Summary of the water volume, and progress of water shortage prevention and mitigation measures in Rayong and Chonburi Provinces for 2015 7 April 2015 Water War Room

0


SUMMARY

OF THE WATER VOLUME, AND PROGRESS OF WATER SHORTAGE

PREVENTION AND MITIGATION MEASURES IN RAYONG AND PROVINCES FOR 2015-16

CHONBURI

 On April 7th 2015 the combined water volume in the 3 reservoirs is = 128.46 MCM. (46.7%) • Decrease since yesterday= -0.64 MCM. 

The Prasae-Nongplalai pipeline (latter 20 km) construction is complete and pumping has started.

1


OVERVIEW

OF WATER SITUATION IN

Chachoengsao Reserve Pond P2

P4

RAYONG-CHONBURI AREA APRIL 7TH 2015

Chonburi

P1

Rayong

Bangphra

Nongkho

Dokkrai

Nongplalai

Klong Yai

Prasae

117.00

21.40

71.40

163.75

40.10

248.00

42.10

6.97

19.40

97.80

11.26

186.95

36%

33%

27%

60%

28%

75%

30.05

5.97

16.40

84.30

8.26

166.95

-0.19

-0.17

0.050

0.767

0.058

P3

P5 P6

Private Pond

Reservoir capacity (MCM) Current storage volume (MCM) 13 Percentage of reservoir capacity Useable storage volume Samnakbok (excluding Dead Storage) Reserve Pond (MCM) Inflow into reservoir (MCM)

P7

Bang Phra res. P9

42.1

82

P-BPN P8

7.0

Nong Kho res.

P10

0.875

0.158

Water volume compared -1.12 -0.97 -0.73 -4.95 -0.40 to previous week -3.50 (-decrease, +increase) -2.09 -6.06 (MCM) Total water volume in 49.07 MCM 128.46 MCM each area (35.5%) (46.7%) Note: * When storage volume falls below 15.2 MCM, it is not possible to transfer water from Klongyai Reservoir to Nongplalai Reservoir

28

187.0

11.3

Khlong Yai res. 97.8 P11Pla Lai res. 19.4 Nong P12 P-NP3 P13 Dok Krai res. P14

Prasae res.

P

28

120 P7

P15

180

P16

Raw Water Pipe Line (EW)

Source of data: Royal Irrigation Department

Demand 2557 (MCM.) Supply (MCM.) Pump Station Raw Water Pipe Line (RID)

Existing Pipe Network

Existing Pipe Network

Constructing Pipe Network

2 Constructing Pipe Network


SUMMARY OF WATER SHORTAGE PREVENTION AND MITIGATION MEASURES IN RAYONG AND CHONBURI PROVINCES Planned water volume Measure

Status

2015 Mar

1. Primary measures 1.1 Water diversion via pumping 7.5 from Prasae to Klongyai Reservoir through the RID’s PS–KY pipeline the Klongnamdaeng Canal 1.2 Water diversion via pumping the RID’s PS–KY pipeline connection to Eastwater’s PSNPL pipeline 1.3 Pump water from Rayong River back to Nongplalai Reservoir using RID’s Wat Lahanyai pump station. 1.4 Pump water from Rayong River 1.5 Water transfer from Bangpakong River รวม 7.5

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec Total

7.5

9.0

9.0

9.0

15.0

15.0

15.0

15.0

15.0

1.0

1.0

7.5

9.0

9.0

9.0

117

Pumping in progress MOU for water usage signed on 19 Feb ’15. Pipe laying in-progress -Pipe-laying progress -30 km beginning section ~5,300 m remaining -20 km end section is complete

2.0 0.5

0.5

1.0

1.5

3.0

4.5

4.5

1.5

15.0

16.5

19.0

20.5

20.0

17.0

135

Note: After updating schedule, construction of the latter half (20 km) of the Prasae-Nongplalai is complete

3


Simulation of water volume in main Rayong Reservoirs

7 Apr. 15 128.5 MCM.

Scenario with Prasae-Konglyai water transfer and reduction of water send to Chonburi


WATER SITUATION

OF

NONGPLALAI, DOKKRAI

Source of data: Royal Irrigation Department

AND

KLONGYAI RESERVOIRS


WATER SITUATION

OF

BANGPHRA

Source of data: Royal Irrigation Department

AND

NONGKHO RESERVOIRS

6


WATER SITUATION

OF

PRASAE RESERVOIR

Source of data: Royal Irrigation Department

7


WATER SITUATION

OF

DOKKRAI RESERVOIR (BY YEAR)

Source of data: Royal Irrigation Department


WATER SITUATION

OF

NONGPLALAI RESERVOIR (BY YEAR)

Source of data: Royal Irrigation Department


WATER SITUATION

OF

KLONGYAI RESERVOIR (BY YEAR)

Source of data: Royal Irrigation Department


WATER SITUATION

OF

BANGPHRA RESERVOIR (BY YEAR)

Source of data: Royal Irrigation Department


WATER SITUATION

OF

NONGKHO RESERVOIR (BY YEAR)

Source of data: Royal Irrigation Department


Progress of pipe-laying of Prasae-Nongplalai pipeline

30 km from beginning (Prasae reservoir to Junction point with new pipeline) 20 km at end (junction with existing RID pipeline to Nongplalai Reservoir)

Location of laid pipeline Progress Summary : 30 km. section (beginning) – ~5,300 m. remaining as of 30 Mar 2015

: 20 km section (tail end) – Completed


สถานีสบ ู นา้ Pumping Station

่ นา้ อ่างเก็บนา้ ประแสร์-หนองปลาไหล, East Water) (โครงการวางท่อสง Outlet

อ่างเก็บนา้ ประแสร์

สถานีสบ ู นา้ ประแสร์ (ใหม่)

สถานีสบ ู นา้ ประแสร์ (เดิม)


สถานีสบ ู นา้ Pumping Station

(Prasae Reservoir-Nongplalai Reservoir pipeline system construction project, East Water) No.

Item

1

Pumps and motors

2

Procurement of pump accessories and control system (M&E)

3

Construction of pump station Land clearing Excavation Foundation and base slab work Lower level walls

4

Installation of pumps and accessories & testing

Planned progress

Actual progress

Mar ‘15

Apr ’15

May ’15

Jun ’15

Jul ’15

Aug ’15

Manufactured and ready for installation (6 sets)

Sep ’15


TUBMA RESERVOIR DEVELOPMENT PROJECT OBJECTIVE To develop raw water reservoir to increase water supply by 47 MCM per year by pumping water from Rayong River and Tubma canal to be stored at the Tubma reservoir P

Tabma Canal pumping station

P Tabma pond pumping station

P

Investment:

Bt.2,200 mil

Capacity:

47 MCM per year

Project duration:

60 months

Progress update:

59.11%

Operating date:

End 2015 (Expedited to be complete

by Sep. 2015, RY River pump ready Jun. 2015) Progress:

Base slabs of Tubma Canal and Rayong River pump stations are built and pipe

laying is in progress (10,044 m). Main pump station design is being finalized.

Source : East Water

Water retaining berm is being constructed.