COST DATA INSIGHT
The Governor’s Academy
Tom Woodruff
Director of Facilities
The Governor’s Academy
September 29, 2025
![]()

COST DATA INSIGHT
The Governor’s Academy
Tom Woodruff
Director of Facilities
The Governor’s Academy
September 29, 2025
Erland’s budgets are reliable from concept through GMP, with the included cost data examples demonstrating how we proactively manage expenses across varying market conditions.


Athletic Field House at Middlesex School Concord, Massachusetts
A two-story athletic field house featuring a spacious, well-equipped fitness center with indoor turf, practice space, two basketball/volleyball courts, and an elevated indoor track.
$37,901,780 (+2.82%)
$/SF: $359/SF
Adams House Renovation at Phillips Academy Andover, Massachusetts
Renovation of existing dormitory consisting of both interior and exterior upgrades. Year of Contract:
-* (Direct Cost + % of Indirect Costs) -Trended numbers are based off ENR’s Construction

LeBaron Briggs Dormitory Renovations at Middlesex School Concord, Massachusetts
Completed gut/rehab of the interior of each dorm, new slate roofs, 150 new exterior windows, overhaul of MEPs, and a small addition to accommodate a new student common room.
11,500


Robert Winsor Dormitory Renovations at Middlesex School Concord, Massachusetts
Completed gut/rehab of the interior of each dorm, new slate roofs, 150 new exterior windows, overhaul of MEPs, and a small addition to accommodate a new student common room.
Hyde Hall & Faculty Housing Campus Renovations at The Fessenden School Newton, Massachusetts
Updating of two kitchens and several restrooms, which encompassed the installation of new countertops and cabinets. Additional enhancements included painting various spaces, upgrading HVAC, electrical, plumbing, and life safety systems, as well as installing new flooring, lighting, and millwork.



Ice Rink Renovation at The Fessenden School Newton, Massachusetts
Updates to building’s 1st-floor walls, flooring, and ceilings; installation of new fire protection services, life safety system, demising walls, ceilings, flooring, metal decking, MEP systems, and ADA accessibility upgrades. Year of Contract:
5,610
Design Center at Tenacre Country Day School
Wellesley, Massachusetts
Ground-up construction of a new two-story design center with state-of-the-art classrooms, as well as the restoration and relocation of the 150-year-old historic headmaster’s house.
Patterson-Sculley House (Residence Life Project) at St. Mark’s School Southborough, Massachusetts
A 3-story residence hall for 150 students. The building consists of a mix of single and double rooms, 12 faculty apartments, as well as a student lounge, 8 group study rooms, 12 study nooks, and a communal kitchen.


Campus Center Addition at Cotting School Lexington, Massachusetts
The 2-story addition houses a full, regulation-sized gymnasium, bowling alley, rock-climbing wall, media and visual arts classrooms, strength and conditioning fitness center, school store/concessions stand, office, and multiple activity spaces.
Year of Contract: 2020 GSF: 25,397 GMP: $12,235,504
Trended GMP: $14,937,170 (+22.1%) Trended $/SF: $588/SF
Master Planning Pricing: Confidential Academy
Erland Construction is supporting a confidential academy with master planning services, providing conceptual pricing for multiple planned campus upgrades.
Phase 1: New Dining Building
GSF: 26,668
Conceptual Estimate: $23,548,987
$/SF: $883/SF
Phase 1A: Existing Servery & Parish Renovation GSF: 6,600 Conceptual Estimate: $650,869 $/SF: $98/SF
Phase 2: New Chapel & Connector Addition GSF: 13,068
Conceptual Estimate: $14,388,527 $/SF: $1,101/SF
Phase 3A: Library Renovation & Ward Expansion GSF: 14,920 Conceptual Estimate: $2,819,720 $/SF: $188/SF
Phase 3B: New Main Entry Addition
GSF: 6,000
Conceptual Estimate: $7,901,227
$1,316/SF
Cost + % of Indirect Costs)