Merchants Park Sewer Extension Select Board Update April 2

Page 1

Merchants Park Sewer Extension

Select Board Update April 2


MN1

Presenting Team

Mike Nelson, PE Project Manager and Associate

Scott Turner, PE, AICP, LEED AP ND QA/QC and Associate


Slide 2 MN1

We can streamline scott and my intros into the agenda slide Mike Nelson, 2026-03-30T16:11:43.751


Agenda ˃ Overview of Project and Site ˃ What’s been accomplished so far? ˃ Next Steps ˃ Permitting and Avon Industrial Park ˃ Schedule


Project Overview Project Goals: • To design & obtain permits for a sewer system serving Merchant’s Park. • Economic & sustainable development • Potential for public private partnership • Enacting goals of Town Master Plan


Existing Conditions Work Completed: • Topographic Survey • Record Plans added • Wetlands Delineated • Geotechnical Program • Basemapping for Design


MN2 MN1

Preliminary Design & Cost Estimate

Task 2: Preliminary Design

Task 3: 75% Design

Preliminary Design Delivered: Feb 2026

Future Flows Under Development

Preliminary Cost Estimate $6.2 - 8M

Pump Station Design Started

Met with FX Messina & Stoughton

Design & Estimates to be Refined

Existing Water / Flow Data Extracted

Construction Specifications

RKG Development Study Underway

Agreements Under Development


Slide 6 MN1

Replace these items in task 2 table with the following: Prelim design delivered Feb 2026 Prelim Cost Estimate $6.2 - 8M Met w/ FX Messina & Stoughton Existing water / flow data extracted RKG development study underway Mike Nelson, 2026-03-30T19:05:20.724

MN2

Replace text in task 3 table: future flow under development Pump station design kicking off Design & estimates to be refined Construction specifications Agreements framed Mike Nelson, 2026-03-30T19:05:43.478


KC1

Project Permitting Permitting Process EJ Notification ENF Submission EIR Process with MEPA (Draft & Final) MWRA & WRC Approvals Prepare and File NOIs Construction Permits

AIP and Merchant’s Permitting is linked

Types of Permits: • Interbasin Transfer Act •

WRC, DCR, MWRA & Stoughton

• MRWA OP.11 • Local Permits •

NOI - ConCom

• MassDOT


Slide 7 KC1

Placeholder Photo - from project profile Katy Carroll, 2026-03-31T14:28:47.233


Grant and Funding Support Task 5: Scope Review Grant Opportunities with Town and Regulators Develop Short List & Prepare Grant / Loan Application Participate in updates and reporting for Design Grant

Remaining Work: • Permitting • Apply costs to rate & fee models • Further develop PPP opportunity • Value Engineer 100% Design • Coordinate Grant seeking with IMA stakeholders


Updated Project Schedule 2026 Task Name

JAN

FEB

MAR

APR

MAY

JUN

2027

JUL

AUG

SEP

OCT

NOV

DEC

JAN

FEB

MAR

APR

MAY

JUN

JUL

Task 1 Data Collection, Wetlands Flagging and Existing Site Plan Reviews - COMPETED

Task 2 Preliminary Design and Estimates of Probable Cost COMPETED

Task 3 Design Development Phase Design

12/1/25 – 7/1/26

Task 4 Project Permitting*

MEPA 4/1/26 – 9/1/27 WRC 3/1 – 9/1

Task 5 Grant and Funding Support – April 2026

4/1/26 – 4/1/27

Task 6 Final Design and Construction Documents Merchant’s Park

7/1 – 9/15

*Water Resource Commission MEPA DEIR & OP.11 submitted for final approvals; approval timelines may vary 3-6 months from submission.

AUG

SEP


Thank You www.fando.com