into a reality. The dedication of these men and women, who very often came to work early and stayed late past sunset, gave the general contractor, architects, and owners what they wanted and deserved,” says Jerry Schaefer, Senior Vice President. From left to right: Bob Livingston, Cory Brown, Dave McAnerney, Chris Mann, Nick Markley, Ann Trave, Mark Webb and Vern Keeth. Not pictured: Roger Svetlecic. Cerner Three Trails will be the third campus project that Flynn has worked on with general contractor J.E. Dunn. Last year, they finished the Cerner Continuous Campus, constructing the entire building envelope. The new development for the healthcare company is 290 acres in Kansas City, Missouri and will house over 15,000 new employees when the campus is completed. Flynn has been given the architectural metal and glazing scopes for the first two buildings, and hopes to land the roofing scope, which will bid later this year. Also, having worked for the University of Kansas Hospital campus in the past, Flynn Midwest will be responsible for the

4

FLYNNFLASH | SUMMER 2015

From left to right: Bob Livingston, Dave McAnerney, Larry Skidmore, Archie MacDonald, Ann Trave, Mike Mauck, Mark Webb, Mike Carter and Vern Keeth. Not pictured: Roger Svetlecic.


KCPD EAST PATROL CAMPUS

4800 MAIN/POPULOUS

■■Submitted by Archie MacDonald

■■Submitted by Mark Webb

The new KCPD East Patrol Campus in Kansas City, Missouri will feature a police division and evidence repository. Flynn Midwest’s scope of work includes 10,000 sq. ft. of Firestone Delta Series wall panels as an exterior rainscreen cladding system, over Knightwall FMI-S Series clip and rail system with 3˝ Roxul CavityRock. Additionally, we fabricated and installed approximately 7,500 sq. ft. of 4mm Alcoa Reynobond ACM fascia and soffit cladding in various locations on the building façade, as well as miscellaneous roof related flashings, conductor heads, and round downspouts.

4800 Main is international architecture firm Populous’ new residence in Kansas City. Flynn Midwest is working on the metal and glazing scopes, as well as roof repair, on the preexisting building. We were able to snap a few photos of our busy crew members.

KANSAS CITY

KANSAS CITY

From left to right: Jeff Stice, Chad Vermillion, Jonathan Folsom, Richard Dykmann, Rodney Williams and Nate Limkemann.

From left to right: Steven May, Dustin Borchert (Foreman), Josh Nichols, Ron Stoner, Justin Barnes, Fred Boyer and Sean Penn.

ONE LIGHT TOWER ■■Submitted by Mark Webb

Glaziers at work on One Light Tower pose for a shot at the base of the building. One Light Tower is a new 25-story glass towered luxury apartment complex in downtown Kansas City.

From left to right: (top) Ronnie Kraus and Shane Miller; (bottom) Ryan Deich and Jack Cragar.

KANSAS CITY From left to right: Dave Schultz, Travis Clark, Robert McCafferty, Ben Davidson, Craig Sass, Rodney Williams, Greg Powell, Mike Jenesse, Mark Clark, Terry Cloud, Jerry Hill, Chris Holbrook, Matt Petree, Joe Lewis, Cody Kelsey, Chris Oakes and Rick Waller.

From left to right: Jamie Boyd and Glen Shoemaker.

FLYNNFLASH | SUMMER 2015

5


AN INTRODUCTION TO FLYNN MID-ATLANTIC Flynn Mid-Atlantic (dba Flynn Control Roofing & Sheet Metal) in Linthicum, Maryland is our newest addition to Flynn Group of Companies. They specialize in roofing, as well as architectural sheet metal fabrication and installation. Operating within a vast 200-mile radius of the Baltimore George Hnat and Washington, D.C. Branch Manager of Flynn Mid-Atlantic metropolitan areas, the company has the ability to travel and get large projects completed. An example of this is a new roof at the US Embassy in Kampala, Uganda in 2001.

We are so excited to have them join our expanding team. We have added a Service Department and in the future will be able to provide the total building envelope to all of our customers in the Mid-Atlantic region.

Branch Manager, George Hnat, started Control Roofing in 2000 with three others and became sole Shareholder in 2009 before partnering with Flynn. “I was looking for a company that had similar values and culture. I needed to know that the acquisition would be growth oriented and also ensure the best possible future for my dedicated employees,” says George.

FRIENDSHIP ANIMAL HOSPITAL ■■Submitted by George Hnat

For over 50 years, Friendship Hospital for Animals has been one of the top medical facilities for dogs and cats in the Washington D.C. area. When the hospital ran out of space, they built an additional floor atop the existing structure. Our crew is installing the wall cladding and rooftop mech equip screen wall. We also installed a white EPDM (cool) roof and added a partial green roof with a special fenced-in

section with K9 grass for the canine patients. A screen wall has planters below each section with climbing vines that will eventually grow over the screen wall. Overall, our goal is to give a pleasant outdoor appearance for when they bring the dogs for exercise in the K9 grass area with an environmentally friendly rooftop.

BALTIMORE 6

FLYNNFLASH | SUMMER 2015

From left to right: William J. Keith, John Horay and Gynaro Coreas.


INTRODUCING REBECCA WELSH We are pleased to announce that Rebecca Welsh has joined Flynn as Branch Manager in our Springfield, Missouri office. Rebecca comes with an abundance of knowledge and experience in the industry, having spent the last ten years at DeWitt & Associates where she was Project Manager for many large jobs such as Missouri State University and St. John’s Tornado Recovery in Joplin. Rebecca was most drawn to Flynn’s capabilities as a total building envelope contractor and is eager to educate the Springfield community on the quality work that Flynn’s skilled craftspeople produce. She added, “I want local owners, architects, and general contractors to make Flynn their first phone call for building envelope projects.”

Rebecca Welsh Branch Manager, Springfield, Missouri

Brynne Smith, President of Flynn’s US Operations, said, “We hired Rebecca for her hands‑on roofing experience, proven leadership, and her strong relationships in the Springfield construction market. Her personality aligns well with Flynn’s culture.” Contact: rebecca.welsh@flynncompanies.com

FLYNN MIDWEST CREW IN SPRINGFIELD

STELLA MARIS ■■Submitted by Archie Tantlinger

The Hospice Center Stellar Maris in Baltimore was in need of a new roof. After the tear-off, the Baltimore team used cold process low VOC materials, so as not to create any potential air quality issues. The new roof installation consisted of Garland 3-ply with white gravel.

BALTIMORE From left to right: (backrow) Alejandro A. Miranda, Jose E. Miranda, Rogelio Echeverria, Jose A. Miranda, Gerardo Lopez, Leonidas Orellana, Moises Guarcax, Luke Tantlinger, (middle) Oscar Marin, Jose “Nelson” Marin, Marvin Quinteros, and (front) Hector Dias.

THANK YOU, KANSAS CITY!

■■Submitted by Jack Carter

Proud to now be a part of Flynn Group of Companies as Flynn Midwest!

KANSAS CITY

Dear Matt (Pierce), I wanted to take a moment to thank you and your Project Team for your work on the Mortgage Lenders of America Headquarters renovation. The renovations on this Project were complex and the project schedule was very condensed. Because of your determination and attitude, the project was completed on schedule and under budget. Overall, the commitment from Flynn Midwest to meet the project schedule exceeded our expectations. Mortgage Lenders of America are very pleased with the quality of the work. We have received several compliments from their employees. This is due in part to the hard work and dedication from Flynn Midwest. I look forward to working with Flynn Midwest again the future.

From left to right: Roy Turner, Sharrod Szydloski, Dan Rogers, Larry Crouch, Gilbert Verdugo, Jack Brazeale, Nick Workman, Karen Smith, Scott Meyer, Jack Carter, Christian Ortegga and Mike Miller. Front: Chris Matteson and Corey Ashburn.

Sincerely, J.E. Dunn Construction Company Mark Patras, LEED AP

FLYNNFLASH | SUMMER 2015

7


LUKE AIR FORCE BASE

FLAGSTAFF

■■Submitted by Ian Anderson

■■Submitted by Kevin O’Dir

This is our first project as Flynn Southwest in the Phoenix area! We are currently installing 540 sq. ft. of insulation, underlayment, and metal roofing on a temporary lodging facility for the US Air Force pilots of Luke Air Force Base in Glendale, Arizona.

The crew is currently removing the existing copper panels for the gated community Forest Highlands. For this reroof, they are installing a new standing copper roof, panels, and fascia.

PHOENIX

FLAGSTAFF From left to right: Ernesto Hernandez, Raul Hernandez, Antonio Bezarra and Raymundo Camacho.

From left to right: Rene Vidal, Sunny Cody, Aldo Rivera, and Orlando Kee.

LITTLE AMERICA CONVENIENCE STORE

THE VILLAGE AT ASPEN PLACE

■■Submitted by Kevin O’Dir

■■Submitted by Kevin O’Dir

For this popular truck stop in Flagstaff, the crew is removing the existing wood shakes and re-sheeting the roof with 70 square shingles.

Aspen Place at The Sawmill is a five-story multiuse building for residential apartments and retail space. The new complex consist of 300 squares of asphalt shingles, 200 squares of built-up roof, and 50 squares of metal.

FLAGSTAFF FLAGSTAFF From left to right: David Martinez, Jacob Perez, Jose Chavarrita, Leandro “Junior” Carillo, Chris Chavez and Jessie Begay, Jr.

8

FLYNNFLASH | SUMMER 2015

From left to right: Thomas Cook, Luis “Bernie” Longoria, Andreas Rivera, Kurt Smith and Matt Rodriguez.


NOTE FROM HUMAN RESOURCES How to Donate to the Families of Nelson and Peta

We’ve set up an online funding site for anyone who would like to make a contribution to the families of Nelson Ferreira and Peta Moreira. All funds raised will be divided equally.

To donate: 1. Visit www.fundrazr.com in any browser on your computer or phone, type “nelson and peta” in the search bar in the top right hand corner, and click on the campaign with the Flynn logo. You can also access this page by going to www.tinyurl.com/nelson-and-peta on any browser on your computer or phone - they will both take you to the same page. 2. Click the “Contribute” button in the yellow/orange box to the right‑hand side of the page, select or enter the amount you would like to donate, enter your name (note that you can check the box to remain anonymous if you would like to), enter a message (optional), choose if you would like to receive campaign update emails by checking or unchecking the box, and click either “Pay with Credit Card or Bank” or “Pay with Pay Pal”. 3. If you have an existing Pay Pal account, simply log in and proceed with payment as you normally would. (You can also choose to continue with Pay Pal as a guest.) If you choose “Pay with Credit Card or Bank” you will be asked to enter your contact information and credit card information. Once complete, click “next” and enter your email address to receive your receipt. Thank you for your contribution!

Need assistance making your donation? If you are having any trouble with the “Pay with Credit Card or Bank” option, please contact support+fundrazr@wepay.com for immediate assistance. If you are having any trouble making your donation via Pay Pal whether through your existing account, or as a guest, please call Pay Pal at 1-888-221-1161 and they will resolve your issue for you. You will get an automated system at first, but can speak with a representative by saying “representative”. You will need to say “representative” multiple times before being connected.

FLYNNFLASH | SUMMER 2015

9


MARCH MADNESS: CANADA’S EAS ST. ANTHONY AIRPORT EXPANSION

LET IT SNOW!

■■Submitted by Anthony Upwards

■■Submitted by Anthony Upwards

Pascal Desjardins, Ken Petersen (Foreman) and John Collier pictured below were busy putting finishing touches on an airport expansion project in St. Anthony which is located on the Great Northern Peninsula of Newfoundland. This required a 2-Ply Modified roof which was completed for Traytown Builders.

Ed Clarke, Mark McDonald (Foreman), Pascal Desjardins and Ken Petersen (Foreman) posed for a picture while taking a break in a big snow bank – one of many the East Coast has seen this winter and spring. In just March alone, Newfoundland saw 40cm+. Crews were busy digging drains and removing/distributing snow for a variety of clients!

ST. JOHN'S

ST. JOHN'S

PALACE ROYAL ■■Submitted by Jodine Baker

With the spring snowfall that the Atlantic Region (especially Halifax) experienced, our crews worked day and night to ensure proper snow removal for customers. Palace Royal was recorded to have approximately 14 to 15 inches of ice with five feet of snow on top!

BABY IT’S COLD OUTSIDE Moncton Branch Manager Eric Veniot took this photo from his desk in late February! Good thing Service Crews were close by to help dig out!

HALIFAX

From left to right: Bradley Clattenburg, Brandon McDonald, Ben Wellwood, Jeff Haslett (Roofing Foreman), Stephen DeWolfe and Jason Vincent (Superintendent).

10

FLYNNFLASH | SUMMER 2015

MONCTON


T COAST HAD A HARSH SPRING! COOL CATS ■■Submitted by Anthony Upwards

Lance Wicks, Jason Dawe (Foreman), Gary Best, Charlie Wells, William Hoeg and James Frizzell were installing a mechanically fastened TPO roofing system at Toromont Cat in St. John’s. This is in addition to repairs that were carried out to metal siding and gutters.

ST. JOHN'S

WE DON’T LIVE IN IGLOOS IN CANADA…WE JUST TAKE BREAKS IN THEM ■■Submitted by Jodine Baker

There was so much snowfall on the roof at a local Loblaw’s, that the crew decided to take advantage and build an Igloo.

HALIFAX

Roofing Crew from left to right: Stephen DeWolfe, Ben Wellwood, Brandon McDonald, and Bradley Clattenburg.

SUCCESSFUL GROWTH OF ARCHITECTURAL DIVISION IN ATLANTIC CANADA

MASTER OF WINTER CONDITIONS AT MASTER PACKAGING

■■Submitted by Eric Veniot

■■Submitted by Kyle Kennedy

Over the last two years, Flynn Moncton has done an increasing amount of work for JDI (Irving Group). The growth of the Architectural Division in Atlantic Canada, including the addition of the Moncton based Metals crews, has created the opportunity to secure our first New Brunswick based JDI (Irving) Cladding Project. Work was underway at Irving’s Lake Utopia Pulp Mill in southern New Brunswick. The job consisted of re-cladding of the existing walls as well as new extensions to the dry and wet ends of the mill.

Winter roofing is always an added challenge but even more so when you're talking about a 96,800 square foot warehouse addition at Master Packaging, a division of Irving’s Group of Companies. Our guys were up to the challenge and pushed through a record setting snowfall winter and spring. Flynn was able to stay well ahead of the projects schedule and it was

MONCTON

MONCTON

nothing but positive feedback! The crew wrapped this job up in April and were excited to finally pack the snow blowers away! From Left to right is Keith Foster (Foreman), Brett Jones, Mat Shepard, Robert Burke, Jeremy Isadore, Joey Love and Matt Thomson.

Pictured above is Leo Cormier, Edgar Cormier, Martin Bourque, Yves Robichaud, Roger Sr. LeBlanc, Alban Cormier and Roger Jr. LeBlanc (Foreman). FLYNNFLASH | SUMMER 2015

11


EAST COAST SPRING SNOWFALL! MONCTON BASED METALS CREW CONTINUED ■■Submitted by Kyle Kennedy

Our Moncton Metals Crew was hard at work at the new Quispamsis K-5 school. The full metal cladding package consisted of 23,500 sq. of Insulation/Girts/Cladding. The cladding is set to be a major focal point of the school due to the extensive use of multiple vibrant colors. The crew wrapped up on site in late spring, well in time for the schools slated fall opening.

FLYNN REELS IN A BIG ONE ■■Submitted by Kyle Kennedy

Flynn angled in the contract for a 72,500 square foot re-roof to accommodate the moving in of North America’s leading outdoor box store Bass Pro Shop. The guys pushed through the harshest conditions including a total winter snow fall of over 380cm. (As Monctonians we honestly wish we were kidding about that). The crew has received high praise from the General Contractors on this job.

MONCTON

MONCTON From left to right is: Walter Denis, Fernando Richard (Foreman), Kris Landry, Peter Brooks and Trent Lewis.

L'ECOLE SECONDAIRE DU SOMMET ■■Submitted by Jodine Baker

Our roofing crew has been working relentlessly on an addition to L’Ecole Secondaire du Sommet to house their new Skilled Trades Program. This was a 53 Square two-ply mod bit torched down application. Flynn did the roofing and the metal siding on the original school back in 2010 and we were asked to come back to complete the Skilled Trades Addition as well. Maybe some of our future start employees will get their training here!

HALIFAX

From left to right (back): Dominic Laplante, Charles Levesque, Jean-Noel LeBlanc (Foreman) and Ronald McDonald. From left to right (front): Noel Duplessis, Marcel LeBlanc, Stephane Breau and Miguel Goguen.

LONG HARBOUR BUILDING 224 ■■Submitted by Anthony Upwards

Dennis Butt (Roofing Manager), Brandon Wicks, Frank Butt, Gary Lee, Corey St. Croix, Gerald Hiscock, Brian Hendry, Philip Christopher, Dave Griffin, Mike Parrott (Foreman) and Mike St. Croix are pictured below at Long Harbour Building 223, an industrial project located in Long Harbour which is now coming to an end. To date, Flynn has been the only roofing company contracted to install modified roofing on site. Once complete, we will have installed nearly 3,500 squares of new modified roofing on site. The project was awarded to us by KBAC Constructors.

ST. JOHN'S

Roofing Crew from left to right: Lewis Gale (Foreman), Zbigniew Wolnik, Tyler Legere, Blaine Glasgow, Reece Michael, Kyi Gale and Jason Vincent (Superintendent).

12

FLYNNFLASH | SUMMER 2015


AMAZON SNOW REMOVAL ■■Submitted by Archie Tantlinger

In order to keep functioning, Amazon needed its data center to keep moving and that meant ridding the rooftop of snow. Flynn Mid-Atlantic responded to their need and cleared 120,000 sq. ft. of the data center. In the past two years, Flynn Mid-Atlantic has cleared two other Amazon data centers of snow – one 200,000 sq. ft. building and one 110,000 sq. ft. building. Before

After

BALTIMORE

BANK OF CANADA ■■Submitted by Michael Quesnel

Ottawa’s Roofing Production crew including Miran Skof, Gilles Lavoie and Guy Jolicoeur worked on 50,600 sq. ft. of mod-bit roofing with 230 skylights in conjunction with PCL. The metals crew of Evans Thornton, Hue O’Donnell, Andrew Krieger, Steve Miles, Michel Henry, Dave Taiillon and Dave Simms pictured below, installed liner and siding on the Penthouse at the Bank of Canada in Ottawa as well.

FLYNNFLASH | SUMMER 2015

13


WESTMOUNT GOLF AND COUNTRY CLUB ■■Submitted by Alex Boterman

CAMBRIDGE

CAMBRIDGE CREWS READY TO ROCK ■■Submitted by Alex Boterman

With the Spring thaw, service crews in Cambridge were running flat out. Dave Bernier and James Hennifent were ready to roll to emergency service jobs first thing in the AM.

From left to right are Paul Kelly, Colton McAleney, Lucas Nanasi and Luis Avila doing roof replacements (shingles and low slope roofing). This is the most prestigious golf course in the area – they did an excellent job.

CARLTON SCHOOL BOARD CRYSTAL BAY LEARNING CENTRE ■■Submitted by Emily Weihrer

The Carlton School Board Crystal Bay Learning Centre consisted of ripping the 24 square BUR conventional roof system down to the 2‑ply vapor barrier. Donovan Conlon, Adam Cooper, Jason Smith, Eric Schultz, Reuben and Denis Lauzon installed a new elastophene sanded vapor barrier in order to keep the roof waterproof for Spring.

CAMBRIDGE

SERVICE WITH A SMILE ■■Submitted by Alex Boterman

Shawn Hancott and Greg Phillips were out putting the finishing touches (reworking the vent stacks as per the consultant and tieing in a final section of flashings) on a full day Kindergarten addition at MacKenzie King School.

OTTAWA

CAMBRIDGE 14

FLYNNFLASH | SUMMER 2015


VUTEQ CANADA

ROYAL BOTANICAL GARDENS

■■Submitted by Stephanie Bartlett

■■Submitted by Dan Castonguay

From left to right: Vance Construction, Dan Camara, Jimmy Furtado (Foreman), Dan Bush, Eduardo Camara, Jason McKay, Antero Furtado and Manuel DaPonte completed this 510 square, 4-ply BUR building expansion.

Pictured below is Cody Xavier, Peter Bendyk (Foreman), Mike Palma, Cory Sturk, Carlos Raposo, Ed Xavier and John Barbosa. The crew has tackled the leaf design on this prestige Phase III at the Royal Botanical Gardens Visitors Centre Project headed up with Ira McDonald Construction Ltd. The leaf is approximately 7300 sq. ft. and completed with 80 mil Carlisle mechanically fastened membrane.

LONDON

SUDBURY WATERSPORTS PROJECT ■■Submitted by Gary Trotter

Sudbury crews are installing “longboard” aluminum cladding siding and soffit at the Sudbury Watersports Project on Ramsey Lake. From left to right: Rej Rancourt (Foreman) and Ron Levesque.

Phase I Tea House was completed by Victor Medeiros and crew last year and Phase II was completed by Carlos Costa and crew during the 2015 winter construction on the attached Visitors Centre at the RBG site. Both Phase I and II were modified membranes.

HAMILTON

SUDBURY

All the crews brought forth excellent quality in completing this very difficult and demanding project. FLYNNFLASH | SUMMER 2015

15


ST. JOSEPH’S HEALTH CARE: LONDON ■■Submitted by Gary Trotter

With General Contractor EllisDon Construction, this re‑roofing project had to be cleared of snow and ice before it began. It was 87 squares of 2-ply mod‑bit, torch. Crews had to be doubled to adhere to a tight project schedule with a firm completion date. It was additional work to an existing contract that was awarded only if project schedules could be met.

LONDON

Pictured in the back row from left to right: Ken Williams, John Doucette, Alex Pepping, Bryson Williams, Don Dadson (Foreman) Drayson Bridge, Marco Adriano and Helder Medeiros (Foreman). Front row: Ernesto Moniz and Joe Moniz.

HUMBER SAFETY AWARD Congratulations to Flynn Crews on the Humber River Hospital Project in Toronto, Ontario for receiving an award for 5 million hours without lost time incident. In addition to this, Dinis Meireis and Tim Speck both were awarded the Monthly Worker Safety Award, presented by the Workers Trade Committee. The members of the Flynn team who participated on this project were: Joe Neiva, Dinis Meireis, Luis Da Costa, Paulo Pimenta, Luis Pereira, Jose Ondas, Junior Watson, Manuel Ondas,Tim Speck, Jose Camacho, Chris Da Silva, Kyle Kanthak, Kirk Dely, Rick Knuth, Sheldon Henry, Kyle Laine, James Jones, Rocal (Marvin) Kelly, Peter Baun, Juan Marin, Cody Lewis, Bailey Wiebe, Craig Crawford, Jared Harvey Neale, Jayson Alexander, Brian Lajeunesse, Ragique Babulal, Joe Fretais, Frank Costa, Carlos Pereira, Helder Rodrigues, Mike Correia, Sandy Sandrelli, Troy Elliot, Angelo Silva, Wayne Moniz, Richard Hunt (Project Manager), Stefano Panarisi (Superintendent) and Brad Noddle (Project Coordinator/ Superintendent).

SAFETY AWARD FOR FLYNN HAMILTON Flynn Hamilton received a Safety Award for “No lost time in Category 3 – 100,000 – 249,999 hours” that was accepted at the HHCA Annual General Meeting and Dinner held in February. Congratulations to all the field workers in Hamilton Branch for this achievement. Joseph Raposo (Centre) receiving award on behalf of Hamilton Branch from Paul Christie, left (Dan Lawrie Insurance Brokers) HHCA Board Member, and Blair Hubber, right, (Lancaster Group) HHCA President.

16

FLYNNFLASH | SUMMER 2015

HAMILTON


THE BERGERON CENTRE FOR ENGINEERING EXCELLENCE – YORK UNIVERSITY TORONTO

For this project currently underway, Flynn is the Total Building Envelope Contractor. The complex geometry and complicated interfaces on this project predominantly demanded thinking outside the box. Flynn’s Design Team met all the necessary requirements; a cladding contractor with technical expertise, experience, and resources to overcome the challenges of this landmark project. The new facility, which is due to open its doors in September 2015, is well on the way from being transformed from vision to reality.

Glazing: Custom Bespoke System, designed in-house by Flynn design engineers. Heavy Industries fabricated, welded and supplied the custom glazing pod framing to Flynn’s design and specification. Cladding: Flynn Accumet – Feature exterior undulating triangular rain-screen panel system, integrated with undulating custom triangular aluminum welded pod framing, and glazing elements. Roof: Flynn roofing and green roofing.

FLYNNFLASH | SUMMER 2015

17


COVER STORY: RYERSON UNIVERSITY STUDENT LEARNING CENTRE ■■Submitted with thanks to Michael Roche, Stefano Parnisi, Luis Calderone, Ragu Gopalan and David Craig

TORONTO

Designed by the architectural team of Snøhetta & Zeidler, the stunning new building provides Ryerson students with an outstanding environment to study, collaborate and discover. The eight-storey Student Learning Centre marks Ryerson’s new face on Yonge Street. It features a glass façade, an elevated plaza, a bridge to the existing library and a range of academic, study and collaborative spaces for Ryerson’s students, faculty and staff. Yonge Street frontage will feature destination retail at and below grade, creating a prominent commercial façade. The triple glazed transparent glass skin of the 155,000 squarefoot Student Learning Centre features a surface design consisting of a unique glass digital frit pattern that creates varying light

18

FLYNNFLASH | SUMMER 2015

qualities within the interior space. A Flynn custom unitized curtain wall system 52,000 sq. ft. was designed for the project, the curtain wall was engineered and tested to accommodate the complex varying façade tilt angles and sloped skylights including an integrated mullion detail to accommodate interior mechanical sun shading. The unique glass frit pattern was required to transition onto the adjoining aluminum panel at the North elevation and Flynn, working with a specialist supplier, achieved this effectively through perforating the pattern into the metal panel, 22,000 sq. ft. Another distinctive, unique and complex feature of the building is the custom blue faceted dome ceiling and soffit designed and


had a hand in securing, supporting and delivering this project, it is a credit to you all and the capabilities and professionalism of our Flynn Team!”

executed in Flynn Accumet panel system. The initial intent was for a ceramic blue tile, however working with Snøhetta/Zeidler at the early design stage, Flynn’s Business Development technical advisers put forward a number of panel mockups and material alternatives. Flynn’s Accumet System comprising of lightweight Alpolic-FR (Fire Rated) Prismatic finish ACM in a custom color was the final choice. The ceiling needed to be light weight, meet fire code and also accommodate the unique triangular multifaceted shape and enable cutouts to accommodate mineral fiber acoustic in-fills while maintaining panel integrity and stability, in total 4,448 Blue Panels.

You can see Michael accepting the award in the picture above or by visiting http://www.glasscanadamag.com/event-reports/ogmaawards-at-top-glass-2015-4009

Offsite construction, detailing and execution of the envelope scopes as an integrated entity was paramount to the performance and æsthetic for this project and a Flynn Total Envelope proposal was chosen. Glazing & panels were modeled in 3D software using INVENTOR. Flynn completed the total envelope including the roofing and green roof of 27,000 sq. ft. Notwithstanding the complexities as outlined above, this was a very restricted site at one of the busiest locations in downtown Toronto where safety was the top priority and logistics were very challenging. The result – an iconic landmark, due to the architectural uniqueness of Snøhetta & Zeidler’s design and Flynn’s design, engineering and attention to detail and workmanship of Flynn’s glazing, metals and roofing trades. The general contractor was EllisDon. With many challenges comes rewards, and on April 15th, the Ryerson University Student Learning Centre won OGMA (Ontario Glass and Metal Association) Awards of Excellence in Execution in Metals and Glass by our industry peers, which was accepted by Michael Roche. Michael says “Congratulations to everyone who

Front row (left to right): Alexander Coutinho, Rui Gomes and Victor Costa; Back row (left to right): Jason Kehoe, Carmon Cinnirella and Luis Soares.

Special thanks to the many talented crews who took part in this project and made it possible!

FLYNNFLASH | SUMMER 2015

19


ST. JOSEPH’S HEALTHCARE CENTRE KING CAMPUS ■■Submitted by Dan Castonguay

Two crews have teamed up with Victor Medeiros and Carlos Costa to complete the St. Joseph’s Healthcare King Campus in East Hamilton; a project valued at 1.1 million dollars. The winter conditions made it tough to maintain the customers deadline; however, the crews managed and stayed on pace to meet the expectations of a March 31, 2015 completion date on this 44,000 sq. ft. multilevel BUR pitch roof removal and going back with a very complex multi-layer Polyiso and tapered system covered with a 2-ply modified Soprema membrane from Peto MacCallum Ltd.

HAMILTON

CONGRATULATIONS, TONY BAITA! Congratulations on the retirement of Tony Baita, Project Manager at Flynn Toronto who has held a number of positions since joining the Flynn team 18 years ago as part of the Peerless Acquisition in 1997. Prior to Peerless, Tony worked for Lorlea Steel Ltd. Tony has always had a great ability to relate to his coworkers, earning him the trust and respect of everyone he has worked with, including customers. He always does what is asked without complaining about it, always gets the job done, and always has the best interest of the company on his mind. He has no immediate retirement plans other than following his wife Gail’s renovation plans, travelling, and continuing to take care of his “metals guy hair” that he is so admired for. All the best in your next chapter, Tony!

TORONTO From left to right: Carlos Graca, Antonio Lourenco, Hugo Costa, Agosthino Medeiros, Joseph Raposo, Nuno Pereira, Elio Melo and Carlos Costa (Foreman).

From left to right is Doug Flynn, Jeff Aviss (VP, Ontario & Quebec), Tony Baita (Project Manager, Toronto), Mark Agius (Branch Manager, Toronto) and John McManus.

SHERWOOD CO-OP ■■Submitted by Troy Csada

REGINA

From Left to right: Joseph Raposo, Victor Medeiros (Foreman), Manuel Alexandre, Ryszard Kotowicz, George Costa, Delfim Costa, Jose Leal, Jose Texeira, Gilberto Fernandes and Dylan Medeiros. The Project Estimator was Carlos Dia and the Project Superintendent was Daniel Castonguay.

20

FLYNNFLASH | SUMMER 2015

From left to right is Ryan McAfee, Adam Kuntz and John Krysak (Foreman) installing counter flashing and cap on the Sherwood CO-OP, a 110 sq. BUR new roof.


WINPAK LTD. ■■Submitted by Jeff Clarkson

Carlos and his crew tackled extreme temperatures while reroofing 202 squares and installing a new EPDM roof system. Safety and quality were top priority to ensure all Winpak's employees and manufacturing equipment were protected during the re-roof project. Winpak Ltd. manufactures distributes high-quality packaging materials and related packaging machines. The company's products are used primarily for the protection of perishable foods, beverages and in health care applications.

WINNIPEG

From left to right: Benjamin Flores, Cameron Nagelkop, Marvin Portillo, David Jones, Carlos Ribeiro (Foreman), and Chris Ryan.

CANADIAN TIRE – SOUTH EDMONTON COMMON

BEAVER TRUCKS

■■Submitted by Connie Applin

This is the second roofing project Flynn has performed for Beaver Trucks in Manitoba. Safety and quality are the main reasons that Flynn has been chosen for their roofing needs. Daniel and his crew had a well-organized site throughout with a strong emphasis on housekeeping and material securement because of the high prairie winds and close proximity to the TransCanada Highway!

■■Submitted by Jeff Clarkson

The new Canadian Tire will be one of the biggest of its kind within Canada. At 1330 squares, with multiple levels, this impressive new building will surely be a one-of-a-kind Canadian Tire and a preferred choice for all customers in the South Edmonton area. Flynn worked with general contractor Norson Construction on the project alongside other trades, including Flynn Metals (panels and cladding). Roofing System: Metal deck, loose laid 6mil poly vapour barrier, 2 layers – 1.75” Firestone poly ISO insulation, 60 mil non-reinforced EPDM, ballasted.

BRANDON

EDMONTON

From left to right: Tomasz Zotara, Terry Rideout (Foreman), Ahmed Sawan, Viaceslavas Jr. Barkovskis and Francis Shanley.

From left to right: Kely Neapew, Daniel McLean (Foremen), Bruce Neapew, Jonathan Shlachetka, Larry Neapew and Matthew Teneycke.

FLYNNFLASH | SUMMER 2015

21


SOUTHEAST EDUCATION CENTRE ■■Submitted by Troy Csada

BLACK AND MAC ■■Submitted by Kevin Bereza

For a Black and McDonald job in Saskatoon, the crew installed 16,236 sq. ft. of metal deck. 12,489 sq. ft. of wall cladding including membrane, insulation, subgirts and flashings. The crew also installed 2,500 sq. ft. of Kingzip 4” insulated roof panel. The General Contractor was VCM.

SASKATOON

REGINA From left to right is Tige Shaw, Blaine Prentice, Toby Barney, Spencer Sayer (Foreman), Dustin Geib and Jon Pelletier (Foreman). They are working on a project in Weyburn, Saskatchewan called Southeast Education Centre. It consists of 130 squares of metal cladding and 34 squares of Accumet 2000.

The crew working on the project, from left to right, was Glen Landell, Foreman Tyler Walls, and Kane Schmidt. Not pictured but also on the project was Ray Blahey.

PARKTOWN HOTEL

KEARL LAKE (KFTT)

■■Submitted by Terry Ozmun

■■Submitted by Connie Applin

Flynn Saskatoon was called by the Parktown Hotel to look after another large ice formation 50 to 60 feet in height from a broken water line that ran all night. Mobilization was done within 24 hours as with warmer temperatures coming in, there was fear of the ice collapsing. The next morning, a steam truck with 1000 gallons of hot water and an 80 lift was dispatched to site to bring the giant. The Foreman on site was Grant Greba.

This is the second contract Flynn Industrial Ltd. has picked up for Kearl Lake (KFTT) working on finishing site completions (PIR panels, gutters/downspouts, and penetrations) for module constructed in the Mod Yard with Kiewit for Imperial Oil. The crew has done such an amazing job that they helped get awarded two storage tanks to construct onsite that are 56 meters in diameter!

SASKATOON

EDMONTON From left to right: Kyley Page, Mark Mullan, Joel Maurice and Guy Drisedelle.

22

FLYNNFLASH | SUMMER 2015


SHAW COURT ■■Submitted by April Luscombe

The original Shaw Court building was built approximately 28 years ago. In 2012, there was a fire in the generator room, which resulted in extensive flooding in the building. Flynn won the full envelope contract with Stuart Olson incorporating metal, glazing, and roofing as a synergy project. Flynn started on site in March 2014 and completed the project in April 2015. The building, from top to bottom, consists of 10,000 sq. ft. of Corten 1 composite panels, 12,000 sq. ft. of Levolux louver screens, 16,000 sq. ft. of green roofs surrounded by glass balustrade wind screen. The main entrance is enclosed by Novem suspension glazing with 7,000 sq. ft. of Zahner solanum and 2,500 sq. ft. of phenolic panel features around the main doors. The front entry contains Stanley revolving

CALGARY doors, Kawneer personnel double doors, and Tyndall stone/ glazing feature wall along with Zahner feature planters to the podium outside.

From left to right: Bert St. Dennis, Alex Adams, Paul Brown, Roman Ruranski, Brendan Dooley, Rob Anderson, Al Light, Terry Kavanaugh, Nikolas Neider, Candice Martinuk, Eric Mitchell, Shayna White, James Cameron, Guy Cotterhill, Andrew Warnick, Brianne Snyder, Danny Tangen, Piotr Wozniak, John Greenwood, Amine Feki, Chris Moore and Shylar Viney.

DELTA +15 ■■Submitted by Courtney Verhelst

CALGARY

Flynn’s service department is pleased to be working with CBRE Limited on this special roof replacement project. Four of Calgary’s skilled service men were tasked with installing 350 sq. ft. of cold applied SBS roof at Delta +15 located in downtown Calgary. The site is a high safety environment and the crews did an excellent job of adhering to the safety requirements. From the demolition to the supply and install of the roofing and sheet metal, this job was completed as a success! Good work gentlemen! From left to right: Wally Netik (Foreman), John Corrigal, David Molloy and Jason Remillard.

FLYNNFLASH | SUMMER 2015

23


FLYNNCREW.com

IS HERE!


FLYNNCREW.COM

Frequently Asked Questions

What is FlynnCrew.com? FlynnCrew.com is our new employee website keeping us all connected and up to date on the latest news and information on our company as a whole, as well as our branches.

What will I find there? On the main page called “Flynn Central”, you’ll find out more about our expansion in the US, big projects, awards, our Safety Programs and Initiatives, scholarship opportunities for children of Flynn employees, our Employee Referral Program, biographies on Flynn’s leaders, contacts, Flynn University, the latest edition of the Flynn Flash, brand new Flynn Videos and of course…MONTHLY COMPETITIONS SO YOU CAN WIN WITH FLYNN! On your branch page, you’ll find: A history of branch projects, upcoming branch events, marriage announcements, baby announcements, charity/sports involvement, thank you letters and letters of appreciation, local weather forecasts, links to our Facebook group that is growing everyday, and more.

How do I get on the site? Just type in flynncrew.com in any browser on your computer, or your mobile device. If it’s your first time visiting you’ll need to click “Register” which is quick and easy. You can: 1. Register using one of your existing Social Media Accounts like Facebook, Twitter, LinkedIn, Google Mail… or… 2. Simply enter your first and last name, your email address, choose your branch from the dropdown menu, set a password and click “create account”

If you have any questions, or story ideas you’d like to submit contact: Kim Hutchison Communications Specialist 905-671-3971 x 1359 Kim.Hutchison@flynncompanies.com (for St. John’s, Halifax, Moncton, Montreal, Ottawa, Sudbury, Hamilton, Cambridge, Toronto, London, Brandon, Winnipeg, Saskatoon and Regina). Or Amanda Schaefer Marketing Administrator 816-874-4478 Amanda.Schaefer@flynncompanies.com (for Calgary, Edmonton, Kelowna, Victoria, Vancouver, Minneapolis, Baltimore, Kansas City, Springfield, Phoenix and Flagstaff).

FLYNNFLASH | SUMMER 2015

27


BRANDON SHOPPERS MALL

SASKATOON INN

■■Submitted by Luis Gravito

■■Submitted by Sean Thompson

BRANDON

Randy Monkman and David McGregor joined together their two crews for a productive day on the Brandon Shoppers Mall to take advantage of the nice weather.

BONNIE DOON POOL ■■Submitted by Connie Applin

This project was undertaken with the City of Edmonton, and safety and scheduling were very critical on this job. With the high school just a stone’s throw away, and the general public near the vicinity, the crew had to make sure the site was properly secured at all times and safety was top notch. The crew consisted of Rob Albert (Foreman), James Mcgee, Essa Treish, Corey Primeau, Shane Cornelius and Barkovskis Viaceaslavas, Jr. Crew safety was impeccable and coordination within the labour budget allocated and within schedule. The city was very impressed with the professionalism displayed by the crew during the life of the project. Roofing system: Remove roof to expose metal deck, torch new VB, adhere insulation in Duotack, torch base protection board, torch cap.

EDMONTON

SASKATOON

For the Saskatoon Inn, Flynn is the General Contractor. This 400 square project involved the removal of existing SBS roof Flynn completed 15 yrs. ago replaced with new SBS. The stair scaffold was required due to mansard roof surrounding the entire building. Guardrails were not required as the parapet height met the requirements. Crews continue to work around the hotel’s schedule as they had certain days during the week in which they were not allowed to work due to the noise it caused. They came to an agreement that they would never rip roof on those “shutdown days”; however, tried to get some insulating and membrane complete or cap sheet as this was a quieter task. It's been difficult juggling activities each day for the men, but they are staying on track and progressing!

WELCOME KEN! We are happy to welcome Kenneth Handy to our Flynn Group of Companies! Handy is the new HR Officer in Edmonton. He has been in the construction industry for six years developing his skills in human resources, business development, and account management. As officer, his main focus will be full cycle recruitment and management of the apprenticeship program and associated internal logistics for the Alberta region. Ken looks forward to expanding his knowledge of Kenneth Handy HR Officer, Edmonton the company’s departments and operations and working with the teams to “further increase Flynn’s presence as a market leader”. He says, “It is an exciting time to be at Flynn, given its ongoing success and tremendous growth.” We’re happy to have you, Ken!

FLYNNFLASH | SUMMER 2015

29


WOMEN’S HOSPITAL ■■Submitted by: Breanne Vanlinge

WINNIPEG

PYLYPOW #10 ■■Submitted by Connie Applin

Foreman Chris Vladicka and crew completed the installation of a loose laid and ballasted 60 mil non-reinforced EPDM roof system on the Pylypow #10 project for local General Contractor Kemway Construction. In a continued growing business relationship, Kemway and Flynn have been working together more often as Flynn has become Kemway’s number one choice when it comes to single-ply roofing installation. With an impressive safety record, project progress, and management, this client relationship is sure to grow continuously over the next few years. Roofing System: Metal deck, loose laid 6 mil poly vapour barrier, 1 layer – 5.33” Type 1 EPS, 60 mil non-reinforced EPDM, ballasted

EDMONTON Flynn production has been working on the Women's Hospital redevelopment project since the summer of 2014. Since the job started, there have been several different crews working on the multi-level building, applying mainly a modified-bituminous membrane roofing system. The crew communicated very well with each other, as well as with other trades working in close proximity. We commend Elkin and the crew for maintaining a safe jobsite, as well as having all safety documentation and paper work in check.

From left to right: Sean Ducharme, Elkin Vergara, Tom Watcher, Viktor Huk, Volodymyr Veselyuk and Yuriy Tovarnytskyy.

30

FLYNNFLASH | SUMMER 2015

From left to right: Wieslaw Lazar, James Mcgee, Chris Vladicka (Foreman), Corey Primeau and Arkadiusz Lazar.

PEREGRINE POINT ■■Submitted by Connie Applin

Crews replaced the substandard and leaking metal roof of an existing apartment building in downtown Edmonton with a more appropriate ARCA warrantied roof system. The installation was made particularly challenging by the 12:12 pitch of the roof along with the complex architectural design. The 12-story building, which contains 69 occupied apartments, is accessed by mast-climbers platforms and a complicated scaffold system.

EDMONTON From left to right: Damien Gardiner, Tom Sawers, Mike Spencer, Mahamed Sahal, Mark Barkley, Morgan Lauriks, John Burrell, Matt Richards, Rodney Jewell, Bill Smith and Dean Kline.


LEDCOR MOD YARD ■■Submitted by Connie Applin

Foreman Derek Saindon and his team are undertaking the installation of wall and soffit cladding, roof deck, internal fire rated walls, and main doors on 25 modular buildings at the Ledcor Mod Yard, Edmonton. One of the challenges is meeting an extremely tight schedule. Once complete, each modular building is transported by road to its final destination at the K + S site in Saskatchewan. Due to the weight of each building, there are only certain periods of the year when these can be transported.

EDMONTON

From left to right: Wayne Ebel, Calvin Johnston, Jamie Ebel, William Ritchie, James Cherry, Mike Smith, Kristian Lear, Greg Wolak, Denny Mills, Dwayne Turner, Curtis Smith, Daniel Viecelli, Jory Cuthill, Dan Weiss, Mykal Chapman, Chris Chapman, Vladimir Hristov, Darcy Hanlon, Derek Saindon (Foreman) and John Shain. Not pictured: Colin Gosselin.

ETS PROJECT

ICONE CONDOS

■■Submitted by Marc Bilodeau

■■Submitted by Marc Bilodeau

Foreman Claude Beaucgesne and the crew worked on this project that included Unitized Curtain Wall from NFL and Curtain Wall Stick from Vitreco. The Glass Ceramic Pattern is from Prelco (Print Jet).

Martin Morin (Foreman) and his crew were working on the 7th and 8th floors of the 40‑floor Icone Condos in downtown Montreal when this photo was taken. They used Curtain Wall Stick from Vitreco and Unitized from NFL.

MONTREAL

MONTREAL

FLYNNFLASH | SUMMER 2015

31


MUSÉE DES BEAUX-ARTS DE MONTRÉAL (MONTREAL MUSEUM OF FINE ART) ■■Submitted by Marc Bilodeau

Marc Bilodeau and Foreman André De Sousa are pictured at the Musée des Beaux-Arts de Montréal, Pavillon 5. Work consists of Curtain Wall at 10’’ depth with steel reinforcement. In the near future, this Curtail should retain 38000 pounds of granite stick.

MONTREAL

MYST CONDOS ■■Submitted by Marc Bilodeau

Foreman Francis Labonté and crews are working on MYST Condos. Pictured is Curtain Wall Stick from Vitreco. All thermos is made with Shucco Spaces because all of the project should be four sides of silicone.

MONTREAL

32

FLYNNFLASH | SUMMER 2015


THE ORPHEUM THEATRE ■■Submitted by Blaine Braun

VANCOUVER

MEC – ANOTHER FLYNN SUCCESS Flynn Vancouver has another project to be proud of. Located just outside Vancouver’s downtown core, Mountain Equipment Coop (MEC) head office was a project that combined practical and effective installation with cooperative efforts of multiple Flynn scopes.

VANCOUVER

Faced with challenges ranging from the elements to access, the Flynn team overcame every hurdle in its path to install quality, finished products. Led by Robert Reynolds, Dan Henning and Kris Lemire, Flynn Glazing performed admirably on this project with an exterior scope that included curtain wall and guardrails. Equally impressive was the team’s execution of an atypical interior glazing package that included back painted glass, magnetic glass boards, all-glass doors, and TVS glazing. Great job guys! Our Architectural Panels division performed equally as well. Led by veteran Foreman Bryce Young, panel crews turned the MEC project into an exercise of precision installation and seamless integration of systems. Here, the visual end product speaks for itself, where interlocking hidden fastener wall panels, standing seam panels, steel decking, Swisspearl, and ‘Oko skin’ wood finished panels blend together to create a modern and quintessentially “West Coast” look. Truly impressive - well done team!

The Orpheum Theatre in Vancouver is considered one of the jewels of Vancouver’s history. It was Vancouver’s largest vaudeville movie palace from the first half of the 20th century and is the only one of its scale in Vancouver to survive. The building is located in the heart of the downtown district and presented multiple setup and access issues. Minimal site storage, multiple roof levels, and snarling downtown traffic for hours at a time while loading/downloading had its challenges for our crew. Thanks guys for a job well done! The crew that worked on this project included Anthony Ly, Son Le, Da Vu, Shane Hildebrand, Miles McColl and Will Foster.

Equal thanks go to the Project Management Team and Superintendents, who steered the ship and reinforced the cooperative efforts that ensured the success of MEC. Thanks go to Boyd Butler (Project Manager), Rey Medina (Project Coordinator), Bruce Leckie (Glazing Superintendent), and Ryan Young (Architectural Panels Superintendent). An all-around great effort by every member of this project – thanks team.

FLYNNFLASH | SUMMER 2015

33


34

FLYNNFLASH | SUMMER 2015


FLYNNFLASH | SUMMER 2015

35


MEDICINE HAT REGIONAL HOSPITAL

VANCOUVER

■■Submitted by Romeo Tarrayo

Start with 27,880 feet of extrusions; 12,302 feet of gaskets; 32,391 screws; 10 trailer loads; and 242 frames as the main ingredients needed to complete this project. Throw in the expertise of three branches (Edmonton led by Tamer Rouby, NFL via Jeremy Lian, and the team of Vancouver) and Flynn’s got the makings of a successful venture. These three teams worked in collaboration to achieve a common goal – to manufacture and install products that were done safely, with the best quality, complete and on time. Of course no jobs come without challenges, but with relentless planning, positive “arguments”, and weekly checks and balances, the glitches were met with solutions and lessons learned. The constant communication led by Vancouver’s Igor Radvan pre-empted a lot of potential show stoppers while Sandro Simicic quarterbacked the fabrication to ensure promised dates were met. Justin Edmiston was able to “grind down” a deal with a trucking service that was efficient and respectful to deal with. On the floor, Kevin Martel kept an eye on quality until his eyes turned red.

The feedback from Tamer Rouby was that Flynn was the “Prime Star” of the job and the owners will highly recommend Flynn for other projects. The building envelope consultant was satisfied with the quality and cooperation on site. Unlike other trades, our site glazing team will not incur any back charges. Feedback that certainly makes everyone involved very proud. Vancouver glazing team from left to right: Justin Edmiston, Sid Boudreau, Romy Tarrayo, Greg Fawcett, Brian Ferrar, Shawn Futerko, Sandro Simicic, Peter Nguyen, Keving Martel, Roderick Simicic, Igor Radvan, Livia Bogdan, Mark Rasley, Nonn Thuon, Jimmy Yon, Nin San, Phong Lang, Hung Nguyen, Lawrence Christensen and Stephen O’Connor.

VANCOUVER TRIM SHOP ■■Submitted by Romeo Tarrayo

Flynn Vancouver continues to build and thrive, thanks in no small part to the growing experience and expertise of its Trim Shop. For the past 11 years, the shop has acted as an anchor for Vancouver field forces for all scopes; providing flashing, girts, snap-lock panels, backpans, roll-forming, and custom orders of every shape, size, and material. Led by the same Foremen since day one of operations, Rav Sandhu has worked tirelessly to build, train, and mentor his team. Management has supported the shop with new breaks, shears, and technology, and the team is adapting and flourishing while taking on the new challenges the Lower Mainland construction has to offer. Flynn Vancouver is proud and grateful to one of its “unsung heroes” in the Trim Shop. Great job guys! Throw anything their way – They Can Do It!

VANCOUVER 36

FLYNNFLASH | SUMMER 2015

From left to right: Rav Sandhu, Kevin Anderson, Samir Beganovic, Romy Tarrayo, Geoff Wallin, Johnson Fong, Steve Stone, Jonathan Shortt, Ernie Taschner and Chris Limpright.


UBC STUDENT UNION

VANCOUVER

■■Submitted by Joe da Costa

Along with Bird Construction, Flynn recently completed the new Student Union Building at the University of British Columbia. The project consisted of 100,000 sq. ft. of roofing on 22 different roofs composed of a white SRI 2-ply bituminous membrane, waterproofing, and damp proofing. This project had its challenges, as it was phased construction with a very aggressive schedule of completion, including limited access due to construction and pedestrian traffic. The crew did an exceptional job meeting their goals. Great job guys. From left to right: Carlos Gomez, Phung Nguyen, Don Kristensen (Foreman), Quang Tran, Petr Pham and Mike Le.

TOUCHDOWN AT YVR AIRSIDE OPERATIONS BUILDING ■■Submitted by Benjamin Hayes

The Vancouver Branch was chosen by General Contractor Graham Construction & Engineering, Inc. for this exciting multi-scope project at the Vancouver Airport. It consisted of three buildings located in the middle of the airport taxiways for everyone to see who passes through the airport. This new facility will replace the existing fire hall and maintenance building. The project was a great example of what Flynn is all about.

VANCOUVER

There’s over 70,000 sq. ft. of metal cladding and accumet panel with a feature wall that has curved panels and a custom gutter system. It also includes custom interior and exterior door surrounds, architectural louvers, exterior curtain wall, skylights, interior storefront, glass guardrails, and custom sunshades. The project schedule was demanding and require a large crew to complete, which was led by Stelios Papanicolaou, Aaron Andrews, Pat Lodge, Dave Sheridan, Ciaran Brenan, Kyle Wakely, Tim Schlinkmann, Flaviano Managuelod, Michael Hayes, Corey Brewer, Colin Nagle, Jordy Neilson, Josh Brown, Kevin Peck and Christian Stockley. It was an excellent display of our safety and quality!

NAV CANADA PENTICTON AIRPORT TOWER ■■Submitted by Chris Sitter

TJ Vandale and his crew successfully completed a 1200 sq. ft. re-roof of the Penticton airport control tower. The project involved removal of existing system and installing a new roof assembly consisting of densdeck, SBS vapour barrier, two layers of poly ISO, densdeck cover board, two plies of SBS membrane and new sheet metal flashing. On top of the roofing scope TJ and his team also installed a new, engineered structural steel perimeter guardrail system, a new emergency access door, a new access hatch complete with structural steel supports, and a new ceiling mounted attic access ladder. The guys really showed that not only are they excellent roofers, but they are excellent all around tradesmen. Way to go team!

KELOWNA From left to right: TJ Vandale, Kendle Beckingham and Jonathon Roberts. Not pictured: Randy Alexander, Kevin Martin and Stuart MacKenzie.

FLYNNFLASH | SUMMER 2015

37


THE LEXINGTON PHASE 2

ROGERS COMMUNICATIONS INC. ■■Submitted by Joe da Costa

■■Submitted by Chris Sitter

Justyn Barber and Don Gaff worked as a team to complete Phase 2 of a tile repair job at The Lexington. The project involved removing ridge caps, installing self-adhered membrane, and re-installing the ridge caps. Barber and Gaff were able to successfully complete this project despite having to demobilize and remobilize several times to attend to leak calls and other service projects. Good work boys!

KELOWNA

The Vancouver roofing department was awarded the re-roof project at Rogers Communications. The building is the home of City TV Vancouver, SportsNet West, and Onni Television – where news, sports, etc. are aired live throughout the day. The project consists of a complete demolition of the existing 19,800 sq. ft. roof and installation of a new Soprema 2-ply Colply ballasted system. This project has been one of the toughest roofing projects completed in recent history in Vancouver, due to the amount of equipment on the roof, as well as having a strict window of work from 9:30 AM to 2:30 PM. Ken Nguyen and crew have done an excellent job in keeping disruption to Rogers Inc. staff to a very minimum, as well as putting a valiant effort in working weekends and holidays, all in an effort to getting the job complete on schedule. Keep up the good work boys. From left to right: (back row) Tai Dang, Hanh Pham, Richard Gryz, Joe da Costa, Paul Manchisi, John Silva, Marcel Perri, (front row) Sau Dinh, Anthony Van, Ken Nguyen. Not pictured: Thu Nguyen.

ROOFING IN NANAIMO ■■Submitted by Gary Stride

This Victoria crew is working in Nanaimo, about 100 km north of Victoria, at the new BC Hydro Operations Centre. Construction of this building meets the “Post Disaster Requirements” of the BC Building Code. Restoring and maintaining electricity after an emergency is a high priority for Emergency Management. “Post Disaster Requirement” compliance mandates that the resistance to seismically induced strain is increased to 1.5 times and the roof fastening requirements are increased to 1.25 times the Building Code. The roof deck of this Operations Centre is of “Nail-lam” construction; 2” x 6” dimensional lumber laid on edge spanning over OWSJ and wide flange beams. If all of the boards that were used in this roof were placed end-to-end, they would span 76 miles!

VICTORIA From left to right: Kyle Ennis, Greg Stannix, Mike Rowland (Foreman), Eric Smirnjak, Darren Brown, Colin Lowrey, Matt Sladich and Stan Craig.

38

FLYNNFLASH | SUMMER 2015

VANCOUVER

100 MILE HOUSE SAFEWAY ■■Submitted by Gary Stride

A Victoria crew led by Wahib Othman and Sean Williams travelled to 100 Mile House for some roofing and metal work on the local Safeway. 100 Mile House is in the South Cariboo on the Cariboo Highway, midway between Kamloops and Prince George. Our work here involved the removal and replacement of the front canopy, removal of cedar shakes, application of waterproofing, and a standing seam roof.

VICTORIA From left to right: Jordan Cooke, Scott Cameron, Sean Williams (Metals Foreman). Not pictured: Whahib Othman (Roofing Foreman).


CAMOSUN COLLEGE TRADES CENTRE ■■Submitted by Gary Stride

Camosun College is the largest Community College on Vancouver Island. Two separate campuses serve almost 20,000 students in both academic and trades training. The Camosun College Trades Centre has been developed to address the predicted trades shortages in Western Canada. This centre will house the training facilities for the revitalized shipbuilding industry in Canada, including marine and metal trades and heavy-duty automotive mechanical repair training. This LEED project will be constructed to the Gold Environmental Standard. Our scope of work on this 80,000 sq. ft. project includes Kingspan panels, metal roofing, siding, glazing, and flat roofing. Foreman Shawn Mason and crew are currently installing the Kingspan panels.

THANK YOU – KELOWNA Dear Mr. Flynn, A Company is judged by the efforts/ attitudes of its employees and those employees in return, reflect the effort/ attitude of their LEADER. It gives us great pleasure, to commend Mr. Chris Sitter (Superintendent of your Kelowna, B.C. Division) for the EXCEPTIONAL, OUTSTANDING SERVICE, we received from Mr. Chris Sitter AND his staff. From his initial quote – very detailed, with additional photos and explanations – to the actual work done (again, documented in a report with photos added) , this was a MOST IMPRESSIVE experience for us.

VICTORIA From left to right: Josh Ketola, James Michalski, Eric Duchesne, Shawn Mason (Foreman), Matt Fisher and Thomas Cordner. Missing: Dave Petrie. Foreman Geoff Myers and crew have five roofs (63,000 sq. ft. of SBS) to complete on this LEED project. There are currently 2,200 student seats in 20 different trades training programs on campus. Once complete, an additional 370 seats will be available. When this building is populated, the existing buildings on campus will be renovated. This project also meets the requirements of the “Wood First Act” – a provincial statute enacted in 2009 to promote the use of wood in provincially funded projects.

Mr. Sitter’s professionalism, his commitment, his integrity and his ethics, combined with his engaging attitude are a perfect combination! Mr. Sitter understands the importance of giving his customer the best service possible – his standards are VERY HIGH and his staff reflects that. Ms. Kimberly Gaskill's (Admin. Manager) help was UNEXPECTED and therefore it was VERY MUCH APPRECIATED. THANK YOU – Mr. Chris Sitter, Ms. Kimberly Gaskill, as well as Ms. Nancy Thiessen , T.J. and Kendel – you were a GREAT TEAM. Needless to say that we will recommend the Kelowna Division of Flynn Canada Ltd. when/where ever we can. Sincerely,

From left to right: Geoff Myers (Foreman), Jun Manzon, Ron Hill, Dylan Solecki, Kyle Heinz, Ross MacKay, Dean Craggs, Jacob Johnson, Jeff Kwizza and Rey Garcia.

Irene and Steven Popyk

FLYNNFLASH | SUMMER 2015

39


BUILDING DY250 CFB ESQUIMALT ■■Submitted by Gary Stride

VICTORIA

Building DY250 is the major physical component of the Fleet Maintenance Facility Shop Consolidation Project for the Maritime Forces Pacific at CFB Esquimalt. This facility is a strategic naval asset that supports the Canadian Pacific Fleet. With a footprint covering the area of seven football fields, it is reportedly the second largest building on the west coast of North America (the Boeing plant in Everett, Washington is the largest). 1,091 civilians work in this building alongside 156 military members.

Flynn’s crews (roofing, metal, and glazing) have been working on the renovations and expansion on the existing structure. Mike Pilling and his crew have been removing and installing new cladding, vapour barrier, and insulation on this current phase of the project.

The naval base was first opened in 1842. Many of the existing shops on the base are over 100 years old, built with bricks that the early sailing ships used as ballast. Once complete in 2018, Building DY250 will incorporate most of the shops that are currently scattered throughout the base in the antiquated buildings. In the planning stages since 1977, DY250 will house the maintenance, fabrication, testing and diagnostics of the navigational, communications, operations, and weapons systems used by the Royal Canadian Navy. A limited amount of R & D is routinely carried out here for the Army and Air Force, as well.

From left to right: Andrew Lohr, Mark O’Hanley, Mike Pilling (Foreman) and Jason O’Hanley.

40

FLYNNFLASH | SUMMER 2015

Brothers Kevin Lohr (Foreman) and Andrew Lohr are shown above putting the finishing touches on the window install on Work Package 6 of the project. Earlier in the year, our Vancouver branch worked with Victoria on another phase of the glazing aspect of this project.


EVERGREEN RAPID TRANSIT ■■Submitted by John Ngo

Flynn Vancouver is happy to be working with SLCW for the design assist and construction of the new Evergreen rapid transit system spanning three cities, 12 buildings, and three scopes of work (glazing, metals, and roofing). The project consists of point fixed fittings, storefront glazing, guardrails, canopies, doors, smoke baffles, faregate barriers, composite panels, metal flashings, snow guards, standing seams, and Kalzip.

built next to CP rail tracks. With these stations having small footprints and difficult access, the construction team had to come up with innovative ways to get the products on the wall, such as creating a custom rail cart to transport our Jekko crane and glass racks along the tracks, and building a 30 ft. high scaffold structure to support our 20’ x 8’ Kalzip machine all the way from Germany in order to run our metal roof panels (as long as 160 ft.) directly onto the roof.

The Service Department was tasked with installation of all TPO and Latchway fall protection products. With a project awarded based on 50 per cent drawings, the Project Management team (John Ngo – Project Manager, Denise Francisco and Charles Thurlow – Project Coordinators) was faced with many challenges from the beginning, such as trying to maintain budget with constant design changes on a daily basis, as well as keeping up with the demands of the client’s multiple construction teams. Access was, and is, the biggest challenge on this project thus far. There is a station tied to an existing running station, as well as several stations

Thanks to the collaborative efforts of JP Schmidt, Ryan Young, Billy Yorke (Glazing, Metals & Service Superintendent), Brett Templeman and Stuart Kent (Glazing Foremen), and Bryce Young (Metals Foreman) for thinking outside the box, with which we were able to overcome all the obstacles. With the new 3D surveying technology, we were able to measure, layout, and order glass and metal panels without the need to bring out the tape measure or go on a man lift. We could save time, money, and be accurate to the millimetre. The project is 25 per cent complete and will run until the end of 2015.

VANCOUVER

From left to right: Brett Templeman, Bryce Young, Ciaran Brennan, Tony Miller, Jessi Castellarin, Michal Lampa, Stuart Kent, Steve Bell, Dustin Castellarin, Randy Alexander, Bryce Gougeon, Kris Bujak, Pat Lodge and Stacey Wurst. Not pictured: Dave Giacomazzi, Josh Brown, Victoria Krenz, Tyler Manweiler, Rafal Strzelecki, Tim Shlinkmann, Aaron Andrews, Flaviano Managuelod, Colin Nagle and Chase Taylor.

FLYNNFLASH | SUMMER 2015

41


TRUDY KELLY RETIRES FROM FLYNN HALIFAX Special thanks to Trudy Kelly, Branch Administrator at Flynn Halifax, for all of her hard work, loyalty and professionalism; not to mention the fact she has trained a good many Branch Managers in the last 14 years!

HALIFAX

FLYNN WINS CRCA ROOFING CANADA AWARD TWO YEARS IN A ROW! We are pleased to share that, for the second year in a row, Flynn has received the CRCA Roofing Canada Award – this year for the Bow Valley Green Roof Project in Calgary. The award was presented at the CRCA Annual General Meeting on May 4th in Vancouver and was accepted by Stephen Teal. In addition to being recognized at the AGM, we will also be featured in the fall/winter edition of the Roofing Canada Magazine. Great job to everyone involved! Below is a message Communications Specialist Kim Hutchison received letting her know the submission was successful: Good afternoon Kim (Hutchison) Congratulations to Flynn Canada Ltd. on winning the 2015 Roofing Canada Award for your Bow Valley College Green Roof submission. Winning two years in a row is one heck of an achievement. Please find attached the letter detailing the win. Please note that since the winner will only be officially announced on May 4th, I would ask that you please keep your win confidential until Flynn actually receives the award.

Keith Courage (VP Atlantic Region) and Trudy Kelly (Branch Administrator, Flynn Halifax)

Doug Flynn said, “I can still remember Trudy on that treadmill in the front of the office in “The Park” in 2000. Our operations in Atlantic Canada have come a long way since that time, and the successes we have had are in no small part thanks to Trudy and her selflessness and willingness to help others.” He continued, “Over the years, I have noticed that there are two types of people in this world; the type of people who light up a room when they enter, and then the type of people where the room lights up after they leave. There is no doubt what category you fit into Trudy, and I know all who have had the pleasure to work with you will miss your positive attitude.” Richard Gryz who worked with Trudy during his time at our Halifax branch says “Trudy, congratulations on your retirement. It is well deserved. Your smile and your infectious laugh made me feel welcome the moment I walked through the door. I thank you for that. I will always cherish my time with you and the others in the Halifax branch. I know that you really enjoyed your trip last year and that you intend to do more travelling. Enjoy yourself and spread that East Coast hospitality wherever your travels take you.” Thanks again Trudy, have a wonderful retirement! You have earned it. 42

FLYNNFLASH | SUMMER 2015

In the event that you have any questions, please do not hesitate to contact either myself of Gisele Vincent directly. Regards, Bob Brunet, CAE, BComm Executive Director Canadian Roofing Contractors' Association (CRCA)


FIRESTONE MASTER CONTRACTOR AWARDS Flynn Canada earned the 2015 Master Contractor Award from Firestone Building Products Company. In addition, Flynn also achieved Inner Circle of Quality Status. “The Annual Master Contractor Program Recognizes our best contractor firms dedicated to installing roofing systems that help commercial buildings achieve long-term performance” said Tim Dunn, president of Firestone Building Products. We’re proud to have offered this award for the last 28 years to recognize our trusted contractor partners who are some of the best in the industry.” Flynn Sellers & Marquis (now operating as Flynn Midwest) also received the Firestone Building Products Master Contractor award for a sixth time, and have received the Inner Circle of Quality Award for the second time. “I commend Flynn Sellers & Marquis for its commitment to quality in 2014, for upholding the high commercial roofing performance standards set forth by Firestone Building Products. We are pleased to recognize Flynn Sellers & Marquis for earning two of the commercial industry’s most distinguished honors and look forward to continuing our partnership in 2015.” Congrats to everyone involved!

T.A.S.K. SUBMISSIONS & WINNER

DUCK TALES Luis Soares found this baby duck on site at the York University project. He cared for it for a few days before finding its mother and siblings!

TEAMWORK ATTITUDE SHARING KNOWLEDGE Our TASK Program (Team/Attitude/Sharing/Knowledge) was designed to promote and share best practices among our branches. Do you have an idea you’d like to submit for review and publication in the next Flynn Flash? If your idea is selected and used, you will also receive a $200 cheque. Ideas can be submitted on the Portal, www.flynncrew.com or to Communications Specialist Kim Hutchison at Kim.Hutchison@flynncompanies.com. Please remember to include your name, branch, a full description of your idea, and photos to accompany it. Thanks and keep those great TASK ideas coming in!

FLYNNFLASH | SUMMER 2015

43


FLYNN BEST PRACTICES ■■Submitted by Jeff Small

VEE MANIFOLD The Vee Manifold from RoofTop Equipment is an improved dispenser for low rise foam adhesive. Its patented design allows a smooth flow of material through the manifold and prevents clogging. Unlike the conventional aluminum block manifolds the Vee Manifold does not require applications of lithium grease to prevent clogging and material will still flow freely after sitting for several days. In the event that the manifold does become blocked it can be easily cleared using an included drill bit. This manifold is compatible with all of the bulk dispensers that Flynn owns, both bag in box and drums.

FLYNN KIN

■■Submitted by Kim Hutchison

FLAT STANLEY VISITS FLYNN TORONTO Pictured is Figgy Wills (daughter of Kelly Wills and Graeme Wills, Metals Foreman at Flynn Edmonton) holding her “Flat Stanley.” Students in Figgy’s class were asked to send their Stanley off to a different location in Canada, and have him sent back with photos and information about his travels ultimately promoting literacy and geography. Figgy asked if she could send Stanley to our Flynn Toronto Branch. While here, Stanley had his picture taken President and CEO, Doug Flynn, COO, John McManus, Director of Health and Safety, Sean Wurster, our Human Resources Team, and our Marketing and Communications team sent Stanley back with a few souvenirs too. Thanks, Figgy!

Taya, age 3, Daughter of David McAdam from Flynn Halifax, was sporting her dad's hard hat...a nice reminder why safety is, and will always be, so important here at Flynn!

VEE MANIFOLD'S STRAIGHT TUBES ENSURE A SMOOTH FLOW OF MATERIAL.

44

FLYNNFLASH | SUMMER 2015


Rivers Campbell, son of Safety Specialist Mark Campbell from Flynn Halifax, looks super comfy and super adorable in this Flynn Hoodie!

Julia Di Santo, 4, daughter of Anna Rozmyslowicz in our Flynn Toronto Branch, was sporting her Flynn Touque to help get through the month of February – one of Toronto’s coldest on record since February, 1875!

Another great photo for our "Flynn Kin" collection! Here is Haleema Othman - daughter of Wahib Othman from our Flynn Victoria Branch!

Mickenzie, daughter of Curtis Lelacheur from Flynn Halifax, looks so stylish in her dad's hard hat - a great reminder that at the end of the day, it's all about making it home safe and sound! So cute!

Lindsay Beaton’s children (Flynn Halifax) Jack (5) and Charli (1) are looking great in their Flynn Gear! Thanks for Sharing!

Clayton Deich, 2, is showing dad Ryan Deich of Flynn Midwest – Kansas City how to wear his hard hat. Thanks for sharing with us.

FLYNNFLASH | SUMMER 2015

45


IN THE COMMUNITY CONNECT TO CAREERS JOB FAIR Katie Dolan, Kim Golberg, and Josh Overholt manned the booth at the “Connect to Careers” Job Fair at the Hamilton Convention Centre! #CtoCJobFair2015.

DENIM DAY AT FLYNN MIDWEST Flynn employees at our Kansas City Branch supported Denim Day. They are pictured in their jeans in an effort to raise awareness against sexual assault. To learn more about the cause and the reason they chose to wear denim, visit http://denimdayusa.org. Way to go KC!

GET PINK’D Pictured from left to right is Ashley Kenway, William Kennedy, Tonia Dawe, Ian Barrett, Jillian Squires and Anthony Upwards proudly supporting the “Get Pink’d Campaign” for Breast Cancer Awareness. Flynn St. John’s joined forces with suppliers/contractors and successfully raised $500.00 for the cause! Great job, St. John’s!

DEFI CANDEREL FUNDRAISER Philippe Thivierg, Dominic Dégarie, Geneviève Forcier, Pascal Vanasse, François Demers and Tony Bacile represented Vitreco during the Defi Canderel fundraiser for Cancer held in Montreal on May 13th. Over $1 million was raised that day. Great job, everyone! To learn more about this fundraiser, you can visit www.deficanderel.com/

CLOWNING AROUND Vancouver Foreman Don Kristensen was helping out in Lethbridge, Alberta, and was lucky enough to meet Ronald McDonald while at lunch.

46

FLYNNFLASH | SUMMER 2015


CAMP BARNARD

FLYNN “K9 UNIT”

■■Submitted by Marnie Pullman

■■Submitted by Romy Tarrayo

Camp Barnard is located in Otter Point, just west of Sooke on Vancouver Island and is a 250 acre camp used year round by a variety of youth and adult organizations. Camp Barnard has been providing a nurturing environment for people to learn new skills and experience nature for more than 70 years.

Last year Flynn Vancouver was visited by the US Border Services, the Washington State Patrol, the Whatcom County Sheriff’s Office, and the Delta and Surrey RCMP. No, it’s not what you think! Administrator Linda Candelaria was approached by the group and asked if our branch would be willing to allow them to use our yard and shop for their K9 Unit training. The Vancouver facility is close to the border crossings and was perfect for what they need. It had enough obstacles, nooks and crannies, and high and low platforms that would allow the dogs to get their training and exercise. Although we were not able to witness some of the drills, we’re sure it would have been very interesting. The official yet cuddly canines sit proud with their partners in the photo below.

When asked to participate in a charity event the Victoria branch was one of several companies who welcomed the task. Flynn provided labour and some material to re-roof their bathroom facility. Our team on the project was as follows: Ken Littleproud (Superintendent), Shawn Mason (Foreman), Matt Fisher (Foreman), Grant Schwabe (Foreman), James Michalski (Apprentice), Austin Hiebert (Apprentice) and Joshua Ketola (Labourer). Thank you to all that participated to make this a successful event!

From left to right: Officers Shan Hanon and Jaxx (Bellingham Police Dept.), Officers Zach Wright and Vektor (Mt. Vernon Police Dept.), Officers Kevin Bean and Destro (Bellingham Police Dept.), Deputy Sheriff Jason Nyhus and Hyde (Whatcom County Sheriff - Bellingham), and our very own Linda Candelaria in the back.

COLORADO YOUTH OUTDOORS EVENT Flynn Southwest recently sponsored a Colorado Youth Outdoors’ (CYO) event in Loveland, Colorado. The CYO encourages families to spend time together outdoors with programs such as The Maverick featuring sporting clay shoot tournaments. Flynn Southwest Director of Operations Matt Behmer and Flynn Midwest VP–Roofing Operations Mike Pierce joined The Maverick for a weekend in support of CYO. Great job!

FLYNNFLASH | SUMMER 2015

47


FLYNN SPORTS SPONSORSHIP WESTMAN HIGH SCHOOL RUGBY Natasha Farren (Service Manager at Flynn Brandon) shared these pictures of her son Conor’s rugby team that was sponsored by Flynn. Below, Conor is pictured (right) with his sister and team captain (left), and again with his team which won the Westman High School Finals! The last time they held the title was 13 years ago! Congratulations!

BRIDGE TOURNAMENT SOCCER Pictured below is Mike Rodrigues’ daughter, Sofia, (bottom row, third from left) and Rick Fernandes’ daughter, Jessica (back row, fifth from the left) with their soccer team after winning the Bridge Tournament. Mike coaches the team that was sponsored by Flynn. Both Mike and Rick are Roofing Foreman at Flynn Hamilton. Thanks for sharing!

48

FLYNNFLASH | SUMMER 2015

WARREN JUNIOR MERCS HOCKEY Jason Walsh, Metals Foreman Winnipeg, coaches the 8-9 year old Girls' Warren Junior Mercs hockey team. This photo was taken at the Stony Mountain flames invitational tournament where the Mercs finished as runners up. The Mercs received support from Flynn through the Sports Sponsorship Program.

VANCOUVER GIRLS' VOLLEYBALL Denise Francisco, Project Coordinator for Flynn Vancouver, received a sponsorship for the 15 year-old Girls Volleyball Team she coaches. Congratulations!


WOOD’S POWR-GRIP TRAINING COURSE ■■Submitted by Bruce Leckie

Wood’s Powr-Grip Co., Inc. began in 1946 as an automotive, electric and small engine repair shop and has grown into a worldwide leader among manufacturers of vacuum lifting tools and equipment. Located in Laurel, Montana, U.S.A. just west of Billings, Wood’s Powr-Grip employs a team of more than 100 in their 55,000 square foot facility.

Left to right – JP Schmidt, Bruce Leckie, Dustin Castellairn, Jessi Castellairn, Roderick Simicic and Steven Stone.

From left to right Ross King, Bryan Wood, Carl Ritterpusch and Brad Wood. If you’ve ever had a malfunction with your below-the-hook vacuum lifter and spent hours, even days trying to troubleshoot the problem, keep your chin up; help is on the way! Wood’s Powr-Grip offers a Two Day Vacuum Lifter Troubleshooting and Repair Workshop biannually to all who are interested. The purpose of the workshop is to inform, educate and equip end‑users with the knowledge necessary to diagnose and repair vacuum lifters that may not be functioning to their optimum capability. Attendees spend time in a classroom situation learning how a vacuum system functions, followed by handson experience in troubleshooting and repairing a vacuum lifter.

Six employees from Flynn Vancouver made the trip down to Montana “The Treasure State”, to take the much anticipated, Wood’s Powr-Grip troubleshoot and repair workshop. To say the visit was a success would be understating the whole experience. The Woods’ “family” were so welcoming. We were made to feel like part of the “family” from the minute we walked in the front door. We also received a personal tour of the factory learning all the process involved in the manufacturing of Wood’s products. Right from the 3” T-handle cup all the way up to the custom made remote controlled counter-balanced 2800 lbs capacity powr-grip cup. We learned that on top of the two courses they run each year, if you have a class of at least six you can get your very own course tailored to your own requirements. We would highly recommend more Flynn branches use this service and keep their power cups certified and in great working order.

SOPREMA TRAINING ■■Submitted by Jodine Baker

Flynn Halifax employees received hands on training from Soprema on April 16th, 2015. Training consisted of best practices and proper installation of Soprema Mod-Bit Products.

Left to Right: Pierre-Luc (Soprema), Chuck Philibert (Soprema), Lewis Gale, Adam Randall, Derrick Shepherd, Chris Huybers, Nick Quirk, Ryan Lunn, Andrew Fader, Steve DeWolfe and Kenny Herritt. Missing from photo: Jeff Haslett and Kyi Gale.

FLYNNFLASH | SUMMER 2015

49


DID YOU KNOW? Flynn is now up and running on Social Media!

For daily updates, photos, videos, articles and more, be sure to: “LIKE” US ON www.facebook.com/FlynnCompanies

FOLLOW US ON

www.linkedin.com/company/flynn-companies

WATCH US ON www.youtube.com/c/flynncompanies


FLYNN SAFETY FIRST AID TRAINING SAVES LIFE It was just another Friday for Metals Foreman Denis Sigouin and colleague Ben Bontemps who were working on the Ottawa Light Rail Transit. The OLRT project currently has a number of different trades actively working together to complete their scope of work on the project. It was on this day, when Denis and Ben were faced with the unexpected opportunity to practice their First Aid Training. Denis and Ben were working alongside a carpenter who was cutting 2 x 4 piece of wood standing up. The worker was using a skill saw to cut the wood when all of a sudden, it kicked back and cut the worker's upper-leg area above the knee. At the time of this incident, Denis and Ben knew they had to do something to help out their fellow worker. They grabbed their first aid supplies and applied pressure to the wound while attempting to close the wound as best they could. They both helped to wrap the injured workers leg using compression techniques to be able to reduce the amount of blood release. Both Flynn workers helped to carry the injured worker to a man lift so that he was ready for the ambulance once it arrived on site. Denis and Ben waited for the ambulance to come so that they knew their fellow worker would be in good hands. Both Denis and Ben should be proud that they were able to use their skills and knowledge from their first aid training to help out a fellow worker. Their picture can be seen in the Safety Star section on the back page.

A special “Thank You” email soon followed: Good Morning Doug, I am emailing you this morning full of pride and thankful for the mindset and culture you have instilled in your company with regards to Health and Safety. Yesterday at the OLRT site in Ottawa there was a serious incident involving a worker from another trade. Two members of your team in Ottawa were witness to the accident and jumped into action. Through all of the training and education that Flynn has provided their team, they acted safely, calmly and effectively, administering first aid until the paramedics arrived. I had the opportunity to speak with a gentlemen from our industry who was witness to the efforts of your team and he could not tell me enough how impressed he was with how they took charge and kept the situation under control. It is very comforting to know that when my husband goes to work every day he has this training and knowledge to put all odds on his side to ensure that he and his team go home to their loved ones. As well, I am certain that the trades that were witness to your team yesterday are confident that when they are on the same job site as Flynn they have competent, educated, safety aware comrades on site with them. I respect your company’s efforts to raise awareness and educate all of your team where Health and Safety is concerned and the role that it plays in our day to day work routines. You have set a standard that is paramount and it was clearly evident yesterday. Congratulations to the entire Flynn family for once again setting a high standard of excellence and awareness. I thank you for your time Doug. One Very Proud Wife, Paula Chateauvert

SCARY SLIP Manny Bandeira and Jorge Da Silva were working on the canopy in Brampton, Ontario and witnessed an elderly man slip and fall on some ice on the road and suffer a few nasty gashes. Manny and Jorge stopped what they were doing and went over to tend to the

man, called 911, and carried him over to his apartment complex a few blocks away. They stayed with him until the emergency services showed up and the man thanked them for their assistance. Their photos can be seen in the Safety Star section on our back page.

FLYNNFLASH | SUMMER 2015

51


SAFETY STARS 2015 Every month, Safety Star submissions are reviewed and someone who demonstrates high levels of safety and professionalism on the job receives the honorary title, and a chance to win an annual Flynn Getaway! This year, we are recognizing both individuals and CREWS who have gone above and beyond safety on their sites! Congratulations to a job well done. To learn more about the Safety Star Program and to nominate someone who you feel should be recognized for their safety efforts, be sure to contact your local Safety Specialist.

2014 ANNUAL SAFETY STAR WINNER Luis Soares Decker – Foreman (Toronto) And the winner of the 2014 Annual Safety Star Award was…Luis Soares from our Flynn Toronto Branch. Congratulations, Luis – and all of our stars who have gone above and beyond to keep themselves, and others they work with and around, safe!

Manny Bandeira Roofer – Material Handler (Toronto)

Jorge Da Silva Sheet Metal, Journeyman (Toronto)

Safety Star of the Month January 2015

Safety Star of the Month February 2015

Denis Sigouin Sheet Metal – Foreman (Ottawa) Ben Bontemps Decker – Assistant (Ottawa) Safety Stars of the Month March and April 2015