PHASE I - DESIGN COORDINATION Design coordination
Contract
Kick off meeting
Technical review
Issue RFI (S)
RFI response
Final client design definition accepted by Element5
Incorporate changes into final design
Issue and approve/ Change order (if applicable)
PHASE II - DESIGN FOR MANUFACTURING AND ASSEMBLY (DfMA) L0D400 model (100%)
Final client design definition accepted by Element5
LOD300 model (50%)
LOD300 review and comments
Develop and issue final drawings & seal
Client approval for manufacturing
Design review
Secure production slot
PHASE III - PRODUCTION Client approval for manufacturing
Production coordination and shop drawings
Procurement / Materials planning
Major milestone necessary to progress to the next step or phase
Billeting
By Element5
CNCing / Assembly
By client
Finishing
Shipping
Jointly