236 Cashel Street, Christchurch
1
GENERAL NOTES
EMILY HIGHAM SARC321
THE CONTRACTOR WILL VERIFY ALL DIMENSIONS ON-SITE, PRIOR TO COMMENCEMENT OF ANY WORK. ANY DISCREPANCIES ARE TO BE RAISED WITH THE PROJECT ARCHITECT IMMEDIATELY. Any substandard construction onsite will be held responsibe by the relevant contractors.
The contractor shall provide all required equipment for the work, such as temporary fencing, and scaffolding.
SARC 321 - Assignment 2 - Core Design EMILY HIGHAM - GROUP A - RICK
TOILET CALCULATIONS GFA= 36 x 27 = 972 MAX OCCUPANCY /FLOOR 972 / 8 = 121.5 people, rounded to 122 ASSUME 60/40 gender split (60 males, 40 females) = 48.8 (rounded to 49) females, 73.2 (rounded to 74) males According to NZBC C1 Table 1 there are required to be: 2 Female WC pans, 2 hand basins GSEducationalVersion 3 Male WC pans, 2 hand basins
Cover Page
The contractor will ensure all rubbish is to be removed from site at the end of construction, prior to take over by the client.
ISSUED: 16/09/2022
PROJECT DESCRIPTION This project is an 8 story mixed use building, where the ground floor is retail, followed by 3 office floors, then, 4 apartment floors. There is also an underground basement carpark. The core takes up 12.5% of the floor space, making these floors 87.5% efficient. The structure of the building is base isolated in the basement, with reinforced concrete columns and beams, and double tee flooring which spans between the primary beams. The structural grid is 9x9m, and the planning grid is 1.5x1.5m to accommodate for offices and carparks.